AGENDA ITEMS A, B & C-CALL TO ORDER, ROLL CALL, DETERMINATION OF QUORUM:
Ralph Page, Chairman called the meeting to order at 7:00 PM.
Commission Members Present: Ralph Page, Michael Lahan, Frank Manfredi, Les King, John Mathieu and Daniel
Daniska. A quorum was present.
Absent: Art Sharron
Also Present: Peter Davis, Director and Deb Delaporta, recording secretary
D. APPROVAL OF MEETING MINUTES:
Upon motion by Frank Manfredi and second by Michael Lahan, the Commission voted unanimously to APPROVE the
minutes of the April 21, 2015 Regular Meeting.
E. COMMUNICATIONS:
The request from Wawecus 105 Associates LLC for full release of bond for SDP #1024 was tabled.
F. PUBLIC HEARINGS:
SUB #425-180 Harland Rd-Re-Subdivision Application of Stephen Majeski and Richard Vendola to create 1
additional lot.
Ralph Page opened the Public Hearing for Subdivision Plan #425. Peter Davis stated that it had been tabled last
month, and after reading the exhibit list explained the proposal to re-subdivide the parcel at 180 Harland Rd. The
original parcel was about 4 acres and subdividing would create a building lot of 1.47 acres, leaving 2.5 acres with the
existing house. Peter stated that this was reviewed and approved by IWWCC last month and that the site has city
water and city sewer and meets subdivision and zoning regulations.
The Public Utilities Department submitted comments that it meets the utility standards, and that a separate bond must
be posted for the utilities. Uncas Health had no comment because the house would be hooked up to City water and
City sewer. There were no other concerns or comments. Ralph Page asked if there was anyone there to speak in
favor of this project. Glenn Gordon, the applicants’ attorney, stated that sight lines indicated on the map showed 600
feet in both directions and that this was part of the original subdivision in 2008 of Anne Sharpe. No one spoke in
opposition, so Ralph Page closed the public hearing. Peter asked if the Commission would consider suspending the
rules so that a vote could be taken on the subdivision. Frank Manfredi made a motion to suspend the rules, second
by Les King. All members were in favor, none opposed. Upon a motion made by Frank Manfredi and second
by Michael Lahan, the Commission voted unanimously to APPROVE the Re-Subdivision.
SP#15-01-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft restaurant w/ drive-thru, within
a designated flood plain of the Shetucket River.
Peter Davis read the exhibit list A-K and added exhibit L which was a revised site plan brought in by Brian Long, the
applicant’s engineer. Peter stated that this application was heard before the IWWCC last month and since no
regulated activities were going to be occurring, only a commercial buffer permit was needed and that this Special
Permit application was dealing strictly with the flood plain. He explained that the site is located north of Highway 395
and two existing gas stations there. At the present time, it is covered with scrub brush and small trees and the entire
lot is within the flood plain. The applicant is proposing to construct a 2300 sq ft building with a parking area and drive
thru. Mr. Davis stated that in order to meet compensatory storage, anything not paved would be excavated out. Peter
pointed out the drainage system on the plan and then asked Brian Long to address the Commission and explain the
engineering and revisions that were proposed. Mr. Long explained the retaining wall change, and the landscaping
buffer to be replaced with additional plantings to supplement what is being removed. Brian then explained the
drainage system. He then referred to the flood impact statement to explain the excavation and drainage. He stated
that the site where the building is will be built up to street level, and the rest of the lot excavated with a retaining wall.
The rest of the lot would be left to grow back to what it was, which Peter Davis stated was what the IWWCCpreferred.
Brian explained that the building would be a built on a slab on grade, with no basement and that the building would be
flood proofed. He also said Public Utilities asked for modifications to have rip rap swale for when they flush their
hydrants.
Mr. Davis stated that the flood impact statement finds that the compensatory storage has been met, and there is no
impact to the resource. At this point, Ralph Page asked if there was anyone there to speak in favor of, or in opposition
to this application, and since there was not, he closed the public hearing.
SDP#1030-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft restaurant w/ drive-thru.
Peter Davis explained the Site Development Plan application. He stated that during the preliminary review, test pits
were asked for because the site was so close to the Shetucket River. They were completed and presented no
problems. There was a bond estimate submitted in the amount of $158,335 and half of that would have to be posted if
the application was approved.
Pat McLaughlin had a few comments. He asked that the bottom of the basin be cleaned out to make it water tight. He
did have an issue with people having to cross in front of the drive-thru to enter the store. Mr. Davis stated that due to
the setup of the lot, that was the only way it could be configured. Mr. McLaughlin was also concerned about the effect
of the salt used in the winter time on the retaining wall, but Brian Long explained that the materials used to construct
the wall had been changed, along with the design. Uncas Health and the City Engineer both had comments about an
old well located on the property that needed to be closed out, and that issue was being addressed by the engineering
company. According to zoning regulations, the 50 ft buffer required along the river could be met. The land would be
allowed to grow back to its natural vegetation to re-establish the buffer. The building would be connected to City water
and City sewer. Ralph Page asked about lighting, which Mr. Long pointed out on the plan. He also asked about sign
requirements, but nothing had been proposed yet. Peter Davis said that would be handled administratively through
the zoning department. Michael Lahan inquired if this would be a 24hr facility, but Brian was not sure. Mr. Long stated
that the DOT had asked for a slight widening of the road in front of the restaurant for a bypass lane, and that issued
was addressed on the plan.
G. OLD BUSINESS: None
H. NEW BUSINESS:
SP#15-01-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft restaurant w/ drive-thru, within
a designated flood plain of the Shetucket River.
Michael Lahan made a motion to approve SP#15-01, with a second from John Mathieu for a unanimous decision
SDP#1030-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft restaurant w/ drive- thru.
Michael Lahan made a motion to approve SDP #1030 with the condition that 50% of the bond be posted prior to
signatures on the mylars. Frank Manfredi seconded the motion, with all in favor for a unanimous decision.
I. EXTENSIONS: None
J: BOND RELEASES:
SDP #1024-79 Wawecus St-Request from Wawecus 105 Associates, LLC for full release of bond. Upon
discussion, a motion was made by Les King to table request, seconded by Frank Manfredi. The Commission voted
unanimously to table the request.
K. ZONING MATTERS: None
L. OTHER BUSINESS:
1. Relative to proposal to create public park on 28 Hammond Ave in honor of Ellis Walter Ruley- Frank
Manfredi spoke about this project and gave the history about Mr. Ruley, a self-taught artist, his life and how the City
came to own this property. Mr. Manfredi has been in contact with Glenn Smith who has written a book and is writing a
documentary about him. He has been working closely with Lottie Scott and Sheila Hayes to help create a public park
and bring tourists to Norwich. Les King made a motion for a favorable recommendation, seconded by John Mathieu,
with a unanimous decision.
2. Relative to Eagle Scout Taylor Stevens building a gazebo at Fontaine Field- Peter Davis explained that
Attorney Driscoll asked that the Commission review the project because it is an improvement to a public facility. Mr.
Davis informed the Commission that all zoning and building procedures would have to be adhered to. After
discussion, Frank Manfredi made a motion, seconded by Michael Lahan to forward a favorable recommendation to
the City Council. Improvements to public park facilities are consistent with the 2013 POCD. The CCP however, did
voice some concerns about the final appearance of the gazebo. No drawings were available for review.
M. ADJOURNMENT: Upon motion by John Mathieu, second by Frank Manfredi, the Commission voted unanimously
to adjourn the meeting at 7:49 PM.
Agenda
COMMISSION ON THE CITY PLAN
Tuesday, May 26, 2015 - 7:00 P.M.
23 UNION STREET NORWICH CONNECTICUT
LOWER LEVEL CONFERENCE ROOM
SPECIAL MEETING
AGENDA
A. CALL TO ORDER
B. ROLL CALL
C. DETERMINATION OF QUORUM
D. APPROVAL OF April 21, 2015 Meeting Minutes
E. COMMUNICATIONS: Request from Wawecus 105 Associates, LLC for full release of
bond, Council Referrals for Public Park Proposal at 28 Hammond Ave, Gazebo at
Fontaine Field
F. PUBLIC HEARINGS:
SUB #425-180 Harland Rd-Re-Subdivision Application of Stephen Majeski and
Richard Vendola to create 1 additional lot
SP#15-01-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft
restaurant w/ drive-thru, within a designated flood plain of the Shetucket River
SDP #1030-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft
restaurant w/ drive-thru
G. OLD BUSINESS: None
H. NEW BUSINESS:
SUB #425-180 Harland Rd-Re-Subdivision Application of Stephen Majeski and
Richard Vendola to create 1 additional lot
SP#15-01-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft
restaurant w/ drive-thru, within a designated flood plain of the Shetucket River
SDP#1030-132 Taftville-Occum Rd-GTO Realty LLC-Construction of 2390 sq ft
restaurant w/ drive-thru
I. EXTENSIONS: None
J. BOND RELEASES:
1. SDP #1024- 79 Wawecus St–Request from Wawecus 105 Associates,LLC for full release
of bond
K. ZONING MATTERS: None
L. OTHER BUSINESS: C.G.S. 8-24 Council Referral:
1. Relative to proposal to create public park on 28 Hammond Ave in honor of
Ellis Walter Ruley
2. Relative to Eagle Scout Taylor Stevens building a gazebo at Fontaine Field
M. ADJOURNMENT: