School Building Committee (2020)
Regular MeetingNorwich, CT · March 28, 2024
Minutes
School Building Committee (2020)
Special Meeting
Held via ZOOM
Thursday, March 28, 2024
6:30 PM
Committee Members Present: Chairman Mark Bettencourt, President Pro Tem Joe DeLucia,
Alderwoman Stacy Gould, William Hull, Gregory Ballassi, Christine DiStasio, Mark Kulos, and Peter
Gauthier.
Committee Members Absent:. Alderwoman Shiela Hayes, Gregory Carabine, and Cindy
Beauregard
Ex-Officio Members Present: Mayor Peter Nostrum; Norwich City Planner Bob Castronova, and
Matthew Brown
Consultants Present: Jeff Anderson, Downes Group; Greg Smolley, DRA; James Barrett, DRA;
CSG; Michael Faenza, CSG
Citizens Present: None.
1. Call to Order and Quorum: Chairman Mark Bettencourt called the meeting to order at 6:32
PM. It was determined that a Quorum was present.
2. Receive sub-committee report and recommendations on cost management for the
Greeneville and Stanton School Projects
Peter Gauthier made a motion to incorporate the sub-committee reports for both the Greeneville
and Stanton School Projects into the minutes of the meeting. Alderwoman Gould seconded the
motion. Voted in Favor: Peter Gauthier, Chairman Mark Bettencourt, President Pro Team Joe
DeLucia, Mark Kulos, William Hull, Alderwoman Stacy Gould, Gregory Ballassi, and Christine
DiStasio. Voted in Opposition: None. Motion passed unanimously.
3. Discussion and action on sub-committee’s recommendation on cost containment
for Greeneville and Stanton School Projects:
President Pro Tem DeLucia raised concerns with Items 8 and 10 0n both reports. For Item 8, he
expressed opposition to the use of bituminous paved walks in lieu of concrete. For Item 10, he is
opposed to removing the mechanical screen on the rooftop designed to hide equipment from view
and the potential noise implication for adjacent neighbors. Ms. DiStasio agreed with Mr.
DeLucia’s concern regarding using asphalt in lieu of concrete. Discussion followed.
Regarding Item 8, it was determined that the bid will remain showing bituminous paved walks,
but it was clarified that concrete would be used within 50 of the entrance to the building and an
add-alternate will be included in the bid for concrete replacement.
With regard to Item 10, a lengthy discussion ensued on the potential of noise to affect the
neighbors to the school versus the cost savings. It was determined that the best course of action
would be to accept the change for Item 10 on both reports, continue to design without screening,
and revisit as necessary following submission to Planning & Zoning. Peter Gauthier requested a
report back on the decision of the Planning & Zoning.
Mark Kulos asked for further discussion on Greeneville Report Items 43 & 44. Chairman
Bettencourt clarified that the items had not been approved for deletion by the subcommittee and
the bleachers and scoreboard would remain in the project. Ms. DiStasio inquired if a Kiln would
be included in the schools. DRA noted there would not. Discussion followed.
Ms. DiStasio discussed Item 47 - utilizing mulch in lieu of a rubberized play surface. She
expressed concern that students will get hurt if the mulch isn’t maintained properly and was
concerned with the cost and time to maintain. CSG committed to incorporating rubberized
surfaces in high wear areas. The committee agreed to proceed with the use of mulch otherwise.
Mark Kulos noted the School Board may need to add a line item for mulch to its budget.
Ms. DiStasio also asked about the installation of sign frames within the schools. It was confirmed
that these accessories will be installed as part of the building construction.
Discussion took place on Item 27 on both reports regarding decreasing the number of boilers
from three to two. Mr. Brown confirmed that three boilers is optimal, however two is acceptable.
President Pro Ten DeLucia questioned the requirement for the number of boilers based on the
larger size of the new Stanton School building. In response, it was explained that the new boilers
will be larger and much more efficient that the boilers current in use at Stanton. Discussion
followed. Additional information on Item 27 is required.
