SUFFOLK WETLANDS BOARD
AGENDA FOR
MARCH 17, 2016
PREPARED BY THE CITY OF SUFFOLK
DEPARTMENT OF PLANNING
A MEETING WILL BE HELD AT 6:00 P.M.
IN THE SUFFOLK CITY COUNCIL CHAMBERS IN
SUFFOLK CITY HALL
PLEASE CALL TO CONFIRM YOUR ATTENDANCE
THE PLANNING DEPARTMENT
AT 514-4060
PRIOR TO
12:00 NOON ON WEDNESDAY, MARCH 16, 2016
GEOFFREY HINSHELWOOD
CHAIRMAN
AGENDA
SUFFOLK WETLANDS BOARD
March 17, 2016
6:00 P.M.
I. Call to Order
II. Roll Call
III. Approval of Minutes
February 18, 2016
IV. Public Hearings –
VMRC#15-1716, submitted by Richard Bartlett of Professional Construction
Consultants, LLC, applicant, on behalf of Patrick Bryant, property owner, for
the installation of a 144 linear foot bulkhead, a 50-foot open-pile pier with a 12-
foot by 23-foot L-head and a 5-foot by 28-foot finger pier, 16-foot by 28-foot
boathouse with boatlift, and 2 watercraft lifts. The project is located at 214
Water Pointe Way along the Nansemond River
V. Restoration Hearings – None
VI. Permit Extensions – None
VII. Old Business – None
VIII. New Business
VIMS May Tidal Wetlands Workshop
IX. Compliance and Inspections – None
X. Adjournment
MINUTES
SUFFOLK WETLANDS BOARD – WORK SESSION
February 18, 2016
6:00 P.M.
The work session of the Suffolk Wetlands Board was held on Thursday, February 18,
2016, at 6:00 p.m., in the City Council Conference Room of the City Hall Building,
442 West Washington Street, Suffolk, Virginia.
MEMBERS: STAFF:
Geoffrey Hinshelwood Karla Williams, Associate City Attorney
Sidney Hazelwood Scott Mills, Interim Deputy City Manager
Darius Davenport Robert Goumas, Director of Planning &
Steven Barnum Community Development
Jeffrey Colley David Parks, Principal Planner
Richard Vroman Amanda Beck, Planner II
C. Robbie Johnson
Brad L. O’Berry
ROLL CALL:
The meeting was called to order by Chairman Hinshelwood. The roll was then called
by Mr. Parks and the Chairman was informed that a quorum was present.
APPROVAL OF THE MINUTES:
Mr. O’Berry pointed out a correction to the November 2015 minutes on Page 1, in
which it stated President and Vice-President, but it should be Chairman and Vice-
Chairman. The minutes were then approved as corrected.
A motion was made to approve the minutes of the January 2016 meeting as distributed
1
which was passed by a voice vote 7 to 0.
NEW BUSINESS:
CBPA Regulations and Development Procedures
David Parks, Principal Planner, gave a presentation on the CBPA Regulations and
Development Procedures in City of Suffolk.
VMRC Living Shoreline General Permit Process
Rachel Maulorico, VMRC, gave a presentation on the VMRC Living Shoreline
General Permit Process.
VMRC #12-1348 - River Bluff Living Shoreline Final Debriefing
Scott Mills, Interim Deputy City Manager, gave a brief presentation on the River
Bluff Living Shoreline and showed some before and after pictures of the site.
Freedom of Information Act
Karla Williams, Associate City Attorney, showed a video on the Freedom of
Information Act.
Upcoming VIMS Trainings
Amanda Beck, Planner II, advised the Board members of various upcoming
trainings, including the Annual VIMS Wetlands Workshop which will be held on
May 5th.
2
ADJOURNMENT:
There being no further business before the Board, the meeting was adjourned.
3
STAFF REPORT
DESCRIPTION
PROPOSED PROJECT: VMRC#15-1716, to install 124 linear foot bulkhead, a 50-foot open-
pile pier with a 12-foot by 27-foot L-head and a 5-foot by 27-foot finger pier, 16-foot by 28-foot
boathouse with 12,500 pound boatlift, an additional boatlift, and 2 watercraft lifts.
APPLICANT: Submitted by Richard Bartlett of Professional Construction Consultants, LLC,
applicant, on behalf of Patrick Bryant, property owner.
LOCATION: The property is located at 214 Water Pointe Way along the Nansemond River.
PERMIT HISTORY: There have been two previous permits for this property. In 2006
VMRC#06-2088 was filed to dredge the boat basin for access to an existing boathouse on an
abutting parcel so that the boathouse was not dry during low tide. During a site visit it was
determined the owner was in violation of Section 28.2-1317 of the Code of Virginia and Section
31-418 of the City of Suffolk Unified Development Ordinance. The permit was placed on hold
until the owner submitted an after-the-fact permit for a wooden deck/wharf pier. In 2007
VMRC#07-2579 was filed to dredge 284 cubic yards of the access channel adjacent to the
property to a maximum depth of -3.0 feet below Mean Low Water, to repair 60 linear feet of an
existing bulkhead, to install 80 linear feet of new bulkhead, and after-the-fact permitting of the 5-
foot by 60-foot wharf pier. The application was never approved due to a boundary line dispute
with an abutting neighbor, regarding the existing boathouse.
VIMS REPORT: A VIMS report for this property was completed and submitted to the City of
Suffolk Wetlands Board on February 27, 2008, which accompanied VMRC#07-2579. There are
no other VIMS reports for this property.
STAFF ANALYSIS
ISSUE
This property consists of a detached single-family dwelling located within the River Wood
subdivision, and the affected property is located on the tidal waters of the Nansemond River.
There is approximately 170 linear feet of shoreline along the property. The existing bulkhead is
starting to fail and erosion behind the bulkhead was evident during a site visit to inspect the
proposed project. Currently, the shoreline is defined by an existing bulkhead, wharf pier, and
vegetated uplands. As the wharf pier was never approved through the previous permits submitted
for this site, it will need to be addressed with this permit. The majority of vegetation is turf, some
mature saltbush, and woody vines.
The applicant is requesting to install a 124 linear foot bulkhead, a 50-foot open-pile pier with a
12-foot by 27-foot L-head and a 5-foot by 27-foot finger pier, 16-foot by 28-foot boathouse with
12,500 pound boatlift, an additional boatlift, and 2 watercraft lifts. The pier structure is outside
of the Wetlands Board jurisdiction and therefore will be permitted by the VMRC. Staff is
currently working with the applicant and the owner on a buffer restoration plan which will
include installation of various kinds of vegetation, to include shrubs and trees. This plan is
Wetlands Board
March 17, 2016
VMRC#15-1716
Page 2 of 4
required because the new bulkhead and riprap will disturb area within the 100-foot Resource
Protection Area Buffer. Staff will review the buffer restoration plan to ensure proper mitigation
of the 100-foot Resource Protection Area Buffer of the Chesapeake Bay Preservation Area, as
well as ensuring consistency with the Riparian Buffers Modification and Mitigation Manual.
CONSIDERATIONS AND CONCLUSIONS
1. The Center for Coastal Resources Management notes that this section of bank along the
Nansemond River is stable, and it is important to note this is likely due to the presence of
bulkhead along the properties of the River Wood subdivision extending northward
roughly 600 linear feet and terminating at a Big Cordgrass marsh. The applicant’s request
to repair 124 linear feet of the existing bulkhead will maintain this bank stability.
2. The applicant is proposing 2 separate cross sectional designs to address the different
embankment heights that exist along the shoreline.
