The Board of Adjustment held its regular monthly meeting on Monday. June 24, 2019 at 5:00 p.m.,
in the Council Chambers at City Hall.
Members Present
Vice-Chair Wendell Miller
Secretary Karen Yarbrough
Justin Cothren
Scott Sanders
At-Large Vacant
Members Absent
None
Visitors Present: Mayor Richard Harris, Contract Planner Kevin Gambrill, City Attorney Trey Smith,
Planning Assistant Lequitta Jones, Public Works Director Kenneth Duvall, City Engineer Glenn
Newman, Building Official Brian Holstein, Floodplain Manager Ben Gray, Morgan Barrett of Barrett
& Associates, and Kevin Boortz.
Welcome Visitors
The First Order of Business was a request to review and approve the minutes of the April 22, 2019
meeting.
Member Cothren made the motion to approve the minutes as written. The motion was seconded by
Karen Yarbrough and passed unanimously.
The Second Order of Business was a public hearing requesting approval from 9.3.3 Special
Exceptions to allow a 10% reduction on the 25-foot front setback requirement making it 22.5 feet on
lots 76 and 77 in an R-1, for property located on South Quincy Avenue of the Sunrise Estates.
Submitted by Dave Garza of Barrett & Associates. (BOA.05.01.3650)
The staff recommended approval.
Member Yarbrough made the motion to approve the Special Exception to allow the 10% reduction.
The motion was seconded by Justin Cothren and passed unanimously.
The Third Order of Business was a public hearing requesting approval for a variance to allow a
building to front yard setback of 9.9 feet in lieu of the required 20 feet for a single-family structure
in the R-3 zone, located at 1015 North Cleveland. Submitted by Kevin Boortz. (BOA.19.06.3651)
Planner Kevin Gambrill said this request is to allow an existing building to have a front building to
property line setback of 9.9 feet in lieu of the required 20 feet and an existing accessory building to
have a side building to property line setback of 5.5 feet in lieu of the required 6 feet. Section 7.2 –
Non-conforming Structure – Where a lawful structure exists at the effective date of adoption or
amendment of the Zoning Code that could not be built under the terms of these regulations by reason
of restricts on area, lot coverage, height, yards, or other characteristics of the structure or its
location on the lot such structure may continue so long as it remain otherwise lawful, subject to the
following provisions:
7.2.1 – Such structure, upon approval of the Board of Adjustment, may be remodeled to maintain the
premises in a safe and usable condition.
7.2.2 – Should a structure be destroyed by any means to an extent of more than 50 percent of its
replacement cost at the time of destruction. It shall not be reconstructed except in conformity with
the provisions of this Zoning Code.
7.2.3 – Such structure, upon the approval of the Board of Adjustment, may be added to, if said
addition meets the area requirements of the land use zoning district in which the structure is located,
provided said use of structure is in conformance with the Zoning Code.
The building permit issuance should be dependent upon satisfying all off-street parking
requirements. Group living quarters is the assumed use of the principal structure. Unless the
Planning Commission chooses to decide upon the parking demand created by the use (see section
4.1.1), Staff would recommend applying those parking standards associated with “Bed & Breakfast”
or “Motel”, or, one parking space for each two guests or bedroom, whichever is greater.
Mr. Kevin Boortz said this is a proposal to remodel an existing approximate 2250-square foot house
(1550 sqsf first floor and 700 sqft second floor). Additional 1000 sqft more or less in the rear for
possible future remodel (400 sqft first floor and 600 sqft second floor). This remodel will be done in
two phases, first floor to be completed by August 1, 2019 and the second floor to be completed by
June 1, 2020. The property is zoned R-3, which requires a 20-foot setback on the front. The current
structure is 9’9” to the front of the house according to the last filed improvement for the said
property. It looks like there was a porch that was enclosed, which I plan to make a porch again. The
setback to the actual house entrance will be approximate 17’3”. I do not plan on making any
structure changes other than the front porch and removing some existing decking off the second
floor entrance. The possible third phase will be the 1000 sqft rear section. Currently, those areas
will be for storage again with no structure changes.
Also I’m requesting approval of the current shed that sits to the right side of the house, current
setback for the sides is 6’ and the shed is at 5’3”. I plan on putting a new roof on it and replacing the
current doors on the front.
Building Official Brian Holstein said for the record the side building setback is 5 feet.
Member Cothren made the motion to approve as submitted. The motion was seconded by Member
Yarbrough and passed unanimously.
Meeting Adjourned
_________________________
Acting-Chairman Wendell Miller
Agenda
Board of Adjustment Agenda
June 24, 2019
The Russellville Board of Adjustment will hold its regular monthly meeting on
Monday, June 24, 2019 at 5:00 p.m. in the Council Chambers at City Hall.
Welcome Visitor
1. A request to review and approve the minutes of the April 22, 2019 meeting.
2. A public hearing requesting approval from 9.3.3 Special Exceptions to allow a 10%
reduction on the 25-foot front setback requirement making it 22.5 feet on lots 76
and 77 in an R-1, for property located on South Quincy Avenue of the Sunrise
Estates. Submitted by Dave Garza of Barrett & Associates. (BOA.05.01.3650)
3. A public hearing requesting approval for a variance to allow a building to front
yard setback of 9.9 feet in lieu of the required 20 feet for a single-family structure in
the R-3 zone, located at 1015 North Cleveland. Submitted by Kevin Boortz.
(BOA.19.06.3651)