Zoning Board of Appeals
Regular MeetingSalem, MA · April 17, 2024
Minutes
City of Salem Zoning Board of Appeals
Meeting Minutes
April 17, 2024
A meeting of the Salem Zoning Board of Appeals (“Salem ZBA”) was held on Wednesday, April 17,
2024 at 6:30 pm via remote participation in accordance with Chapter 2 of the Act of 2023 and a Special Act
extending remote participation meetings.
Chair Nina Vyedin calls the meeting to order at 6:33 pm.
Chair Vyedin explains how individuals can participate in the meeting remotely via Zoom, and that
instructions to participate remotely can also be found on the Salem website. Ms. Vyedin also
explains the rules regarding public comment.
ROLL CALL
Those present were: Nina Vyedin, Paul Viccica, Ellen Simpson, Carly McClain, Hannah Osthoff,
and Stephen Larrick. Also in attendance were Daniel Laroe – Staff Planner, Voula Orfanos —
Zoning Officer, and Jonathan Pinto – Recording Clerk. Those absent were: None
CONTINUANCES
Location: 21 Chestnut Street (Map 25, Lot 444) (R2 Zoning District)
Applicant: Philip Gillespie
Project: A continuation of a public hearing for all persons interested in the petition of
PHILLIP GILLESPIE at 21 CHESTNUT STREET (Map 25, Lot 444) (R2
Zoning District) for a Special Permit per Section 3.3.5 Nonconforming Single- and
Two-Family Structures to construct an 18 ft x 51 ft. one-story addition to the
residence. The residence is an existing non-conforming historic structure. The
existing non-conforming one-story addition to be torn down is 37 feet long. The
new addition will extend an additional 14 feet along the wall for a total of 51 feet.
This petition received the Board of Appeals approval on June 7, 2021. The
applicant is reapplying as the granted Special Permits have expired.
Documents and Exhibitions
• Application date-stamped January 10, 2024, and supporting documentation
Chair Vyedin introduces the petition. Mr. Viccica recuses himself from the matter.
Attorney Philip Gillespie introduces himself and explains this was an addition that was planned
during COVID but got curtailed. He states he would like the special permits reissued to continue
with the project. Mr. Gillespie discusses the existing addition and presents floor plans. The existing
brick wall that separates 21 from 19 Chestnut Street goes out beyond where the kitchen wing ends,
according to Mr. Gillespie. Mr. Gillespie next presents elevations showing existing and proposed
conditions. A plot plan showing the existing addition and proposed addition is also shown.
Ms. Osthoff confirms with Mr. Gillespie that the only nonconformities are existing and not made
worse by the proposal.
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Chair Vyedin asks if the plans have changed at all since initial approval, and Mr. Gillespie confirms
they have not.
Chair Vyedin opens the floor to public comment but there is none.
Mr. Gillespie summarizes the statement of grounds.
Motion and Vote: Ms. Simpson motions to approve the petition of PHILLIP GILLESPIE at 21
CHESTNUT STREET (Map 25, Lot 444) (R2 Zoning District) for a Special Permit per Section 3.3.5
Nonconforming Single- and Two-Family Structures to construct an 18 ft x 51 ft. one-story addition to the
residence, replacing an existing nonconforming addition, subject to the following standard conditions:
1. Petitioner shall comply with all city and state statutes, ordinances, codes, and regulations.
2. All construction shall be done as per the plans and dimensions submitted to and
approved by the Building Commissioner.
3. All requirements of the Salem Fire Department relative to smoke and fire safety shall be
strictly adhered to.
4. Petitioner shall obtain a building permit prior to beginning any construction.
5. Exterior finishes of the new construction shall be in harmony with the existing structure.
6. A Certificate of Occupancy is to be obtained.
7. A Certificate of Inspection is to be obtained.
8. Petitioner is to obtain approval from any City Board or Commission having jurisdiction
including, but not limited to, the Planning Board.
9. Unless this Decision expressly provides otherwise, any zoning relief granted does not
empower or authorize the Petitioner to demolish or reconstruct the structure(s) located
on the subject property to an extent of more than fifty percent (50%) of its floor area or
more than fifty percent (50%) of its replacement cost at the time of destruction. If the
structure is demolished by any means to an extent of more than fifty percent (50%) of its
replacement cost or more than fifty percent (50%) of its floor area at the time of
destruction, it shall not be reconstructed except in conformity with the provisions of the
Ordinance.
10. All construction shall be done per the plans and dimension submitted to and approved
by this Board. Any modification to the plans and dimensions must be approved by the
Board of Appeals unless such changes are deemed a minor field change by the Building
Commissioner in consultation with the Chair of the Board of Appeals.
11. Petitioner shall schedule Assessing Department inspections of the property, at least
annually, to project completion and a final inspection upon project completion.
Ms. McClain seconds the motion. The vote is five (5) in favor (Nina Vyedin, Ellen Simpson, Carly
McClain, Hannah Osthoff, and Stephen Larrick) and none (0) opposed. The motion passes.
Location: 30 Northey Street (Map 36, Lot 0020) (R2 Zoning District)
Applicant: Flora Tonthat
2
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Project: A continuation of a public hearing for all persons interested in the petition of
FLORA TONTHAT at 30 NORTHEY STREET (Map 36, Lot 0020) (R2 Zoning
District) for a Special Permit per Section 3.3.3 Nonconforming Structures and
Section 3.2.8 Affordable Accessory Dwelling Units of the Salem Zoning
Ordinance to construct an Accessory Dwelling Unit (ADU) in an existing 20’ x
30’10” accessory building. In addition, a Variance from section 4.1.1 Dimensional
Requirements for side and rear setback requirements. The detached garage is
nonconforming regarding side yard and rear yard setbacks at less than one foot.
The proposed accessory dwelling is seven hundred and nine square feet (709)
where nine hundred square feet (900) is allowed.
Documents and Exhibitions
• Application date-stamped December 14, 2023, and supporting documentation
Chair Vyedin introduces the petition.
Ms. McClain clarifies that the petition might just be for the special permit, and not for a variance.
Flora Tonthat introduces herself and her architect, and they explain that the petitioner’s home is a
bed and breakfast in an R2 residential lot, with an existing CMU garage in the back. The petitioner
recently received approval for a demolition delay waiver from the Historic Commission. The
proposal is to keep the existing footprint and three of the CMU walls, and to change the use from
garage/storage to an ADU for Ms. Tonthat’s daughter, who is an artist and would like to use the
space to live and work. She would also aid in her mother’s business.
The petitioner describes the existing setbacks and presents a site plan and floor plans, along with
photos of existing conditions. Elevations are also presented.
Chair Vyedin confirms the proposal would not increase any nonconformities, and the petitioner
confirms, which is why the special permit only is needed. Chair Vyedin also asks for clarification
between a bed and breakfast residence and a bed and breakfast business. The petitioner explains
that Massachusetts General Law makes a distinction between the two, where a residence only has
three rooms. This is the type Ms. Tonthat resides in and operates.
Mr. Viccica asks about the CMU walls and if they have been engineer reviewed, as he has concerns
about the viability of saving them. He notes that if all the walls must come down, the ADU would
need to come back before the Board because it would be considered a brand-new building and
additional parameters would apply. The petitioner indicates a structural analysis will be done.
Ms. Simpson states she likes the use of permeable pavement and opines that the addition of an
ADU is a benefit.
Chair Vyedin notes public comment letters, many of which are in support from neighbors. There
was one letter from a resident that was concerned about a hardship being shown, which is no longer
relevant because the applicant is not seeking a variance.
Chair Vyedin opens the floor to public comment.
3
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Ward 5 City Councilor Jeff Cohen of 12 Hancock Street introduces himself as Ms. Tonthat’s
husband. He states the property is a spectacular building from 1809 and speaks in favor of the
proposal.
Mandy Spittle of 8 Woodbury Court introduces herself and speaks in support of the proposal. She
speaks highly of the property and of Ms. Tonthat as a neighborhood member.
Mr. Viccica recommends a special condition for the project to be redesigned if construction needs
to change regarding the analysis of the existing CMU walls.
Motion and Vote: Mr. Viccica motions to approve the petition of FLORA TONTHAT at 30
NORTHEY STREET (Map 36, Lot 0020) (R2 Zoning District) for a Special Permit per Section 3.3.3
Nonconforming Structures and Section 3.2.8 Affordable Accessory Dwelling Units of the Salem Zoning
Ordinance to construct an Accessory Dwelling Unit (ADU) in an existing 20’ x 30’10” accessory building,
subject to the following standard conditions:
1. Petitioner shall comply with all city and state statutes, ordinances, codes, and regulations.
2. All construction shall be done as per the plans and dimensions submitted to and
approved by the Building Commissioner.
3. All requirements of the Salem Fire Department relative to smoke and fire safety shall be
strictly adhered to.
4. Petitioner shall obtain a building permit prior to beginning any construction.
5. Exterior finishes of the new construction shall be in harmony with the existing structure.
6. A Certificate of Occupancy is to be obtained.
7. Petitioner is to obtain approval from any City Board or Commission having jurisdiction
including, but not limited to, the Planning Board.
8. All construction shall be done per the plans and dimensions submitted to and approved
by this Board. Any modification to the plans and dimensions must be approved by the
Board of Appeals unless such changes are deemed a minor field change by the Building
Commissioner in consultation with the Chair of the Board of Appeals.
9. Petitioner shall schedule Assessing Department inspections of the property, at least
annually, to project completion and a final inspection upon project completion.