3. Projected Impacts:
a. Rip Rap – The applicant is proposing to install 37 linear feet of riprap directly
adjacent to an existing boathouse that is in disrepair. A minimum cut of one foot
to stabilize the toe of the riprap is required, with a slope of 1:1.5 which is roughly
in keeping with the shoreline on that portion of the property. The application
indicates that there will be a total of 111 square feet of impact in the CBPA
Resource Protection Area, requiring mitigation in line with the Riparian Buffers
Manual. The applicant has proposed to restore the buffer area with 800 square feet
of new vegetation. This mitigation plan will be reviewed by city staff
administratively.
b. Bulkhead – Installation of 124 linear foot bulkhead, including replacing existing
bulkhead, will have minimal impact on subaqueous lands along sections B-E, and
will be in-line from sections E-I, with construction occurring in non-vegetated
wetlands along sections F-H. Sections A-B of the project will have a minimal
impact to non-tidal vegetated wetlands, and to offset construction effects the
applicant is proposing to remove 80 square feet of the existing marginal wharf so
that wetlands plants may be reestablish along this portion of the property.
c. Open-pile Pier – Construction of the open-pile pier proposes to take access
directly from the existing wharf pier, and construction will occur over non-
vegetated wetlands within the Nansemond River, therefore there will be no
wetland vegetation impacted by the pier. This action is exempt from the Wetlands
Board’s action.
d. Boat Lift and Boathouse – The proposed boathouse will be built upon non-
vegetated wetlands within the Nansemond River and there should be no impact.
The boat lifts should have no impact to the wetlands on this site as the piles will
be installed on non-vegetated wetlands. This action is exempt from the Wetlands
Board’s action.
Wetlands Board
March 17, 2016
VMRC#15-1716
Page 3 of 4
e. Additional Watercraft Lifts – Similar to the boat lifts the two proposed watercraft
lifts should have no adverse impact. There will be no wetland vegetation impacted
by the construction. This action is exempt from the Wetlands Board’s action.
f. Marginal Wharf – The applicant is proposing to remove 80 square feet of the
existing marginal wharf to allow upland wetland vegetation to reclaim this section
of the property. The remaining portion of the marginal wharf is within the
Chesapeake Bay Preservation Area Resource Protection Area Buffer, and is being
mitigated through a buffer restoration plan which staff will review
administratively.
4. The previous VIMS report that was submitted in 2008 addressed the replacement of the
existing bulkhead, dredging 284 cubic yards of the access channel adjacent to the
property, and an after-the-fact permit for the wharf pier:
a. Replace Existing Bulkhead – The report stated the installation of 80 linear feet of
new bulkhead in addition to the existing bulkhead was appropriate for this site.
b. Dredging – VMRC#07-2579 proposed dredging 284 cubic yards of the access
channel adjacent to the property, part of which would include dredging the
existing boat slip. VIMS concluded that the boat slip is subtidal and only a small
portion of non-vegetated wetlands would be impacted, therefore they were
approved due to minimal effects on wetlands.
5. Due to the impacts within the Resource Protection Area of the Chesapeake Bay
Preservation Area Overlay District the applicant will be required to submit a buffer
restoration plan in accordance with Unified Development Ordinance Section 31-
415(d)(1)(D), Buffer Area Requirements. The applicant will be required to show the
restoration of impacted areas due to the construction of the wharf pier and wooden
walkway up to the principal dwelling. The applicant will also be responsible for
restoration of any trees that are impacted by this shoreline project. This application
proposes removing 80 square feet of the marginal wharf; therefore there will be no
impact to the woody groundcover along the bank on the southeastern lot line. The
applicant is proposing that 924 square feet of impact will occur in the RPA Buffer, to be
restored by 800 square feet of vegetation such as understory trees, shrubs, and woody
groundcover. The applicant is currently working with staff to complete the restoration
plan that will address impacted areas within the 100-foot RPA Buffer. Obtaining a
building permit will be conditional of staff approval of the buffer restoration plan first.
6. This shoreline project will be required to obtain a land disturbance permit through the
Department of Public Works. An erosion and sediment control plan will have to be
prepared by the applicant and submitted to Public Works prior to any work being done on
site. No building permit will be issued prior to Public Works approving the erosion and
sediment control plan.
RECOMMENDATION
Due to the existing conditions on site, and the condition of the bulkhead, it is staff’s opinion that
Wetlands Board
March 17, 2016
VMRC#15-1716
Page 4 of 4
the site in question is appropriate for the proposed installation of new bulkhead, an open-pile pier
with a L-head platform and finger pier, a boathouse, two boat lifts, and two watercraft lifts.
Therefore, staff recommends approval of Joint Permit Application VMRC#15-1716 with the
following conditions.
1. Prior to the issuance of a building permit for the construction of the bulkhead, pier,
boathouse, and boat lifts the applicant shall have a buffer restoration plan approved by
staff, and which shows the installation of vegetation in the disturbed area within the
Resource Protection Area of the Chesapeake Bay Preservation Area Overlay District.
2. The applicant is required to have an approved erosion and sediment control plan prior to
any land disturbance at 214 Water Pointe Way.
3. The installation of wetland tolerant vegetation shall be installed in the 80 square foot area
where the existing marginal wharf structure will be removed. The vegetation shall be
installed during the appropriate season and will be inspected by staff after installation.
Attachments
Exhibit A – Zoning/Land Use Map
Exhibit B – VMRC Application
Exhibit C – 2008 VIMS Report, 2015 VMRC Report
General Location Map
s
S S LA
LV D TE N L N
K R IS Y N
A D R IV D IN G IV E
IN B W E
R WATCH D R
TS CRO
DW ET
GO RN
B
U VE
I
TE R W AY
WA
R
LA
FA L
RT 5
L
8 A
K E
£
¤
58
JO N
A THANS
W AY
« £
¬
13¤ 58
£
¤58 RT 58
PR
UD R
EN
RI
BLV VE E
D IV
R W
R
OO D
TR
D N
E
S M O
CE
N
A
Y S M ILL R D
M UR PH
N
E
AV
RIV
OD
ER
O RD
W
NG
LO
DR
ROO K
NM
A IN
IL L O W
E
ST B
E A D
W
W I L L IA M S R D
M
E
L A K
DY DR
N
ORM
AN
VMRC15-1716
Esri, HER E, DeLorme, MapmyIndia, © OpenStreetMap contributors, and the GIS
user community
JOINT PERMIT APPLICATION
VMRC#15-1716
CONDITIONS
1. Prior to the issuance of a building permit for the construction of the bulkhead, pier,
boathouse, and boat lifts the applicant shall have a buffer restoration plan approved by
staff, and which shows the installation of vegetation in the disturbed area within the
Resource Protection Area of the Chesapeake Bay Preservation Area Overlay District.
2. The applicant is required to have an approved erosion and sediment control plan prior to
any land disturbance at 214 Water Pointe Way.
3. The installation of wetland tolerant vegetation shall be installed in the 80 square foot area
where the existing marginal wharf structure will be removed. The vegetation shall be
installed during the appropriate season and will be inspected by staff after installation.
EXHIBIT A
VMRC#15-1716 Zoning Map
NANSEMOND
RIVER
TE
RB
URY C OVE
RLM
WA
R
IV
W AY
D ER
OO
W
ER
AT
WO OD
W
MIST
ING TID
TRA MORN VE
CO
Y
LM RIDGE
CE
W
AT
E R
E PO IN
TE
W
AY
LANE
26J*2*42 RL
AD
RO
ER
RIV
elopment Overlay District
MUD
MUD RZ2-13
³
RZ2014-00009
B-2
1 inch = 358 feet
Esri, HERE, DeLorme, MapmyIndia, © OpenStreetMap contributors, and
the GIS user community
Get email alerts for Suffolk
A daily email when new agendas and minutes are posted.