Central Oklahoma Master Conservancy District Board Meeting
Regular MeetingNorman, OK · July 2, 2020
Minutes
MINUTES OF REGULAR BOARD MEETING
CENTRAL OKLAHOMA MASTER CONSERVANCY DISTRICT
Thursday, July 2, 2020
In accordance with Senate Bill 661, which temporarily modified the Open Meeting Act as approved by Governor
Stitt on March 18, 2020, the Central Oklahoma Master Conservancy District hosted a virtual meeting option for
the Regular Board Meeting on July 2, 2020 at 6:30 P.M. using the following options:
Teleconference dial in number 1-866-899-4679, access code 275-161-789
Videoconference https://global.gotomeeting.com/join/458006221 , access code
275-161-789
A. Call to Order by Chairman Roger Frech at 6:30 pm.
Roll Call:
Present: President Roger Frech (videoconference)
Board Member William Janacek (videoconference)
Board Member Amanda Nairn (videoconference)
Board Member Casey Hurt (videoconference)
Board Member Michael Dean (teleconference)
Absent: None
Staff Present: Kyle Arthur, General Manager
Kelley Metcalf, Administrative Assistant
Tim Carr, Interim Supervisor
B. Statement of compliance with Open Meeting Act. Kelley Metcalf, Administrative Assistant, stated the
notice of the monthly board meeting had been posted in compliance with the Open Meeting Act.
C.1. Introduction of new Board Member Michael Dean of Del City. President Roger Frech introduced Michael
Dean of Del City.
C.2. Status report of the Del City Pipeline Project from Alan Plummer Associate’s, Inc. (Alan Swartz, Oklahoma
Area Leader). Alan Swartz reported Line 2 right-of-way cleanup is approximately 90% completed. Pipeline
marker posts have been installed every 100 feet along the pipeline. Crews are continuing to remove debris and
excess pipe from the work area. Spool pieces for the ARV and BOV have been delivered to the Contractor’s yard.
Line 3 crews have laid from Station 152+60 to Station 160+00. Backfill densities have all been above specification
minimums. Crews have been working for 2 ½ weeks to trace a small leak that kept the pressure test between
Stations 143+33 and 153+20 from passing. The pressure test passed on June 30th. It turned out that there was a
significant amount of air in the pipe that had not been removed and there was no leak. Crews are working to
backfill the exposed bells between Stations 143+33 and 153+20. Right-of-Way has been cleared to I-240.
Temporary fencing has been erected for livestock on one property. Crews are working to install Air Valve and
Blow-Off vaults along the section of tested line. A shutdown request for Line#3 has been submitted and
approved for the 6th through the 15th of July. This will tie in the line at Station 99+95 and approximately Station
154+00 and bring it into service.
D.3. Consideration and possible approval of minutes of the Regular Board Meeting held on Thursday, June 4,
2020. William Janacek made a motion to approve the June 4, 2020 Regular Board Meeting minutes seconded by
Casey Hurt. Roll call vote:
President Roger Frech Yes
Treasurer Jann Knotts Abstain
Secretary Kevin Anders Abstain
Member William Janacek Yes
Member Amanda Nairn Yes
Member Casey Hurt Yes
Member Michael Dean Abstain
Motion Passed.
D.4. Consideration and possible approval of financial statements for operating account for May 2020. The
President entertained a motion to approve the May 2020 financials with a correction to the footnote on page 1,
$902,635.67, for the year to date Del City pipeline loan advances, should be $1,248,988.06. Jann Knotts made a
motion seconded by Amanda Nairn to approve the May 2020 financials with recommended correction. Roll call
vote:
President Roger Frech Yes
Treasurer Jann Knotts Yes
Secretary Kevin Anders Yes
Member William Janacek Yes
Member Amanda Nairn Yes
Member Casey Hurt Yes
Member Michael Dean Yes
Motion Passed.
D.5. Discussion, consideration, and possible approval of Execution of Memorandum of Agreement with
OWRB and USGS for stream gaging fiscal year ending June 2021, Cost $19,300.00. Discussion was held. Amanda
Nairn made a motion seconded by Casey Hurt for execution of Memorandum of Agreement with OWRB and
USGS for stream gaging fiscal year ending June 2021. However, a correction needs to be made, the COMCD cost
share is not $19,300 it is $12,400.00. Roll call vote:
President Roger Frech Yes
Treasurer Jann Knotts Yes
Secretary Kevin Anders Yes
Member William Janacek Yes
Member Amanda Nairn Yes
Member Casey Hurt Yes
Member Michael Dean Yes
Motion Passed.
