Buckman Direct Diversion Board
Regular MeetingSanta Fe, NM · October 2, 2025
Minutes
MINUTES OF THE
CITY OF SANTA FE & SANTA FE COUNTY
BUCKMAN DIRECT DIVERSION BOARD MEETING
October 2, 2025
1. Call to Order
This regular meeting of the City of Santa Fe & Santa Fe County Buckman Direct Diversion
Board meeting was called to order by Commissioner Justin Greene, BDD Board Chair at
approximately 4:00 p.m. in the Council Chambers, City Hall, 200 Lincoln Avenue, Santa Fe,
New Mexico.
2. Roll Call: Roll was called and a quorum was present as shown:
BDD Board Members Present: Member(s) Excused:
Commissioner Justin Greene, Chair Rolf Schmidt-Petersen, Citizen Member
Councilor Carol Romero-Wirth
Councilor Jamie Cassutt
Commissioner Hank Hughes
Peter Ives, Citizen Member Alternate
T. Egelhoff, The Club at Las Campanas, [non-voting member]
BDD Board Alternate Members Present:
Bradley Prada Facilities Manager
Nancy Long, BDD Board Consulting Attorney
Kyle Harwood, BDD Board Consulting Attorney
Bernardine Padilla, BDD Public Relations Coordinator
Matt Sandoval, BDD Operations Superintendent
Samantha Secrist, BDD Accounting Supervisor
Brandi Martinez, BDD Administrative Assistance
Jay Lazarus, Glorieta Geoscience
Peter Hunt, Glorieta Geoscience
Reid Williams, Glorieta Geoscience
Larry Pierce, Glorieta Geoscience
Others Present:
Joni Arends, CCNS
1
3. Approval of Agenda
There were no changes to the agenda and upon motion by Councilor Romero-Wirth and
second by Councilor Cassutt, the motion to approve the agenda passed by unanimous [5-0]
voice vote.
4. Approval of Consent Agenda
There were no questions regarding the Consent Agenda and Councilor Romero-Wirth moved
to approve. Councilor Cassutt seconded and the motion passed by unanimous [5-0] voice
vote.
8. Action Items: Consent Agenda
a. Request for Approval of a Contract Amendment to the Professional
Services Agreement (PSA) with Glorieta Geoscience, a Division of GZA
GeoEnvironmental to revise the cumulative not-to-exceed amount from
$125,000 to $190,000 due to a clerical error.
b. Request for Approval to Re-authorize Unexpended Funds in the Major
Repair and Replacement Fund in the Total Amount of $2,253,916 from
FY2025 to FY2026.
i. Request for Board Approval of a Budget Amendment Resolution
(BAR) to Re-Authorize the Unexpended Funds.
c. Request for Approval of a Professional Services Agreement with
Arrowhead Security d/b/a Vet-Sec Protection Agency for Security
Services at Buckman Direct Diversion (BDD) in the amount of
$204,811.20 plus applicable NMGRT for Fiscal Year 2026.
d. Request for Approval to award ITB #26005 “BDD Water Treatment
Plant Chemicals” to various vendors for fiscal year 2025/2026 for an
estimated total amount of $625,000
5. Approval of Minutes
a. Approval of the September 4, 2025, Buckman Direct Diversion Board
Meeting Minutes
Upon motion by Councilor Romero-Wirth and second by Councilor Cassutt, the September
4, 2025 minutes were approved by unanimous [5-0] voice vote.
6. Matters from the Public – None were presented.
7. Presentations and Informational Items
a. Monthly Update on BDD Operations
MATT SANDOVAL (BDD Operations Superintendent): Thank you,
Chairman Greene, members of the Board. I’ll be presenting the BDD Operations Report for
the month of September 2025. The BDD diversions and deliveries have averaged a million
gallons per day as follows: raw water diversions averaged 4.66 million gallons per day;
drinking water deliveries through Booster Station 4A/5A, 4.19 million gallons per day; raw
Buckman Direct Diversion Board:
October 2, 2025 2
water delivery to Las Campanas at Booster Station 2A, .40 million gallons per day. And for
the month of September 2025, BDD contributed 37 percent of the water to the City and the
County. And I will stand for questions.