Clarification was requested on the placement of security keycard locks, Item 25. Chairman
Bettencourt clarified that keycard access was required on exterior access doors and certain crucial
areas inside the facilities, such as the IT computer room. Discussion followed. Final specs will be
done through FF&E. Other discussion will take place in future security meetings.
Item 9 - Sunscreens. A brief discussion took place on this item, further discussion is required.
Item 3 - Fixed windows. This change was accepted for enhanced security and avoided
maintenance. The use of privacy screens on classroom doors was discussed, however this feature
is typically no longer used for security/safety reasons. Further discussion was held on interior
door security features.
Ms. DiStasio asked about other decorative signage, however this topic will be discussed during
the construction phase.
Bill Hull motioned to approve the sub-committee reports for both the Greeneville and Stanton
School Projects with the changes listed. Alderwoman Gould seconded the motion. Voted in
favor: Peter Gauthier, Chairman Bettencourt, President Pro Ten DeLucia, Mark Kulos, Christine
DiStasio, Gregory Ballassi, Alderwoman Gould, William Hull. Voted in opposition: None. The
motion was approved unanimously.
Greeneville cost savings approved by the Committee totaled $2,931,410. Additional information is
needed to address $1,312,775 of potential additional savings.
Stanton cost savings approved by the Committee totaled $4,101,526. Additional information is
needed to address $1,651,857 of potential additional savings.
4. Cost containment suggestion to accelerate Uncas School Project. Submit grant
application for Uncas and Moriarty Project. Discussion and possible action, adding
only grant for Uncas to current CSG scope.
Chairman Bettencourt explained the reasoning for submitting the Uncas grant application at the
same time as the Moriarty application, which would be to accelerate the application as a cost
savings measure (prevent cost escalation by accelerating the project.) He discussed this
previously with CSG, who submitted a quote to complete the grant application only for $45,000.
The intent would be to submit an RFP for a project manager. Discussion followed.
Bill Hull motioned to authorize CSG to complete the Grant Application for Uncas School for
$45,000. Chairwoman Gould seconded the Motion. Discussion Followed. Voted in Favor:
Peter Gauthier, Chairman Bettencourt, President Pro Ten DeLucia, Mark Kulos, Christine
DiStasio, Gregory Ballassi, Alderwoman Gould, William Hull. Voted in opposition: None. The
motion was approved.
Bob Castronova discussed the need for a contract amendment to allow CSG to complete the grant
application and was asked by Chairman Bettencourt to amend the contract as necessary.
5. Adjournment: Chairwoman Gould made a motion to adjourn the meeting. Mark Kudos
seconded the motion. Voted in Favor: Peter Gauthier, Chairman Bettencourt, President Pro Ten
DeLucia, Mark Kulos, Christine DiStasio, Gregory Ballassi, Alderwoman Gould, William Hull.
Voted in opposition: None. The motion was approved and the meeting ended at 7:54 PM.
Respectfully Submitted
Jeanne Kurasz
Recording Secretary
Revised - Katherine Rose, Recording Secretary
Greeneville Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Meeting
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
PENDING Proposed windows are as shown reduces construction field
1 Standardize/Optimize Window Layout ($36,640) ($36,640) ($36,640)
systematized. Standard Detailing efficiencies
2 Reduce Glazing by 20% ($72,000) ($72,000) ($72,000) ACCEPT
PENDING Staff / student comfort and health
3 Provide fixed windows in lieu of operable windows ($67,105) ($67,105) ($67,105) no comment
issue.
this was identified to be considered as an
Eliminate waterjet floor cut outs (currently an $80,000 allowance
4 see comments ($40,000) allowance as design progresses, the current
is carried in the SD estimate) carry 40k allowance
budget includes an allowance of $80,000.
