Public Works Committee
Regular MeetingTumwater, WA · January 5, 2023
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and Charlie
Schneider.
Staff: Water Resources & Sustainability Director Dan Smith, Sustainability
Coordinator Alyssa Jones Wood, and Department Assistant II Bonnie Hale.
Others: Meridith Greer, Greer Environmental Consulting.
APPROVAL OF
MINUTES: PUBLIC
WORKS
COMMITTEE,
DECEMBER 8, 2022:
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to approve the minutes of December 8, 2022 as published. A
voice vote approved the motion unanimously.
SOLSMART Sustainability Coordinator Jones Wood presented the proposal to initiate
PROGRAM efforts for the City to receive accreditation as a SolSmart community.
PROPOSAL: SolSmart is a national technical assistance and designation program designed
to recognize local jurisdictions for encouraging solar energy growth and
addressing barriers to solar energy. The program was created in 2016 by the
U.S. Department of Energy’s Solar Energy Technologies Office. The
SolSmart program has Bronze, Silver, and Gold designation levels. Eight
communities in Washington have been designated under SolSmart with four
communities designated as Bronze, one community as Silver, and three Gold
designations (City of Olympia, City of Issaquah, and the City of Mercer
Island). The SolSmart designation is an action identified within the Thurston
Climate Mitigation Plan. The first step in receiving the designation is
submittal of a Solar Statement to enable the City to receive technical
assistance for the program from a SolSmart consultant. The technical
assistance is provided at no cost to the City.
SolSmart assists the City in reducing solar soft costs for residents and
businesses installing solar on their homes and businesses. Soft costs are
actions required through the permitting process, which can account for 66%
of the total cost for installing solar photovoltaic (PV) systems. SolSmart
estimates soft costs can be approximately $2,500 per system. The goal of the
program is to eliminate soft costs to make installation of the systems
transparent and easier to understand.
The first step for pursuing SolSmart designation is to connect with SolSmart
technical assistance providers through a consultation call. During the call,
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 2
technical assistance providers describe the program and process, learn about
the City’s solar goals, and identify the applicable SolSmart Designation
Criteria for the City. The consultation call and all technical assistance are
provided at no cost because of a grant through the U.S. Department of
Energy. The City is targeting for SolSmart Silver because of staff capacity
with a future goal to achieve SolSmart Gold.
Coordinator Jones Wood advised that she has completed the first
consultation call with the technical advisors. The next step is submittal of
the written commitment (Solar Statement) to enable the City to receive
technical assistance. Following successful designation as a SolSmart
community, the City is able to publicize the designation and display a glass
plaque signaling to the community the City’s efforts to reduce barriers for
the installation of solar energy systems.
Coordinator Jones Wood described the steps required to achieve Silver
SolSmart designation. To receive Gold SolSmart designation, the City must
meet the requirements for Bronze and Silver designations, as well as
requirements for Gold SolSmart designation. Those requirements include
codifying the zoning ordinance to eliminate barriers and commit to a three-
business day turnaround for permit review for small rooftop solar systems.
Councilmember Althauser described the experience he encountered when he
installed a small rooftop solar system on his house. The process for permit
review entailed a 40-day period delaying the ability for his system to
generate energy. Another challenge within the process is the requirement for
the Department of Labor and Industries (LNI) to inspect electrical work as
opposed to the City inspecting electrical. Coordinator Jones Wood
responded that she understands the City oversees residential solar and L&I
oversees commercial; however, L&I also must inspect electrical. She plans
to contact City of Olympia staff to learn how Olympia was able to work with
L&I in order to achieve Gold accreditation.
Councilmember Althauser added that another factor not under the control of
the City is the requirement for Puget Sound Energy (PSE) to install the
appropriate meter for the solar system. Between the L&I inspection and PSE
meter installation, over two months in the summer lapsed without the ability
to generate at least 32 kilowatts of clean electricity.
Councilmember Althauser asked about plans for the Tumwater School
District to receive a SolSmart designation. Coordinator Jones Wood advised
that the City and L&I serve as the permitting agencies. The school district
would not be eligible to seek SolSmart designation because they are not a
permitting agency.
Chair Swarthout inquired about the coordination between the SolSmart
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 3
program and energy providers. Coordinator Jones Wood explained that as
part of the City’s process for seeking accreditation, staff will develop a solar
webpage offering a one-stop location for residents and businesses to obtain
information on local installers, available financial incentives, financing
options, and protections as a consumer for solar installations.
