Public Works Committee
Regular MeetingTumwater, WA · February 8, 2024
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 1
CONVENE: 8:01 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and Angela
Jefferson.
Staff: City Administrator Lisa Parks, City Attorney Karen Kirkpatrick,
Finance Director Troy Niemeyer, Water Resources and Sustainability
Director Dan Smith, Transportation and Engineering Director Brandon
Hicks, Assistant Transportation and Engineering Director Mary Heather
Ames, Engineering Services Manager Bill Lindauer, Water Resources
Program Manager Patrick Soderberg, Transportation Engineer 1 Bernie
Gertje, Water Resources Specialist Carrie Gillum, Water Resources
Specialist Dave Kangiser, and Administrative Assistant Bonnie Hale.
SELECTION OF City Administrator Parks reported that every two years when new members
COMMITTEE CHAIR: join the committee, an election of the Chair is required. She invited
nominations for Chair.
Councilmember Althauser nominated Councilmember Swarthout to serve as
Chair of the Public Works Committee.
No other nominations were offered.
VOTE OF Through a unanimous vote, Councilmember Swarthout was elected to
AFFIRMATION: serve as Chair of the Tumwater Public Works Committee during 2024
and 2025.
ISRAEL ROAD AND Manager Lindauer briefed members on the request to approve authority to
LINDERSON WAY solicit for bids and authorize the Mayor to sign a public works contract, as
PEDESTRIAN AND well as some authorities to for road closures, detours, and some night work
BICYCLE on the project.
IMPROVEMENTS
PROJECT, The project location is from Capitol Boulevard to Linderson on Israel Road.
AUTHORITY TO The project scope is repair of distressed pavement along Israel Road and
SOLICIT safety improvements for pedestrian and bicycle mobility throughout the
BIDS AND corridor. The project is partially funded with federal funds.
RECOMMEND
AWARD The improvements begin Linderson Way along Israel Road extending to
Capitol Boulevard. A small segment of Linderson Way south of Israel Road
is included in the scope for repair. The scope also includes selected sidewalk
improvements, as well as pedestrian crossings to include the existing school
crossing, rebuilding a crossing at the Tumwater Library at Market Street, and
an adding a crossing between the Tumwater Fire Station and 6th Avenue off
Israel Road totaling three pedestrian crossings along Israel Road.
Roadway improvements include pavement repair for distressed areas
(alligator cracking & potholes), repair of any utility trenching that has failed
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 2
over time, and full-depth repair of the utility trenching completed as part of
the recent project along Israel Road. The overlay will be a full width asphalt
overlay through the entire project limits and includes the addition of geogrid
within the overlay to increase the design life and shore up some areas with
questionable soils. Minor storm drainage conveyance repairs are also
included in the project scope to reduce existing drainage problems along the
roadway. Following completion of the project, all utilities will be reinstalled
to meet current standards enabling a longer design life over time. New
pavement marking with select signing is included with signs replaced as
needed to meet current standards, as well as upgrading signs at pedestrian
crossing locations.
Manager Lindauer described pedestrian and bicycle safety improvements. A
major component is reconstruction of selected sidewalks, ADA ramps, and
driveways throughout the project site. Most areas for improvement were
identified to ensure ADA compliance. Traffic lane widths will be adjusted to
enable the expansion of the bicycle lanes. Current bicycle lanes are five feet
wide. The project will expand bike lanes to six feet wide. An existing
pedestrian crossing at Tumwater High School will remain but will be
upgraded with a replaced center area of the refuge island and upgraded
signing at the crossing. The pedestrian crossing at Tumwater Library at
Market Street will be upgraded to add a central refuge island for pedestrian
safety and rectangular flashing beacons. A new crossing near 6th Avenue
will include a center refuge island.
In terms of the difficulty of the project, the main issue is constructability as
the area is a high traffic area. City vital services, the library, and Tumwater
High School are all located along Israel Road along with residential uses
located throughout the entire corridor. The work zone and phasing of the
project are major components of the project. One important factor is the
timeline of completing the project to minimize impacts to the public. The
majority of the work can be constructed while maintaining two-lane traffic.
The major issue is the paving operation, as it will require ongoing
construction along one side of the road to the opposite side of the road to
include grinding and paving operations. Staff is requesting the ability to
utilize traffic detours, road closures, and potential night work. Staff will
evaluate the needs during construction and utilize the options as required to
expedite the construction of the project to minimize impacts to the public.
The paving project should require approximately one week to complete. All
project options would be reviewed by staff and Director Hicks prior to
implementation. The options also include a public notification component to
ensure project contractors are aware of the length and time to schedule any
of the options. Staff is working with the City’s communications staff to
ensure a robust public outreach process.
Councilmember Jefferson inquired about the timing of the project. Manager
Lindauer advised that the project is scheduled for construction in May and
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 3
June 2024.
Manager Lindauer reported the estimated construction cost is between $1.5
million to $2 million. The project is funded partially with federal funds
administered by the Thurston Regional Planning Council with the match
from the Tumwater Transportation Benefit District (TBD) and the
Transportation Capital Facilities Plan.
Councilmember Althauser asked whether the pedestrian island for the 6th
Avenue crossing near the Tumwater Fire Department would interfere with
fire trucks leaving the Fire Department. Manager Lindauer advised that he
believes the placement of the refuge island would not interfere with Fire
Department operations. He offered to follow-up with the Fire Department.
Director Hicks added that the pedestrian refuge island is not located near the
exit of the Fire Department for fire trucks. The location of the island is
located at the public entrance to the Fire Department. Fire apparatus would
not encounter any turning issues or restrictions.
Councilmember Althauser asked about the nature of the work that would be
completed during evening hours. Manager Lindauer said the evening work
would likely be paving, as most grinding would be completed during
daylight hours. Although paving operations can be loud, the benefit of
paving at night reduces impacts to the public during the day.
Councilmember Althauser asked whether the request for the committee is to
issue bids and allow the Mayor to sign the contract. He asked about the
typical process of the committee reviewing a proposal for recommendation
to the Council to award the contract. Director Hicks explained that the
typical scenario for capital projects is a request to the committee to authorize
staff to solicit bids, as well as a request to recommend the City Council
authorize the Mayor to sign the contract with the lowest responsible bidder.
Staff does not typically seek the committee’s approval of the contract award
unless the bids are greater than the estimate.
Councilmember Althauser asked for concurrence that the Council must
approve the award of the contract. Director Hicks affirmed the Council
approves the award of the contract.
Director Hicks pointed out that the federal funds received for the project
were administered and awarded through Thurston Regional Planning
Council (TRPC). Staff is appreciative of the support the City receives from
TRPC. The project is a TBD-funded project and was included in the paving
program. The original project scope was expanded to include pedestrian and
bicycle improvements to leverage additional federal grant funds.
Chair Swarthout asked whether the library crossing includes flashing lights
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 4
when pedestrians cross. Manager Lindauer affirmed the crossing would be
equipped with flashing beacons.
Chair Swarthout inquired about the extent of new sidewalks along the
corridor on the south side of Israel Road as some sections of sidewalk are
missing. Manager Lindauer advised that entire corridor currently has a
continuous sidewalk on the south side of the road; however, many sections
need are in need of repair. The project will replace sidewalks.
MOTION: Councilmember Jefferson moved, seconded by Councilmember
Althauser, to authorize staff to: (1) solicit bids for the Israel Road and
Linderson Way Pedestrian and Bicycle Improvements project, (2)
recommend the City Council award and authorize the Mayor to sign a
public works contract with the lowest responsible bidder, (3)
recommend the City Council authorize road closures and detours within
the project vicinity for the duration of the project, and (4) recommend
the City Council authorize night work adjacent to residentially zoned
property when necessary to reduce impacts to the public and avoid
impacts to critical public services. A voice vote approved the motion
unanimously.
Director Hicks sought concurrence by the committee to authorize staff to
place the action on the Council’s consent calendar for its consideration
following evaluation of the bids by staff. The committee agreed with the
request.
ISRAEL ROAD AND Manager Lindauer said the action pertains to the previous project and is a
LINDERSON WAY request for a project prospectus for submittal to satisfy federal grant
PEDESTRIAN AND requirements. The request is to recommend the Council authorize the Mayor
BICYCLE to sign the updated prospectus. The updated prospectus is a document
IMPROVEMENTS submitted to the federal government for release of the construction funds.
PROJECT, LOCAL
AGENCY FEDERAL Chair Swarthout reviewed the request to the committee.
AID PROSPECTUS:
MOTION: Councilmember Jefferson moved, seconded by Councilmember
Althauser, to recommend the City Council approve and authorize the
Mayor to sign the Local Agency Federal Aid Project Prospectus for the
Israel Road and Linderson Way Pedestrian and Bicycle Improvements
project. A voice vote approved the motion unanimously.
SERVICE PROVIDER Director Smith shared information on the background of the project. The
AGREEMENT WITH storage reservoir project is similar to existing reservoirs in the City. The
RH2 ENGINEERING City currently has two welded steel standpipe storage tanks and one above
FOR THE ground cement concrete storage tank. The Airport Reservoir Tank located
SOUTHEAST WATER near the airport is inactive but houses telecommunications equipment serving
RESERVOIR DESIGN as a revenue-generator for the City.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 5
PHASES I, II, AND III
The design of a storage tank considers the size and volume necessary to
serve a designated area. Water tanks contain operational volume or the
amount of water pumped between wells, equalization storage to meet peak
hour demands during peak seasons, fire suppression for community safety,
and emergency storage serving as a buffer.
The proposed project was originally included in the 2010 Water System Plan
based on forecasted modeling accounting for growth and demand on the
system. During that period, the City acquired property southeast of 93rd
Avenue where growth was anticipated to occur in the future. Since then, The
Preserve subdivision was developed with other areas slated for future
development. The location was deemed ideal to balance the City’s water
system. The project site was reaffirmed in the 2021 Water System Plan.
In addition to the new reservoir, a number of new water sources are proposed
over the next several years. As the new sources are developed and become
operational, a new storage tank is necessary to provide additional capacity to
manage the system as it expands. A new 3-million-gallon reservoir was
recommended to address storage and pressure deficiencies in the 350 zone,
along with expansion of the water system along 93rd Avenue SW and
associated system components. The 2010 Water System Plan identified the
need for a 2.5-million-gallon tank, which subsequently increased to a 3-
million-gallon during the last Comprehensive Plan update. The project
includes the addition of distribution infrastructure along 93rd Avenue and
Old Highway 99 to ensure other properties have access to the water system
and to support future development.
Manager Lindauer reviewed the specifications of the project. The project
consists of a storage tank, access road, and system upgrades to connect the
new water tank to the existing water mains on 93rd Avenue and Old
Highway 99. A 16-inch water main will be installed along 93rd Avenue
constructed from Kimmie Road to the water tower site with a tie to an
existing segment that was previously installed for The Preserve
development.
The tank site property is owned by the City. An easement was granted on
privately owned property in 2012 to provide sufficient area to construct a
maintenance access road to 93rd Avenue.
The proposal is a Service Provider Agreement with RH2 Engineering, Inc.
for the Southeast Water Reservoir Design Phases I, II, and III. The company
is very qualified and has completed similar work for other jurisdictions. The
company will serve as the prime consultant on the project and will work with
several subconsultants to provide permitting and design services,
geotechnical work, and completion of a topographical survey.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 6
Councilmember Jefferson inquired about the possibility of any pocket
gophers residing within the project site. Manager Lindauer replied that the
project includes a Mazama Pocket Gopher Study. Staff does not anticipate
the presence of gophers within the project site.