D.6. Consideration, and possible vote of Election of Vice Chairman. The office of Vice President is now open.
Roger Frech stated the floor is open for nominations and a self-nomination is allowed. William Janacek, Michael
Dean, and Amanda Nairn volunteered. The President stated the votes should be cast by secret ballot via email to
Kelley Metcalf, Administrative Assistant for the District, by end of day on July 3, 2020. Amanda Nairn removed
her name. Legal Counsel stated he will research secret ballot in respect to the Open Meeting Act law and report
his findings.
E.7. General Manager’s Report.
o Title Transfer
o Rough draft to PowerPoint presentation has been mostly completed
o Will send to James Allard and Dean Couch for input and review
o Trying to better assess insurance impacts for assets that would be transferred
Meeting with Watkins Insurance the week of 6/29 to discuss
o Dean and I drafted, and I have signed and sent, the letter to James Allard at BOR requesting to amend the
temporary water contract
o Change monthly accounting to annual
o Clarify reporting year to match federal water year (Oct-Sept)
o Increase usage amount from 10,000 ac-ft to 25,000
o Attended a meeting at the City of Norman regarding an effort by a consultant to assess their building codes
relative to “green” building/infrastructure and low impact development
o City Council goal to have codes that encourage/incentivize green building
o Met with city staff: holistic overhaul needed, out-of-date, does not incentivize
o This meeting sought input from developers and builders
o Positive ultimate impact for Thunderbird with the hopeful implementation of develop projects that would
better control run-off
o Work continues the floating wetlands
o Students have been out each week
o All units have been power-washed and are mostly reassembled and structurally reinforced
o As of the writing of this report, 14 of the 20 units have been planted and are in the water; hope to have the
remainder done in the next week to two weeks
o Technology upgrades
o New laptop for use in the Board room has been delivered
o A camera for virtual meetings has been installed
o A new wireless router has been installed to address speed requirements for streaming video
o Met individually with both Del City and Midwest City (Tim Carr also attended)
o Del City: met with interim City Manager Mike Cantrell and new Board member Michael Dean. Also met
with Beverly Palmer, City Attorney
o MWC: met with treatment plant supervisor Mark Roberts
o Preparing to perform an equipment inventory
o Evaluating equipment that we use infrequently and could otherwise be rented
o Identifying items for auction
o Will come to the Board with any recommendations for approval
o Fencing project on the south and east side of the dam, as requested by BOR, is ongoing. The two areas
considered most critical have been completed.
o Plan to post position for permanent maintenance Supervisor
o Held interview with Travis Boone, pipeline inspector, to ultimately replace our current inspector (Dennis Yarbro)
for the remainder of the Del City pipeline project
o New air conditioning interface panels have been fabricated for each of the VFD (Variable Frequency Drives) in
the pumping plant
o Will allow back-mounted air conditioners to better and more efficiently circulate air around the VFD
o Participated in Zoom meeting with OU (Nairn and Knox) and the OWRB on the OU CEES Capstone project
o Trend analysis with potential engineering solutions for identified water quality issues is the chosen project
o Discussed the trend analysis proposal that OWRB is working on with Julie Chambers
o Discussed integrating an analysis of water quality improvement/technologies based upon findings
E.8. Legal Counsel Report.
Worked on new board member appointment
Reviewed contracts on temporary water. Prepared a summary that will be sent to the 3-city attorneys
Traveled to the District office to review title transfer and other documents
Worked with Kyle Arthur on presentation for partial title transfer
E.9. New business (any matter not known prior to the meeting and which could not have been reasonably foreseen
prior to the posting of the Agenda) Michael Dean inquired about timeline for board meetings to be held in person.
The President responded the District has upgraded the Board Room and can transition to a hybrid meeting and then
to an in-person meeting in the future, depending on the pandemic conditions.
F. Kevin Anders made a motion seconded by Jann Knotts to adjourn. Roll call vote:
President Roger Frech Yes
Treasurer Jann Knotts Yes
Secretary Kevin Anders Yes
Member William Janacek Yes
Member Amanda Nairn Yes
Member Casey Hurt Yes
Member Michael Dean Yes
Motion Passed.
Regular session ended 7:45 PM
Agenda
CENTRAL OKLAHOMA MASTER CONSERVANCY DISTRICT
AGENDA FOR REGULAR MEETING
Kyle Arthur, General Manager
TIME: 6:30 P.M.
THURSDAY, July 2, 2020
THIS MEETING WILL BE CONDUCTED BY VIDEOCONFERENCE AND TELECONFERENCE.
IF YOU ARE NEW TO THE “GO TO MEETING” APP, PLEASE INSTALL BEFORE MEETING START TIME.
VIDEOCONFERENCE: TO JOIN THE MEETING USING A COMPUTER, SMARTPHONE, OR TABLET, GO TO
HTTPS://GLOBAL.GOTOMEETING.COM/JOIN/275161789
MEETING ACCESS CODE: 275-161-789.
TELECONFERENCE: TO LISTEN TO THE MEETING USING A TELEPHONE, CALL 1-866-899-4679 ENTER ACCESS
CODE: 275-161-789.
IN THE EVENT THE COMMUNICATION LINK OR CONNECTION IS LOST AND THE MEETING IS INTERRUPTED,
THE DISTRICT WILL MAKE EVERY EFFORT TO RESTORE THE LINK OR CONNECTION WITHIN THIRTY (30)
MINUTES AND THE MEETING WILL THEN CONTINUE. IF THE DISTRICT IS UNABLE TO RESTORE THE LINK OR
CONNECTION WITHIN THIRTY (30) MINUTES AFTER IT IS LOST, THE MEETING WILL BE RECONVENED ON
MONDAY, JULY 6, 2020 AT 6:30 PM. THE RECONVENDED MEETING WILL BE CONDUCTED IN THE SAME MANNER
AS NOTICED HEREIN, AND BOARD MEMBERS WILL PARTICIPATE IN THE SAME MANNER AS NOTICED HEREIN.
ANY RECONVENED MEETING SHALL BEGIN WITH A ROLL CALL VOTE AND SHALL THEN PROCEED TO THE
AGENDA ITEM THAT WAS UNDER DISCUSSION WHEN THE LINK OR CONNECTION WAS LOST.
A. CALL TO ORDER AND ROLL CALL
B. STATEMENT OF COMPLIANCE WITH OPEN MEETINGS ACT
C. ADMINISTRATIVE:
1. INTRODUCTION OF NEW BOARD MEMBER MICHAEL DEAN OF DEL CITY.
2. STATUS REPORT OF THE DEL CITY PIPELINE PROJECT FROM ALAN PLUMMER ASSOCIATES, INC. (ALAN
SWARTZ, OKLAHOMA AREA LEADER).
D. ACTION:
3. CONSIDERATION AND POSSIBLE APPROVAL OF MINUTES OF THE REGULAR BOARD MEETING HELD ON
THURSDAY JUNE 4, 2020.
4. CONSIDERATION AND POSSIBLE APPROVAL OF FINANCIAL STATEMENTS FOR OPERATING ACCOUNT FOR
MAY 2020.
5. DISCUSSION, CONSIDERATION AND POSSBILE APPROVAL OF EXECUTION OF MEMORANDUM OF
AGREEMENT WITH OWRB AND USGS FOR STREAM GAGING FISCAL YEAR ENDING JUNE 2021, COST $19,300.00.
6. CONSIDERATION AND POSSBILE VOTE OF ELECTION OF VICE CHAIRMAN.
E. DISCUSSION:
7. GENERAL MANAGER’S REPORT.
8. LEGAL COUNSEL REPORT.
9. NEW BUSINESS (ANY MATTER NOT KNOWN PRIOR TO THE MEETING AND WHICH COULD NOT HAVE BEEN
REASONABLY FORESEEN PRIOR TO THE POSTING OF THE AGENDA)
F. ADJOURN
BOARD MEMBER ATTENDANCE METHOD:VIDEOCONFERENCE: ROGER FRECH, KEVIN ANDERS, AMANDA NAIRN,
JANN KNOTTS, WILLIAM JANACEK, CASEY HURT TELECONFERENCE: MICHAEL DEAN
Get email alerts for Norman
A daily email when new agendas and minutes are posted.