CHAIR GREENE: Anything from up here? Yes, sir.
MEMBER IVES: Thank you, Mr. Chair. Quick question, in the minutes from
the last meeting, Jesse had reported that the City had received approximately 31 percent –
that should say Buckman had received 31 percent of the San Juan-Chama allocation. And
when I looked at the report and this is page 5 which is the chart with all of the details on what
waters to where, it indicated that Buckman or rather San Juan-Chama had diverted was 3,477
which is approximately 67 percent at least of the City’s allocation of 5,200 acres a year. And
so I’m trying to understand the difference.
MR. SANDOVAL: I’d defer to Kyle, please.
CHAIR GREENE: Oh, we’re lawyering-up.
KYLE HARWOOD (BDDB Counsel): No, no, no, this is the water nerd hat
not the lawyer hat.
The reason that that is possible, Citizen Member Ives/Councilor Ives, is because the
City and the County do carryover storage from prior years in Abiquiu and so they’re able to
release that water for diversion at the BDD. Despite the fact that the San Juan-Chama project
did deliver to all contractors 31 percent of the firm yield this calendar year. Does that help?
MEMBER IVES: Certainly helps and I looked at the chart on page 2 which is
the City storage which listed approximately 10.5 acre-feet still in storage in three different
reservoirs.
MR. HARWOOD: Ten thousand.
MEMBER IVES: Yeah, sorry, 10,000.
MR. HARWOOD: You gave me a little bit of a jump there – 10 acre-feet
isn’t going to get us very far. I’m sorry, so the question again, Councilor Ives.
MEMBER IVES: So I had seen the ten five and I sort of remember from past
meetings that I thought our actual water in storage was under that figure. So I could be
wrong and maybe it was just because it was reporting on Abiquiu as opposed to El Vado and
Heron as well, which account for some 6,500 acre-feet here.
MR. HARWOOD: There’s very little in El Vado. It’s down for repairs and
will be for a very long time unfortunately independent of the current federal shutdown. And
there is some in Heron but I would trust the aggregate number in that draft. I’m not
intimately familiar with how it has been going up and down of late but years ago the City and
the County did begin a proactive program of getting several years of diversion into storage
above the BDD for years like we’re experiencing this year.
MEMBER IVES: Yeah, and quite frankly the El Vado at 5,100 acre-feet just
seemed high knowing that that dam is under all sorts of repairs at this point in time.
MR. HARWOOD: It should be 180,000 acre-feet when it’s working properly
but it’s very low right now.
MEMBER IVES: So it sounds like additional acreage was drawdown on our
stored water.
MR. HARWOOD: They way I would think about it is that the current year
water available to contractors is the checking account and that water in storage is the savings
account and whatever is in savings can be released for diversion as long as it doesn’t exceed
our environmental permit at the BDD.
Buckman Direct Diversion Board:
October 2, 2025 3
MEMBER IVES: Got you. I would love to just get confirmation that we then
released presumably about 1,700 acre-feet out of storage.
MR. HARWOOD: The way I would think of it is that we released all 3,000
that is showing as being diverted from the system and only 31 percent of the City’s 5,230 and
only 31 percent of the County’s 375 was made available to those two entities this year. Does
that help?
MEMBER IVES: You know, that makes it an accounting issue and I’m just
trying to figure out what got pulled from where and what the numbers are because it didn’t
seem to quite make sense.
MR. HARWOOD: I’ll work on a question back to Jesse and Bill and copy
Brad and Matt and I think I know how to frame the question: what did we start with for the
year? What did we receive and what did we release and divert today? It’s a little bit of the
difference between cash and accrual accounting if that would give you a better – Good for
now?
MEMBER IVES: Good for now. Thank you.
CHAIR GREENE: So I am going to ask, what do you attribute the drop from
55 percent in the same month last year to 37 this year?
MR. SANDOVAL: Chair Greene, members of the Board, so you’ll see the
previous six months we kind of over pumped so that strategy this year was to pump during
the summer months and then kind of taper off. So actually by the end of the year we’re
going to pump more water than previous years but the strategy was to do it in the summer
months.
CHAIR GREENE: And pump you mean just hit the wells?
MR. SANDOVAL: Sorry, divert.
MEMBER IVES: One more. Thank you, Mr. Chair. I note too at the last
meeting Jesse had indicated we had two artesian Buckman Wells that we actually have to
pump because we can have a lot of pressure built up in those wells – and this might again be
a Kyle question – but I was just wondering how that plays into our return flow obligations
with an artesian well like this because if we have to pump them to keep them functional
presumably if it’s [inaudible] interest isn’t being necessary produced.
MR. SANDOVAL: Thank you and I’ll defer that to Kyle.
MR. HARWOOD: I’m going to give a less [inaudible] answer unfortunately
to this question. I think that the artesian nature of the Buckman Wells which were in that
condition in the 70s when they were pumped, if water is diverted and puts beneficial use it
would need to be accounted for to the State Engineer’s Office, that pumping would go into
the groundwater model, it would tell the City, in this case, what the surface water impacts of
their groundwater pumping are. But there’s nothing sort of inherently about the artesian
nature of the wells that really gets away from the basic water right accounting of diversions
need to be accounted for and modeled appropriately for compliance with the permit. As you
know, I did work on that permit a lot many years ago but that’s really a City, Jesse, Marcos
and Bill sort of detail question and I don’t want to say more because I’m not sure how else
they would answer that question, if that’s okay.
MEMBER IVES: Perfectly fine. It’s the first time that I’ve ever seen any
reference to us having artesian Buckman wells and I was just curious how that played into
the permitting and return-flow obligations.
Buckman Direct Diversion Board:
October 2, 2025 4
MR. HARWOOD: Artesian wells have a whole different set of regulatory
requirements that I’m sure Jay could speak to here if you’re interested after the meeting. But
fundamentally, they were artesian when they were initially drilled. In fact, there are stories
of people rafting this section of the river in the 60s and the 70s and the water was coming out
of the well casing above the height of a person. I’ll leave you on that historical note.
MEMBER IVES: Yes, thank you and thank you, Mr. Chair.
CHAIR GREENE: Anybody else? Thank you, Matt.
MR. SANDOVAL: Thank you.
7. B. Report from BDD Facilities Manager
BRADLEY PRADA (Facilities Manager): Thank you, Chair Greene. Good
afternoon, Board members and guests. This report outlines the progress on the key projects,
procurement and staffing as of October. We’ve made progress on the design-build project,
and major repair and replacement projects are advancing well. We have a detailed update on
the ongoing hiring efforts to fill several positions.
First, LANL MOU negotiation continues earnestly with LANL personnel. We are
preparing to bring a completed MOU to the Board in the coming months.
Next, the MR&R Fund, quotes have been successfully received for the pumps. These
pumps are required for 1A and 2A. This purchase will be processed immediately and funded
through the MR&R Fund.
Finally, on to the design-build project: our internal team is currently meetings on
weekly basis. This team includes AECOM, Wright Water, BDD Legal and BDD staff. We
are preparing for the receipt of the revised design-build proposal. Following a
comprehensive review of the revised proposed, we are ready to move forward into contract
negotiations.
Staff, BDD personnel to work diligently with City staff to address exist8ing
vacancies. I won’t go into too much detail but as you can see from the list we are making
solid progress. The list has gotten smaller and smaller each. And we’ll continue to make this
one of the top priorities. I’ll stand for questions.
MEMBER IVES: I know from the minutes of last month’s meeting, it said
that on the rebuild that you were moving into the next phase but there was no explanation of
what that next phase was. So I was just curious, what was intended? Is that the contract
negotiations?
MR. PRADA: Thank you, Mr. Chair and Peter Ives, the next phase was the
revised proposal.
MEMBER IVES: Got you. And that’s all I had – oh, actually on the LANL
MOU, I know there was much talk about giddy-up last month in the minutes, and now it’s
something in the coming months so I was just curious as to where we are in that process and
if you have any clearer timeframe in bringing that back to the Board.
MR. PRADA: I’ll defer to Kyle.
MR. HARWOOD: Thank you, Citizen Member Ives. We have recently taken
a slightly different approach to the technical request on the MOU and we’re hoping that that
will get us past the current disagreement and I hope very much that we bring you an MOU
ready for execution for the November Board meeting.
MEMBER IVES: Should I ask what the disagreement is?
Buckman Direct Diversion Board:
October 2, 2025 5
CHAIR GREENE: Is it that $90,000 or something?
MR. HARWOOD: We’ve recently tried to take a slightly different approach
to the funding of the sampling which we hope will be successful.
CHAIR GREENE: It’s our going away gift to Councilor Romero-Wirth.
Please try harder, faster. Tell them we’re pressured internally –
MR. HARWOOD: Harder, faster, yes, sir.
MR. PRADA: We will definitely make that our top priority.
CHAIR GREENE: Great, thank you. Again, if there’s a role that either
myself or the vice chair can do to push that, we can write a letter, we can do all sorts of
things – [In response to a raised hand from the public, Chair Greene advised this was not the
appropriate time for matters from the public.]
I had an additional question to the pumps, what’s the lead time on those?
MR. PRADA: Thank you, Mr. Chair, 20 weeks.
CHAIR GREENE: Twenty weeks?
MR. PRADA: After we receive the PO. So there’s a process internally here
in Buckman and also at the City to produce that PO and then as soon as we get through that,
it’s 20 weeks after that.
CHAIR GREENE: And those are replacements or just kind of kept in storage
until we need them or do you preemptively –
MR. PRADA: They are going to be shelved until needed.
CHAIR GREENE: Okay, great.
9. Action Items: Discussion Agenda – None were presented.
10. Matters from the Board
MEMBER IVES: Just one question because I may have missed it in today’s
activity. I looked at the chemical award and there’s no reference to fluoride; has that been
ceased?
COUNCILOR ROMERO-WIRTH: Right, it doesn’t affect BDD. It’s a City
thing.
MEMBER IVES:. So does BDD put in fluoride?
MR. PRADA: Chair, Peter Ives, once again, we are not injecting fluoride.
MEMBER IVES: Have we in the past?
COUNCILOR ROMERO-WIRTH: I think it would be better to either get a
briefing on this if this is something that the Board is interested in or get the right people to
answer these questions. I don’t want a misstep here. The thing that we passed doesn’t affect
BDD.
MEMBER IVES: I understand that I just don’ know –
COUNCILOR ROMERO-WIRTH: There’s a lot of history on this which I do
not have in front of me and would hate to even attempt because there’s a lot there.
MR. PRADA: I’d like to add something. It is naturally occurring and already in
the water that we produce.
MEMBER IVES: And, as we know, the CDC, may they rest in peace, have
specific limits to the amount of fluoride and my recollection is that the ambient fluoride than the
CDC recommended limit by some small percentage. I guess it wasn’t a great amount – I’m just
Buckman Direct Diversion Board:
October 2, 2025 6
wondering if the policy of the BDD has been to include fluoride in the past and whether we
stopped it.
COUNCILOR ROMERO-WIRTH: There is a County resolution and again I
would like to defer these questions to either offline or for presentation we could talk about the
history on this. I really don’t want to do it kind of shotgun because I want to make sure we are
being really accurate.
MEMBER IVES: Always prefer accuracy. If we could have a brief update on
that, on what has been the policy, if it has changed. And, again, I just hadn’t seen fluoride in any
of these chemicals.
COUNCILOR ROMERO-WIRTH: There’s a County resolution that is
significant on this.