Manager Lindauer said the project consists of three phases with the first
phase involving water tank design, site improvements, construction of the
access road, and connecting a water main from the tank to main line along
93rd Avenue. The Phase II scope includes the water main work on 93rd
Avenue from Kimmie Street. Phase III work is the installation of a 16-inch
water main and connection to existing infrastructure on Old Highway 99
from 93rd Avenue. The project was phased to provide the ability to work on
specific phases when funding becomes available. All three phases must be
completed in order for the entire system to function; however, it is possible
to install the water tank and connect the tank to the water main along 93rd
Avenue and delay connection along Old Highway 99 until funding becomes
available.
The scope of work for the service provider agreement includes a survey
component, hydraulic modeling of the water tank to identify affects of
pressure and storage capacities within the water system, a preliminary design
component to enable value engineering to determine the water tank type to
achieve greater savings, geotech investigation and recommendations,
permitting through Thurston County, pocket gopher study, and a cultural
resources review. A number of permits are required for the project. The
water tank design includes the structural components and an outbuilding for
mechanical devices. The service provider will design based on the City’s
design plan and specifications and construction estimate. The agreement
includes construction support service during construction of the project. The
design schedule requires approximately 12 months to complete with an
anticipated completion date by early 2025. Total consultant fees are
$1,658,845.00 allocated between the three phases of the project. The
funding source is from the Water Fund Capital Facilities Plan.
Director Smith advised that the project funds were separated with 20%
allocated from operating income and 80% from connection fees. When the
project was first envisioned in 2012, the project cost estimated at
approximately $9 million. Today, the probable cost of construction based on
initial work with the consultant would total approximately $30 million.
Staff, at this time, is uncertain as to the funding mix in terms of loans or
bonds. Staff is working with finance staff as the project moves forward.
Debt acquisitions may be assumed in phases as each phase is constructed.
The Water System has not assumed any debt since 2015. Debt spreads costs
over time and reduces impacts to ratepayers over time with new customers
connecting to the system to help to fund the debt.
Manager Lindauer invited questions from members.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 7
Chair Swarthout asked about the extent of new water lines installed along
93rd Avenue. Manager Lindauer referred to an aerial illustration and
identified existing and new lines.
Chair Swarthout asked how The Preserve currently receives water service.
Manager Smith replied that the subdivision is connected to an existing water
main along Old Highway 99. The project would upgrade the distribution
main serving the subdivision with a new 16-inch water main.
Chair Swarthout asked whether the project would qualify for funding from
the State Public Works Trust Fund. Director Smith said staff has explored
funding opportunities through the trust fund to secure some design funds for
the project; however, the City failed to qualify and the trust fund had limited
funds available and was only funding higher ranked projects, such as system
emergencies.
Councilmember Althauser asked about the possibility of latecomer fees from
future development along 93rd Avenue to help recoup the cost. Director
Smith replied that he anticipates special connection fees would be assessed
for properties connecting to the water main along 93rd Avenue. Additionally,
the City’s brewery wellfields will become operational at a cost of $2.5
million for design and permitting with over 30 wells to decommission and
construction of a new treatment facility for the wells put in production. The
City is pursuing some significantly large projects for the Water Utility to
address needs and growth of the community anticipated over the next 20
years.
Discussion ensued on project ranking of other City projects, rate increases in
the future, and bonding capacity. Director Smith explained that the project
as listed on the CFP is not listed by priority. Staff is also pursuing a Water
Utility Cost of Service Study to assess affordability of water rates and
necessary projects to ensure the City can afford the projects moving forward
and whether connections fees are appropriate to help offset some of the
larger projects that are intended for growth and capacity.
Councilmember Althauser commented on the possibility of the Council
conducting a work session or including the proposal as a Council
consideration to ensure a more comprehensive discussion because of the size
and cost of the project.
Councilmember Jefferson supported the recommendation.
City Administrator Parks added that she and Director Niemeyer have
discussed options to provide additional information prior to the biennial
budget discussion on different alternatives available to the City for financing
capital projects as well as reviewing revenue projections. Funding of capital
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 8
projects as well as transportation improvements is dependent upon funding
sources that may become available through the state or the federal
government. Completing design positions projects to be shovel-ready and
ensures the City is able to compete for grant awards competitively.
