Nyack Water Board Meeting
Regular MeetingNyack, NY · March 9, 2023
Minutes
March 9, 2023
A regular meeting of the Board of Water Commissioners was held on the
above date at 9 North Broadway, Nyack, NY. The meeting was called to order by
Chairman McDowell at 4:30 PM.
The following were present:
William McDowell Chairman
Michelle Bullock Commissioner
Eileen Colarell Commissioner
John Phillips Commissioner
Elizabeth Turk Commissioner
Barbara Kunar Secretary
Kelvin Smith Acting Superintendent
Jim Roberts H2M architects & engineers
Absent:
Thomas Lynch Superintendent
Upon motion by Commissioner Bullock, second by Commissioner Colarell,
and carried, the Board accepted the minutes of February 9, 2023.
The Cash Flow Statements for February 2023 was presented to the Board
for review.
Schloss & Schloss, PLC submitted their proposal to continue to serve as
legal counsel to the Board. Commencing March 21, 2023 their monthly retainer
will be $1,450.00.
Upon motion by Commissioner Phillips, second by Commissioner
Colarell, and carried, the Board voted to retain Schloss & Schloss as the
Water Department counsel and authorized Chairman McDowell to sign the
agreement.
Torres T Landscaping submitted a proposal for lawn service for the coming
season, April 2022 through November 2022. The cost, which is the same as last
year, is $1,500.00 per month ($12,000.00 season total). Maintenance includes
weekly mowing of 2 sites, string trimming of pathways and walks and blowing all
hard surfaces.
Upon motion by Commissioner Phillips, second by Commissioner Turk,
and carried, the Board voted to accept Torres T Landscaping’s proposal for
lawn maintenance.
H2M architects + engineers projects update:
1. Emergency Water Main Repairs:
• H2M contacted J Fletcher Creamer (JFC) to initiate restarting work
outside the plant. JFC will advise H2M and Nyack Water as to
schedule resumption of repairs.
2. Route 9W Culvert Leak Repair:
• Nyack Water and H2M decided it would be best to isolate the
leak in the 9W culvert to determine where the leak originated.
Environmental Construction completed the project on 3/7/23.
3. Master Planning efforts are ongoing:
• GIS/Modeling
A. Fine tuning the hydraulic model to be an accurate
representation of the water system.
B. On 3/8/23 the GIS team completed a web map of the
distribution system. This will be undergoing a secondary
review to ensure accuracy.
• Asset Management – asset management database is nearly
complete. Next steps include aging the assets and evaluating
their condition.
• Capital Planning – asset condition assessment will be tied to
capital plan. This component along with developing potential rate
cases should be the priority after the water main work in front of
the plant is completed.
4. Plant Operational Assessments:
• Continue to lend support on technical issues.
• Helping trouble shoot demand increases and demand
management.
• H2M in conjunction with the Water Department and Neal Systems
has been evaluating the effluent flow being pumped into the
system.
5. Watermain Installation Phase A:
• GCE has completed all main installation.
• GCE will complete removal of old Fire Hydrants and perform any
necessary trench maintenance in the next two weeks.
• H2M is realigning roadways to be included in Phase B and C of the
watermain project and completing design for submission and
approval by RCDOH. H2M anticipates bidding Phase B in June/July
2023 with a construction start of Fall 2023.
6. Plant Upgrade for PFAS removal:
• RCDOH provided review comment in collaboration with NYSDOH.
H2M is addressing all comments and concerns of both regulatory
agencies and will proceed to a 90% submission thereafter.
• H2M has obtained NYSDEC wetland approval pending notice of
the project in the Town of Clarkstown local newspaper. The
NYSDEC will then provide an approval after the affidavit is
received.
• Design team and subconsultants continue on schedule.
7. Lead Service Lines:
• RCDOH is holding periodic check-ins on the status of the
inventory investigation. H2M will assist the Water Department as
needed.
8. Emergency Response Plan, Cybersecurity and Vulnerability Assessment
• The Health Department has reached out to remind the Water
Department that an updated ERP an VA is due soon. H2M will
prepare these reports on behalf of the Water Department.
Our 2016 Jeep Patriot has been totaled by the Insurance Company. The
market/settlement value is $13,726.92. The original title, which the Insurance
Company needs, is missing. Secretary Kunar will request a duplicate title from
DMV.
Upon motion by Commissioner Colarell, second by Commissioner
Bullock, and carried, the Board voted to release the vehicle and accept
payout from the Insurance Company pending title receipt.
Klaus Wimmer, Regional Manager from Homeland Towers made a brief
presentation to the Board regarding the proposed cell tower on the Water Plant
property. Following the presentation, he answered questions as they arose.
The 2023-2024 Budget was not ready for presentation.
Superintendent’s Report:
Acting Superintendent Smith reported on the following items:
1. Route 9W/Catherine Street Culvert Leak – Environmental Construction
Company installed two (2) new valves. One valve is north of the culvert
and one valve is south of the culvert.
2. Leak – Route 9W/Catherine Street – While working in preparation for the
culvert repair, what was assumed to be another leak flooded the fire
house on Catherine Street.
• Our foreman contacted Admiral Conservation Services (ACS) for
leak detection. ACS determined the leak to be further south on
Route 9W. It was not in the determined location.
• Ray Jovine Leak Detection was called by Mr. Smith.
• CCE excavated in search of the leak. No leak was found.
• In conclusion, ACS should no longer be contracted for leak
detection. Their charge is astronomical (currently approximately
$4,000 per day) and their detection record is poor.
3. West Nyack Road Break – On February 22, 2023 a leak was discovered In
front of Pizzarena, 726 West Nyack Road. It was determined to be from the
system improvements. GCE was contacted and made the repair.
4. Fire Hydrants – Ordered six (6) new Hydrants from Sigelock. Hydrants
were delivered on March 8, 2023.
At 5:50 PM, upon motion by Commissioner Phillips, second by Commissioner
Bullock, and carried, the Board moved into executive session to discuss personnel
issues. At 5:59 PM upon motion be Commissioner Phillips, second by
Commissioner Bullock, and carried the Board moved out of executive session.
Our next meeting will be Thursday, April 13, 2023.
There being no further business, upon motion by Commissioner Colarell,
second by Commissioner Bullock, and carried, the meeting was adjourned at 6:24
PM.
Respectfully submitted,
Barbara Kunar