Chairman Johnson called the meeting to order at 5:00 pm.
Members Present: Kent Johnson, Anne Krogstad and Kurt Schrang
Members Excused: Paul Schultz and Jeremy Flint
Staff Present: Jason Gallo, Robert Duffy, Ald. Charlie Shaw and Chris Dehnert
2. Approve the April 10, 2019 Minutes: Motion by Schrang to approve the April 10, 2019 minutes; second by
Krogstad. Motion carried 3-0.
3. Blink Retail Store – Consider/approve a Façade Update at 165 E. Wisconsin Avenue: Gallo explained
this request is for approval of a façade update on a building in the downtown. Updates include a new larger
window, add new wood panels and paint all new & existing panels “White Dove”, and widen the door opening to
the west to make both doorways even. On the second floor the existing brick will be cleaned, the guardrail will be
replaced, and the wood above the windows and panels along the roof edge will be painted “White Dove”. Staff is
concerned there is not enough contrast between the proposed color and the brick. Laurel Whelan, building owner,
plans to have the brick cleaned, remove the purple along the roof edge, and paint the building in a light color
similar to another building in the downtown. Gallo will check to see if the other building was ever approved for the
building color as painted. Whalen clarified the window will have a bronze frame and the railing will be a dark
brown. She said it is a simple building and wants to showcase the brick and clean lines. Members agreed with the
proposed colors and questioned what the plans are for the water table and gutter system. Whelan said they plan
to have the water table repaired, gutters cleaned up and all bracketing painted with “White Dove”. She added the
new tenant intends to have a projecting sign, and Gallo noted signage is not part of this request as staff may be
able to administratively approve it if it complies with the sign code. Motion by Schrang to approve the façade
update for Blink retail building at 165 E. Wisconsin Avenue as submitted; second by Krogstad. Motion carried 3-0.
4. JDJ Properties of Oconomowoc – Consider/approve Exterior Façade Renovations for 357 W.
Wisconsin Avenue: Gallo explained this request is also for approval of a façade update to a building. The owner
intends to paint the building a dark gray “Fieldstone”, replace the shingles on the roof with pre-finished metal
panels in a lighter gray (“Ash Gray”), box in the pillars with an LP wrapping material, and add a 8’ x 12’ vestibule
with a gable roof onto the front entrance. Staff recommends approval of this request. Mark Jurczuk, building
owner, said he will be adding a fence around the dumpster located next to the building consisting of smart siding
to match the building color. He also plans to paint the brick on his building. Members suggested that he not paint
the brick due to maintenance concerns; suggested that the columns and end gable on the vestibule should be
painted white; and questioned what code requirements were for the depth of the vestibule and how it will impact
parking stalls. Jurczuk does not want to lose the handicap stalls so he may have to reduce the size of the
vestibule. Motion by Krogstad to approve the exterior façade update for JDJ Properties of Oconomowoc at 357 W.
Wisconsin Avenue as proposed with the following building colors: the main building and the walls of the vestibule
will be painted “Fieldstone” (dark gray); the metal roof panels will be “Ash Gray” (light gray); the columns and
gable end of the vestibule will be painted white; the roof will be black shingles and the existing stone will remain
as is; second by Schrang. Motion carried 3-0.
5. Vespera II – Consider/approve Building Plans for Condominium Units to be located on St. Andrews
Drive: Gallo explained this request is to approve the plans of 3 different types of condominium units to be built on
St. Andrews Drive and the streets behind. This area was developed in 2006 as a Planned Development with 36
condominium units consisting of single family, duplexes and one commercial unit. Seven units were built (3
S:Clerk\Committees-Commissions\Architectural\2019\ACMin 5-8-19
duplexes and 1 single-family home) and then development stopped due to the economic downturn. All the current
homes in this development have frontage on St. Andrews Drive. The new proposal includes 6 duplexes with
frontage on St. Andrews Drive and 7 duplexes on the streets behind it. The existing duplexes have two stories and
the proposal consists of duplex ranches. The existing buildings have unique features and characteristics and were
built with a Tuscan Mediterranean style which was originally approved by the Architectural Commission. Gallo
recommends approval of the units that do not abut St. Andrews Drive and postpone approval of the design for the
units on St. Andrews Drive. The applicant, Craig Caliendo, said he can design and build something that can blend
with the other units nicely but does not intend to have tile roofs or stucco exteriors. He would include architectural
features like pergolas and half walls, shingled roofs in a terra cotta color, dark brown gutters, stone window sills
and a wood-look garage door. Caliendo indicated he would be willing to incorporate other modifications to make
these units look similar to the current buildings in the development and was looking for direction from the
members. He was willing to come back with updated plans that include more masonry and details but they will not
be 2-story buildings. The members requested Ken Ulickey, President of the Homeowners Assn for the
development, to give input on the proposed building plans. Ulickey said Caliendo has attempted to work with them
and appreciated his efforts to include more Mediterranean details but the buildings will still be different than the
existing homes. He said the emails/letters that were sent to the members indicate people want more questions
answered before these buildings are approved. Ulickey said there are concerns that if the buildings are approved
now, they will not be able to change anything. Gallo noted this is a unique situation as the existing buildings are
part of Vespera, and the new buildings will be part of Vespera II. There will also be separate plans and documents
which will govern the Vespera II development. Members noted Mediterranean architecture does not have to be 2-
story buildings but instead is included in the details and colors, such as window trim, window style, trellis’,
landscaping, columns, stone accents, etc. The proposed garage doors are acceptable and stone chimneys are
not necessary. Members said Caliendo should consider their suggestions and come back with more details; the
developer should work with the current owners; trying to duplicate what has already been built can be expensive
but some things can be done to make them similar; not enough detail has been presented; this is a perfect
example of what happens when the economy takes a turn; and it is nice when an applicant works out the details
and then presents the plan to the Architectural Commission. Caliendo doesn’t agree that his plans were
premature; he has reached out to the current homeowners and it is hard to design around the desires of 7 owners.
He agreed to look at rubber (tile) roofs, believes he has been given enough direction and is willing to work with the
homeowners. Motion by Krogstad to table the building plans for Vespera II condominium units on St. Andrews
Drive until the applicant is ready to return; second by Schrang. Motion carried 3-0.
6. Reports and comments from the City Planner: None.
7. Reports and comments from the Architectural Commissioners: None.
8. Adjourn: Motion by Schrang to adjourn at 6:00 pm; second by Krogstad. Motion carried 4-0.
Chris Dehnert, Deputy City Clerk
S:Clerk\Committees-Commissions\Architectural\2019\ACMin 5-8-19
Agenda
City of Oconomowoc
ARCHITECTURAL COMMISSION MEETING
Wednesday, May 8, 2019 @ 5:00 PM @ City Hall, Conf. Room #3
NOTICE: If a person with a disability requires the meeting be accessible or materials at the meeting be in an
accessible format, call Diane Coenen, City Clerk, at least 48 hours prior to the meeting at 262-569-2186, or
TDD at 262-569-3272 to request adequate accommodations.
AGENDA:
1. Roll Call and Confirmation of appropriate meeting notification.
2. Approve Minutes of April 10, 2019.
3. Blink Retail Store – Consider/approve façade update at 165 E. Wisconsin Avenue.
4. JDJ Properties of Oconomowoc – Consider/approve façade update at 357 W. Wisconsin Avenue.
5. Vespera II – Consider/approve building plans for condominium units to be located on St. Andrews
Drive.
6. Reports and comments from the City Planning Department.
7. Reports and comments from the Architectural Commissioners.
8. Adjourn.
Diane Coenen, City Clerk
Members of other City governmental bodies (boards, commission, committees, council, etc.) may attend the above
noticed meeting of the Architectural Commission in order to gather information. The only action to be taken at the above
noticed meeting will be action by the Architectural Commission. Architectural Commissioners should notify the City
Clerk's Office at 262-569-3236 if they are unable to attend.
S:\Committees - Commissions\Architectural\Agendas\2019\ACAgda 5-8-19.doc
City of Oconomowoc
Architectural Commission Meeting Minutes
April 10, 2019
Chairman Johnson called the meeting to order at 5:00 pm.
Members Present: Kurt Schrang, Kent Johnson, Anne Krogstad and Paul Schultz
Members Excused: Jeremy Flint
Staff Present: Jason Gallo and Chris Dehnert
2. Approve the March 13, 2019 Minutes: Motion by Schultz to approve the March 13, 2019 minutes; second
by Johnson. Motion carried 4-0.
