Capital Improvements Plan Advisory Committee Meeting
Regular MeetingTomball, TX · December 9, 2019
Agenda
NOTICE OF REGULAR CAPITAL IMPROVEMENTS PLAN ADVISORY
COMMITTEE MEETING
CITY OF TOMBALL, TEXAS
MONDAY, DECEMBER 9, 2019
5:30 P.M.
Notice is hereby given of a meeting of the Capital Improvements Plan Advisory
Committee, to be held on Monday, December 9, 2019 at 5:30 P.M., City Hall, 401 Market
Street Tomball, TX 77375, for the purpose of considering the following agenda items. All
agenda items are subject to action. The Capital Improvements Plan Advisory Committee
reserves the right to meet in a closed session for consultation with attorney on any agenda
item should the need arise and if applicable pursuant to authorization by Title 5, Chapter
551, of the Texas Government Code.
1.0 Call to Order
2.0 Public Comments and Receipt of Petitions [At this time, anyone will be allowed to speak
on any matter other than personnel matters or matters under litigation, for length of time
not to exceed three minutes. No Council/Board discussion or action may take place on a
matter until such matter has been placed on an agenda and posted in accordance with
law.]
3.0 Approve the Minutes of the Capital Improvements Plan Advisory Committee Meeting of
August 12, 2019.
4.0 New Business:
4.1 Discussion and possible action on the status of Impact Fees and action regarding
filing a semi-annual report with respect to the Capital Improvements Plan and
report to City Council.
Page 1 of 26
4.2 Discussion and Action Regarding establishing the next meeting of the Capital
Improvement Plan Advisory Committee to file a semi-annual report with respect to
the progress of the Capital Improvement Plan as required by Section 395.058 of
the Texas Local Government Code.
5.0 Adjournment
CERTIFICATION
I hereby certify that the above notice of meeting was posted on the bulletin board of City Hall; City
of Tomball, Texas, a place readily accessible to the general public at all times, on the 5th day of
December, 2019 by 5:00 p.m., and remained posted for at least 72 continuous hours preceding the
scheduled time of said meeting.
Doris Speer
____________________
Doris Speer
City Secretary, TRMC
This facility is wheelchair accessible and accessible parking spaces are available Requests
for accommodations or interpretive services must be made 48 hours prior to this meeting.
Please feel free to contact the City Secretary's office at (281) 290-1002 or FAX (281) 351-
6256 for further information.
AGENDAS MAY ALSO BE VIEWED ONLINE AT www.ci.tomball.tx.us.
Page 2 of 26
Regular Capital Improvements Plan Advisory Committ
Agenda Item Meeting Date: December 9, 2019
Data Sheet
Topic:
Background:
Origination:
Recommendation:
Party(ies) responsible for placing this item on agenda:
ACTION TAKEN
Approval Readings Passed Other
Yes No 1st 2nd
Page 3 of 26
Regular Capital Improvements Plan Advisory Committ
Agenda Item Meeting Date: December 9, 2019
Data Sheet
Topic:
Approve the Minutes of the Capital Improvements Plan Advisory Committee Meeting of August 12, 2019.
Background:
Origination:
Recommendation:
Party(ies) responsible for placing this item on agenda:
ACTION TAKEN
Approval Readings Passed Other
Yes No 1st 2nd
ATTACHMENTS:
De s c r i pt i on
CIPAC Minutes - 08-12-2019
Page 1 of 3
Page 4 of 26
MINUTES OF SPECIAL
CAPITAL IMPROVEMENT PLAN
ADVISORY COMMITTEE MEETING
CITY OF TOMBALL, TEXAS
MONDAY, AUGUST 12, 2019
5:00 P.M.
1.0 The meeting was called to Order at 5:02 p.m. by Chairman Tague. Other members present were:
Commissioner Richard Anderson
Commissioner Michael Chambers
Commissioner Dane Dunagin
Commissioner Darrell Roquemore
Commissioner Will Benson Jr.
