Capital Improvement Advisory Committee
Regular MeetingTerrell, TX · May 25, 2023
Agenda
AGENDA
Capital Improvement Advisory
Committee
6:00 PM - Thursday, May 25, 2023
City Council Chambers, 201 E. Nash Street, Terrell, TX
Board Members
Danny Stephens, Member
Gabriel Cabrera, Member
Garrett Carlisle, Member
Joe Hood, Member
Clint Howie, Member
Trini B. Jones, Member
Debra Kelley, Member
Shayne Phillips, Member
Jorge Vargas, Member
Chris Snapp, City Engineer
NOTICE IS HEREBY GIVEN that the Capital Improvement Advisory Committee will conduct a
meeting at 6:00 p.m. on Thursday, May 25, 2023, at Terrell City Hall located at 201 East Nash
Street. The meeting is open to the public with limited seating in the Council Chambers.
Page
1. CALL TO ORDER
2. HEAR REMARKS FROM VISITORS.
3. DISCUSSION ITEMS
3.1. Review the Impact Fee CIP and Reports and other related information 3 - 30
presented by Freese & Nichols and City Staff
CIAC Presentation
3.2. Consider Remaining Schedule and update. 31
Project Schedule
Page 1 of 31
4. ADJOURN.
I, the undersigned authority, do hereby certify that the above
NOTICE OF MEETING of the Capital Improvement Advisory
Committee is a true and correct copy of said NOTICE, which
has been posted on the front OUTDOOR BULLETIN BOARD
CABINET FOR AGENDAS of the Terrell City Hall, Terrell,
Texas, a place convenient and readily accessible to the
General Public and on the website at cityofterrell.org, and
which has been continuously posted for a period of seventy-
two (72) hours prior to the date and time said meeting was
convened. Posted Monday, May 22, 2020 – 5:00 p.m.
_______________________________________
Dawn Steil, City Secretary
This facility is wheelchair accessible and accessible parking spaces are available. Requests
for accommodations or interpretive services must be made 48 hours prior to this meeting.
Please contact the City Secretary’s office at 972-551-6600 for further information. Braille is not
available.
The Capital Improvement Advisory Committee Reserves the Right to Adjourn into Executive
Session to Seek Legal Counsel on a Matter Which the Canon of Legal Ethics Demands to
Preserve the Attorney-Client Privilege Pursuant to Section 551.071(2) of the Texas
Government Code.
Page 2 of 31
ITEM 3.1.
May 25, 2023
Capital Improvements
Advisory Committee (CIAC)
Page 3 of 31
Impact Fee Basics and
Land Use Assumptions/Growth Rates
Road, Water and Wastewater Impact Fee Program Update
ITEM 3.1.
Agenda
Impact Fee Basics & Process
1
Service Areas
and Growth Rates
2
CIAC Discussion and
Comment on LUA Growth Rates
Page 4 of 31
3
ITEM 3.1.
Role as CIAC Member
Provide Comment:
• Land Use Assumptions
• Capital Improvement Plans (CIP)
• Impact Fee
CIAC Meetings and Action Items:
1. May 25th: 101, LUA Growth Rates
2. August 24th: LUA and CIPs
3. December 14th: Impact Fee and Collection Rates
4. February 2nd: Collection Rates and
Recommendation to Council
Page 5 of 31
ITEM 3.1.
What is an Impact Fee?
Mechanism for funding the infrastructure
necessary to accommodate new development
including:
• One-time charge
• Funding of certain new facilities
• Recoupment of certain capital improvements
Structured approach
Page 6 of 31
to assessment of fees
ITEM 3.1.
Basis of Impact Fees?
New development should pay for a portion of the cost
of public infrastructure required to serve it.
Page 7 of 31
5
ITEM 3.1.
Types of Impact Fees?
ROADWAY
• Based on size of development, service
area, and type of development
• Collected at time of building permit
WATER & WASTEWATER
• Based on meter size
• Collected at time of connection to system
• Collected and applied citywide
Page 8 of 31
Both types of fees are calculated based on Service Units –
units of development brought online
6
ITEM 3.1.
Why do Cities have Impact Fees?
• Pay for Cost of Development Related to Required
Capacity of System
• New Connections Take Available Capacity From Water
and Wastewater Mains
• New Developments Add Vehicles Traveling the
Roadways
• The Fees Provide an Additional Revenue Paid by
Developers Because of These Impacts
• Eliminates All Costs Being Paid by Existing Residents
• Other Cities We Would Expect to be in Competition
With Have Impact Fees
Page 9 of 31
7
ITEM 3.1.
How are Impact Fees Set?
• Project Population/Employment and Annual
Growth Rates
• Develop Land Use Assumptions
• Determine Capital Improvements to Meet Growth
Demands
• Evaluate Water, Wastewater and Roadway Required
to Meet Growth
• City Decides What Percent of Capital Costs Are
Charged to Developers
Page 10 of 31
8
ITEM 3.1.
Why should the Developer not pay 100%
of the cost of new Infrastructure?
• Projects become unaffordable
• When growth occurs, everyone benefits
• Example: If a new development causes us to build a
new water tower. Existing water customers
obviously get some benefit out of that too, not just
the new development.
Page 11 of 31
9
ITEM 3.1.
Will Impact Fees Hurt Growth?
• As long as the cost of developing in Terrell is
attractive to developers, impact fees should not
restrict growth. A developer looks at all of his
costs: land cost, impact fees, construction cost,
utility connection fees, building permits, etc.
Impact fees are just one part of that.
Page 12 of 31
10
ITEM 3.1.