3. Twisted Fire – Consider/approve a Patio Structure at 515 E. Wisconsin Avenue: Gallo explained the
applicant wants to install a permanent patio structure along the front elevation of his business on Wisconsin
Avenue. A previous business had an outdoor patio at this location, but the proposed patio will be a permanent
structure consisting of 16” gauge black steel columns, a corrugated roof and outdoor rope lighting. Currently there
is a handicapped parking stall in this space which Gallo suggested could be relocated along the east or west
elevations near the entry. He added the Plan Commission normally reviews the number and location of parking
stalls; however, this item is not going to the Plan Commission so the Architectural Commission should consider
the parking when reviewing this request. There is room for 16 tables with 4 chairs each under the patio structure
and seat a total of 64 patrons. The roof edge of the structure will be setback 7’ from the front property line and no
taller than the roof of the restaurant. The applicant is also requesting approval to replace the existing sign
structure with a new two-sided sign on top of the patio roof panels facing perpendicular to Wisconsin Avenue.
Each side will be 24 sf, which is smaller than their previous sign and within code requirements. The sign will be
illuminated by gooseneck lighting. Gallo recommended approval though he had concerns with the overall number
of parking stalls due to the additional patio seating. He added staff had concerns with the front wall structure and
vehicular traffic on Wisconsin Avenue. Terry Boyle of Flux Design said the roof will consist of heavier gauge
translucent clear fiber panels, the only hard pipe lighting will be for the gooseneck lights, and the string lighting will
be on a heavier cable with 40 watt 2-1/2” tall Edison bulbs. The intent of the string lighting is that it will weave back
& forth from steel posts on the front edge of the patio to the roof along the whole end of the patio structure to
create a canopy of lights. Dimitri Glavas, property owner, showed a picture to the members from his phone of
what the lighting will look like. Members asked if he would consider adding black painted bollards along the front
edge or shorter bollards in between the taller posts of the structure along Wisconsin Avenue for additional safety.
Glavas said the previous owner didn’t have to take any special precautions for the patio which the members
agreed. Overall the members liked the look of the proposed structure. Motion by Schultz to approve the patio
structure as submitted for Twisted Fire at 515 E. Wisconsin Avenue; second by Krogstad. Motion carried 4-0.
Commissioner Krogstad recused herself to present the next item.
4. Cornerstone Pub – Consider/approve Exterior Façade Renovations for 24 S. Main Street: Gallo
explained the owner of this building in the downtown is requesting approval to renovate the east, south and part of
the west elevations of his building to bring more visibility to his business on South Main Street. Currently a part of
the west elevation has already been renovated to reflect a cream color brick with gray & brown accents, and the
applicant intends to mirror the same color and accents on the remaining elevations. Plans also include
incorporating more windows; outdoor seating surrounded by a railing on the east elevation; concrete planters; and
a railing around the outdoor tables and chairs with an awning on the south elevation. The only signage shown on
the plans is a single wall sign on the south elevation illuminated with gooseneck lighting. Gallo requested
clarification of any signage for existing tenants in the building. The applicant also intends to move the dumpster
S:Clerk\Committees-Commissions\Architectural\2019\ACMin 4-10-19
currently placed on the south elevation to a new enclosure on the southwest corner of the building. The applicant,
John Suttner, was present along with Ben Freeland and Anne Krogstad of MSI General. Krogstad explained the
old façade around the building will be removed and the brick under it will be painted to match the west elevation.
Some new windows will be installed which will match existing with black aluminum frames. The new façade will
also include accent striping and metal coping on the rooftop, both to match the existing west elevation. The fire
escape and other items will be removed from the south elevation, and a new masonry elevator shaft will be added
on the corner. The driveway to the south is currently used for parking post office trucks but will be closed off to
allow for the outdoor seating. Suttner intends to add a curb to close off the alley, and any mail trucks that park in
this area will have to back out of the driveway. Members said the building will have a modern look and asked if the
applicant would consider arched windows on the front of the building to add interest. Suttner said while arched
windows may look nice, he intends to mirror the existing windows on the building which are square. He added
there will only be one tenant left on the 3rd floor so there will be no additional signage on the building. Freeland
noted the dumpster will be chain link and slats, and the catch system and gutters will be painted to blend into the
building. Motion by Schrang to approve the exterior façade renovations for the Cornerstone at 24 S. Main Street
as presented; second by Schultz. Motion carried 3-0-1 (Krogstad abstained).
5. Reports and comments from the City Planner: Gallo reported that assistant Planner Kristi Weber had a
healthy baby boy and is doing well. She will be off the remainder of April, all of May and June.
