Public Works Committee
Regular MeetingTumwater, WA · January 4, 2024
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmember Michael Althauser.
Staff: City Administrator Lisa Parks, City Attorney Karen Kirkpatrick,
Finance Director Troy Niemeyer, Water Resources and Sustainability
Director Dan Smith, Transportation and Engineering Director Brandon
Hicks, Assistant Transportation and Engineering Director Mary Heather
Ames, Engineering Services Manager Bill Lindauer, Water Resources
Program Manager Patrick Soderberg, Communications Manager Ann Cook,
and Administrative Assistant Bonnie Hale.
APPROVAL OF
MINUTES:
PUBLIC WORKS
COMMITTEE,
DECEMBER 7, 2023:
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
approve the minutes of December 7, 2023 as presented. A voice vote
approved the motion.
SMALL WORKS Director Smith briefed members on the proposed contract for tenant
CONTRACT WITH JA improvements for City space at South Puget Sound Community College.
MORRIS
CONSTRUCTION The proposed contract with JA Morris Construction is for tenant
FOR THE TENANT improvements at South Puget Sound Community to accommodate Water
IMPROVEMENTS Resources & Sustainability Department. The project is comprised of two
FOR CITY OF classrooms, two small existing offices, and a service area located between
TUMWATER OFFICE the classrooms to convert those spaces to work spaces. The classrooms
SPACE AT SOUTH currently house cabinets and large science desks. Options for reusing the
PUGET SOUND cabinets and desks were analyzed and deemed not possible because of the
COMMUNITY configuration of their construction. The cabinets and desks will be removed.
COLLEGE: In some cases some other equipment will be reused when possible. Flooring
will be covered with a new floor to keep costs minimal. One entrance to the
area of the classrooms will be removed and replaced with a solid wall to
create a lobby. The main staff entrance is the back door of the offices.
Concrete improvements are included in the project to ensure a contiguous
sidewalk into the entrance at the rear of the building for staff. A wall will be
constructed to bisect the classroom. An area will be created for reviewing
maps, conducting water quality tests, setting up for field procedures, or other
tasks related to field work. Within the work space, three remote desk areas
will be created to accommodate growth in staff, field staff, and visitors. A
bisecting area will feature a door into a conference room to serve as a place
for team meetings and any other large meeting needs. Another space will be
converted to a smaller private meeting space. No changes are proposed for
existing restrooms.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 2
The college has indicated the building is not subject to any other uses at this
time. Adjacent to the leased space is another large classroom, which could
benefit the department’s education program or training of stormwater
employees. The project also includes space for an employee lunchroom and
an area for copiers, office equipment, and IT servers. The site presents
future opportunities to expand.
Staff is exploring flooring options with carpet in the conference spaces and
office spaces consisting of a blend of three different carpets. Staff is working
with Windfall Lumber in Tumwater to provide accent panels for the lobby
area to accommodate department signage. The paneling is from reclaimed
wood pallets from Africa, South America, and Central America. The panels
will be sanded and finished. The lunchroom and other work spaces will
feature linoleum using a different type of flooring to eliminate removal of
existing flooring. The module flooring interlocks and will be installed on top
of the existing floor consisting of recycled laminate considered an
environmentally sustainable product.
Director Smith described the bidding process with the City utilizing MRSC’s
Small Works Roster for general contractors. On November 13, 2023, staff
conducted a site visit of the project site with five contractors participating
and asking questions. The bid submittal deadline was November 29, 2023.
The City received two formal bids. The architect’s estimate for the project
was $271,498. JA Morris Construction’s bid was $273,094 with another bid
received of $239,856. However, the low bidder was not fully responsive to
the request with a number of items missing from the proposal that were
necessary for the project. As JA Morris Construction was fully responsive to
the request and included a statement of values consistent with the architect’s
estimate, the company was selected to construct the project.
Staff recommends the committee forward a recommendation to the City
Council to approve and authorize the Mayor to sign a Small Works Contract
with JA Morris Construction for the Tenant Improvements for City of
Tumwater Office Space at South Puget Sound Community College
(SPSCC).
Chair Swarthout asked about the possibility of utilizing wood from the Trails
End property. Director Smith advised that after discussions with Windfall
Lumber and the architect on other options available the recommendation was
not to utilize materials from the Trails End property because of the cost to
refurbish the materials.
