School Building Committee (2020)
Regular MeetingNorwich, CT · February 25, 2025
Minutes
School Building Committee (2020)
Regular Meeting
City Hall, R00m 335
100 Broadway, Norwich, CT
And via ZOOM
Tuesday February, 2025
6:30 PM
Committee Members Present: Chairman Mark Bettencourt, President Pro Tem Joe DeLucia,
Mark Kulos, Cindy Beauregard, Christine DiStasio (ZOOM), William Hull, Gregory Ballassi and Sheila
Hayes.
Committee Members Absent: Alderwoman Stacy Gould, Peter Gauthier and Gregory Carabine.
Ex-Officio Members Present: Mayor Peter Nystrom and Assistant Superintendent Susan Lessard.
Consultants Present: Bob Sierpinski (ZOOM), Bob Harris (ZOOM), Matthew Brown (ZOOM),
Mike Faenza, Tim Smith and Jim Guiliano from CSG, Greg Smolley from DRA, and Jeff Andersom
and Frank Tomcak from Downes Construction.
Citizens Present: None.
I. Call to Order and Quorum: Chairman Mark Bettencourt called the meeting to order at 6:33
PM.
II.Approval of Minutes: William Hull made a motion to approve the January 22, 2025 regular
meeting minutes as written.
Sheila Hayes arrived to the meeting at 6:33PM. Gregory Ballassi seconded the motion. Sheila
Hayes, Cindy Beauregard, Gregory Ballassi, William Hull, President Pro Tem Joe DeLucia and
Chairman Mark Bettencourt voted in favor. Christine DiStasio abstained. The motion passed.
Sheila Hayes made a motion to approve the February 19, 2025 special meeting minutes as
amended. Sheila Hayes, Cindy Beauregard, Gregory Ballassi, William Hull, President Pro Tem
Joe DeLucia and Chairman Mark Bettencourt voted in favor. Christine DiStasio abstained. The
motion passed.
III.Reports: All reports to be submitted in writing for inclusion to the record. SEE ADDENDUM.
IV.Consent Agenda: Invoices to be approved for payment
Stanton
CSG – Invoice #23006-023 - $16,850.45
Downes – Invoice #S010 - $3,694.40
DRA – Invoice #23012.00 #16 - $7,466.69
IES – Invoice #20021 - $789.75
Greeneville
CSG – Invoice #23005-023 - $17,286.38
Downes – Invoice #G010 - $3,694.40
DRA – Invoice #23013.00 #16 - $19,421.71
IES – Invoice #20020 - $798.00
Uncas
CSG – Invoice #24024-004 - $15,967.07
DRA – Invoice #24005.00 #3 - $274,131.27
Moriarty
CSG – Invoice #23007-010 - $10,220.86
DRA – Invoice #24006.00 #3 - $269,048.66
Sheila Hayes made a motion to accept the consent agenda including
the above invoices. Cindy Beauregard seconded. The chairman called the roll of
members present and all were in favor.
V.Executive session: Interviews for Construction Manager for Uncas and Moriarty
Schools and selection of finalist for interviews. Ex-Officio members, City of
Norwich/BOE staff, owners rep and project architects will be invited to attend at
the pleasure of the committee.
Chairman Mark Bettencourt asked for a motion to remove from the executive session agenda
the call to select a finalist for interviews. Sheila Hayes made the motion. William Hull
seconded. The chairman called the roll of members present and all were in favor.
Sheila Hayes made a motion to enter executive session at 6:38 PM for the purpose of holding
Interviews for Construction Manager for Uncas and Moriarty Schools, and that Ex-Officio
members, City of Norwich/BOE staff, owners rep and project architects be invited to attend at
the pleasure of the committee. William Hull seconded. The chairman called the roll of
members present and all were in favor.
The executive session ended at 9:33 PM and no votes were taken during that time.
VI.Discussion and possible action on selection of CM for Uncas and Moriarty school
projects.
William Hull made a motion that the committee hire O&G Industries to be the construction
manager for the Uncas and Moriarty Elementary School projects. Mark Kulos seconded. The
chairman called the roll of members present and all were in favor.
VII.Adjournment: William Hull made a motion to adjourn at 9:35 PM. Gregory Ballassi seconded.
The chairman called the roll of members present and all were in favor. The motion passed
unanimously.
