Public Works Committee
Regular MeetingTumwater, WA · April 6, 2023
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and Charlie
Schneider.
Staff: City Attorney Karen Kirkpatrick, Water Resources and Sustainability
Director Dan Smith, Capital Projects Manager Don Carney, Engineering
Services Manager Bill Lindauer, Transportation Manager Mary Heather
Ames, Water Resources Specialist Dave Kangiser, and Administrative
Assistant Bonnie Hale.
Others: Meridith Greer, Greer Environmental Consulting.
APPROVAL OF
MINUTES: PUBLIC
WORKS
COMMITTEE,
MARCH 9, 2023:
MOTION: Councilmember Schneider moved, seconded by Chair Swarthout, to
approve the minutes of March 9, 2023 as published. A voice vote
approved the motion. Councilmember Althauser abstained.
RESOLUTION NO. Consultant Meridith Greer with Greer Environmental Consulting, briefed the
R2023-007 committee on the proposed resolution to delegate signature authority for
DELEGATION OF grant documents for design of the Somerset Hill Fish Passage Barrier
SIGNATURE Removal Project.
AUTHORITY FOR
GRANT DOCUMENTS Percival Creek originates from Trosper Lake and travels through the City to
RELATED TO Capitol Lake. Some of the limiting factors of the creek are fish passage
SOMERSET HILL barriers, stream temperature, and the lack of large wood debris and habitat.
FISH PASSAGE The City is pursuing many projects along Percival Creek. The creek has 10
BARRIER REMOVAL potential barriers or areas where roads cross the creek. One full barrier is
DESIGN: located at Sapp Road. The City has been working on the design for that
project with the City receiving construction funding for construction in
summer 2024. Two potential barriers are located at Somerset Hill and north
of I-5 are owned by the Department of Fish and Wildlife.
The Somerset Hill project area includes a 5-foot culvert of approximately
103 feet in length serving as a partial barrier because of velocity. The area
was assessed in 2015 and reassessed in 2022 confirming the culvert serves as
a partial barrier. Ideally, a correctly sized culvert enables fish and water to
move naturally throughout the creek. Following measurements of all
footprints in the area of the culvert, the minimum crossing size is 22 feet,
which will require a larger culvert than the 19-foot culvert for the Sapp Road
project.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 2
The City is seeking funding from the Washington State Recreation and
Conservation Office’s Salmon Recovery Funding Board to fund the design
work for the project. The grant is for $280,000, and the funding source
requires no match from the City. One of the requirements of the grantee is
for the City to adopt a resolution authorizing the City to submit an
application for the grant.
Staff continues to work with Skillings to complete a type size and location
study for the culvert. Staff is considering three different culvert designs of a
three-sided box culvert, installation of a prefabricated bridge, or installation
of a steel plate arch culvert. All options have different pros and cons from a
cost perspective. Skillings is completing the report, which will provide more
information on moving forward to complete the design grant application.
The project can potentially impact Chum, Coho, Chinook, steelhead, and
residential trout based on fish sampling in 2019 documenting salmon in the
system. Fish are unable to travel above Sapp Road, which speaks to the
importance of continuing work along the creek to ensure access to the
system by fish.
Ms. Greer requested the committee recommend the City Council approve
and authorize the Mayor to sign Resolution No. R2023-007 Somerset Hill
Fish Passage Barrier Removal Design. She invited questions from the
committee.
Councilmember Schneider inquired about the difficulty of removing the
culvert without collapsing the road. Ms. Greer said one option is replacing
the culvert with a similar type of culvert followed by replacing top fill. The
option of a prefabricated bridge, which creates more open space, involves
installing the bridge and stabilizing the bank in the area to avoid a cave-in.
Skillings is considering those options as it evaluates alternatives in addition
to costs to construct and the feasibility of options that will ensure the project
is stable and strong to hold existing fill and the roadway.
Director Smith added that the resolution authorizes the Director of Water
Resources and Sustainability to sign and administer all grant paperwork.
Chair Swarthout asked whether the project area is also near an area that the
City had experienced some sewer backup. Ms. Greer replied that one of the
goals of the project is to protect existing infrastructure to include sewer
infrastructure serving the neighborhood. In the past, the neighborhood has
experienced sewer overflow issues. The City installed a remote metering
device to alert the City to potential overflow activity. The existing
configuration of the culvert increases water velocity directly to the bank
creating concerns of bank erosion and potentially destroying trees that might
impact sewer lines from uprooted tree root systems.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 3
Chair Swarthout reviewed the proposed request for consideration.
MOTION: Councilmember Schneider moved, seconded by Councilmember
Althauser, to recommend the City Council approve and authorize the
Mayor to sign Resolution No. R2023-007 Somerset Hill Fish Passage
Barrier Removal Design. A voice vote approved the motion
unanimously.
SERVICE PROVIDER Manager Carney reported the proposal is a service provider agreement with
AGREEMENT WITH HDR Engineering for the Old Highway 99 and 79th Avenue Roundabout
HDR ENGINEERING, project located at the intersection of Old Highway 99 and 79th Avenue.
INC. FOR THE OLD Additionally, the project includes sidewalk improvements on 79th Avenue
HIGHWAY 99 AND near a proposed trail and park. Frontages along the City’s new Maintenance
79TH AVENUE and Operations facility and the park will be improved as part of the project
ROUNDABOUT with other improvements of small sections between the site and the new
PROJECT: roundabout to ensure no gaps exist in the sidewalk.
In the 2016, the Transportation Master Plan identified the intersection for
improvement. The current level of service at the intersection is significantly
low. The roundabout will increase level of service to A. Additionally, the
Old Highway 99 Corridor Study identified the need for a roundabout at that
intersection.
Manager Carney displayed a concept design of the roundabout that was
prepared as part of the Old Highway 99 Corridor Study. The design is
similar to the design for the roundabout at Trosper Road and I-5 for
consistency within the City’s transportation system. The next step is
completing 100% design and estimates necessary to initiate construction.
The consultant fees total $735,000 and the source of funding is from
transportation impact fees. Additional funds are from the General
Government, Water, Sewer, and Stormwater Utility Capital Facilities Plans
(CFPs).
Councilmember Schneider asked about the timing of the roundabout in terms
of construction of the park. Manager Carney explained that it is dependent
upon the timing of design for both projects. The intent is completing designs
quickly and initiating construction as soon as possible. However, at this
time, it is difficult to forecast the timing of each component.
Councilmember Althauser asked about the timing for deliverables from the
consultants. Manager Carney said 30% design for the roundabout is
scheduled for completion by late summer 2023 with 60% design completed
in late spring 2024. Completion of design and construction drawings is
scheduled for late 2024.
Councilmember Althauser asked whether the analysis reflected any
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 4
acknowledgement of the safety aspect associated with roundabouts by
slowing traffic. Manager Carney advised that although he was not a party to
the Old Highway 99 Corridor Study, roundabouts are associated with
improving traffic safety as roundabouts slow traffic and decrease the impacts
of vehicle accidents.
Chair Swarthout reviewed the proposed request for consideration.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
Mayor to sign the Service Provider Agreement with HDR Engineering,
Inc. for the Old Hwy 99 and 79th Ave Roundabout. A voice vote
approved the motion unanimously.
AUTHORITY TO Manager Lindauer reported the request is for authorization to solicit
SOLICIT BIDS AND construction bids and increase change order authority for the project.
AWARD CONTRACT
FOR THE 2023 During the planning phase of paving projects, staff utilizes the pavement
PAVEMENT condition index, a system of evaluation of roadways in the City for
MAINTENANCE prioritization of road projects. The information is verified during field visits
PROJECT: with engineers to ensure repairs are timely based on the extent of damage to
the roadway. Another project goal is maximizing Transportation Benefit
District (TBD) funds to ensure expenditure of funds is appropriate for the
project to increase the life of roadways.
The proposed project is larger than most pavement projects the City has
completed. Two components of the project include paving and maintenance.
The paving component entails asphalt overlays and inlays. The project
includes sidewalk ramp repairs, replacement of manhole covers, and minor
stormwater drainage repairs. The roadway maintenance component includes
the Citywide pavement-marking project combined this year with the
pavement project. The project involves restriping the roadways throughout
the City. A plastic pavement marking replacement component is also
included for specific roadways to replace existing plastic pavement markings
and damaged or missing raised pavement markings throughout the City. An
important part of the maintenance component is the crack sealing and
roadway repair to crack seal pavement to prevent water from infiltrating into
the roadway.
Manager Lindauer displayed an aerial illustration of the project area
comprised of roadways throughout the City. He shared a copy of the
pavement maintenance map designating the different areas of the project.
Manager Lindauer reported the engineer’s estimate for the project is $4
million with an expectation that the range would be $3.6 million to $4.4
million dependent upon bids received as asphalt pricing is in constant flux.
Funding is from the TBD. The project timeline is 50 working days or
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 5
approximately 2-1/2 months. The schedule includes bid opening in mid-May
and contracting by mid-June with construction from July through August and
early September.
Currently, Tumwater Municipal Code designates change order authority of
10% of the project cost. In previous projects, the authority was increased to
20%. The request is to increase the authority to 20% because pavement
projects are different from other design-bid-build projects as the work is fast-
paced and contractors mobilize for a large volume of work in a short span of
time. The proposal enables staff some flexibility during the project to ensure
the best outcomes for the project when conditions change in the field.
Councilmember Schneider commented that during his participation in the
Adopt-a-Road Program, he continually picks up plastic road markings. He is
also concerned about the markings that could possibly enter the City’s storm
drains. He asked whether the plastic markings are installed based on a state
or federal requirement. Manager Lindauer advised that installation of plastic
markers is a local decision; however, due to the Pacific Northwest climate,
striping is a “hit or miss” option, which is why raised pavement markings are
used to help delineate roadways during inclement weather. The devices have
a lifespan and will eventually become dislodged.
Manager Lindauer addressed questions on the change order authority
request. Manager Lindauer said the increase authorizes a change in the
contract price up to 20%. The change in authority has been implemented for
previous pavement projects. The issue does not pertain to funding as the
TBD has sufficient funds to absorb an increase in cost. The main purpose is
to accommodate quick changes based on the type of project. Once a
contractor begins moving asphalt, the process is extremely expensive to stop.
City Attorney Kirkpatrick added that additionally, the City has been able to
expand the scope of work because pricing was favorable, which was possible
because of the increase in change order authority.
Chair Swarthout asked about the status of the partnership with Thurston
County for various components completed on previous projects.
Transportation Manager Ames explained that discussions have occurred with
Thurston County staff. City staff has worked with Thurston County on the
roadway striping component for previous projects; however, at this time, a
nexus is lacking for jointly working with Thurston County. Joint
conversations are continuing to identify projects where it is possible to
participate.
Chair Swarthout reviewed the proposed request for consideration.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to authorize staff to solicit bids for the 2023 Pavement
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 6
Maintenance Project and recommend City Council award and authorize
the Mayor to sign a public works contract with the lowest responsible
bidder. Staff also requests that the Public Works Committee
recommend the City Council increase the change order authority
provided to the Transportation and Engineering Director under
Tumwater Municipal Code 2.14.060 to 20 percent for this project. A
voice vote approved the motion unanimously.
AGREEMENT WITH Director Smith reported on statewide recognition the City is receiving for its
CLEARCREEK best management practices deployed for managing beaver activities during
CONTRACTORS FOR an upcoming presentation by Water Resources Specialist Dave Kangiser and
THE 2023 PALERMO City stormwater staff.
LAGOON DREDGING
& MAINTENANCE Director Smith presented the proposal, which was presented to the
PROJECT: committee last June during a review of the interlocal agreement with the
Washington State Department of Transportation (WSDOT), which serves as
the primary responsible party for the Palermo Superfund Project. WSDOT
has been investigating the contaminant plume, PCE, and TEC contaminants
moving through the Palermo neighborhood. The aeration lagoon serves as a
catch basin for surface water draining around the edge of the neighborhood
perimeter.
Following adoption of the interlocal agreement in 2022, staff solicited bids
and received one bid, which was higher than scoped with WSDOT. In
January 2023, staff sought an amendment to increase the amount of the
contract with WSDOT. The City is managing the project and is responsible
for soliciting bids and developing the contracts with the contractor, and
WSDOT is responsible for paying the contractor. The amendment increased
the funds to cover any additional costs. Another bid was released to solicit
other contractors. The City received only one bid from the original bidding
contractor at a cost of $126,650. The contractor is qualified.
Director Smith shared a cross section diagram of the work and described
components of the project. The contractor is responsible for removal of
sediment. Permitting is currently in process by the City, which serves as the
lead permitting agency. Staff submitted a hydraulic project application to
the Department of Fish and Wildlife. Following execution of the contract,
staff anticipates the contractor will develop a health and safety plan and
work plan. The work should take no longer than one month. The project is
scheduled for completion by July 31, 2023.
Staff requests the Public Works Committee recommend the City Council
approve and authorize the Mayor to sign the Agreement with Clearcreek
Contractors for the Palermo Lagoon Dredging & Maintenance Project in the
amount of $126,650.
Chair Swarthout inquired about the source of the sediment composition.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
April 6, 2023 Page 7
Director Smith explained that the sediment is from the stormwater system as
it drains towards the golf course. Sediment is generated as surface waters
flow through the system. Geoengineers completed a hazardous profile of the
site in 2019-2020 during the development of the project scope. At that time,
the sediment was not determined to be hazardous; however, sediment will be
tested prior to removal to determine if contamination exists.
MOTION: Councilmember Schneider moved, seconded by Chair Swarthout, Staff
requests the Public Works Committee recommend the City Council
approve and authorize the Mayor to sign the Agreement with
Clearcreek Contractors for the Palermo Lagoon Dredging &
Maintenance Project in the amount of $126,650. A voice vote approved
the motion.
STORMWATER Specialist Kangiser reported the capacity grant is a standard grant received
CAPACITY GRANT by the City from the Department of Ecology to assist the City in meeting its
AGREEMENT WITH permit compliance obligations under the stormwater National Pollutant
DEPARTMENT OF Discharge Elimination System (NPDES) permit requirements. The grant is
ECOLOGY used for printing of educational and informational materials, staff training,
AMENDMENT NO. 1: and in support of the Equity Index Mapping project. Recently, the
Legislature provided an additional $25,000. The additional amount extends
the grant period from March 31, 2023 to June 30, 2023. The additional
funds will be used for a water quality monitoring program and other
educational opportunities with the school district on several projects, as well
as expansion of the petway station project.
The request to the committee is to recommend the City Council approve and
authorize the Mayor to sign Amendment No. 1 to the 2021-23 Capacity
Grant supporting the City’s stormwater program.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
Mayor to sign Amendment No. 1 to the 2021-23 Capacity Grant
supporting the City’s stormwater program. A voice vote approved the
motion unanimously.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:49 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, April 06, 2023
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee, March 9, 2023
4. Resolution No. R2023-007 Delegation of Signature Authority for Grant Documents Related to
Somerset Hill Fish Passage Barrier Removal Design (Dan Smith)
5. Service Provider Agreement with HDR Engineering, Inc. for the Old Highway 99 and 79th Avenue
Roundabout Project (Don Carney)
6. Authority to Solicit Bids and Award Contract for the 2023 Pavement Maintenance Project (Bill
Linddauer)
7. Agreement with Clearcreek Contractors for the 2023 Palermo Lagoon Dredging & Maintenance
Project (Steve Craig)
8. Stormwater Capacity Grant Agreement with Department of Ecology Amendment No. 1 (Dan
Smith)
9. Additional Items
10. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/85266585854?pwd=YVVOTUk1Z2lRMXg0NkduTS9sUVByQT09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 852 6658 5854 and Passcode
326357.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.