Board of Control
Regular MeetingTallmadge, OH · December 3, 2021
Minutes
CITY OF TALLMADGE BOARD OF CONTROL
Minutes of Meeting Scheduled For: Friday, December 3, 2021 @ 9:00 a.m.
Members Present: Mayor Kline, Law Director Raber, Finance Director Gilbride,
Service Director Rorar (Pres. of Council excused)
Meeting Chaired By: Mayor Kline Minutes: Karen
Morgan
Item 1) Call To Order and Approval of B.O.C. Minutes for November 12th meeting
The Mayor called the meeting to order at 9:07 a.m. Rorar: Before we approve the minutes,I’d
like to make a small correction. I think I said in Item 2 “that it’s like a renewal, not that it is
one”. It is not a contract renewal, it’s a new contract but it’s like a renewal because we’ve
worked with them before. They were the lowest of the 2 bidders and as we were satisfied with
their work in the past, we are OK with this. The Mayor moved to approve the minutes of the
November 12th meeting with the amendment made by Mr. Rorar; seconded by Raber. Vote to
approve: 4/0.
Item 2) Authorizing the Mayor to enter into a contract for the repair and remodeling
of the Tallmadge Police Station with R 2 K Contracting in the amount of $276,624.00, as
approved in Ord. 104-2021
Rorar: So we went out to bid for the remodel and it included the painting and the carpeting and
some of the bathroom fixtures and we got the one bid from R 2 K Contracting out of the
Rootstown area. They submitted several references and we called and verified all the references.
Everyone spoke highly of them, saying they do outstanding work. They’ve even remodeled a
police station up in S. Euclid. Raber: How much under everyone else were they? Rorar: There
were no other bids. Kline: For the record, the appropriation for 2021 is -$57,000 so therefore I
have no problem awarding this contract subject to city council adopting an ordinance that will be
in front of them on December 9th reappropriating funds from the safety fund capital. So I will
make the motion to enter into a contract for the repair and remodeling of the Tallmadge Police
Station with R 2 K Contracting in the amount of $276,624.00 subject to council adopting an
ordinance for the reappropriation of funds from the safety fund capital; seconded by Raber.
Raber: Mike, please do not inform them they are officially awarded until after that legislation is
adopted. Rorar: OK.
Vote to approve: 4/0.
Item 3) Consideration and approval of Change Order #4 to Lockhart Concrete
Company which adds widening of the intersection at the Tallmadge Reserves allotment for
the East Avenue/Washburn Road intersection improvement project at an increased cost of
$1,000.00, bringing the new contract price to $1,226,928.00 (original project approved in
Ord. 50-2021).
Rorar: (passes out a handout) The original width of that was supposed to be 35 feet, but for
whatever reason, when we went to tie into the road that Pulte did for the Tallmadge Reserve, it
was 37 feet and we can’t have a narrow . . . we had to match it. So that’s the issue. I did call
Pulte about it and they are looking into why it was widened so we can come back on them if we
need to and they are well aware of that. It’s one of those things where we go to tie in and it’s not
wide
-2-
enough and you’ve got to match, or you’re going to have a bottleneck there . . . Gilbride: I move
to approve Change Order #4; seconded by Raber. Vote to approve: 4/0.
Item 4) Consideration and approval of Change Order #5 to Lockhart Concrete
Company which adds work cutting a hole in the yard drain for piping in the East
Avenue/Washburn Road intersection improvement project at an increased cost of $200.00,
bringing the new contract price to $1,227,128.00 (original project approved in Ord. 50-2021).
Rorar: This is an engineering issue. The catch basin was to be installed however it has an open
ditch that ties into it so the top of the catch basin was higher than the open ditch. So, the ditch
water had no where to go so you had to punch a hole in the catch basin and sometimes when you
do that, they come pre-fab that way however, this was an engineering error and I’m not sure why
it wasn’t caught, but we had to punch a hole in that thing to let the ditch water go into the catch
basin. Raber: I move to approve Change Order #5; seconded by Gilbride. Vote to approve:
4/0.
Item 5) Consideration and approval of Change Order #6 to Lockhart Concrete
Company which adds asphalt to tie into the Tallmadge Reserves allotment for the East
Avenue/Washburn Road intersection improvement project at an increased cost of $638.75,
bringing the new contract price to $1,227,766.75 (original project approved in Ord. 50-2021).
Rorar: So this is the same area where we had to widen the intersection 2 feet. When we go to
the match, you can see in the photographs I supplied you there’s only an inch and a half of
asphalt and we have to tie into 5 inches of asphalt, 6 inches of asphalt and the reason why it was
so narrow is because the paver, as it came out of the hole, raised up so we had to find where it
actually met the 5 inch mark and that’s what we ended up doing. So, again they had to cut back
about 10 more feet to find that spot so it’s there. Raber: I move to approve Change Order #6;
seconded by Gilbride.
Discussion: Mayor: Is this something we should talk to Fetchco about and send them an
invoice? Rorar: They are aware of both the widening and this. Mayor: So are you going to
generate a bill? Rorar: I want to make sure we’re done. I think there may be another issue
coming so I just wanted to make sure. Mayor: So then they’ll issue a check back to us. We said
we’d cover it but then we could at least put the money back in the funds. Rorar: Again, the
Fetchco people are totally aware of these instances. Vote to approve: 4/0.
Item 6) Consideration and approval of Change Order #7 to Lockhart Concrete
Company granting a contract time extension TBD for the East Avenue/Washburn
intersection improvement project (original project approved in Ord. 50-2021).
Rorar: Due to the issue with getting material, they’ve been some weeks behind. They’ve been
trying to get the stormwater, they finally got that, the same way with the stackpoles, they finally
have those however they’re still 2 weeks out to get one more box for the traffic lights, so it will
probably be another 3 weeks before they’re functional. The weather is now coming on and you
can’t get grass to grow this time of year. Lastly, you have to pave when the temperature is at 50
degrees or higher (air temperature and ground temperature) and right now, I’m not comfortable
-3-
doing that final inch and a half of pavement when it’s that way, so I’m fine with giving them an
extension. Talked this morning with them and we’re looking at May 16th. We need to be done
with that pavement by then. It should be plenty of time to get the plants opened. They can do it
earlier, but there again we need to wait for the ground temperature to get to that 50 degree mark.
Mayor: But they’re substantially complete now, right? Rorar: Yes. They’re going to work up
until Christmas and do the final rough grade, and get everything strawed – no seed because it
won’t grow, but they still have to saw everything and they still have a sidewalk to put in. They
will continue to work until they can’t. But that final pavement and grass seed will not go down
until spring. Mayor: They’re striping today . . .and that temporary stripe will stay on until the
top coat goes back on and the traffic light will begin working within the next couple of weeks.
As soon as the traffic control box comes in. Rorar: Yes. Hopefully by Christmas. Mayor:
And they’re striping as if the traffic light was going to be turned on for the turn lanes. Rorar:
And they’ll barricade the one turn lane going into North Washburn because that’s not open yet
anyway but the rest of the turn lanes should be open. Mayor: That doesn’t affect us finance-
wise does it? Or do we have to encumber money? Gilbride: It’s already encumbered, at issue
will be next year when all these transactions take place if there are change orders that we don’t
have appropriated. Rorar: I see one more change order coming, we’ll probably have to install a
catch basin in the one lady’s yard because it looks like she’s going to have a swimming hole if
we don’t. Mayor: But we could do that over the winter in-house and not by the contract since
it’s really outside of the scope of the job. Rorar: No, it’s part of the job – it’s part of the
engineering. The engineering didn’t catch it and we probably need to do it before the sidewalk
goes in. Gilbride: Isn’t there a change order for the county report that we have to approve?
Rorar: And the reason why it’s not in this list is they haven’t approved it yet. Mayor: The
county? Gilbride: It’s their timeline for doing this. Rorar: They’ve already done it. Gilbride:
The county timeline for informing us that they’ve approved the change order . . . Rorar: I’m
working on that right now. Raber: We could have probably done it contingent upon council
approving it. But if you will be coming back with another one anyway, we can do it then.