Chair Swarthout shared that she was recently advised by L&I that the
department is required to inspect electrical work within 72 hours of being
notified. She is unsure as to the turnaround time for PSE.
Coordinator Jones Wood asked the Public Works Committee to recommend
the City Council authorize the Mayor to sign a solar statement to begin the
process of seeking SolSmart accreditation.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council authorize the Mayor to sign
a solar statement to begin the process of seeking SolSmart accreditation.
A voice vote approved the motion unanimously.
GRANT Consultant Greer reported the City received a Washington State Department
AGREEMENT WITH of Ecology grant to complete three Stormwater Management Action Plans
THE DEPARTMENT (SMAPs) for the three highest priority subbasins within the City. SMAPs
OF ECOLOGY FOR are watershed-based approaches to stormwater management, which allow
SMAP staff to collect data about each subbasin and specifically tailor management
STORMWATER actions to help improve water quality based on several factors including land
BASIN PLANNING: use, pollutants of concern, and habitat health. The current focus is the
Trosper Lake Subbasin to meet a permit deadline by March 31, 2023. Some
of the subbasin priorities include developing an enhanced street sweeping
plan, developing and implementing a ditch maintenance program, launching
the business source control program effective in 2023 focusing on businesses
located within the subbasin, and development of a stormwater monitoring
program. The remaining two subbasins of focus over the next year include
West Mottman Subbasin and Fish Pond Creek Subbasin.
The Department of Ecology grant funds 75% of the City’s total cost. She
asked the committee to move the agreement forward to the City Council.
The grant agreement expires January 31, 2025. The City of Tumwater’s
Stormwater Utility will cover the remaining 25% of the project cost.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
Mayor to sign the Grant Agreement with the Department of Ecology for
SMAP Stormwater Basin Planning. A voice vote approved the motion
unanimously.
GRANT Consultant Greer reported the golf course received Salmon Safe Certification
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 4
AGREEMENT WITH in 2019. Salmon Safe is a standard many golf courses are achieving to make
THE DEPARTMENT golf courses and other facilities salmon safe and friendly for salmon. Part of
OF ECOLOGY FOR the certification required providing stormwater treatment for the parking lot.
THE GOLF COURSE Some other requirements have been completed. The next step is designing
PARKING LOT the golf course parking stormwater retrofit project. The parking lot is
STORMWATER scheduled for resurfacing in summer 2023. The agreement helps staff to
RETROFIT DESIGN: align the projects concurrently. Currently, stormwater from the parking lot
drains untreated to the Deschutes River from two locations at the Tumwater
Valley Golf Course parking lot. The proposal is to design a bioretention
facility to capture stormwater from the golf course parking lot and provide
treatment before discharging to Deschutes River. The facility will treat for
total suspended solids (TSS), dissolved copper, total phosphorous, and
dissolved zinc.
Funding from the Department of Ecology will cover 46.4% of the total
project cost with the remaining from the City’s Parks and Facilities Capital
Budget. The two proposals include the grant agreement with the Department
of Ecology and a Service Provider Agreement with Skillings Inc. for the
Golf Course Parking Lot Stormwater Retrofit Design of $84,000.
Chair Swarthout inquired about the status of the Valley Athletic Club
parking lot and any interest by the club to participate in the project.
Consultant Greer advised that the project scope is only applicable to the golf
course parking lot. Water Resources Department goals include technical
assistance to local businesses. Should the club convey interest in retrofitting
its parking lot, staff would meet with the business to provide assistance.
Staff is currently working on stormwater and flood-related issues as part of
the Deschutes River Flood Reduction Study. There could be future
opportunities if the study identifies areas that might benefit from retrofits for
stormwater.
Councilmember Althauser asked about the loss of parking spaces caused by
the retrofit project. Consultant Greer responded that the conceptual designs
do not represent any loss of parking spaces. The project scope is an area of
5,000 square feet located north of the parking lot between the parking lot and
the Deschutes River. The priority is not losing parking spaces.
Chair Swarthout questioned whether the club is required to treat its
stormwater. Director Smith replied that there are no retrofit requirements by
the state unless the business was planning to complete some improvements.
Chair Swarthout reviewed the requested action.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 5
Mayor to sign the Grant Agreement with the Department of Ecology for
the Golf Course Parking Lot Stormwater Retrofit Design. A voice vote
approved the motion unanimously.
SERVICE Consultant Greer requested the committee recommend the City Council
PROVIDER approve and authorize the Mayor to sign the Service Provider Agreement
AGREEMENT WITH with Skillings Inc. for the Golf Course Parking Lot Stormwater Retrofit
SKILLINGS INC. Design.
FOR THE GOLF
COURSE PARKING
LOT
STORMWATER
RETROFIT DESIGN:
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
Mayor to sign the Service Provider Agreement with Skillings Inc. for the
Golf Course Parking Lot Stormwater Retrofit Design. A voice vote
approved the motion unanimously.
SERVICE Director Smith commented on some inconsistent information contained
PROVIDER within the staff report and advised that the amendment request is for
AGREEMENT WITH $21,620. The amendment is requested for Greer Environmental Consulting
GREER to accommodate project changes over the last year since the initial agreement
ENVIRONMENTAL was executed to include the addition of one project and several scopes for
CONSULTING another project. The new project is for the Percival Creek Culvert across
AMENDMENT 2: Percival Creek at Somerset Hill Drive caused by bank erosion from an
undersized culvert and high velocity flows. The project has been added to
the contract. Project management is $42,095.
A second change in scope is the Deschutes River Reduction and Erosion
Study at the former brewery properties to determine factors causing flooding
and steps to reduce flooding. Some additional stakeholder efforts were
requested by the Department of Ecology. The grant increased since the
original project scope was negotiated with Greer Environmental Consulting.
Staff is proposing to add several additional tasks at a cost of approximately
$4,000 in project management additions.
The last change pertains to the East Linwood Basin Retrofit project.
Because the City was unable to reach an agreement with the property owner
to acquire property necessary for managing stormwater through best
management practices, the grant received by the City cannot be utilized at
this time. Other elements evaluated for the project were deemed not cost-
effective for stormwater treatment. Staff continues to pursue additional
options, such as downstream treatment. Consultant Greer has pursued
conversations with other local agencies to consider a larger flood
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 6
management grant for the entire watershed. Consequently, the return of the
grant to the Department of Ecology affects the agreement resulting in a
decrease within the agreement of $24,470.
The total revised contract cost is $305,970 representing an additional
$21,620. The request is to recommend the City Council approve and
authorize the Mayor to sign the Service Provider Agreement with Greer
Environmental Consulting Amendment 2 for project management services in
an amount not to exceed $21,620.00.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
Mayor to sign the Service Provider Agreement with Greer
Environmental Consulting Amendment for project management
services in an amount not to exceed $21,620.00. A voice vote approved
the motion unanimously.
WATER SYSTEM Director Smith provided an update on water supply capacity as a
CAPACITY continuation of a conversation on the Comprehensive Water System
UPDATE: Management Plan adopted in 2021.
Director Smith displayed a series of images and graphs during his
presentation. Water capacity is based on water system equivalent residential
units (ERUs). The formula is used to forecast the number of residential,
commercial, and industrial uses that could be developed and supported by
the City’s water system. The City has a total water right portfolio
representing end use allocation of current water customers totaling 22,756
ERUs. Additional ERU requests include 170 ERUs in 2020, 1,136 ERUs in
2021, and 274 ERUs in 2022. Water rights to accommodate those ERUs are
reserved for those projects. The amount of requested ERUs is closely
tracked to avoid exceeding water rights capacity. Nearing or exceeding the
capacity threshold could result in a development moratorium.
Today, the City’s total water portfolio is approximately 34,710 ERUs. Of
that amount, approximately 1,600 ERUs are reserved, 22,756 ERUs are
existing customers, and another 3,278 ERUs are designated for future uses.
The City submitted two water right applications to the Department of
Ecology. One application is for the Southwest Wellfield, which would need
to be significantly modified to acquire the water right at the desired capacity
of 19,435 ERUs. The application is a placeholder and could be generated
from other water right applications if a path forward can be identified to
satisfy Department of Ecology requirements. The second water right
application is for 4,736 ERUs and is being actively pursued. If successful
with the two water right applications, the total amount of capacity of ERUs
would be 36,125 providing the City with additional headway for the
provision of water.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 7
One of the challenges of the City’s watershed, the Deschutes River, is
finding new water. New sources could be from agriculture water rights or
subdivisions that might convert to City water (generally do not provide new
capacity as the water right had been allocated). Today, the City has
approximately 10,000 ERUs that are not obligated.
Councilmember Schneider mentioned the proposal of a soda bottling plant
near the airport and the possibility of using one million gallons of water. He
asked about the timeline for using a million gallons of water and the source
of the water. Director Smith advised that the source of water would be the
City’s water system. The proposed use is forecasted to be 600,000 gallons of
water a day at full operation, representing a significant user. The City has
the capacity of serving a significant user but it would result in approximately
7,000 ERUs remaining in reserve.