6. Reports and comments from the Architectural Commissioners: None.
7. Adjourn: Motion by Schultz to adjourn at 5:39 pm; second by Schrang. Motion carried 4-0.
Chris Dehnert, Deputy City Clerk
S:Clerk\Committees-Commissions\Architectural\2019\ACMin 4-10-19
Planning Department
Architectural Commission Background - May 8th 2019:
5:00 pm at City Hall in Conference Room #3
Item #3 – Blink Building; Façade Update, 165 E. Wisconsin Avenue
The applicant is request ing approval of a façade update to the soon-to-be former Blink Art isan
Bout ique building located at 165 E. Wisconsin Avenue. The owner will be replacing the
windows, new wood panels, new guardrail, paint ing the wood in front of the building and
enlarging the door opening. The second story glass windows will contain similar mullions of
the current windows.
Staff is support ive of this applicat ion as another Downtown Business façade is gett ing a
facelift. The one item that should be discussed is the proposed color of the lower half of the
building will be “White Dove”. Currently there is a light colored brick beneath the windows,
with yellow siding on either side of the windows. The lower half of the building is currently
light, but the change is going even lighter. In addit ion, the roof cornice detail currently is
painted purple and grey. This decorat ive element will be re-painted the “Dove White” color.
One color sample of the “Dove White” was submitted to Planning and will be shared during the
meet ing. Planning will leave the color approval up to the members of the Architectural
Commission.
The building sides are shared with Whalen’s Coffee & Ice Cream to the west and Old Theatre
Mall to the east with neither wall being exposed. No changes are being proposed for the
backside of the building.
Administrative Approval & Sign Permit Required: For future business tenants, signage must
be applied for per the Administrat ive Approval process from the Planning Department, and
then a sign permit from Building Inspect ion located on the second floor of City Hall for $25 per
sign.
Recommendation:
Approve the Façade Update Plans for Blink Building located at 165 E. Wisconsin Avenue, as
presented, subject to the AC members agreeing with the proposed color scheme.
Item #4 – JDJ Properties of Ocon; Façade Renovations, 357 E. Wis. Ave.
The applicant is request ing approval of new façade for the exist ing building. The changes
include replacing the blue colored shingles with new grey pre-finished metal panels, box out
the exist ing columns with a decorat ive wrapping, paint the ent ire building Fieldstone color
and add a vest ibule at the front entrance.
Signage Approval & Permit Required: If this is a mult i-tenant building, the City will require a
master signage plan prior to approval of any new signs. Once the master sign plan is approved,
Architectural Commission Meeting Background
May 8th, 2019 – Page 2
the tenants can apply for Administrat ive Approval from the Planning Department, and then a
sign permit from Building Inspect ion located on the second floor of City Hall for $25 per sign.
Recommendation:
Approve the Façade Plan Amendment for 357 E. Wisconsin Avenue as submitted.
Item #5 – Vespera Condominiums II; Building Plan Approval, St. Andrews Dr.
The applicant is interested in finishing the Vespera Condominium project. The exist ing
development was approved in 2006 with 36 total condominiums, consist ing of single-family
and duplex units. Since that t ime, seven units were constructed. Of the 29 remaining units,
the developer would like to change the site plan and is asking for approval of 26 units, a
decrease from the original count by three less units. Their plan is to construct 13 buildings, all
duplex units. There will be a mix of three different unit types, including the B-B, the C-C and
the D-E.
The previous development was approved as a Planned Development (PD) and all the
architecture of all units required approval by the Architectural Commission. This will cont inue
as the case, the units will need review and approval by the Architectural Commission.
The exist ing seven resident ial units were built with Tuscan Mediterranean style architecture.
This style and the cost associated with the development was not successful at this locat ion.
Staff realizes that the level of detail and amenities (finishes, intricate patterns, textured walls,
t ile roofs) will not be incorporated into the final units. Now the developer is asking to remove
the t ile roofs and replace with dimensional asphalt shingles. There are other details in the
construct ion that are being scaled back. Staff will allow the applicant to walk you through the
changes.
Staff reviewed the applicat ion and not iced the colored renderings were not included. Staff
reached out to the applicant and asked that those be presented at the meet ing. Staff also
asked the applicant to increase the exterior details for the units along St. Andrews Drive, to be
more consistent with the exist ing units. As the units feather back from the roadway, the
amount of gingerbread details could then be reduced. Staff feels the presented architecture is
sat isfactory for the units not abutt ing St. Andrews Drive, but the six buildings with frontage on
St. Andrews Drive should ramp up the level of detail to be more consistent with the exist ing
units.
The applicant has reached out and had meet ings with the exist ing owners. At this t ime, the
exist ing owners have not made a formal statement regarding this request. Although not
required, it would be beneficial to have the support of the exist ing owners.
Recommendation:
Approve the proposed architecture for the units not abutting St. Andrews Drive and
postpone the architectural design for the buildings directly on St. Andrews Drive.