TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 8, 2023 Page 1
CONVENE: 8:03 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and Charlie
Schneider.
Staff: Transportation and Engineering Director Brandon Hicks, City
Attorney Karen Kirkpatrick, Engineering Services Manager Bill Lindauer,
Engineer II Daryl Epstein, and Administrative Assistant Cathy Nielsen.
APPROVAL OF
MINUTES: PUBLIC
WORKS
COMMITTEE, MAY
18, 2023
MOTION: Councilmember Schneider moved, seconded by Councilmember
Althauser, to approve the minutes of May 18, 2023 as published. A
voice vote approved the motion unanimously.
ISRAEL ROAD AND Manager Lindauer briefed the committee on the Israel Road and Linderson
LINDERSON WAY Way Water Main Project and Schedule 74 Project Plan and Construction
WATER MAIN Agreement. Schedule 74 is a process that establishes rules for converting
PROJECT, existing Puget Sound Energy (PSE) overhead distribution system lines to
SCHEDULE 74 underground within a project’s limits. The proposed action is linked directly
PROJECT PLAN AND to the overall water main project. The project will underground 3,115 feet of
SCHEDULE 74 overhead power lines within the limits of Linderson Way to Capitol
UNDERGROUND Boulevard on Israel Road. The project includes service connection
CONVERSION replacements to each affected property served by the distribution line. The
CONSTRUCTION PSE agreement consists of two linked agreements. The Schedule 74 Project
AGREEMENT: Plan is the first agreement and includes all the main components of the
project such as scope of work, construction plans and specifications, work
requirements, operating rights, basic construction work schedule, and
construction cost estimate. The second agreement is the construction
agreement between the City of Tumwater and PSE that is similar to the
agreement for the Trosper Road underground project. The construction
agreement references the Schedule 74 Project Plan as an attachment.
PSE will provide the conduits and transformers for the project and will
install the electrical system, coordinate and complete changeovers and
transfers for new services, remove, deactivate, and replace the existing
electrical system after the new system is installed, and provide project
inspection services during the City’s portion of the project when the City
installs conduits and other components.
The City’s responsibility for the project is construction of the utility trench,
installation of conduits (provided by PSE), and install service and other
transformers. PSE will follow up and complete the connections.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 8, 2023 Page 2
The estimated cost of the project is a cost-sharing agreement of 60% by PSE
and 40% by the City of Tumwater. The overall total construction cost for
undergrounding is $947,187.00. PSE’s cost estimate for its share is
$568,312.00. The City’s cost share is $378,875.00.
Manager Lindauer invited questions from the committee.
Chair Swarthout asked about the timing of the project. Manager Lindauer
replied that construction is scheduled during August through September
2023.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to recommend the City Council approve and authorize the
Mayor to sign the Puget Sound Energy (PSE) Schedule 74 Project Plan
and Schedule 74 Construction Agreement, to complete utility
undergrounding conversion for the Israel Road and Linderson Way
Water Main Project. A voice vote unanimously approved the motion.
ISRAEL ROAD AND Manager Lindauer reported the Israel Road and Linderson Way Water Main
LINDERSON WAY Project replaces an aging water main along Israel Road and Linderson Way.
WATER MAIN The project is included in the Water Capital Facilities Plan and is supported
PROJECT, in the 2021 Comprehensive Water System Plan update. The project is
AUTHORITY TO required to replace aging asbestos water mains originally installed in the
SOLICIT BIDS AND 1960s. The mains are close to the end of design life and need replacement,
RECOMMEND as well as to provide a safe and reliable water system to the community.
AWARD:
The project scope of work includes replacement of the water main on Israel
Road from Interstate 5 to Capitol Boulevard totaling approximately 3,750
feet of water main and replacement of the water main along Linderson Way
from Israel Road south to the access point to the Department of Labor and
Industries building totaling approximately 950 feet of water main. The
project includes upgrading all water service connections along the project
length in addition to City right-of-way, replacement of pavement and
sidewalk affected by the trenching operation for the project. Following
completion of the project, the imprint of trenching along the roadway will be
visible with an asphalt overlay of the affected roadway scheduled for next
year. The project includes utility underground improvements for PSE
underground conversion from Linderson Way to Capitol Boulevard along
Israel Road of 3,115 feet, as well as the City’s service connection upgrades
underground to the property line to different property owners to include City
Hall. Additional overhead utility conversions are included as part of
coordinating work with other private utilities.
Manager Lindauer displayed an aerial view of the project site.
An important component of the project was phasing construction because
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 8, 2023 Page 3
Israel Road is one of the City’s main roads. However, other alternative
routes are available to avoid construction activities. Staff is pursuing public
outreach to provide information to the public about the project. One aspect
is identifying alternative routes for the public to avoid the construction site.
As most of the construction activity is located along the center of the road,
those motorists who cannot use another route will have access on both sides
of the roadway. During utility trenching work, traffic will be limited to the
south side of the road. The goal is to maintain two-way traffic during the
entire construction process in each direction with some stoppages and
limitations during the project. The main traffic issue is access to Tumwater
High School as many students drive to school creating some traffic issues
along the project site. Summer recess is scheduled to begin on June 20, 2023
and end on September 5, 2023. During that timeline, the contractor will
focus trenching work in front of the school prior to school starting in
September. The construction site will enable access for fire and police and
City Hall vehicles.
Councilmember Althauser inquired about right and left turn lane access for
fire and police emergency calls during construction. Manager Lindauer said
that at some time during construction, access points will be limited for left
turns. In those cases, flaggers will assist in left turn movements if
emergency access is required. Staff will coordinate emergency access with
both the Police Department and the Fire Department during construction.
The provisions for access are included in the contract with the contractor, as
well as discussed with the contractor during the pre-construction meeting
and coordinated with the City during the project.
The Engineer’s estimate for the project is $2,997,283.28. Bids will likely
range from $2.7 million to $3.2 million because of unknown material costs
based on the current market. Water main improvements are funded by the
Water Capital Facilities Plan. For undergrounding and the City’s cost share,
the amount is funded by the Transportation Capital Facilities Plan. Duration
of the project is approximately 50 working days or 2.6 months. The
project schedule is dependent upon timing by the contractor and the
availability of material. Final cleanup will likely be during the first two
weeks in October. The current project schedule (if approved) includes
releasing the bid later in the day with bid opening on June 22, 2023 with
construction estimated to commence at the end of July 2023.
Manager Lindauer invited questions.
Councilmember Alternative questioned the timing associated with the Fire
Department requiring flagging assistance if responding to an emergency call.
Manager Lindauer said the project is linear in nature and the contractor will
start at one point, trench, install, and refill the trench and then move to the
next segment. The timing of any disruptions will be relatively short. Most
contractors can install water lines up to 150 to 200 linear feet each day.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 8, 2023 Page 4
Interruptions will be intermittent throughout the project at different times.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Schneider, to authorize staff to solicit bids for the Israel Road and
Linderson Way Water Main project and recommend City Council
award and authorize the Mayor to sign a public works contract with the
lowest responsible bidder. A voice vote approved the motion
unanimously.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:30 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, June 08, 2023
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee, May 18, 2023
4. Israel Road and Linderson Way Water Main Project, Schedule 74 Project Plan and Schedule 74
Underground Conversion Construction Agreement (Bill Lindauer)
5. Israel Road and Linderson Way Water Main Project, Authority to Solicit Bids and Recommend
Award (Bill Lindauer)
6. Additional Items
7. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/86481919716?pwd=Nmk3MGVScWZ4NWxsMTF5Und2ZzJYdz09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 864 8191 9716 and Passcode
311396.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.