Director Smith displayed and described an average day demand graphic
reflecting the City’s ability to meet daily customer water demands. Today,
the average day demand is 2.5 million gallons. The graph forecasts both
growth and demand. Another tracking mechanism is the City’s existing
ability to pump sufficiently to meet demands on an average day. Based on
the planning horizon, the City is able to meet average day demands through
2038. The graph also reflects how several future large users (1 million
gallons per day) would impact the forecast, which is forecasted in the water
system planning process. Based on the forecast, the City would be able to
accommodate two additional large users.
Councilmember Althauser questioned how future large uses could impact
capacity during the summer when usage is higher. Director Smith explained
that many of the improvements forecasted over time increase the City’s
capacity to meet demand. The maximum day demand as forecasted in the
planning level estimate could be affected by different variables during the
summer, such as the loss of source, or a surge in irrigation use. The issues
experienced by the City of Lacey are related more to conveyance rather than
production factors. The City’s water system modeling accounts for peak day
demands and fire flow demands throughout the year.
Director Smith referred to the City’s existing ability to pump water. By
2028 after the first large user comes on line, the City may experience
significant challenges to meet the demand. A number of projects have been
identified to avoid that situation. With the recent acquisition of the Lathrop
Water System, the City can exercise those water rights of 300 gallons per
minute. Last year, the City purchased the golf course water right, which
needs to be activated and added to the system. Those two projects add 8,000
gallons per minute per day to meet demands to the end of the planning
horizon. Additionally, the City’s brewery wellfield project is underway
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 8
providing 10,000 future gallons per minute per day to help meet maximum
day demands.
The biggest challenge in terms of future source is the Southwest Wellfield as
the project is uncertain and requires some modifications.
With some system modifications, the City currently produces approximately
7 million gallons of water a day. Based on capacity, the City is able to
accommodate some significant users in the future.
Director Smith responded to questions about the City’s ability to keep pace
with water system infrastructure needs. Future infrastructure needs are
forecasted in the Comprehensive Water System Plan by identifying areas of
deficit flows, lower pressures, or areas of future greater demands, etc. Water
system modeling determines the kind of infrastructure improvements
required.
Director Smith reviewed the circumstances resulting in the temporary loss of
Well 17. The City was able to meet demand during that period.
Director Smith reviewed future milestones:
Consultant – Scope Development and Preliminary Planning with
Carolla Engineers
Hiring of Water Resources Program Manager – Focus will be on
source development, integration of Lathrop water rights, and Well 15
reliability by adding backup power source
Projects – Brewery Wellfield, Golf Course Integration, well
decommissioning
Water Rights Acquisitions
Pursue new water right applications
Councilmember Schneider commented on his concern that the planning
horizon of 2028 was inadequate for planning future water capacity needs
because of the inherent long process of obtaining water rights. He asked
whether conservation measures were factored within the capacity and usage
forecasts. Director Smith affirmed water conservation measures are factored
within the planning timeline. The City sponsors a conservation program.
Staff will be exploring the revision of the current conservation plan as the
City develops new incentives and considers different programs, especially
because LOTT Clean Water Alliance does not plan to offer water
conservation incentives. Another planning line within the forecast represents
a level without any water conservation. He added that the need may have
changed with the advent of technology in appliances and updated regulations
to reduce water consumption. Staff is working on researching other types of
water conservation programs.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 5, 2023 Page 9
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 9:08 a.m.
Prepared by Valerie Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, January 05, 2023
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee, December 8, 2022
4. SolSmart Program Proposal (Alyssa Jones Wood)
5. Grant Agreement with the Department of Ecology for SMAP Stormwater Basin Planning (Dan Smith)
6. Grant Agreement with the Department of Ecology for the Golf Course Parking Lot Stormwater
Retrofit Design (Chuck Denney)
7. Service Provider Agreement with Skillings Inc. for the Golf Course Parking Lot Stormwater Retrofit
Design (Chuck Denney)
8. Service Provider Agreement with Greer Environmental Consulting Amendment 2 (Dan Smith)
9. Water System Capacity Update (Dan Smith)
10. Additional Items
11. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/87896010681?pwd=cjErOGtwcjlHdmQrdzlyYTkzMUM4UT09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 878 9601 0681 and Passcode
567159.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.
Get email alerts for Tumwater
A daily email when new agendas and minutes are posted.