And the following special condition:
1. Should the existing CMU walls that abut adjacent properties, cannot be maintained as a
part of the project, that would be deemed a major field change and therefore, the
petitioner would need to come back and present the new project to the Salem Board of
Appeals.
Ms. McClain seconds the motion. The vote is five (5) in favor (Nina Vyedin, Carly McClain, Ellen
Simpson, Hannah Osthoff, and Paul Viccica) and none (0) opposed. The motion passes.
REGULAR AGENDA
Location: 8 Woodbury Court (Map 36, Lot 005) (R2 Zoning District)
Applicant: Helen Sides
4
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Project: A public hearing for all persons interested in the petition of HELEN F. SIDES,
ARCHITECT, LLC at 8 WOODBURY COURT (Map 36, Lot 005) (R2 Zoning
District) for a Special Permit per Section 3.3.5 Nonconforming Single- and Two-
family Structures of the Salem Zoning Ordinance to demolish an existing deck
and then to construct a new 5.5’ x 7.5’ one-story addition with a deck that
measures 9’ x 15.5’. The proposed addition will be two (2) feet from the rear
yard setback. In the R2, 30 feet for the rear yard setback is required.
Documents and Exhibitions
• Application date-stamped February 29, 2024, and supporting documentation
Chair Vyedin introduces the petition. Mr. Viccica recuses himself from the matter.
Jeremy and Mandy Spittle of 8 Woodbury Court introduce themselves. Ms. Spittle presents and
discusses the existing and proposed floor plans. She also presents a plot plan with existing and
proposed conditions. The existing stairs from the deck will be removed, and the back of the home
will become the main entrance. The staircase will have stair rails and safety improvements for the
couple’s daughter, and there will be an expanded mudroom. Mr. and Ms. Spittle discuss the
property history and existing easement and existing nonconformities, none of which will be
increased by the proposal.
Chair Vyedin confirms that the removal of the existing stairs will remove a nonconformity, and that
none of the nonconformities will be increased.
Chair Vyedin opens the floor to public comment but there is none. Chair Vyedin summarizes the
petitioner’s statement of grounds, noting the proposal will not have any negative impacts.
Motion and Vote: Ms. Osthoff motions to approve the petition of HELEN F. SIDES, ARCHITECT,
LLC at 8 WOODBURY COURT (Map 36, Lot 005) (R2 Zoning District) for a Special Permit per Section
3.3.5 Nonconforming Single- and Two-family Structures of the Salem Zoning Ordinance to demolish an
existing deck and then to construct a new 5.5’ x 7.5’ one-story addition with a deck that measures 9’ x 15.5’,
subject to the following standard conditions:
1. Petitioner shall comply with all city and state statutes, ordinances, codes, and regulations.
2. All construction shall be done as per the plans and dimensions submitted to and
approved by the Building Commissioner.
3. All requirements of the Salem Fire Department relative to smoke and fire safety shall be
strictly adhered to.
4. Petitioner shall obtain a building permit prior to beginning any construction.
5. Exterior finishes of the new construction shall be in harmony with the existing structure.
6. A Certificate of Inspection is to be obtained.
7. Petitioner is to obtain approval from any City Board or Commission having jurisdiction
including, but not limited to, the Planning Board.
8. Unless this Decision expressly provides otherwise, any zoning relief granted does not
empower or authorize the Petitioner to demolish or reconstruct the structure(s) located
on the subject property to an extent of more than fifty percent (50%) of its floor area or
more than fifty percent (50%) of its replacement cost at the time of destruction. If the
structure is demolished by any means to an extent of more than fifty percent (50%) of its
5
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
replacement cost or more than fifty percent (50%) of its floor area at the time of
destruction, it shall not be reconstructed except in conformity with the provisions of the
Ordinance.
9. All construction shall be done per the plans and dimension submitted to and approved
by this Board. Any modification to the plans and dimensions must be approved by the
Board of Appeals unless such changes are deemed a minor field change by the Building
Commissioner in consultation with the Chair of the Board of Appeals.
10. Petitioner shall schedule Assessing Department inspections of the property, at least
annually, to project completion and a final inspection upon project completion.
Ms. McClain seconds the motion. The vote is five (5) in favor (Nina Vyedin, Carly McClain, Ellen
Simpson, Hannah Osthoff, and Stephen Larrick) and none (0) opposed. The motion passes.
Location: 84-86 Derby Street (Map 41, Lot 064) (B1 Zoning District)
Applicant: Maitland Mountain Farms, LLC
Project: A public hearing for all persons interested in the petition of MAITLAND
FARMS, LLC at 84-86 DERBY STREET (Map 41, Lot 064) (B1 Zoning
District) for a Special Permit per Section 3.1.2.D Principal Uses-Industrial Uses
of the Salem Zoning Ordinance to open a distillery with a tasting room.
Documents and Exhibitions
• Application date-stamped March 19, 2024, and supporting documentation.
Chair Vyedin introduces the petition.
Andy Varela and Holly Maitland introduce themselves, along with business partner Daniel Spacek.
Ms. Maitland states she is a lifelong Salem resident and cofounder of Maitland Farms. Ms. Maitland
discusses the farm history, and the proposal for a new small-scale distillery with a tasting room. She
discusses their focus on culinary excellence, local produce, community engagement, providing a local
CSA, and their co-founding of the Mack Park food farm. Ms. Maitland stresses her dedication to
community, and states that the distillery would be an expansion of their family farm, bringing
together unique flavors from the region. The tasting room will be a venue for locals to engage and
learn about distillation, local crafts, and sustainable agriculture. Ms. Maitland states she is committed
to meeting all regulatory and zoning requirements and thinks of the business as a community hub
and partnership with the community.
Mr. Varela indicates he is representing himself as a resident, and not in his capacity as a city
councilor. Mr. Varela discusses the proposal in more detail, and notes there are other businesses in
town that operate under this special permit, such as Couch Dog, Notch, and Deacon Giles. Mr.
Varela notes they are the only agriculture entity in Salem, and that they will be making spirits from
the local products they grow. He states they received 346 signatures in favor of the proposal from a
6
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
neighborhood petition, with 94 signatures from the immediate neighborhood. Mr. Varela also
indicates they had a community meeting recently to address any concerns, which went well.
Mr. Spacek presents floor plans showing the distillery and tasting room layout, and Mr. Varela
discusses the plans in more detail. The tasting room will be 276 square feet of the total 950 square
feet.
Ms. Vyedin asks about deliveries. Mr. Varela explains they will be bringing stuff seasonally from the
2.5-acre small plot farm, such as sugar beets and potatoes. The produce will be brought in through
the front. Raw materials will go to the back, where there is a three-bay sink to mash items for
distillate, followed by fermentation and distillation. Mr. Varela discusses the distillation process and
states the hours would be noon to 10PM Tuesday through Sunday.
Mr. Viccica asks about the waste. Mr. Varela contends waste will be coming offsite every day, as
they are limited on where they can keep trash, especially with the easement at the back of 84. All the
mash will go back to the farm to be composted and used for animal feed.
Ms. Osthoff asks if any community neighbors raised concerns, and Mr. Varela said not really. He
explains that a direct abutter was a little skeptical initially, but once the project was thoroughly
explained it put them at ease. Mr. Varela also notes that Deacon Giles operates a 300 gallon still,
whereas this proposal would be 50 gallons.
Ms. McClain asks about the number of jobs being created locally. Mr. Varela indicates there will be
one full-time employee for distillation and general work split between the farm and distillery, along
with one full time manager and four to five part-time employees in the tasting room.
Ms. Simpson asks about food offerings. Mr. Varela states that food is a big part of what they do,
but that they will need to get approval from licensing. If approved, they would extend food
offerings, with the goal of lightly prepared food options like sandwiches or salads. The emphasis
would be using agriculture in its wholeness, and Mr. Varela also indicates they would use the space
as a CSA pickup for the neighborhood once per week during the season.
Ms. Vyedin asks what the petitioners would be distilling. Mr. Varela says a vodka, a gin, and
eventually bringing in agave nectar to make tequila. Then, he states, they would slowly start to age
out rums and whiskeys. Mr. Varela explains the space is small, so the focus would be on the tasting
room rather than buying things to take out.
Mr. Larick asks about the capacity, and Mr. Varela indicates the tasting room can accommodate 25
guests. The goal is to also find space for a second smaller restroom, as currently there is only one
ADA accessible bathroom.
Chair Vyedin opens the floor to public comment.
Heidi Kepnes of 4 Bentley Street introduces herself as an 18-year resident of the neighborhood. She
speaks highly of Maitland Mountain Farms, and states she was thrilled when she found out about
the proposal. Ms. Kepnes speaks in favor of the only urban farm in Salem.
7
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Lucia Delnegro of 22 English Street introduces herself and states she has been here since 1996. Ms.
Delnegro says she loves Maitland Farm, and speaks in favor of the farm and proposal.
Ward 5 City Councilor Jeff Cohen of 12 Hancock Street introduces himself and states he is very
proud that the petitioners are driving many of the climate sustainability discussions in the city. He
contends it is important to encourage local sustainable businesses and speaks in favor of the
proposal.
Patrick Shultz of 48 Summer Street introduces himself and speaks in favor of the proposal. Mr.
Shultz comments on Ms. Maitland and Mr. Varela’s professionalism as well as their character.
Charles Hildebrand of 46 English Street introduces himself and states he lives right around the
corner. He speaks in favor of the petition.
Mr. Viccica notes there were letters submitted in favor as well.
Mr. Varela summarizes the statement of grounds and speaks on the positive aspects of the proposal
for the community. Mr. Varela indicates everything will be electrified as well.
Motion and Vote: Ms. McClain motions to approve the petition of MAITLAND FARMS, LLC at 84-86
DERBY STREET (Map 41, Lot 064) (B1 Zoning District) for a Special Permit per Section 3.1.2.D Principal
Uses-Industrial Uses of the Salem Zoning Ordinance to open a distillery with a tasting room, subject to the
following standard conditions:
1. Petitioner shall comply with all city and state statutes, ordinances, codes, and regulations.
2. All construction shall be done as per the plans and dimensions submitted to and approved by the
Building Commissioner.
3. All requirements of the Salem Fire Department relative to smoke and fire safety shall be strictly
adhered to.
4. Petitioner shall obtain a building permit prior to beginning any construction.
5. Exterior finishes of the new construction shall be in harmony with the existing structure.
6. A Certificate of Occupancy is to be obtained.
7. A Certificate of Inspection is to be obtained.
8. Petitioner is to obtain approval from any City Board or Commission having jurisdiction
including, but not limited to, the Planning Board.
9. Unless this Decision expressly provides otherwise, any zoning relief granted does not empower
or authorize the Petitioner to demolish or reconstruct the structure(s) located on the subject
property to an extent of more than fifty percent (50%) of its floor area or more than fifty percent
(50%) of its replacement cost at the time of destruction. If the structure is demolished by any
means to an extent of more than fifty percent (50%) of its replacement cost or more than fifty
percent (50%) of its floor area at the time of destruction, it shall not be reconstructed except in
conformity with the provisions of the Ordinance.
10. All construction shall be done per the plans and dimension submitted to and approved by this
Board. Any modification to the plans and dimensions must be approved by the Board of
Appeals unless such changes are deemed a minor field change by the Building Commissioner in
consultation with the Chair of the Board of Appeals.
11. Petitioner shall schedule Assessing Department inspections of the property, at least
annually, to project completion and a final inspection upon project completion.
8
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Ms. Simpson seconds the motion. The vote is five (5) in favor (Nina Vyedin, Hannah Osthoff, Carly
McClain, Paul Viccica, and Ellen Simpson) and none (0) opposed. The motion passes.
Location: 23 Glendale Street (Map 33, Lot 646) (R1 Zoning District)
Applicant: Fred J. Dion Yacht Yard, Inc.
Project: A public hearing for all persons interested in the petition of FRED J. DION
YACHT YARD, INC. at 23 GLENDALE STREET (Map 33, Lot 646) (R1
Zoning District) for a Special Permit per Section 3.3.2 Nonconforming Uses of the
Salem Zoning Ordinance to extend and change the nonconforming boatyard use
by demolishing several connected sheds and constructing a new and larger shed in
the same portion of the property. In addition, a Variance from section 4.1.1
Dimensional Requirements to allow the existing nonconforming lot coverage ratio
of 40.8% to be increased to 48.8%. In the R1, 30% lot coverage is the maximum.
Also, a Variance from Section 4.1.1 Dimensional Requirements to allow the
building to extend an additional 16 feet along the existing rear set-back line of 5
feet, where the required rear setback is 30 feet.
Documents and Exhibitions
• Application date-stamped March 21, 2024, and supporting documentation
Chair Vyedin introduces the petition.
Attorney Bill Quinn introduces himself on behalf of the petitioner and explains this is a business at a
site near the ocean that has been here for a long time. He describes it as a large industrial use,
working on and pulling/launching yachts and boats. Mr. Quinn indicates this is one of only a
couple of boatyard facilities in eastern Massachusetts with the capacity to handle the size of yachts
that come and go from the site. The business exists in a neighborhood as is because of a series of
permits issued long ago and updated over periods of time, according to Mr. Quinn. He states it is
an existing nonconforming but legal use in an R1 neighborhood. Mr. Quinn indicates several boat
storage sheds are currently inadequate in size to store and do work on the boats during winter. The
proposal is to demolish two particular sheds shown on the site plan and to construct a somewhat
larger, but not higher/taller, large shed with a steel skeleton and metal surface like the other
buildings. Mr. Quinn discusses recent changes to the petitioners’ circumstances, noting no longer
having adequate space to store the number of boats they try to service. For many years they were
able to rent storage space on the former Bertini property off Jefferson Avenue, but no longer can
because the City permitted a large residential development at that location. Mr. Quinn also notes
there are few sites in the city where outdoor boat storage even exists. Pursuant to review with the
city and legal research, it was determined the best course of action was to enlarge the indoor storage
space with the proposal. Mr. Quinn introduces Sydney Atkins, whose father owned and operated
the business for decades. Ms. Atkins now manages the property and has developed the proposed
plans. Mr. Quinn also discusses a new sewer facility that will serve the neighborhood, and that his
client has agreed to alter the design of the building to accommodate the new sewer line and keep it
9
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
accessible to the city. DEP is involved, and all relevant regulations would apply, and be subject to a
vigorous environmental review.