Others present:
Community Development Director – Craig Meyers
Public Works Director – Beth Jones
City Attorney – Loren Smith
Assistant City Engineer – Wesley Stolz
Community Development Coordinator – Elizabeth Jones
2.0 No Public Comments were received.
3.0 Motion was made by Commissioner Dunagin, second by Commissioner Anderson, to approve
the Minutes of the Capital Improvements Plan Advisory Committee Meeting of June 10, 2019.
Motion carried unanimously.
Discussion/Action of the Following Items:
4.0 New Business:
4.1 Presentation and Discussion of Land Use Assumptions, Capital Improvements Plan (CIP)
and Impact Fee Analysis for Water and Wastewater, relating to possible adoption of
updated Impact Fees; Consideration of Written Comments to be Provided to the City
Council; in accordance with Chapter 395, Texas Local Government Code; Making Other
Findings and Providing Details Related Thereto.
Craig Meyers, Community Development Director and Richard Weatherly,
Consultant provided summary of Impact Fees and opened discussion for
Commissioners.
Page 2 of 3
Page 5 of 26
Minutes
Capital Improvement Plan Advisory Committee Meeting
August 12, 2019
Page 2 of 2
4.2 Discuss and finalize comments and recommendation of Impact Fees to be presented to
City Council on October 7, 2019.
Commissioner Roquemore made a motion to recommend a 15% increase each year over
the next five years for the water impact fee and the maximum allowable for the
wastewater impact fee; second by Commissioner Anderson.
Motion carried unanimously.
5.0 Motion was made by Commissioner Anderson, second by Commissioner Benson, to adjourn.
Motion carried unanimously.
Meeting was adjourned at 5:53 p.m.
Page 3 of 3
Page 6 of 26
Regular Capital Improvements Plan Advisory Committ
Agenda Item Meeting Date: December 9, 2019
Data Sheet
Topic:
Discussion and possible action on the status of Impact Fees and action regarding filing a semi-annual report
with respect to the Capital Improvements Plan and report to City Council.
Background:
Origination:
Recommendation:
Party(ies) responsible for placing this item on agenda:
ACTION TAKEN
Approval Readings Passed Other
Yes No 1st 2nd
ATTACHMENTS:
De s c r i pt i on
PowerPoint
Page 1 of 19
Page 7 of 26
Capital Improvement Projects
Advisory Committee
Impact Fee Update
December 9, 2019
Page 2 of 19
Page 8 of 26
Current Impact Fees
Page 3 of 19
Page 9 of 26
Impact Fees Collected
• Fiscal Year 2019
• $361K for water
• $362K for sanitary sewer
• $0K for drainage
• Fiscal Year 2020 (as of December 2, 2019)
• $64K for water
• $64K for sanitary sewer
• $265K for drainage
Page 4 of 19
Page 10 of 26
Impact Fees Fund Balances
• Fund Balances (as of December 2, 2019)
• $2.4M for water
• $1.8M for sanitary sewer
• $73K for drainage
Page 5 of 19
Page 11 of 26
Current Projects
Page 6 of 19
Page 12 of 26
Alley Improvement Project
• Description: Enhancement to Alleyways in the Downtown area (100
Block North and South of Main) to include pavement and lighting.
In addition we will also complete sidewalks in areas of Downtown
and Zion Road to the remaining areas as well as the addition of a
parking area near Commerce Street and Cherry Street. Pavement,
lighting
• Progress: A contract has been issued for the design and is currently
75% complete. Staff is working with the TEDC for possible grants to
the business owners along the identified alleyways for
improvements.
Page 7 of 19
Page 13 of 26
Page 8 of 19
Page 14 of 26
Page 9 of 19
Page 15 of 26
Page 10 of 19
Page 16 of 26
Page 11 of 19
Page 17 of 26
M121 West Drainage Channel
Page 12 of 19
Page 18 of 26
11
M121 Drainage Channels
Description: The M121 basin consists of two drainage channels, i.e. 121W
& 121E, and an associated detention pond (M500), serving a central area
of Tomball. Project is to alleviate conditions that cause localized flooding
and eliminate on-site detention.
Progress:
– Pipeline Relocation project for removal and lowering of pipelines
along the project location, has been awarded to MK Constructors with
an estimated completion date of May 17, 2020.
– Channel digging has been awarded to Rebel and began construction
on December 2, 2019. Estimated completion is 4th quarter of 2020.
– Harris County is to reconstruct and widen Holderrieth Road.
Page 13 of 19
Page 19 of 26
12
Medical Complex Dr. Extension
SEGMENT 4
Segment 4B
Segment 4
Description: Segment 4 of the proposed Medical Complex Corridor
commences at Cherry St and continues easterly to South Persimmon
and terminates at Hufsmith-Kohrville as well as from South
Persimmon to the TEDC Business and Technology Park. Medical
Complex Corridor is depicted on the COT’s Major Thoroughfare Plan
as a major east-west connector to FM 2920 (east & west of Tomball).
Seg. 4B Estimated cost: $20M = $4.0M (TEDC Funded) and $16M (City
of Tomball Funded)
Progress: Segment 4B design is approximately 80% complete.
Three properties have been acquired for ROW, four properties are
pending closing and the final two are in negotiations. Construction 13
Page 14 of 19
estimated to begin Spring 2020.
Page 20 of 26
Broussard Community Park
Description: Proposed Community Park located on E. Hufsmith near the intersection of Zion
Rd. The park will include soccer fields and interactive areas.
Progress:
Construction phase of all fields, pond grading, entrance, parking areas and irrigation is
100% complete. Fields will be ready for play Spring 2020.
An Interlocal Agreement for the maintenance and operation of Broussard Park has been
executed between the City and Harris County. Harris County is currently in the process
of installing the walking trails and picnic areas throughout the park; once all trails are
installed exercise equipment will be installed. The Sensory Cottage, ADA swing and
fishing pier have been installed. A wildflower area has been designated and will be
planted in the spring.
A contract has been issued for the installation of electrical to the park and construction
of the restroom and concession stand area.
Page 15 of 19
Page 21 of 26
14
Broussard Community Park
Page 16 of 19
Page 22 of 26 15
Additional Projects Underway…
• Rudolph Road Sewer – currently complete for design and
working to acquire needed Right-of-Way and Easements.
Two remaining parcels needed for acquisition before
project can go to construction.
• Sewer Plant Improvements (Critical Needs Assessment) –
Approx. $4.0M improvements and repairs are being done.
Construction of Phase I is approximately 99% complete and
Phase II is currently in the process of being prepared for
bid.
• Wayne Stovall Park Improvements – Design for renovation
of the equipment barn has been completed to include a
restroom. Staff is working to develop bid specifications to
solicit bids.
Page 17 of 19
Page 23 of 26
Additional Projects Underway…
• Zion & E. Hufsmith Utility Improvements – Installation of water line along Zion
has been completed. The installation of the water, sewer and gas from
Broussard Park to the Harris County Flood Control Ditch is currently 90%
complete; this will connect the force main at Broussard Park to the Lift Station
at Snook and provide utility services to the new residential developments
along E. Hufsmith.
• M&R for Matheson Park – an assessment of the park was completed to
determine the highest priority for repairs and replacement of park equipment.
The assessment was utilized to develop a park Master Plan for Matheson;
based on that Master Plan staff is currently in the process of creating a new
vision with needed enhancements and upgrades with Kompan.
• Theis Attaway Nature Center – an Invasive Species Study has been completed
and implementation of Phase I should begin Spring 2020. A Visioning
Document has been prepared for the needed enhancements for Theis in order
to ensure proper maintenance of the Nature Center and staff is currently
working with the donor family to formulate a plan for the future.
Page 18 of 19
Page 24 of 26
Questions / Comments
Page 19 of 19
Page 25 of 26
Regular Capital Improvements Plan Advisory Committ
Agenda Item Meeting Date: December 9, 2019
Data Sheet
Topic:
Discussion and Action Regarding establishing the next meeting of the Capital Improvement Plan Advisory
Committee to file a semi-annual report with respect to the progress of the Capital Improvement Plan as
required by Section 395.058 of the Texas Local Government Code.
Background:
Origination:
Recommendation:
Party(ies) responsible for placing this item on agenda:
ACTION TAKEN
Approval Readings Passed Other
Yes No 1st 2nd
Page 26 of 26