What can Impact Fees Pay for?
construction surveying engineering land acquisition debt service
Water supply, treatment, and roadway facilities
distribution facilities
Impact fees can also pay for
Page 13 of 31
required updates to the included in the
• Impact Fee schedule Impact Fee
• Impact Fee CIP Capital Improvement Plan 11
ITEM 3.1.
Background
• Council Actions Adopting impact fees:
• Initiated in 2004 – Ordinance 2217
• Updated in 2009 – Ordinance 2400
• Updated in 2014 – Ordinance 2597
• Updated in 2019 – Ordinance 2767
• Fees must be updated every 5 years. This is a
statutory requirement.
• Study determines the maximum fee allowable by
state law
• City Council sets the actual fee to be collected
Page 14 of 31
from new development
12
ITEM 3.1.
Historic Impact Fee Revenue
RECENT IMPACT FEES REVENUE HISTORY
$900,000
$800,000 TOTAL REVENUE (FY05-FY22) =
$4,124,527
$700,000
$600,000
$500,000
$400,000
$300,000
$200,000
$100,000
Page 15 of 31
$-
FY18 FY19 FY20 FY21 FY22
13
ITEM 3.1.
Overview of Study Tasks
Service Areas
Land Use Assumptions
Service Units
Existing Capacity, Usage & Deficiencies
Ch 395, TLGC
Projected Demand Technical
Capital Improvements Plan Requirements
Service Unit Equivalency
Cost per Service Unit Calculation Addressed in
Page 16 of 31
Study Report
Discuss CIAC Recommendation to Council
14
ITEM 3.1.
Current Fee Schedule (Single Family)
April 2, April 2, April 2, April 2, April 2,
Effective Date
2019 2020 2021 2022 2023
Water $1,221 $1,221 $1,221 $1,221 $1,221
Wastewater $2,167 $2,167 $2,167 $2,167 $2,167
Roadway* $1,952 $2,220 $2,500 $2,795 $3,104
Total $5,340 $5,608 $5,888 $6,183 $6,492
*For development within West and East service areas; $0 for Brushy Creek
Service area
Page 17 of 31
15
ITEM 3.1.
16
Benchmarking
Page 18 of 31
ITEM 3.1.
Policy Considerations
• What rate to collect; retain
previous rate?
• Application of Fee
• Residential vs. Non-residential
• Special Considerations
• Incremental Increases
• Special Considerations
• Exemptions
• Public Schools, Public Housing
Page 19 of 31
• As defined by policy
ITEM 3.1.
Fee Collection Process
1 Final plat submission
2 Fee calculated and assessed upon final plat approval
3 Fee collected at time of building permit issuance
Fees used to implement projects in the
4 Impact Fee Capital Improvement Plan
Fees are imposed on:
Page 20 of 31
• New development
• Expansion
• Change in use to higher intensity development
ITEM 3.1.
Service Areas and
Growth Rates
Page 21 of 31
ITEM 3.1.
Roadway Service Area
• Confined to city
limits
• Service areas up
to 6-mile
diameter
• Fees must be
spent in the
service area in
which they are
captured
Page 22 of 31
ITEM 3.1.
Water Service Area
• Confined
to ETJ
• One
service
area
Page 23 of 31
ITEM 3.1.
Wastewater Service Area
• Confined to
ETJ
• Does not
include
Northspur and
Eastland
developments
• One service
area
Page 24 of 31
ITEM 3.1.
Land Use/Growth Assumptions
• 10-year growth projections by service area
• Based on trend/forecasted community
growth
• Population/employment used to derive
demand from future development
• Basis for CIP development
Page 25 of 31
ITEM 3.1.
Proposed Developments (10-year)
Single-Family Multi-Family Estimated Estimated
Development Units Units Population Employment
Hillside Ranch 654 0 1,929 0
The Woodlands 278 0 820 0
The Preserve 550 0 1,623 0
Crossroads MF
Phase 1 0 285 568 0
Crossroads MF
Phase 2 0 300 598 0
Griffith and Lovers 8 0 24 0
Hunters Ridge 52 0 153 0
Terrell Assisted
Living 0 66 132 0
Griffith Forest Tract 350 0 1,033 0
The Cedars at Rose
Hill 34 0 100 0
Rose Hill Estates 170 0 502 0
Westwood 0 900 1,795 50
Magnolia Estates 41 0 121 0
Terrell Senior Living
Phase 3 0 88 175 0
Creekside Estates 440 0 1,298 0
Rose Hill Adult
Community 70 0 207 0
Western Security 1,200 300 4,138 0
Page 26 of 31
Evening Star 1,200 0 3,540 0
Eastland Park 0 0 0 12,900
Northspur 1,450 0 4,278 2,000
Arboretum Estates 2,390 630 8,307 600
Total 8,887 2,569 31,339 15,550 24
ITEM 3.1.
Growth Assumptions
• 2020-2022:
5% annual
growth
• Projected
Water: 10%
CAGR
• Projected
Roadway: 7%
CAGR
Page 27 of 31
25
ITEM 3.1.
CIAC Action: Recommendation of
Growth Rate
Page 28 of 31
ITEM 3.1.
May 25
Impact Fee 101, Growth Rates
for Land Use Assumptions
Aug 24
LUA, CIPs and Prelim
Cost per Service Unit Calculations
Impact Fee Calculations Dec 14
and Collection Rate
Feb 2
Page 29 of 31
Recommendation Letter to Council
ITEM 3.1.
May 25, 2023
Capital Improvements
Advisory Committee (CIAC)
Page 30 of 31
Impact Fee Basics and
Land Use Assumptions/Growth Rates
Road, Water and Wastewater Impact Fee Program Update
ITEM 3.2.
Page 31 of 31
Get email alerts for Terrell
A daily email when new agendas and minutes are posted.