Sydney Atkins introduces herself and provides some history and background on her family and the
business, which formed in 1914 right before the Salem fire. It started as a travel lift, and now
services and stores many boats. She discusses the importance of storage for the boatyard. She also
discusses how boating and the business have evolved over time, the short work season, and the
other existing limitations. Ms. Atkins explains this is the only commercial waterfront access, and so
thy are a steward to man other marine businesses.
Mr. Quinn discusses the site plan and explains the relief in more detail. Most of the building would
be conforming in setbacks, and the petitioner seeks two variances and one special permit to expand
the scale of the business on location by expanding the storage facility. The variance is needed for lot
coverage, where the maximum is 30 percent, and the existing 40 percent would be increased to 48
percent. A variance to extend the nonconforming setback by 16 feet along the current setback of 5
feet.
Ms. Atkins presents an overhead map and discusses the property and proposal more. Mr. Viccica
asks about the existing building heights. Ms. Atkins states the whole building will be equivalent to
the peak of one of the two existing buildings at 30 feet.
Mr. Viccica asks if there will be any change in what work is conducted in the new facility compared
to what currently is done and Ms. Atkins states there will not be. He also asks about toxic materials,
and Ms. Atkins explains that the business is heavily regulated with water samples submitted
quarterly, catch basins for paint, crushed stone flooring, and other details. Nothing would differ
with the new building.
Ms. Atkins describes the travel lift and procedure for pulling boats out of the water. Chair Vyedin
asks how many boats they can accommodate. Ms. Atkins states currently 40 to 60 boats indoors,
and another 20 to 30 outside. She indicates the new building will allow for an incremental 30 boats.
Ms. Simpson asks if certain boats can only be stored indoors, and Ms. Atkins states that is correct,
and that for some it is a matter of preference, where a premium is paid. Indoor storage is also
necessary to work on boats out of season in a temperature-controlled environment.
Chair Vyedin opens the floor to public comment.
Ward 5 City Councilor Jeff Cohen of 12 Hancock Street introduces himself and thanks Ms. Atkins
for being a great neighbor. He speaks in favor of the proposal, and notes that the boatyard allowing
the use of the land as an emergency bypass is a huge favor to the community.
Kerry Heath of 16 Ocean Avenue introduces herself and states she is concerned that the height of
the new building will block her water view. She suggests that her view would not be blocked if the
height were limited to that of the office building.
Ms. Vyedin confirms that the height is under 35 feet and is therefore conforming with respect to
height. Mr. Viccica notes that no height variance is being sought, and that no one has a guarantee of
a water view.
10
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
Steve Kapantais of Wysteria Street (no number given) introduces himself and states his concerns
regarding traffic have been addressed.
Mr. Quinn discusses hardship and statement of grounds.
Motion and Vote: Mr. Viccica motions to approve the petition of FRED J. DION YACHT YARD, INC.
at 23 GLENDALE STREET (Map 33, Lot 646) (R1 Zoning District) for a Special Permit per Section 3.3.2
Nonconforming Uses of the Salem Zoning Ordinance to extend and change the nonconforming boatyard
use by demolishing several connected sheds and constructing a new and larger shed in the same portion of
the property. In addition, a Variance from section 4.1.1 Dimensional Requirements to allow the existing
nonconforming lot coverage ratio of 40.8% to be increased to 48.8%. In the R1, 30% lot coverage is the
maximum. Also, a Variance from Section 4.1.1 Dimensional Requirements to allow the building to extend an
additional 16 feet along the existing rear set-back line of 5 feet, where the required rear setback is 30 feet,
subject to the following standard conditions:
1. Petitioner shall comply with all city and state statutes, ordinances, codes, and regulations.
1. All construction shall be done as per the plans and dimensions submitted to and
approved by the Building Commissioner.
2. All requirements of the Salem Fire Department relative to smoke and fire safety shall be
strictly adhered to.
3. Petitioner shall obtain a building permit prior to beginning any construction.
4. Exterior finishes of the new construction shall be in harmony with the existing structure.
5. A Certificate of Occupancy is to be obtained.
6. A Certificate of Inspection is to be obtained.
7. Petitioner is to obtain approval from any City Board or Commission having jurisdiction
including, but not limited to, the Planning Board.
8. All construction shall be done per the plans and dimension submitted to and approved
by this Board. Any modification to the plans and dimensions must be approved by the
Board of Appeals unless such changes are deemed a minor field change by the Building
Commissioner in consultation with the Chair of the Board of Appeals.
9. Petitioner shall schedule Assessing Department inspections of the property, at least
annually, to project completion and a final inspection upon project completion.
Ms. Osthoff seconds the motion. The vote is five (5) in favor (Nina Vyedin, Ellen Simpson, Carly
McClain, Paul Viccica, and Hannah Osthoff) and none (0) opposed. The motion passes.