PENDING Long-term maintenance /
Abuse resistant drywall in corridors in lieu of ceramic tile (explore
5 ($104,163) ($104,163) ($104,163) durability / cleanability. Major interior no comment
additional materials)
perception impact.
PENDING Duplicate item. Savings for
as shown reduces construction field
6 Simplify ceramic tile wall patterns ($28,655) ($28,655) see item #20 simplification of tile pattern taken in item 20
efficiencies
below.
Eliminate generator and provide batteries/inverters for PENDING Long term maintenance /
7 ($265,527) ($265,527) ($265,527) mobile generator could be utilized
emergency lighting. operational labor / operational costs impact.
Change Concrete Sidewalks (50%) to Bituminous Paved Walks ADD ALT
8 ($230,938) ($230,938) ($230,938) ACCEPT
(w/in 50' of school) (MAKE ADD-ALTERNATE FOR CONCRETE) FOR CONC
PENDING High Performance Building
9 Eliminate Sunshades ($51,800) ($51,800) ($51,800) no comment
Standard (HPBS) component
Eliminate Mechanical Screens or relocate roof top equipment PENDING ACCEPT - Must confirm that RTU screening is
10 ($174,959) ($174,959) ($174,959)
(P&Z approval) P&Z not a planning and zoning requirement
Synthetic rubber floor in gym in lieu of wood floor (long term
11 ($35,422) ($35,422) ($35,422) ACCEPT - Owner preference?
maint. costs) (look into wood grade options)
Utilize HM or FRP doors at exterior in lieu of Alum Storefront
12 ($16,500) ($16,500) ($16,500) ACCEPT
(except main entries)
Reconfigure benches in corridor breakout areas to eliminate
13 ($7,500) ($7,500) ($7,500) ACCEPT
kneewall
Manual operated roller shades in lieu of motorized as stated in
14 ($5,673) ($5,673) ($5,673) ACCEPT
narrative common area & media center (lock down concern)
Bituminous concrete curb in lieu of cast-in-place concrete.
(Except where curbing abuts concrete sidewalk, where integral
15 ($113,170) ($113,170) ($113,170) ACCEPT
concrete walk and curb are required) (DRA) (Look into Precast
Curbs)
Reduce Building SF to 81,600 sf (DRA) - (ongoing efforts to ACCEPT Currently testing how close we can
16 ($352,921) ($352,921) ($352,921)
reduce) get to target
17 Replace TerraSlat with Ground-Face CMU (DRA) see item #36 see # 36
18 Epoxy flooring in lieu of ceramic at single toilet rooms (DRA) ($7,834) ($7,834) ($7,834) ACCEPT
Acrovyn Wall Protection in lieu of ceramic at single toilet rooms
19 ($16,500) ($16,500) ($16,500) ACCEPT
(DRA)
Reduce ceramic corridor wall tile from 4’-3 7/8” to 3’-7 ¼”
20 .Remove one course 4 ¼” x 12 7/8” and adding 1 course of 4 ¼” ($20,412) ($20,412) ($20,412) ACCEPT
x4 ¼” (DRA)
Greeneville Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Meeting
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
21 Sheet Linoleum in lobbies in-lieu of rubber tile (DRA) ($8,680) ($8,680) ($8,680) ACCEPT
22 Reduce Marker /Tackboards by 10% (DRA) ($18,753) ($18,753) ($18,753) ACCEPT