Respectfully Submitted, Katherine Rose
Monthly Project Update
John B. Stanton Elementary School Committee Project Project Current
386 New London Turnpike, Norwich, CT Chairman Start Date End Date Project Phase
Prepared by: Issue Date: Construction
M. Bettencourt March 2023 August 2027
Michael Faenza 2.20.25 Documents
PROJECT DESCRIPTION CRITICAL PATH MILESTONES
START TARGET ACTUAL
DATE COMPLETION COMPLETION
Design and construction of a New Elementary School on the John B. Stanton Elementary School Owner’s Representative Contract
3.6.23 N/A 3.6.23
site. The existing building will be demolished following the construction of the new School. Award
City Letter to State regarding Grant
3.8.23 N/A 3.8.23
Amounts
ACCOMPLISHMENTS (PAST 30 DAYS)
Norwich Projects added to state
1. State Payment Request #7 has been submitted. Currently, we are awaiting payment and bonding package via Special 6.8.23 N/A 6.8.23
approval to begin the next request. Legislation at 80% reimbursement
Grant Application Submission 3.6.23 10.1.23 9.15.23
2. The State approved our PCR submission on 1/28/25. This approval has allowed us to go
out to bid for Contractor pricing. At this time the project has been advertised by Downes, Architect Contract Award N/A 7.24.23
with walkthroughs completed for both project sites on 2/13/25. Notification from OGA requiring
1.5.24 1.12.24 2.2.24
additional information
SD Drawing Package Complete 7.24.23 1.31.24 1.31.24
UPCOMING ACTIVITIES (NEXT 30 DAYS)
SD Estimate 1.31.24 2.27.24 3.18.24
1. Project bids are due on March 6, 2025 at City Hall. Bid will be received by the Purchasing
Commissioning Agent RFP 3.26.24 4.17.24 4.17.24
Department / Downes and publicly opened via a Zoom conference call for bidders to call
into to hear the results. DD Drawing Package 3.19.24 6.6.24 6.6.24
2. Following the opening of the bids, Downes Construction will conduct scope reviews and DD Phase Estimate 6.6.24 7.12.24 7.12.24
assemble a Guaranteed Maximum Price (GMP) for submission to the Building Committee Inland Wetland Review 6.6.24 6.6.24 6.6.24
and City for Approval.
June Special CCP Meeting 6.26.24 6.26.24 6.26.24
Construction Document Package 6.6.24 10.4.24 10.4.24
ATTENTION POINTS
Construction Document Estimate
10.4.24 11.12.24 11.12.24
Reconciliation
PCR Meeting 11.26.24 11.26.24 11.26.24
Approval to Bid 1.28.25 1.28.25
Monthly Project Update
John B. Stanton Elementary School
386 New London Turnpike, Norwich, CT
Prepared by: Issue Date: Budget Update
Michael Faenza 2.20.25
Monthly Project Update
Greeneville Elementary School Committee Project Project Current
165 Golden Street, Norwich, CT Chairman Start Date End Date Project Phase
Prepared by: Issue Date: Construction
M. Bettencourt March 2023 August 2026
Michael Faenza 2.20.25 Documents
PROJECT DESCRIPTION START TARGET ACTUAL
CRITICAL PATH MILESTONES
DATE COMPLETION COMPLETION
Design and construction of a New Elementary School on the former site of the Greeneville
Owner’s Representative Contract
Elementary School. 3.6.23 N/A 3.6.23
Award
City Letter to State regarding Grant
ACCOMPLISHMENTS (PAST 30 DAYS) 3.8.23 N/A 3.8.23
Amounts
3. State Payment Request #7 has been submitted. Currently, we are awaiting payment and Norwich Projects added to state
bonding package via Special 6.8.23 N/A 6.8.23
approval to begin the next request.
Legislation at 80% reimbursement
4. The State approved our PCR submission on 1/28/25. This approval has allowed us to go Grant Application Submission 3.6.23 10.1.23 9.15.23
out to bid for Contractor pricing. At this time the project has been advertised by Downes,
Architect Contract Award N/A 7.24.23
with walkthroughs completed for both project sites on 2/13/25.
Notification from OGA requiring
1.5.24 1.12.24 2.2.24
additional information
UPCOMING ACTIVITIES (NEXT 30 DAYS) SD Drawing Package Complete 7.24.23 1.31.24 1.31.24
3. Project bids are due on March 6, 2025 at City Hall. Bids will be received by the Purchasing SD Estimate 1.31.24 2.27.24 3.18.24
Department / Downes and publicly opened via a Zoom conference call for bidders to call Commissioning Agent RFP 3.26.24 4.17.24 4.17.24
into to hear the results.