Director Smith advised that he would work with the City Administrator to
schedule a briefing to the Council during a work session to review both the
project as well as the funding and budget elements.
The committee agreed to schedule the proposal as a Council consideration
item to enable staff to move forward with the design contract while affording
a larger conversation by the Council.
MOTION: Councilmember Jefferson moved, seconded by Councilmember
Althauser, to place the proposal as a Council Consideration item for the
February 20, 2024 Council meeting and recommend the Council
authorize the Mayor to sign the Service Provider Agreement with RH2
Engineering, Inc. for the Southeast Water Reservoir Design Phases I, II,
and III. A voice vote approved the motion unanimously.
Councilmember Althauser disconnected from the meeting.
2023-2025 Specialist Kangiser briefed members on the National Pollutant Discharge
STORMWATER Elimination System (NPDES) Permit Compliance Grant to support activities
CAPACITY GRANT and ensure compliance of the City’s stormwater permit. The grant amount is
FROM THE $130,000 for two years.
DEPARTMENT OF
ECOLOGY: Previous capacity grants have funded programmatic requirements for the
permit such has planning, outreach and education, printed materials, public
participation stewardship involving restoration activities, mapping
components in conjunction with the GIS team, the Illicit Discharge Detection
Elimination Program (spill response capabilities), pollution source control,
business inspection program (new requirement in 2023), construction-related
inspections, and operations and maintenance.
Some funds were used for field equipment purchases in support of field
activities. Other funds enabled the City to provide a dumpster program for
homeowner associations to help manage private stormwater facilities and
ponds. Other funds supported the work by Meridith Greer on the equity
index project.
A new permit will be issued to the City in August 2024. The permit includes
new requirements pertaining to riparian restoration goals and several new
street sweeping requirements. The new permit includes some incentives and
requirements for stormwater facility design and construction where feasible.
Another project is the Budd Inlet TMDL (Total Maximum Daily Load) for
dissolved oxygen. Several new requirements are included in the TMDL to
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 9
meet new stormwater requirements for water quality, overall nutrient
reduction, and mapping exercises including spatial analysis based on land
use.
Staff recommends the Public Works Committee recommend the City
Council approve and authorize the Mayor to sign 2023-2025 Stormwater
Capacity Grant Agreement from the Washington Department of Ecology
(ECY).
Director Smith shared information on the successful receipt of three water
quality grants from the Department of Ecology for nutrient reduction,
development of a monitoring plan, construction funding for riparian
restoration and in-water work at Pioneer Park, and stormwater improvements
at Beehive Industrial Park.
MOTION: Councilmember Jefferson moved, seconded by Chair Swarthout, to
recommend the City Council approve and authorize the Mayor to sign
2023-2025 Stormwater Capacity Grant Agreement from the Washington
Department of Ecology (ECY). A voice vote approved the motion.
SERVICE PROVIDER Specialist Gillum briefed members on the proposed second amendment to
AGREEMENT WITH the Service Provider Agreement with HDR Engineering for the Corrosion
HDR ENGINEERING Control Study.
FOR THE
CORROSION HDR Engineering has been working on the City’s Corrosion Control Study
CONTROL STUDY for the last several years. In 2019, the City was designated as a large public
AMENDMENT 2: water system (population over 50,000). Based on the requirements of the
Environmental Protection Agency’s (EPA) lead and copper rule for large
public water systems, the City is required to demonstrate optimal corrosion
control within the City’s water system.
The City contracted with HDR Engineering in 2021 to complete a study and
provide a report. In November 2022, the report was submitted to the State
Department of Health (DOH) as the state is the regulating agency for the
lead and copper rule. In February 2023, the City received a response from
DOH indicating that the study did not completely satisfy all requirements
and additional information was needed to consider the study as complete:
1. Evaluate treatments to identify optimal corrosion control treatment
for the water system.