23 Reduce vinyl wall covering by 25% (DRA) ($13,218) ($13,218) ($13,218) ACCEPT
24 Reduce casework by 5% (DRA) ($73,229) ($73,229) ($73,229) ACCEPT
CARD READERS - Ed Spec - calls for all interior and exterior doors;
25 SD outline Spec calls for all exterior and IT Closet doors interior. TBD TBD
Reduce exterior doors by 5% (DRA) (additional investigation)
At single-story roof areas 4’x4’ x16” footings with 5-#6 each way
26 ($51,230) ($51,230) ($51,230) ACCEPT
(DRA)
(2) Boilers in-lieu of (3). Boilers shall be Thermal Solution
AMP2000. Removing third boiler also eliminates the boiler pump, ACCEPT (Mechanical Engineer
27 ($77,000) ($77,000) ($77,000)
piping, accessories, and electrical connections associated with it. Recommendation)
(DRA)
28 Eliminate radiant floor heating for K and PK classrooms. (DRA) ($194,100) ($194,100) ($194,100) ACCEPT - Confirm with Owner
ACCEPT (Plumbing Engineer
29 Provide PVC for underslab drainage in-lieu of cast iron (DRA) ($37,500) ($37,500) ($37,500)
Recommendation)
Scupper overflows (where possible) in-lieu of hard-piped
30 ($112,500) ($112,500) ($112,500) ACCEPT
secondary drains (DRA)
Remove large format A/V system from the Gym Cafeteria PENDING Must review with Owner. School
31 ($51,800) ($51,800) ($51,800) no comment
(platform and presentation space is in the Cafeteria Gym). (DRA) operational capacity
PENDING Must review with Owner. School
32 Remove basic theatrical lighting system (DRA) ($50,000) ($50,000) ($50,000) no comment
operational capacity
Aluminum secondary feeders from transformer to main
33 ($10,000) ($10,000) ($10,000) ACCEPT
switchgear (DRA)
PENDING Long term upkeep and
34 Fabric Ductwork in Gymnasium in-lieu of metal (DRA) ($37,500) ($37,500) ($37,500) no comment
maintenance.
35 Remove large fans in Gym (DRA) ($43,500) ($43,500) ($43,500) ACCEPT
36 Use brick in lieu of ACM and Terra-Cotta ($358,292) ($358,292) ($358,292) ACCEPT
PENDING DRA strongly recommends use at
further discussions with manufactures once
37 Provide admixture in lieu of topical moisture mitigation system ($160,000) ($160,000) ($160,000) SOG conditions to mitigate flooring adhesive
material is selected
failures
38 Reduce curtain wall at stair towers by 50% ($97,850) ($97,850) ($97,850) ACCEPT
this was identified as not needed and
Eliminate ceramic tile within stair towers (this was reduction was
39 see comments removed during the SD reconciliation process
captured in SD estimate)
and is currently reflected in current budget.
40 Eliminate ceramic tile on CMU out side of stair tower ($6,300) ($6,300) ($6,300) ACCEPT
PENDING Not practical to apply in corridor
41 reduce metal lockers by 25% and provide cubbies ($3,276) ($3,276) ($3,276) no comment
application. low value
PENDING Duplicate item. Value taken in item
42 plastic laminated window sill in lieu of hardwood sills ($12,300) ($12,300) ($12,300) no comment
60 below.
REVIEW Must review for program
43 Eliminate bleacher system in Gym (possible FF&E) ($51,800) ($51,800) ($51,800)
compliance with Owner
REVIEW Must review for program compliance
44 Eliminate scoreboard in Gym ($10,360) ($10,360) ($10,360)
with Owner
45 utilize painted steel bollards in lieu of stainless steel ($64,336) ($64,336) ($64,336) ACCEPT
Use standard ceiling tile and grid in lieu of Linear metal ceilings REVIEW Recommend some use -- will look to
46 ($69,941) ($69,941) ($69,941)
(review options with DD set) reduce amount
Greeneville Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Meeting
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
47 utilize mulch in lieu of rubberized play surface ($369,778) ($369,778) ($369,778) ACCEPT
Millwork in class rooms to include base cabinets and upper
48 ($495,000) ($495,000) ($495,000) ACCEPT - must assess impact on FF+E budget
cabinets only, all remaining items to be FF&E
49 Revise building massing to eliminate multiple roof transitions TBD similar to item #16
50 Investigate building layout to relocate gym to lower level. TBD similar to item #16
Eliminate Site Furnishings (Benches, Trash Receptacles & Bike
51 Racks) (keep bike racks if required reduce or eliminate benches ($38,125) ($38,125) ($38,125) ACCEPT
and receptical)
Eliminate the Curbing at the Playground Fencing (per Details on
52 Drawing SD-3) investigate other options related to changing ($35,016) ($35,016) ($35,016) ACCEPT
surface)
53 Change Rubberized Play Areas to Standard Duty Paving ($340,585) ($340,585) ($340,585) ACCEPT
During SD Reconciliation and discussions with
Retaining walls to consist of 30% concrete walls, 30% versa-Lok Civil Engineer the percentages of wall types
54 and 40% Open Cut ledge (this has been incorporated in to the see comments based on preliminary soils investigations was
reconciled SD Estimate. agreed upon and cost are represented in the
budget estimate
REVIEW Must review for program compliance
55 Delete divider curtain in Gym ($20,720) ($20,720) ($20,720)
with Owner
56 Delete Rock climbing wall in Gym ($15,540) ($15,540) ($15,540) ACCEPT
Delete transom panels above all interior doors (DRA to follow
57 ($15,750) ($15,750) ($15,750) ACCEPT
through during DD)
58 Provide solid surface window sills in lieu of hardwood sills $8,200 $8,200 $8,200 ACCEPT
59
SUBTOTAL COST MANAGEMENT SAVINGS: ($4,543,498) ($3,674,732) ($868,766) ($2,931,410) ($310,658) ($1,312,775) $0
## Design & Estimating Contingency ($454,350) ($367,473) ($86,877) ($293,141) ($31,066) ($131,278) 0
## Escalation ($199,914) ($161,688) ($38,226) ($128,982) ($13,669) ($57,762) 0
## General Liability Insurance ($36,384) ($29,427) ($6,957) ($23,475) ($2,488) ($10,513) 0
## State Education Fund ($1,361) ($1,101) ($260) ($878) ($93) ($393) 0
## CM Payment & Performance Bond ($34,868) ($28,201) ($6,667) ($22,497) ($2,384) ($10,075) 0
## Construction Contingency ($158,111) ($127,879) ($30,233) ($102,011) ($10,811) ($45,684) 0
## CM Fee ($65,142) ($52,686) ($12,456) ($42,029) ($4,454) ($18,822) 0
TOTAL COST MANAGEMENT SAVINGS: ($5,493,629) ($4,443,188) ($1,050,441) ($3,544,423) ($375,622) ($1,587,301) $0
Stanton Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Mtg.
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
PENDING Proposed windows are as shown reduces construction field
1 Standardize/Optimize Window Layout ($44,910) ($44,910) ($44,910)
systematized. Standard Detailing efficiencies
2 Reduce Glazing by 20% ($67,760) ($67,760) ($67,760) ACCEPT
PENDING Staff / student comfort and health
3 Provide fixed windows in lieu of operable windows ($93,551) ($93,551) ($93,551) no comment
issue.
this was identified to be considered as an
Eliminate waterjet floor cut outs (currently an $80,000 allowance is ACCEPT In reconciled schematic design
see comments ------------ ($40,000) allowance as design progresses, the current
carried in the SD estimate) carry 40k allowance estimates
budget includes an allowance of $80,000.
4
PENDING Long-term maintenance /
Abuse resistant drywall in corridors in lieu of ceramic tile (explore
5 ($114,713) ($114,713) ($114,713) durability / cleanability. Major interior no comment
additional materials)
perception impact.
PENDING Duplicate item. Savings for
as shown reduces construction field
6 Simplify ceramic tile wall patterns ($22,133) ($22,133) see item #20 simplification of tile pattern taken in item 20
efficiencies
below.
PENDING (Electrical Engineer) Long term
Eliminate generator and provide batteries/inverters for emergency
7 ($265,527) ($265,527) ($265,527) maintenance / operational labor / mobile generator could be utilized
lighting.
operational costs impact.
Change Concrete Sidewalks (50%) to Bituminous Paved Walks (w/in 50' ADD ALT
8 ($438,464) ($438,464) ($438,464) ACCEPT
of school) (MAKE ADD-ALTERNATE FOR CONCRETE) FOR CONC
PENDING High Performance Building
9 Eliminate Sunshades ($46,200) ($46,200) ($46,200) no comment
Standard (HPBS) component
Eliminate Mechanical Screens or relocate roof top equipment (P&Z PENDING ACCEPT - Must confirm that RTU screening is
10 ($142,999) ($142,999) ($142,999)
approval) P&Z not a planning and zoning requirement
Synthetic rubber floor in gym in lieu of wood floor (long term maint.
11 ($35,422) ($35,422) ($35,422) ACCEPT - Owner preference?
costs) (look into wood grade options)
Utilize HM or FRP doors at exterior in lieu of Alum Storefront (except
12 ($15,000) ($15,000) ($15,000) ACCEPT
main entries)
13 Reconfigure benches in corridor breakout areas to eliminate kneewall ($7,500) ($7,500) ($7,500) ACCEPT
Manual operated roller shades in lieu of motorized as stated in narrative
14 ($5,100) ($5,100) ($5,100) ACCEPT
common area & media center (lock down concern)
Bituminous concrete curb in lieu of cast-in-place concrete. (Except
15 where curbing abuts concrete sidewalk, where integral concrete walk ($167,458) ($167,458) ($167,458) ACCEPT
and curb are required) (DRA) (Look into Precast curbs)
Stanton Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Mtg.
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
ACCEPT Currently testing how close we can
16 Reduce Building SF to 81,600 sf (DRA) - (ongoing efforts to reduce) ($384,242) ($384,242) ($384,242)
get to target
17 Replace TerraSlat with Ground-Face CMU (DRA) see # 39
18 Epoxy flooring in lieu of ceramic at single toilet rooms (DRA) ($7,761) ($7,761) ($7,761) ACCEPT
19 Acrovyn Wall Protection in lieu of ceramic at single toilet rooms (DRA) ($16,500) ($16,500) ($16,500) ACCEPT
Reduce ceramic corridor wall tile from 4’-3 7/8” to 3’-7 ¼” .Remove one
20 ($21,273) ($21,273) ($21,273) ACCEPT
course 4 ¼” x 12 7/8” and adding 1 course of 4 ¼” x4 ¼” (DRA)
21 Sheet Linoleum in lobbies in-lieu of rubber tile (DRA) ($21,672) ($21,672) ($21,672) ACCEPT
22 Reduce Marker /Tackboards by 10% (DRA) ($21,549) ($21,549) ($21,549) ACCEPT
23 Reduce vinyl wall covering by 25% (DRA) ($22,500) ($22,500) ($22,500) ACCEPT
24 Reduce casework by 5% (DRA) ($74,481) ($74,481) ($74,481) ACCEPT
CARD READERS - Ed Spec - calls for all interior and exterior doors; SD
25 outline Spec calls for all exterior and IT Closet doors interior. Reduce TBD TBD
exterior doors by 5% (DRA) (additional investigation)
26 At single-story roof areas 4’x4’ x16” footings with 5-#6 each way (DRA) ($59,026) ($59,026) ($59,026) ACCEPT
(2) Boilers in-lieu of (3). Boilers shall be Thermal Solution AMP2000.