CHAIR GREENE: We’ll come prepared with where the County complicates
this. Anything else?
11 Next Meeting
a. Thursday, November 6, 2025
12. Adjourn
The Board adjourned at 4:20 p.m.
Approved by:
Justin Greene (Nov 2, 2025 23:05:47 MST)
____________________________
Justin Greene, Board Chair
Respectfully submitted:
Wordswork
ATTEST TO
KATHARINE E. CLARK
Santa Fe County Clerk
Buckman Direct Diversion Board:
October 2, 2025 7
Agenda
Agenda Amended - Regular Meeting of the
Buckman Direct Diversion
Board
October 2, 2025 at 4:00 PM
Council Chambers
City Hall Front Door Entry
200 Lincoln Avenue
Procedures for Buckman Direct Diversion Board Meeting
The agenda and packet for the meeting will be posted
at https://santafe.primegov.com/public/portal.
Meeting Zoom Link: https://santafenm-gov.zoom.us/j/85068470377
1. Call to Order
2. Roll Call
3. Approval of Agenda
4. Approval of Consent Agenda
5. Approval of Minutes
a. Approval of the September 4, 2025, Buckman Direct Diversion Board Meeting
minutes
6. Matters from the Public
7. Presentations and Informational Items
a. Monthly Update on BDD Operations. (Matt Sandoval, BDD Operations
Superintendent, mgsandoval@santafenm.gov, 505-955-4501).
b. Report from the BDD Facilities Manager. (Bradley Prada, BDD Facilities
Manager, bxprada@santafenm.gov, 505-955-4507).
8. Action Items: Consent Agenda
a. Request for Approval of a Contract Amendment to the Professional Services
Agreement (PSA) with Glorieta Geoscience, a Division of GZA
GeoEnvironmental to revise the cumulative not-to-exceed amount from
$125,000 to $190,000 due to a clerical error. (Samantha Secrist, BDD
Accounting Supervisor; sasecrist@santafenm.gov, 505-955-4506; Bradley
Prada, BDD Facilities Manager, bxprada@santafenm.gov, 505-955-4507)
Buckman Direct Diversion Board
October 2, 2025
Page 1 of 2
b. Request for Approval to Re-authorize Unexpended Funds in the Major Repair
and Replacement Fund in the Total Amount of $2,253,916 from FY2025 to
FY2026. (Samantha Secrist, BDD Accounting Supervisor;
sasecrist@santafenm.gov, 505-955-4506; Bradley Prada, BDD Facilities
Manager, bxprada@santafenm.gov, 505-955-4501)
i. Request for Board Approval of a Budget Amendment Resolution (BAR)
to Re-Authorize the Unexpended Funds.
c. Request for Approval of a Professional Services Agreement with Arrowhead
Security d/b/a Vet-Sec Protection Agency for Security Services at Buckman
Direct Diversion (BDD) in the amount of $204,811.20 plus applicable NMGRT
for Fiscal Year 2026. (Samantha Secrist, BDD Accounting Supervisor;
sasecrist@santafenm.gov, 505-955-4506; Bradley Prada, BDD Facilities
Manager, bxprada@santafenm.gov, 505-955-4507.)
d. Request for Approval to award ITB #26005 “BDD Water Treatment Plant
Chemicals” to various vendors for fiscal year 2025/2026 for an estimated total
amount of $625,000. (Samantha Secrist, BDD Accounting Supervisor;
sasecrist@santafenm.gov, 505-955-4506; Bradley Prada, BDD Facilities
Manager, bxprada@santafenm.gov, 505-955-4507.)
9. Action Items: Discussion Agenda
10. Matters from the Board
11. Next Meeting:
a. Thursday, November 6, 2025
12. Adjourn
Persons with disabilities in need of accommodations, contact the City Clerk’s office at
955-6521, five (5) working days prior to meeting date.
Buckman Direct Diversion Board
October 2, 2025
Page 2 of 2
Get email alerts for Santa Fe
A daily email when new agendas and minutes are posted.