2. Identify constraints that limit or prohibit the use of a particular
treatment.
3. Evaluate the effect of chemicals used for treatment on other water
quality treatment processes.
4. Recommend optimal treatment option for the Tumwater system
based on evaluation.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 10
The report to DOH is due in August 2024. HDR Engineering completed the
revisions to the report in December 2023. Staff reviewed the report and
provided feedback and recommended changes. HDR Engineering
incorporated the changes and addressed the requirements as requested by
DOH. However, DOH is recommending aeration treatment as the best
method for the Tumwater system for the airport wells, which are the only
wells not equipped for aeration treatment. Well 15 is the largest producer
within the wellfield. Review comments were forwarded to HDR in January
2024. Staff believes the report is ready for submittal to DOH. DOH has
indicated it may take six months to review the report. The request to the
committee is to recommend Amendment 2 to the Service Provider
Agreement with HDR Engineering to extend the term of service with no
change in funding to enable the submittal of the revised Corrosion Control
Study and to afford additional time for DOH to review and respond.
Chair Swarthout inquired as to whether the extension to June 20, 2024 would
be sufficient to enable DOH to respond. Specialist Gillum advised that the
date as indicated in the staff report should have reflected December 31, 2024
to enable sufficient time for DOH to respond.
City Attorney Kirkpatrick advised that approval by the committee was not
necessary as the extension can be approved by the City Administrator. No
action by the committee is necessary at this time. Additionally, she clarified
that previous action by the committee on the Stormwater Capacity Grant
would include placement of the proposal on the Council’s consent calendar.
Director Smith added that the primary purpose of the briefing was to update
the committee on the Corrosion Control Program and current activities
underway and recommendations moving forward for the project. The new
requirements could have significantly impacted the financial operation of the
Water Utility. As noted by staff, some chemical additions were
recommended initially and upon further review, staff was able to determine
aeration as an effective treatment. Staff will continue to monitor the water
system. The requirement is a new optimization requirement as the water
system is considered a “large” system. If there is room for improvement, the
Water Utility is required to act to fill any gaps. HDR Engineering has
assisted staff in identifying any gaps and completed the report. City crews
are working throughout the City checking services lines to residential
properties and monitoring other issues that speak to corrosion control to
ensure the system is optimized and safe. Well 15 includes the improvements
recommended in the report.
OTHER BUSINESS: City Administrator Parks referred to the staff report for the election of Chair
and information on concerns that future agenda topics would likely require a
longer meeting exceeding the one-hour period established by the committee.
Previously, meetings were scheduled not to exceed 90 minutes rather than 60
minutes. Staff requests confirmation by the committee to change the
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
February 8, 2024 Page 11
timeframe of committee meetings to reflect 90 minutes rather than 60
minutes to avoid potential timing conflicts.
Chair Swarthout and Councilmember Jefferson supported the request and
requested a follow-up with Councilmember Althauser to confirm his support.
City Administrator Parks acknowledged the request.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 9:19 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, February 08, 2024
8:00 AM
1. Call to Order
2. Roll Call
3. Selection of Committee Chair (Lisa Parks)
4. Israel Road and Linderson Way Pedestrian and Bicycle Improvements project, Authority to Solicit
Bids and Recommend Award (Bill Lindauer)
5. Israel Road and Linderson Way Pedestrian and Bicycle Improvements Project, Local Agency
Federal Aid Prospectus (Bill Lindauer)
6. Service Provider Agreement with RH2 Engineering for the Southeast Water Reservoir Design
Phases I, II, and III (Bill Lindauer)
7. 2023-2025 Stormwater Capacity Grant from the Department of Ecology (Dave Kangiser)
8. Service Provider Agreement with HDR Engineering for the Corrosion Control Study Amendment 2
(Carrie Gillum)
9. Additional Items
10. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/82620645052?pwd=SVR4akFXb0w3eko3bGt5dmc5dFlzQT09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 826 2064 5052 and Passcode
704632.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA