Public Works Committee
Regular MeetingTumwater, WA · March 9, 2023
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 9, 2023 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmember Charlie Schneider.
Excused: Councilmember Michael Althauser.
Staff: Transportation and Engineering Director Brandon Hicks, Water
Resources Specialist David Kangiser, and Administrative Assistant Cathy
Nielsen.
CONSULTANT Director Hicks reported the proposed agreement is a standard boilerplate
AGREEMENT WITH agreement. Since the project received federal funds, the City is required to
TIERRA RIGHT OF use the Washington State Department of Transportation agreement provided
WAY SERVICES, to the City. The committee last received an update on the project in fall
LTD, FOR RIGHT-OF- 2022.
WAY SERVICES ON
THE X STREET The project site is located at the intersection of Capitol Boulevard and X
ROUNDABOUT Street. The roundabout project was included in the Capitol Boulevard
PROJECT Corridor Plan, as well as verified during the feasibility study following
completion of the plan. The project limits include north of W Street to
several hundred feet south of X Street, as well as both sides of X Street as an
approach. Project design of the project is approximately 90% complete.
Work on right-of-way activities began in 2022. The next step is negotiating
with property owners following approval of the agreement. Staff anticipates
the acquisition of right-of-way will require several years to complete. The
goal is to construct the project in 2025.
Director Hicks displayed a copy of the right-of-way plan. The City plans to
acquire property rights from eight separate parcels. Two of the parcels
would entail a full acquisition of the parcel with six partial acquisitions and
six temporary construction easements. All acquisitions are under the
provisions of eminent domain or condemnation. When offers are extended
to owners, the letters include information on eminent domain acquisitions to
include information on the invocation of property owner protections under
the Uniform Relocation Act. The proposal is not a request for approval of
eminent domain or the condemnation process.
The two properties for full acquisition are situated in the area where the
future roundabout would intersect with the building. The two parcels are
under one ownership housing one business located at the northwest corner of
the intersection. The property would also house stormwater facilities as part
of the improvement project. The City pays for fair market value for the
properties and buildings as well as providing funds to help the business
relocate and reestablish the business.
Director Hicks said staff reviewed proposals and selected Tierra Right of
Way Services as the preferred right-of-way consultant for the project. The
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 9, 2023 Page 2
City previously worked with the consultant on the Deschutes Valley Trail
segment from Tumwater Historical Park to the Brewery Park at Tumwater
Falls. The agreement is for $150,000 based on a best estimate as it could
entail more or less time dependent upon whether property owners are willing
to work with the City.
Tierra Right of Way Services oversees the elements of right-of-way
acquisition with the exception of management and oversight of all work.
Some of the services include appraisals, review of plans in terms of
compensation to property owners, negotiations with property owners,
relocation services, and project certification.
The City was successful in securing $5.6 million in grants from five different
grant sources. The project cost is $7.1 million project. Most of the grants
were obtained through the efforts of Transportation Manager Mary Heather
Ames. All local funds for the project are from the Transportation Capital
Facilities Plan and the respective utility Capital Facilities Plans for
replacement of storm, sewer, and water utilities.
Staff requests the Public Works Committee recommend the City Council
approve and authorize the Mayor to sign the Local Agency Professional
Services Negotiated Hourly Rate Consultant Agreement, in substantially
similar form as approved by the City Attorney, with Tierra Right of Way
Services, LTD, in the amount of $150,000, for right-of-way services on the
X Street Roundabout Project.
Councilmember Schneider spoke to the number of roundabouts involved in
the Trosper Road-Capitol Boulevard Improvement project and questioned
why X Street was selected for a roundabout rather than other intersections
located closer to the project area. Director Hicks explained that the first
roundabout as part of the project is located at Trosper Road and Capitol
Boulevard followed by a roundabout at T Street, which the City is not
pursuing at this time because a large portion of the property required for the
roundabout was owned by the Washington State Department of
Transportation (WSDOT) Olympic Region. WSDOT used the property as a
public works facility and the area has some ground contamination. The
status of the property is unknown at this time, which is why the City is not
pursuing the T Street roundabout at this time. The fourth roundabout is the
Dennis Street/Capitol Boulevard roundabout. The City is pursuing Safe
Routes to School funding for the Dennis Street roundabout.
Director Hicks explained the timing of the acquisition process. The City will
pursue mutually agreeable terms; however, should the City encounter an
impasse within the next six months to a year, the City would need to initiate
condemnation actions that essentially establishes a clock on the timing for
securing property rights.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
March 9, 2023 Page 3
Chair Swarthout asked about the possibility of receiving additional federal
funds to fund the project fully. Director Hicks said staff continues to
monitor grant programs. It is unlikely staff would locate additional federal
funding as the project has maximized the federal funds on the project.
Federal funding requires a minimum match of 13.5% from other sources of
funds to include local funds. Other grant agencies are a possibility but the
City has received funds from other agencies for other City projects.
CONSENSUS: The Public Works Committee recommends the City Council approve
and authorize the Mayor to sign the Local Agency Professional Services
Negotiated Hourly Rate Consultant Agreement, in substantially similar
form as approved by the City Attorney, with Tierra Right of Way
Services, LTD, in the amount of $150,000, for right-of-way services on
the X Street Roundabout Project.
BARNES LAKE 2023 Specialist Kangiser presented the Barnes Lake 2023 Budget and Work Plan.
BUDGET & WORK The request is to recommend the City Council approve the 2023 draft Barnes
PLAN Lake Management District Work Plan and Operating Budget.
In 2022, the lake received treatments targeting lily pads, bladderwort, and
pond weed. The 2022 scope of work included monitoring previous lake
treatments. In 2020, the lake received a fluridone treatment as a part of a
four-year treatment cycle. Those treatments were hindered by low water in
the lake. Some of the targeted species for fluridone were trapped in dry
wetland areas surrounding the lake. The treatment was not as successful as
envisioned. The diquat herbicide treatment in 2022 was successful for
treating bladderwort not treated in 2020. The budget includes continued
treatment applications in 2023 and 2024 of diquat herbicide and other
recommended applications by the contractor. The cost of treatments and
labor has increased in the last several years resulting in increased costs of the
consultant in 2023 and 2024. The budget has some reserve funds to cover
the increase in costs. The draft work plan incorporates a typical budget year
in addition to funds for production of a newsletter for members.
CONSENSUS: The Public Works Committee recommended the City Council approve
the draft 2023 Barnes Lake Management District Work Plan and
Operating Budget.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:24 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, March 09, 2023
8:00 AM
1. Call to Order
2. Roll Call
3. Consultant Agreement with Tierra Right of Way Services, Ltd, for Right-of-Way Services on the X
Street Roundabout Project (Brandon Hicks)
4. Barnes Lake 2023 Budget & Work Plan (Dan Smith)
5. Additional Items
6. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/83922926167?pwd=aGc2TVQvRmxYd1dEZGZLUUtCQ2pDdz09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 839 2292 6167 and Passcode
824324.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.
Get email alerts for Tumwater
A daily email when new agendas and minutes are posted.