Chair Swarthout added that she was also curious as to the amount of lumber
saved from the Tails End property that could be repurposed for the City’s
new Maintenance and Operations facility.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 3
Director Hicks advised that staff plans to utilize some of the lumber saved
from the former Trails End facility. Most of the lumber will be used in the
main lobby of the new facility.
Councilmember Althauser asked about the move-in date for staff. Director
Smith responded that based on the construction timeline, the anticipated
move-in date would be in mid-May or end of May.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to
recommend the City Council approve and authorize the Mayor to sign a
Small Works Contract with JA Morris Construction for the Tenant
Improvements for City of Tumwater Office Space at South Puget Sound
Community College (SPSCC). A voice vote approved the motion.
WATER SERVICE - Director Smith reported the Cost of Service Study was approved by the
COST OF SERVICE Council as part of the scope of work within the contract with Carollo
RATE STUDY Engineers.
DISCUSSION:
During the adoption process of the Water System Plan, a number of
questions were raised pertaining to policies, financial elements, equity in
water rates and connection fees, implementation of rates, and how effective
rates are in covering the cost of the capital improvement program for the
Water Utility.
The cost of service study will:
• Collect Data
• Develop/Refine Financial Plan
• Analyze Cost of Service
• Design Rate and Fee Schedules
• Develop Rate Model
• Document and Present Cost of Service Study Results
• Evaluation of Additional Rate Design Alternatives
One question of concern surrounds affordability. Traditionally, water
systems consider affordability using median household income or the annual
cost of a water bill annually. If the cost is 2.5% or less of the median
household income, the amount is considered an affordable rate. In
Tumwater, the median household income is $77,849 as of 2023.
Tumwater’s entire utility bill, based on 2024 analysis, totals $1,479 annually
or less than 2.5%, which is deemed an affordable rate for the community as
it is less than 2.5% of the median household income. However, when
comparing the rates to a low-income household earning $31,000 annually,
the utility bill is less affordable. The study will consider affordability
differently based on recent work completed by Texas A&M University by
calculating affordability differently, considering other household bills, and
rate comparisons for minimum wage earners.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 4
The study will explore a new formula identifying household size, income of
the household, and other household costs to produce a ratio. Director Smith
shared an example scenario that considers two minimum wage earners
totaling $62,400 as the household income and estimated monthly expenses of
$4,757 using University of Washington ALICE data for Thurston County.
The result suggested the rates were affordable for the household. The study
will examine water rates as well as combined rates of all utilities most
customers receive in Tumwater. The second metric of the study will explore
rates for minimum wage households. For a minimum wage earner, payment
of the utility bill would require a minimum of 7.5 hours of minimum wage
work based on a 40-hour workweek. Carollo Engineers will explore rates of
both a range of household incomes within the community and the
affordability metric of median households, because the City community
includes many living in the lower income range.
Another element to be explored in terms of designing a different rate
structure is average water use versus essential use. Many customers have
irrigation systems with rates typically spiking during summer months.
Irrigation is not considered an essential use. Other models consider a certain
volume of water integrated within the base rate. In Tumwater, the base rate
is approximately $10 a month. The study will explore opportunities to
include additional increments of water per day within the base rate to avoid
spikes in bills during summer months.
The study will explore equity in rates and connection fees and whether the
City’s current rates and fees pay for the impacts of users and City growth.
Rates are intended to cover operations, maintenance, treatment, and asset
replacements over time. Connection fees are intended to assist in financing
future growth of the system.
Historically, Tumwater’s connection fees have increased 2% per budget
year. During the development of the capital program in 2023, staff
recognized larger projects are related to growth and new sources of water. A
low 2% increase in connection fees while water rates increase steadily over
time resulted in a change by increasing the rate of connection fees to pay
more into the system annually.
Councilmember Althauser said he understands that the amount of the
connection fee is based on the potential use with a larger connection more
expensive than a residential connection. He asked whether the equity
assessment would not only consider the size of the connection but the user as
well to a greater degree to distinguish between an industrial user requiring
larger connections to utilize more water, which also adds stress to the system
as large users are able to access water at an economic rate and scale while
residential users are essentially subsidizing the entire system to some degree.
For example, the impact from a very large business that utilizes more water
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 5
is likely more than the impact from a property owner connecting a new
accessory dwelling unit (ADU). Director Smith confirmed it is an issue the
study will address because currently, the scale increases for connection fees
from a ¾” meter to a 6” meter with larger meters increasing in cost based on
a standard calculation the City has utilized from American Water Works
Association that is used by utilities across the country. The study will
explore the cost of increases to ensure equity and whether larger businesses
are paying the appropriate fees based on demands a business places on the
system. The study will explore different formulas for increased sizes and
whether the methodology for ADUs should be evaluated for a possible
change.
The last major policy review was in 2010 resulting in no changes in the
policies included within the last Water System Plan. Many policies are
included in the Water System Plan encompassing over 11 pages covering
customer service, supply, regional policies, and specific water system
financial policies. The plan also includes design standards and performance
criteria, as well as organizational policies. All policies need re-evaluation in
the context of the different department structure, City structure, and changes
in some operational practices. The intent is to review the policies prior to the
next update of the Water System Plan scheduled in eight years. Staff will
conduct a review of existing policies with additional support from the
Operations Manager and other departments impacted by the policies. Draft
changes will be presented to the committee during the course of the review.
Director Smith invited feedback and suggestions for the consultant to review.
He noted a recent conversation with a customer who was interested in the
City’s metrics for designing the rates from a perspective of affordability and
equity for customers.
Manager Soderberg said the cost of service study will be in conjunction with
the work to seek new water sources. It is timely to complete both efforts
concurrently. Additionally, the consultant is developing a dashboard
enabling staff to continually add changes in the cost of services as costs of
labor, materials and other charges increase or decrease. The dashboard will
also assist staff during the review of equitability cost of service for different
types of customers to document how any increases in cost might impact
different types of customers. Those two components are vital for staff to
make good decisions moving forward as well as how the City establishes its
rate payment system.
Chair Swarthout asked whether the City’s rate structure distinguishes
between single family and multi-family users. Director Smith displayed a
graphic depicting different rates for residential customers. Residential
customers are charged on a tier structure — the more you use, the more you
pay. During summer, water use can triple primarily because of irrigation for
both residential and commercial uses. Commercial rates are a static rate and
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 6
typically begin at Tier 2, similar to residential customers. Commercial rates
are slightly higher than residential rates. Commercial customers that irrigate
property have a separate meter for irrigation to ensure irrigation is not added
to the volume of sewer use. The irrigation meter is charged at higher Block
3 of $3.99 per 100 cubic feet.
Chair Swarthout asked about the rate charged to commercial uses utilizing a
significant amount of water. Director Smith replied that large commercial
users typically pay a Block 2 rate. Based on volumes, the rates may increase
to Block 3 or 4.
Chair Swarthout asked about the extent of available water system services
south of the City along Littlerock Road and Old Highway 99. Director
Smith said the system does not extend entirely along each corridor to City
limits. However, based on a current project off Old Highway 99 related to
the reservoir, the City is extending service further south. Through the
development process, large developments requiring water are required to
extend utilities to the projects, which is typically how the City extends its
water system.
Chair Swarthout inquired as to the process the City utilizes to determine the
size of water mains to serve future needs, such as the recent water main
replacement project along Israel Road. Director Smith said the Israel Road
project was a City-sponsored project. If the project had been a developer-
driven project, the City’s Water System Plan would identify future needs and
require oversizing the water main with the City participating in a cost-share
to the extent that funds are available through an oversize agreement with the
developer. In City-sponsored projects, if a larger water main is required, the
City would fund oversizing the water main as part of the capital program.
Discussion ensued on circumstances involving assessments for future
development potential and latecomer fees.
Director Smith explained that if new development extends a water main
across existing development or if the City determined a need to extend the
water main, in both cases a latecomers or special assessment fee would apply
to the parcels. At this time, a property owner desiring water and sewer
would pay for the cost of extending those services to the property unless
there was a specific reason for the City to extend the services, such as
mitigating a water quality impact or public health issue.
Because the City is the preferred water system provider within the City’s
urban growth boundary, any new subdivision developing within the urban
growth boundary requires the developer to extend utility services to the
development through a partnership with Thurston County.
Chair Swarthout inquired about the timeline for the study. Director Smith
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
January 4, 2024 Page 7
said the study is scheduled over six months. Most of the study should be
completed to help inform the next budget process.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:58 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, January 04, 2024
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee, December 7, 2023
4. Small Works Contract with JA Morris Construction for the Tenant Improvements for City of
Tumwater Office Space at South Puget Sound Community College (Dan Smith)
5. Water Service - Cost of Service Rate Study Discussion (Dan Smith)
6. Additional Items
7. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/81725082670?pwd=UTJrLzNxbFJpRmxTc1REQ1IrVlFxZz09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 817 2508 2670 and Passcode
367271.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.