FLOOD PLAIN PERMIT COMMITTEE MEETING
201 West Gray, Building A, Conference Room D
Monday, December 19, 2016
3:30 p.m.
Minutes
PRESENT: Shawn O’Leary, Director of Public Works
Susan Connors, Director of Planning/Community Development
Ken Danner, Subdivision Development Manager
Jane Hudson, Principal Planner
Sherri Stansel, Citizen Member
OTHERS PRESENT: Carrie Evenson, Stormwater Engineer
Rachel Warila, Staff
Greg Hall, Street Superintendent
Chris Serrano, Construction Manager
Bob Flume, Citizen
The meeting was called to order by O’Leary at 3:31.
Item No. 1, Approval of Minutes:
O’Leary requested a roll call of the committee. Five members of the committee were present
and a quorum was established. Scott Sturtz and Neil Suneson were absent. O’Leary called for
a motion to approve the minutes from the meeting of November 7, 2016. A motion was made
to approve the minutes by Ken Danner. Seconded by Sherri Stansel. Approved 5-0.
Item No. 2, Flood Plain Permit Application No. 580:
O’Leary stated this application was for the Havenbrook Street bridge replacement project
over Brookhaven Creek located approximately 200 ft. east of 36th Avenue N.W. about 1 block
south of West Robinson Street. Carrie Evenson gave the Staff Report for this application and
Flood Plain Permit Committee meeting
December 19, 2016
Page 2
mentioned the applicant was the City of Norman Public Works Department with City
Engineer Scott Sturtz who was not present.
Evenson stated that the existing bridge consists of 9 -108” corrugated metal pipes (CMPs) that
was constructed in 1982. She said that on September 25, 2016, the bridge was closed by the
City of Norman due to collapse of the roadway and an investigation by the Department of
Public Works determined that the existing corrugated metal stormwater pipes under the
roadway were corroded to the extent that 2 of the pipes had collapsed allowing the roadway to
settle by over 2 vertical feet.
She said with this emergency repair project, the City is proposing to demolish the portions of
the existing bridge that must be repaired, and replace the 9 existing 108’ CMPs with 9 new
“coated” CMPs of the same size. Evenson presented a map of the bridge project depicting the
floodway and floodplain, explaining that the new CMPs will be the same size as the previous
pipes but will be coated inside and outside with a protective product to ensure a longer life in
corrosive soil conditions. She said work to replace the CMPs will require the construction of a
temporary cofferdam to divert stream flow away from half of the CMPs at a time, to provide a
dry work environment. She said that other deficient structural elements of the existing bridge
will be repaired or replaced as needed and the existing concrete pavement and sidewalk will
also be replaced. She said that because the existing CMPs are being replaced with new coated
CMPs of the same size in the same location, no rise in the Base Flood Elevation is anticipated.
She then presented some photos of the bridge failure which showed why the roadway needed
Flood Plain Permit Committee meeting
December 19, 2016
Page 3
to be closed and some photos depicting the bridge repairs underway and the removal of the
corroded CMPs.
Evenson mentioned the Applicable Ordinance Sections were Fill Restrictions in the
Floodplain, City Council Approval, No Rise Considerations and Emergency Authority, which
have all been addressed in the report.
O’Leary introduced Greg Hall, Streets and Stormwater Superintendent, the project manager
for this project. He explained that this application was for a significant problem that occurred
unexpectedly in September, which led to one minor vehicular accident but that the Norman
Police Department worked quickly to close the bridge before there were any injuries. He said
that City staff had done a great job exploring options and alternative repairs, including
everything from a 2 million dollar bridge to the use of CMPs. O’Leary said the floodplain
ordinance dictated part of this choice in the desire not to make any changes in the floodplain.
He added that the bridge would be put back exactly the way it was and that part of the work
would be done by City crews, saving money in the process.
O’Leary asked the FPC if they had any comments of questions regarding this application.
Stansel asked if the coated CMPs were a new product and O’Leary responded that they have
been around since about the 1970s to 1980s but were not required for use unless placed in
reactive soils that tend to react negatively to metal pipe. He explained that reactive soil was
not identified during the previous pipe installation and that the bridge did last for 34 years. He
said that bridges of this type could last up to 60 years but the reactive soil created holes in the
Flood Plain Permit Committee meeting
December 19, 2016
Page 4
metal pipe that eventually caused it to collapse. He said that the pipe sizing and the wall
configuration was found to be sufficient but the material itself failed, which is why they are
replacing it with a coated material that will not react to the soil conditions at the project area.
Stansel asked if the soil at Brookhaven Creek is different than the soil in other areas around
Norman. O’Leary said there were reactive soils in the western part of the City more often than
other parts. Danner said this was one of the reasons the City uses different pipe for the
waterlines because they were becoming corroded by the soil. O’Leary stated that metal pipes
tend to react worse in the western part of the City than the eastern part due to the soil
conditions, so if they choose to use metal pipes coatings are now required.
Connors asked if the entire bridge would have to be repaired before the road could be opened
up for traffic. O’Leary replied they were repairing half of the bridge and that the road would
remain closed because there were 9 pipes in a series and because of equipment access all 9
pipes could not be repaired at the same time. He said all repairs would need to be made before
the road could reopen, which could happen around February or March, 2017; if the weather
cooperates and everything else goes as expected. Stansel asked where the concrete from the
repair would be hauled off to and Greg Hall said that there was very little but that it would be
broken into pieces and used as rip rap material.
O’Leary asked Bob Flume if he had any questions or comments. Flume said he was a property
owner on 36th Street and he had received a floodplain notice in the mail and he had come to
the meeting early and already discussed his concerns with Carrie Evenson. O’Leary asked for
Flood Plain Permit Committee meeting
December 19, 2016
Page 5
a motion from the committee. Danner recommended approval of Floodplain Permit
Committee application #580, which was seconded by Connors. Motion approved 5-0.
A motion was made by Danner which was seconded by Connors. Approved 5-0.
Item No. 3, Miscellaneous Discussion:
1. There were no applications for the January 3, 2017 meeting.
2. There were no pending application for the January 17, 2017 meeting.
O’Leary asked if there was anything else from the committee and there was not. O’Leary
called for a motion to adjourn. Connors motioned to adjourn, seconded by Danner. Motion
was approved 5-0. Meeting adjourned at 3:45 p.m.
Agenda
FLOODPLAIN PERMIT COMMITTEE
AGENDA
Monday, December 19, 2016
MEETING TIME: 3:30 p.m.
MEETING PLACE 201 West Gray, Building A, Conference Room D
1. Approval of Minutes from the November 7, 2016 meeting.
2. Floodplain Permit Application No. 580: Application is for the emergency repair of the Havenbrook
Street bridge over Brookhaven Creek.
3. Miscellaneous Discussion:
a. The filing deadline for application submittals for the January 3, 2017 meeting is Wednesday,
December 14, 2016. Currently, there are no pending applications (the meeting will be held on
Tuesday, January 3rd instead of Monday, January 2nd due to City Offices being closed for the
New Year’s holiday).
b. The filing deadline for application submittals for the January 17, 2017 meeting is Wednesday,
December 28, 2016. Currently, there are no pending applications (the meeting will be held on
Tuesday, January 17th instead of Monday, January 16th due to City Offices being closed for the
Martin Luther King holiday).