ACCEPT (Mechanical Engineer
27 Removing third boiler also eliminates the boiler pump, piping, ($77,000) ($77,000) ($77,000)
Recommendation)
accessories, and electrical connections associated with it. (DRA)
28 Eliminate radiant floor heating for K and PK classrooms. (DRA) ($194,100) ($194,100) ($194,100) ACCEPT - Confirm with Owner
ACCEPT (Plumbing Engineer
29 Provide PVC for underslab drainage in-lieu of cast iron (DRA) ($37,500) ($37,500) ($37,500)
Recommendation)
Scupper overflows (where possible) in-lieu of hard-piped secondary
30 ($112,500) ($112,500) ($112,500) ACCEPT
drains (DRA)
Remove large format A/V system from the Gym Cafeteria (platform and PENDING Must review with Owner. School
31 ($51,800) ($51,800) ($51,800) no comment
presentation space is in the Cafeteria Gym). (DRA) operational capacity
PENDING Must review with Owner. School
32 Remove basic theatrical lighting system (DRA) ($50,000) ($50,000) ($50,000) no comment
operational capacity
Aluminum secondary feeders from transformer to main switchgear
33 ($10,000) ($10,000) ($10,000) ACCEPT
(DRA)
PENDING Long term upkeep and
34 Fabric Ductwork in Gymnasium in-lieu of metal (DRA) ($37,500) ($37,500) ($37,500) no comment
maintenance.
35 Remove large fans in Gym (DRA) ($43,500) ($43,500) ($43,500) ACCEPT
Stanton Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Mtg.
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
Reduce bus lane to 30' in-lieu of 35' wide. (NOTE: The width was set at
36 35' to allow curb side/parallel parking for additional parking for overflow ($23,850) ($23,850) ($23,850) ACCEPT
events) (DRA) (review with fire marshall
37 Entirety of Southmost Elevations in Split-Faced CMU (DRA) ($138,146) ($138,146) ($138,146) ACCEPT
Inverse the horizontal slat to vertical slat percentages from 14%
38 horizontal slat to 86% horizontal slat; 86% vertical slat to 14% vertical No Change
slat. (DRA)
ACCEPT - Consider keeping limited ACM at
39 Use brick in lieu of ACM and Terra-Cotta ($285,939) ($285,939) ($285,939)
entries
Stanton Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Mtg.
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
PENDING DRA strongly recommends use at
further discussions with manufactures once
40 Provide admixture in lieu of topical moisture mitigation system ($201,600) ($201,600) ($201,600) SOG conditions to mitigate flooring adhesive
material is selected
failures
41 Reduce curtain wall at stair towers by 50% ($39,300) ($39,300) ($39,300) ACCEPT
this was identified as not needed and
Eliminate ceramic tile within stair towers (this was reduction was removed during the SD reconciliation
42 see comments
captured in SD estimate) process and is currently reflected in current
budget.
43 Eliminate ceramic tile on CMU. ($15,792) ($15,792) ($15,792) ACCEPT
PENDING Not practical to apply in corridor
44 reduce metal lockers by 25% and provide cubbies ($3,744) ($3,744) ($3,744) no comment
application. low value
PENDING Duplicate item. Value taken in
45 plastic laminated window sill in lieu of hardwood sills ($13,530) ($13,530) ($13,530) no comment
item 60 below.
REVIEW Must review for program
46 Eliminate bleacher system in Gym (possible FF&E) ($51,800) ($51,800) ($51,800)
compliance with Owner
REVIEW Must review for program
47 Eliminate scoreboard in Gym ($10,360) ($10,360) ($10,360)
compliance with Owner
48 utilize painted steel bollards in lieu of stainless steel ($123,077) ($123,077) ($123,077) ACCEPT
Use standard ceiling tile and grid in lieu of Linear metal ceilings (review REVIEW Recommend some use -- will look to
49 ($54,192) ($54,192) ($54,192)
options with DD set) reduce amount
50 utilize mulch in lieu of rubberized play surface ($421,519) ($421,519) ($421,519) ACCEPT
Millwork in class rooms to include base cabinets and upper cabinets only ACCEPT - must assess impact on FF+E
51 ($496,451) ($496,451) ($496,451)
all remaining items to be FF&E budget
52 Revise building massing to eliminate multiple roof transitions TBD similar to item #16
Relocate students to allow construction to be completed in one phase safety, construction efficiencies and reduced
53 ($632,560) ($632,560) TBD PENDING Must review options with Owner
and reduces overall schedule. schedule
Eliminate Site Furnishings (Benches, Trash Receptacles & Bike Racks)
54 ($38,125) ($38,125) ($38,125) ACCEPT
(keep bike racks if required reduce or eliminate benches and receptical)
Eliminate the Curbing at the Playground Fencing (per Details on Drawing
55 ($35,770) ($35,770) ($35,770) ACCEPT
SD-3) investigate other options related to changing surface)
56 Change Rubberized Play Areas to Standard Duty Paving ($388,241) ($388,241) ($388,241) ACCEPT
REVIEW Must review for program
57 Delete divider curtain in Gym ($20,720) ($20,720) ($20,720)
compliance with Owner
58 Delete Rock climbing wall in Gym ($15,540) ($15,540) ($15,540) ACCEPT
Delete transom panels above all interior doors (DRA to follow through
59 ($16,100) ($16,100) ($16,100) ACCEPT
during DD)
Stanton Elementary School
COST MANAGEMENT LOG
3/19/2024 (Updated 3/27 and 3/28) Reviewed by Sub-Committee 03/27/24 - REV 03/28/24 BC Mtg.
PROPOSED VALUE AND RECOMMENDATION COMMITTEE RECOMMENDATION TEAM COMMENTS
ADDITIONAL
Item #
Estimated w/o POSSIBLE
Description Recommended Pending APPROVE REJECT DISCUSSION DRA Downes
Markups ALTERNATE
NEEDED/ P&Z
60 Provide solid surface window sills in lieu of hardwood sills $9,020 $9,020 $9,020 ACCEPT
61
SUBTOTAL COST MANAGEMENT SAVINGS: ($5,726,977) ($4,149,209) ($1,577,768) ($3,392,162) ($353,956) ($1,366,166) $0
## Design & Estimating Contingency ($572,698) ($414,921) ($157,777) ($339,216) ($35,396) ($136,617) 0
## Escalation ($251,987) ($182,565) ($69,422) ($149,255) ($15,574) ($60,111) 0
## General Liability Insurance ($45,862) ($33,227) ($12,635) ($27,164) ($2,834) ($10,940) 0
## State Education Fund ($1,715) ($1,243) ($473) ($1,016) ($106) ($409) 0
## CM Payment & Performance Bond ($43,951) ($31,843) ($12,108) ($26,033) ($2,716) ($10,484) 0
## Construction Contingency ($199,296) ($144,390) ($54,905) ($118,045) ($12,317) ($47,542) 0
## CM Fee ($82,110) ($59,489) ($22,621) ($48,635) ($5,075) ($19,587) 0
TOTAL COST MANAGEMENT SAVINGS: ($6,924,595) ($5,016,886) ($1,907,709) ($4,101,526) ($427,975) ($1,651,857) $0
Agenda
City of Norwich
School Building Committee (2020)
Special Meeting
Thursday, March 28, 2024 at 6:30pm
Held Virtually via Zoom
1. Call to order: Determination of a quorum
2. Receive sub-committee report and recommendations on cost management for
the Greeneville and Stanton School Projects.
3. Discussion and action on Sub-committee’s recommendation on cost containment
for Greeneville and Stanton School Projects.
4. Cost containment suggestion to accelerate Uncas School Project.
Submit grant application for Uncas with Moriarty project.
Discussion and possible action, adding only grant for Uncas to current CSG
scope.
5. Adjournment
Join Zoom Meeting
https://us02web.zoom.us/j/81740985514
Meeting ID: 817 4098 5514
One tap mobile
+13092053325,,81740985514# US
Dial by your location
+1 646 876 9923 US
Get email alerts for Norwich
A daily email when new agendas and minutes are posted.