MEETING MINUTES
March 20, 2024
Ms. Osthoff states she has one edit: “track removal” should be changed to “trash removal”.
Motion and Vote: Ms. Osthoff motions to approve the minutes from the March 20, 2024, meeting
of the Zoning Board of Appeals, as amended. Ms. Simpson seconds the motion. The vote is four
(4) in favor, one (1) abstained, and none (0) opposed. The motion passes.
11
City of Salem Zoning Board of Appeals
April 17, 2024 DRAFT Meeting Minutes
OLD/NEW BUSINESS
Extension of Variances at 266, 282, 286, and 282R Canal Street and 2 Kimball Court
Chair Vyedin introduces the matter. No one is present from the petition, and no motion is made or
matter voted on.
Next Meeting
May 15, 2024
ADJOURNMENT
Motion and Vote: Ms. McClain motions to adjourn the meeting. Ms. Osthoff seconds the motion.
The vote is all in favor. The motion passes.
The meeting ends at 9:24 PM on March 20, 2024.
For actions where the decisions have not been fully written into these minutes, copies of the
Decisions have been posted separately by address or project at:
https://www.salem.com/zoning-board-appeals/pages/zoning-board-appeals-decisions-2024
Respectfully submitted,
Daniel Laroe, Staff Planner
12
Agenda
CITY OF SALEM, MASSACHUSETTS
BOARD OF APPEALS
98 WASHINGTON STREET SALEM, MASSACHUSETTS 01970
TEL: 978-619-5685
DOMINICK PANGALLO
MAYOR
NOTICE OF MEETING
Notice is hereby given that a meeting of the Salem Zoning Board of Appeals will be held
on April 17, 2024, at 6:30 p.m.
via remote participation in accordance with Chapter 2 of the Acts of 2023.
Nina Vyedin, Chair
Important Announcement:
Every effort will be made to ensure that the public can adequately access the
proceedings in real time, via technological means. In the event that we are unable to do
so on matters not requiring a public hearing, we will post on the City of Salem’s website
an audio or video recording, transcript, or other comprehensive record of proceedings
as soon as possible after the meeting.
Individuals may participate remotely in the meeting via a remote participation platform
called Zoom. Members of the public and/or parties with a right and/or requirement to
attend this meeting may access the remote participation meeting through any one of
the following ways:
Attending the Virtual Public Meeting:
• Go to Website link:
https://us02web.zoom.us/j/83964128644?pwd=cTNlTlFic2pKNWlOZnV3dW9yb1l
oUT09 go to the website link https://zoom.us/join and enter meeting ID #839
6412 8644 followed by meeting password 011324 if directed to do so on
screen.
• Dial toll-free phone number 877-853-5257. When prompted enter meeting ID
#839 6412 8644 followed by meeting password 011324 if directed. Those
calling in will not have access to the direct video feed of the meeting but can
follow along with the project materials available for
download at Salem.com/ZBA.
• Watch the meeting live on Salem Access Television Chanel 22.
• Project materials are available for download at (https://tinyurl.com/SalemZBA)
Providing Public Comment During the Meeting:
Members of the public attending this meeting virtually will be allowed to make
comments during the portion of the hearing designated for each agenda item. Members
1
City of Salem Zoning Board of Appeals
Agenda for April 17th, 2024
of the public will be asked to use the virtual “Raise Hand” function in Zoom to indicate
that they would like to provide comment.
• Dial *9 on your phone’s dial pad to raise your hand if you are using the toll-free
number.
• Click the “Raise Hand” button if you are using the Zoom application on your
computer or phone.
For each agenda item, the moderator will identify attendees with raised hands by
their screenname or the last 3 digits of their telephone number and will then unmute
them. The moderator will then request that the attendee unmute their device to
provide their full name, address, and comment for the record.
The moderator will go down the list of attendees in the order presented by the Zoom
application. The attendee list is ordered so that phone numbers are first, followed by an
alphabetical list of the screen names of attendees accessing Zoom through a computer,
tablet, or smartphone. Anyone that speaks about an issue unrelated to the agenda
items will be immediately muted.
Providing Public Comment Before the Meeting:
Members of the public can alternatively email their comment before the start of the
meeting to zoningboardcomments@salem.com.
Familiarizing Yourself with Zoom:
We encourage members of the public to install and familiarize themselves with Zoom in
advance of the meeting.
If you plan on providing public comments and are logging into this meeting via the
Zoom application, please test your speakers and microphone ahead of time. If we have
trouble hearing you when you speak, we will move on to the next person and try to
return to you later in the list. If this happens, we recommend that you call the toll-free
number to access the meeting and provide your comment.
Persons requiring auxiliary aids and services for effective communication such as sign
language interpreter, an assistive listening device, or print material in digital format or a
reasonable modification in programs, services, policies, or activities, may contact the
City of Salem ADA Coordinator as soon as possible and no less than two (2) business
days before the meeting, program, or event.
The Zoom meeting will open 15 minutes before the start of the meeting to allow
participants to connect and practice with the audio and raise hand functions.
Know your rights under the Open Meeting Law M.G.L. c. 30A § 18-25 and City
Ordinance § 2-2028 through § 2-2033.
2
City of Salem Zoning Board of Appeals
Agenda for April 17th, 2024
MEETING AGENDA
I. ROLL CALL
II. CONTINUANCES
1. Location: 21 Chestnut Street (R2 Zoning District)
Applicant: Philip Gillespie
Description: The petition of PHILLIP GILLESPIE at 21 CHESTNUT STREET (Map
25, Lot 444) (R2 Zoning District) for a Special Permit per Section 3.3.5
Nonconforming Single- and Two-Family Structures to construct an 18 ft x 51 ft.
one-story addition to the residence. The residence is an existing non-conforming
historic structure. The existing non-conforming one-story addition to be torn
down is 37 feet long. The addition is proposed to extend an additional 14 feet
along the wall for a total of 51 feet. This petition received the Board of Appeals
approval on June 7, 2021. The applicant is reapplying because the Special
Permits granted in 2021 have expired.
***Requested to be last on the agenda***
2. Location: 30 Northey Street (R2 Zoning District)
Applicant: Flora Tonthat
Description: The petition of FLORA TONTHAT at 30 NORTHEY STREET (Map
36, Lot 0020) (R2 Zoning District) for a Special Permit per Section 3.3.3
Nonconforming Structures and Section 3.2.8 Affordable Accessory Dwelling Units
of the Salem Zoning Ordinance to construct an Accessory Dwelling Unit (ADU) in
an existing 20’ x 30’10” accessory building. In addition, a Variance from section
4.1.1 Dimensional Requirements for side and rear setback requirements. The
detached garage is nonconforming regarding side yard and rear yard setbacks at
less than one foot. The proposed accessory dwelling is seven hundred and nine
square feet (709) where nine hundred square feet (900) is allowed.
III. REGULAR AGENDA
1. Location: 8 Woodbury Court (R2 Zoning District)
Applicant: Helen Sides
Know your rights under the Open Meeting Law M.G.L. c. 30A § 18-25 and City
Ordinance § 2-2028 through § 2-2033.
3
City of Salem Zoning Board of Appeals
Agenda for April 17th, 2024
Description: The petition of HELEN F. SIDES, ARCHITECT, LLC at 8
WOODBURY COURT (Map 36, Lot 005) (R2 Zoning District) for a Special Permit
per Section 3.3.5 Nonconforming Single- and Two-family Structures of the Salem
Zoning Ordinance to demolish an existing deck and then to construct a new 5.5’
x 7.5’ one-story addition with a deck that measures 9’ x 15.5’. The proposed
addition will be two (2) feet from the rear yard setback. In the R2, 30 feet for
the rear yard setback is required.
2. Location: 84 – 86 Derby Street (B1 Zoning District)
Applicant: Holly Maitland
Description: The petition of MAITLAND FARMS, LLC at 84-86 DERBY STREET
(Map 41, Lot 064) (B1 Zoning District) for a Special Permit per Section 3.1.2.D
Principal Uses-Industrial Uses of the Salem Zoning Ordinance to open a distillery
with a tasting room.
3. Location: 23 Glendale Street (R1 Zoning District)
Applicant: Fred J. Dion Yacht Yard, Inc.
Description: The petition of FRED J. DION YACHT YARD, INC. at 23 GLENDALE
STREET (Map 33, Lot 646) (R1 Zoning District) for a Special Permit per Section
3.3.2 Nonconforming Uses of the Salem Zoning Ordinance to extend and change
the nonconforming boatyard use by demolishing several connected sheds and
constructing a new and larger shed in the same portion of the property. In
addition, a Variance from section 4.1.1 Dimensional Requirements to allow the
existing nonconforming lot coverage ratio of 40.8% to be increased to
48.8%. In the R1, 30% lot coverage is the maximum. A Variance from Section
4.1.1 Dimensional Requirements to allow the building to extend an additional 16
feet along the existing rear set-back line of 5 feet, where the required rear
setback is 30 feet.
IV. APPROVAL OF MINUTES
Minutes from March 20, 2024
V. OLD/NEW BUSINESS
Extension of variances at 266, 282,286 and 282R Canal Street and 2 Kimball
Road.
VI. ADJOURNMENT
Know your rights under the Open Meeting Law M.G.L. c. 30A § 18-25 and City
Ordinance § 2-2028 through § 2-2033.
4
City of Salem Zoning Board of Appeals
Agenda for April 17th, 2024
This agenda is subject to change.
Know your rights under the Open Meeting Law M.G.L. c. 30A § 18-25 and City
Ordinance § 2-2028 through § 2-2033.