DD Drawing Package 3.19.24 6.6.24 6.6.24
4. Following the opening of the bids, Downes Construction will conduct scope reviews and
DD Phase Estimate 6.6.24 7.12.24 7.12.24
assemble a Guaranteed Maximum Price (GMP) for submission to the Building Committee
and City for Approval. Inland Wetland Review 6.6.24 6.6.24 6.6.24
June Special CCP Meeting 6.26.24 6.26.24 6.26.24
ATTENTION POINTS Construction Document Package 6.6.24 10.4.24 10.4.24
Construction Document Estimate
10.4.24 11.12.24 11.12.24
Reconciliation
PCR Meeting 12.2.24 12.2.24 12.2.24
PCR Meeting Follow-up 12.4.24 12.4.24 12.4.24
Approval to Bid 1.28.25 1.28.25
Monthly Project Update
Greeneville Elementary School
165 Golden Street, Norwich, CT
Prepared by: Issue Date: Budget Update
Michael Faenza 2.20.25
Monthly Project Update
John M. Moriarty Elementary School Committee Project Project Current
20 Lawler Lane, Norwich, CT Chairman Start Date End Date Project Phase
Prepared by: Issue Date: Schematic
M. Bettencourt March 2024 TBD
Michael Faenza 2.20.25 Design
PROJECT DESCRIPTION START TARGET ACTUAL
CRITICAL PATH MILESTONES
DATE COMPLETION COMPLETION
Design and construction of a New Elementary School on the John M. Moriarty Elementary School
site. The existing building will be demolished following the construction of the new School. Schematic Design Phase 12.1.24 1.30.24
Design Development Phase 2.1.25 6.5.25
ACCOMPLISHMENTS (PAST 30 DAYS)
CM Proposals Due 2.6.25 2.6.25 2.6.25
1. Working group meetings have been completed over the past few weeks with District
BC Review of Submitted Proposals 2.6.25 2.18.25 2.18.25
Administration and School Staff as we look to complete the schematic design phase.
Special Meeting to Review
2.19.25 2.19.25 2.19.25
2. CM Responses have been received. Building committee members evaluation sheets have Proposals & Establish Shortlist
been tabulated, and a special Building Committee has been held to review the proposals Interviews of Selected Firms 2.25.25 2.25.25
and establish a shortlist. Interviews will be conducted at the next regular building
committee meeting.
UPCOMING ACTIVITIES (NEXT 30 DAYS)
1. Working group meetings will continue for this project.
2. The project is currently in the Design Development Phase.
ATTENTION POINTS
Monthly Project Update
Uncas Elementary School Committee Project Project Current
280 Elizabeth Street Extension, Norwich, CT Chairman Start Date End Date Project Phase
Prepared by: Issue Date: Schematic
M. Bettencourt March 2024 TBD
Michael Faenza 2.20.25 Design
PROJECT DESCRIPTION START TARGET ACTUAL
CRITICAL PATH MILESTONES
DATE COMPLETION COMPLETION
Design and construction of a New Elementary School on the Uncas Elementary School site. The
existing building will be demolished following the construction of the new School. Schematic Design Phase 12.1.24 1.30.24
Design Development Phase 2.1.25 6.5.25
ACCOMPLISHMENTS (PAST 30 DAYS)
CM Proposals Due 2.6.25 2.6.25 2.6.25
1. Working group meetings have been completed over the past few weeks with District
BC Review of Submitted Proposals 2.6.25 2.18.25 2.18.25
Administration and School Staff as we look to complete the schematic design phase.
Special Meeting to Review
2. CM Responses have been received. Building committee members’ evaluation sheets have Proposals & Establish Shortlist – 2.19.25 2.19.25 2.19.25
been tabulated, and a special Building Committee has been held to review the proposals FOR DISCUSSION
and establish a shortlist. Interviews will be conducted at the next regular building Interviews of Selected Firms 2.25.25 2.25.25
committee meeting.
UPCOMING ACTIVITIES (NEXT 30 DAYS)
1. Working group meetings will continue for this project.
2. The project is currently in the Design Development Phase.
ATTENTION POINTS
Monthly Project Update
Teacher’s Middle School Committee Project Project Current
15 Teachers Drive, Norwich, CT Chairman Start Date End Date Project Phase
Prepared by: Issue Date: Pre-Grant
M. Bettencourt February 2025 TBD
Michael Faenza 2.20.25 Application
PROJECT DESCRIPTION START TARGET ACTUAL
CRITICAL PATH MILESTONES
DATE COMPLETION COMPLETION
Design and construction of a New or Renovated Middle School on the Teachers Middle School site.
The existing building will either be demolished following the construction of the new School or CSG Proposal Issued 1/22/25
renovated. Develop Education Specifications 2/1/25 4/30/25
Develop Grant Application Estimate 5/1/25 6/15/25
ACCOMPLISHMENTS (PAST 30 DAYS)
Develop Grant Application 5/1/25 6/29/25
1. A project kick-off meeting is being scheduled. We are currently targeting the week ending
2/28/25. Submit Grant Application 6/30/25 6/30/25
UPCOMING ACTIVITIES (NEXT 30 DAYS)
2. Continue assembly of items needed for project Grant Application.
ATTENTION POINTS
Monthly Project Update
Samuel Huntington Central Office Conversion Committee Project Project Current
80 West Town Street, Norwich, CT Chairman Start Date End Date Project Phase
Prepared by: Issue Date: Pre-Grant
M. Bettencourt February 2025 TBD
Michael Faenza 2.20.25 Application
PROJECT DESCRIPTION START TARGET ACTUAL
CRITICAL PATH MILESTONES
DATE COMPLETION COMPLETION
Design and construction of the Samuel Huntington Elementary School to create a new Central Office
and Adult Education Facility. CSG Proposal Issued 1/22/25
Develop Education Specifications 2/1/25 4/30/25
ACCOMPLISHMENTS (PAST 30 DAYS) Conceptual Design Proposal
2/19/25 2/19/25
1. A project kick-off meeting is being scheduled. We are currently targeting the week ending Submission and Review
2/28/25. Conceptual Design Process 3/1/25 4/15/25
2. A proposal for a Facilities Study / Concept Design was provided by DRA for review and Develop Grant Application Estimate 5/1/25 6/15/25
approval. This was reviewed and approved at the 2/19/25 Special Building Committee Develop Grant Application 5/1/25 6/29/25
Meeting.
Submit Grant Application 6/30/25 6/30/25
UPCOMING ACTIVITIES (NEXT 30 DAYS)
3. Continue assembly of items needed for project Grant Application.
ATTENTION POINTS
February 25, 2025
City of Norwich
Stanton & Greeneville Schools
SPN #104-0118N & 104-0119N
Subject: DCC Building Committee Agenda
A. Pre-construction Schedule Update
1. Work Completed
Bid Advertisement
Invitation To Bid
Pre-bid Walkthrough
Addendum 1 Issued
2. Work in Progress
Finalize Addendums
Finalize PLA
Address Balance of Pre-bid RFI’s
Adjust Bid Due Dates
3. Work to Start
Bid Tabulation
Bid Opening
Prepare Scope Review Agendas
GMP Prep
4. Other Critical Items/Milestones
Building Permit
Conformance Set of Drawings
Agenda
City of Norwich
School Building Committee (2020)
Regular Meeting
Tuesday, February 25, 2025 at
6:30pm City Hall, Room 335 and
virtually via Zoom (see below)
1. Call to order: Determination of a quorum
2. Approval of Minutes- 1/22, 2/19
3. Reports: All reports to be submitted in writing for inclusion to the record.
4. Consent Agenda:
Invoices to be approved for payment:
Stanton
CSG – Invoice #23006-023 - $16,850.45
Downes – Invoice #S010 - $3,694.40
DRA – Invoice #23012.00 #16 - $7,466.69
IES – Invoice #20021 - $789.75
Greeneville
CSG – Invoice #23005-023 - $17,286.38
Downes – Invoice #G010 - $3,694.40
DRA – Invoice #23013.00 #16 - $19,421.71
IES – Invoice #20020 - $798.00
Uncas
CSG – Invoice #24024-004 - $15,967.07
DRA – Invoice #24005.00 #3 - $274,131.27
Moriarty
CSG – Invoice #23007-010 - $10,220.86
DRA – Invoice #24006.00 #3 - $269,048.66
5. Executive session: Interviews for Construction Manager for Uncas and Moriarty
Schools and selection of finalist for interviews. Ex-Officio members, City of
Norwich/BOE staff, owners rep and project architects will be invited to attend at
the pleasure of the committee.
6. Discussion and possible action on selection of CM for Uncas and Moriarty school
projects.
7. Anything else to be brought before the committee.
8. Adjournment
Join Zoom Meeting:
https://us02web.zoom.us/j/82540059779?pwd=OiubK69Chojpk2sg9XqLJa5My7wgeV.1