City Council
Regular MeetingSouth St. Paul, MN · March 28, 2022
Minutes
SOUTH ST. PAUL CITY COUNCIL
MINUTES OF MARCH 28, 2022
1) Mayor James Francis called the regular meeting of the City Council to order at 7:00 p.m.
on March 28, 2022
2) ROLL CALL:
Present: Mayor Francis
Councilmembers Bakken, Dewey, Hansen, Kaliszewski,
Podgorski
Absent: Councilmember Seaberg
Staff Present: City Administrator, Joel Hanson
Assistant City Administrator, Shelly Anderson
3) Agenda
Moved by Kaliszewski/Bakken
MOVED: To approve the agenda as presented.
Motion carried 6 ayes/0 nays
4) Approve Bid for City Hall Remodel
Moved by Kaliszewski/Bakken
MOVED: To approve the bid and two (2) alternates to Weber Construction for
the remodeling project at City Hall in the amount of $2,095,000 as recommended by
Wold & Associates.
Motion carried 6 ayes/0 nays
City Council Minutes of March 28, 2022 1
5) Adjournment
Moved by Dewey/Podgorski
MOVED: That the special meeting of the City Council adjourn at 7:16 p.m.
Motion carried 6 ayes/0 nays
Approved: April 18, 2022
___________________________
City Clerk
City Council Minutes of March 28, 2022 2
Agenda
City of South St. Paul
COUNCIL AGENDA – SPECIAL MEETING
125 3rd Ave N.
Monday, March 28, 2022
7:00 p.m.
Meeting Location: Training Room
1. CALL TO ORDER:
2. ROLL CALL:
3. AGENDA:
A. Approval of Agenda
Action – Motion to Approve
Action – Motion to Approve as Amended
4. GENERAL BUSINESS:
A. Approve bid on City Hall Remodel
6. ADJOURNMENT:
A CITY COUNCIL AGENDA REPORT – SPECIAL MEETING
DATE: March 28, 2022 4 -A
DEPARTMENT: ADMINISTRATION
Prepared by: Joel Hanson, City Administrator
ADMINISTRATOR: JRH
AGENDA ITEM:
ACTION TO BE CONSIDERED: CONSIDERING AWARDING BIDS FOR CITY HALL REMODELING
PROJECT TO LOWEST RESPONSIBLE BIDDER
OVERVIEW:
We have been studying various options for renovations to City Hall to meet today’s operational
needs. Bidding was authorized for a project consisting of five major components. They are:
Expanded workspace for patrol/sergeants’ area
New front counter area in administration to enhance customer service
Replacement of the roof over the Fire Station and other enhancements to the
administration and living areas
Renovations to the Community Development area to make more efficient use of
workspaces and improve the customer service counter
Expansion of the Work-Out room and the addition of shower/changing rooms in the
lower level that will be made available for all employees to use as well as a remodeled
breakroom.
Bids for this work were received on Thursday, March 24th. Seven contractors submitted bids for
the project. The bidding consisted of a base bid and two add/alternates. One was for a vehicle
exhaust system in the Fire Department. The other was for the remodeling of the
administration/living area of the Fire Station. The bid results were as follows:
Base Alternate Alternate Total
Bid #1 #2 W/Alternates
Weber, Inc. $1,667,000 $64,000 $364,000 $2,095,000
Versacon, Inc. $1,672,000 $64,707 $517,523 $2,254,230
Century Construction $1,689,000 $60,000 $460,000 $2,209,000
Ebert Construction $1,696,000 $58,500 $435,000 $2,189,500
Jorgenson Construction $1,775,000 $60,000 $462,000 $2,297,000
CM Construction $1,920,800 $56,800 $548,800 $2,526,400
Meisinger Construction $2,412,000 $54,200 $570,000 $3,036,200
The project budget of $3.6 million was based on construction costs of $2.5 million, professional
fees and testing costs of $700,000, and FF&E (furniture, fixtures, and equipment) costs of
$400,000. The low apparent bid of $2,095,000 includes both add alternates. To that amount we
also need to factor in about $50,000 for temporary office/living quarters for the Fire Department
for next spring when the work would be done in their area. An additional $58,200 is needed if
we undertake the Council Room technology upgrades that were discussed at our March 14th
work session. With all of those costs included and realizing these number do not include a
contingency for unexpected work modifications, the total cost for the entire project should be
about $3.3 million.
Weber Construction is being vetted by Wold & Associates. They are located in North St. Paul
and here is a link to their website: https://www.webercompanies.com Wold will be present at
Monday’s work session with a recommendation for your consideration. Subject to Wold’s
review and recommendation, Staff supports the award of the entire project (with the two
add/alternates).
SOURCE OF FUNDS:
2022 Capital Project Funds Line Item of $3.6 million
Get email alerts for South St. Paul