Mayor: It’s not going to hurt us, the intersection’s done today once they get that stripe on,
except for turning the lights on, and all of the other items outside of the driving path. Gilbride:
We really bore the brunt of trying to get asphalt down in the winter and it was crappy and we had
lots of problems with it, so looking back, I think it’s worth saving the time to put that asphalt in
at the right temperature. Rorar: It is what it is. Gilbride: Well at least you made it more
drivable. Rorar: We were able to meet that temperature for that short period, and everything
worked out alright. Thankfully. We had a really warm day yesterday and that asphalt was hot!
Mayor: I move to approve Change Order #7 for a time extension for the East Avenue/Washburn
Road intersection improvement project until May 16, 2022; seconded by Raber. Vote to
approve: 4/0.
Item 7) Consideration and approval of Change Order #1 to Cleveland Freightliner,
Inc. increasing the original price for the lease/purchase of a box truck (Ord. 40-2021) by
$6,259.00 because of production issues that made them switch manufacturers. This brings
the new contract price to $133,280.00.
-4-
Rorar: This is a state bid and the sub-contractor for the box part of this truck couldn’t meet the
demand with covid problems etc. so they had to switch to another supplier and that drove the
price up an extra $6,259. Mayor: What department is this for? Rorar: Water and Sewer. The
purchase was originally authorized by Ord. 40-2121 and because this was financed through a
bank lease, this portion will have to passed without an appropriation but they have the funds to
do that. Mayor: So someone will have to request the purchase order then. Gilbride: Yes.
Mayor: I move to approve Change Order #1 to Freightliner, Inc. to add $6,259.00 to the
purchase price for a new total of $133,280.00; seconded by Raber. Vote to approve: 4/0.
Item 8) Additional Items? None.
Item 9) Adjournment. The meeting was adjourned at 9:23 a.m.
Board of Control minutes distributed electronically December 22, 2021/km
Agenda
BOARD OF CONTROL AGENDA
For Special Meeting To Be Held Friday
December 3, 2021 @ 9:00 a.m.
Item 1) Call To Order and Approval of B.O.C. Minutes for November 12th meeting
Item 2) Authorizing the Mayor to enter into a contract for the repair and remodeling of the
Tallmadge Police Station with R 2 K Contracting in the amount of $276,624.00, as approved in
Ord. 104-2021.
Item 3) Consideration and approval of Change Order #4 to Lockhart Concrete Company
which adds widening of the intersection at the Tallmadge Reserves allotment for the East
Avenue/Washburn Road intersection improvement project at an increased cost of $1,000.00,
bringing the new contract price to $1,226,928.00. (Original project approved in Ord. 50-2021).
Item 4) Consideration and approval of Change Order #5 to Lockhart Concrete Company
which adds work cutting a hole in the yard drain for piping in the East Avenue/Washburn Road
intersection improvement project at an increased cost of $200.00, bringing the new contract price
to $1,227,128.00. (Original project approved in Ord. 50-2021).
Item 5) Consideration and approval of Change Order #6 to Lockhart Concrete Company
which adds asphalt to tie into the Tallmadge Reserves allotment for the East Avenue/Washburn
Road intersection improvement project at an increased cost of $638.75, bringing the new contract
price to $l,227,766.75. (Original project approved in Ord. 50-2021).
Item 6) Consideration and approval of Change Order #7 to Lockhart Concrete Company
granting a contract time extension TBD for the East Avenue/Washburn Road intersection
improvement project. (Original project approved in Ord. 50-2021).
Item 7) Consideration and approval of Change Order #1 to Cleveland Freightliner, Inc.
increasing the original price for the lease/purchase of a box truck (Ord. 40-2021) by $6,259.00
because of production issues that made them switch manufacturers. This brings the new contract
price to $133,280.00.
Item 8) Additional Items?
Item 9) Adjournment.
attachments: bid document for Police Station remodeling and Change Orders 4, 5, 6, 7, and 1.
Board of Control Agenda distributed electronically November 30, 2021/km