Public Works Committee
Regular MeetingTumwater, WA · May 23, 2024
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmembers Michael Althauser and Angela
Jefferson.
Staff: City Attorney Karen Kirkpatrick, Finance Director Troy Niemeyer,
Water Resources and Sustainability Director Dan Smith, Transportation and
Engineering Director Brandon Hicks, Assistant Transportation and
Engineering Director Mary Heather Ames, Engineering Services Manager
Bill Lindauer, Water Resources & Sustainability Program Manager Patrick
Soderberg, Construction Engineer Colby Fletcher, and Administrative
Assistant Bonnie Hale.
CONSTRUCTION Manager Lindauer reported the proposal is a request for additional funds for
CONTRACT WITH the I-5/Trosper Road/Capitol Boulevard Reconfiguration project specific to
ACTIVE a change order authority increasing from 10 percent to 20 percent.
CONSTRUCTION, INC.
FOR THE INTERSTATE The project consists of three roundabouts on Trosper Road and 6th Avenue,
5/TROSPER Trosper and Capitol Boulevard, and Trosper Road and the I-Ramps, Linda
ROAD/CAPITOL Street improvements, construction of a new roadway (6th Avenue) from
BOULEVARD Trosper Road to Lee Street, construction of the I-5 northbound on and off
RECONFIGURATION ramps, and a complete rebuild of the storm, sewer, and water system within
PROJECT, REQUEST project limits. The project included full utility undergrounding of all dry
FOR ADDITIONAL utilities, street lighting, crosswalk beacon systems at roundabouts, and
CONSTRUCTION landscaping and irrigation.
FUNDS:
The construction project was awarded to Active Construction Company for
$12,150,150.00. The standard 10 percent change order authority provided
by Tumwater Municipal Code 2.14.060 is ten percent for a total construction
budget of $13,365,165.00. The project is approximately one month from
substantial completion. Staff anticipates completion by the end of July
enabling an accurate projection of the total cost of the project. It is likely
the budget will exceed the change order percentage by an additional four
percent bringing the project total to approximately $13,851,171.00. Staff
requests the committee authorize change order authority to 20 percent to
ensure any remaining project issues could be accommodated. At a 20
percent change order authority, the project total would be $14,580,180.00.
The difference between the original bid was approximately $2,300,000.00
based on a 20 percent change order. However, the projection of a 14 percent
change order would equate to an increase of approximately $1,500,000.00.
The project was extremely complex with many components with cost
increases attributed to project quantity increases. Because the project is
based on unit bid pricing, each unit the contractor bids and installs needs to
be compensated. In some instances, an increase in quantities occurred
because of an estimating shortfall or installation of the product was not
identified in the national bid item, which required rectification. As a rule,
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 2
the majority of quantity increases were attributed to rock and asphalt as a
function of more material needs to build the project than originally
forecasted. Some of the reasons were due to construction phasing and how
the contractor performed the work, such as temporary pavement. In those
particular instances, the means and methods were required to ensure proper
completion of the project. Staff addressed some quantity issues on the
project.
Another unanticipated increase pertained to the unknowns of
undergrounding utilities, which were challenging in an area of an old
roadway with many existing undergrounded utilities. The project
encountered a large number of unknown existing utilities and utility
conflicts during the project.
The project team pursued due diligence to explore existing utilities locations
and potholes for further investigation. However, following investigation,
many utilities were installed in the ground either unknown or at another
location. Upon trenching and further investigation, redesign was necessary
as well as adjustments in a number of locations to avoid existing
underground utilities, which also was impacted by phasing of the project
with sewer, water, and storm drain installed first followed by Puget Sound
Energy (PSE) trenches. The phasing aspect of the project added complexity
to the work. Additionally, the project encountered unknown obstructions
and obstacles discovered during digging of the trenches. During trenching,
a void was discovered under Linda Street of a sizable size likely caused by
an ongoing water leak. The void required over-excavation and remediation
to avoid future issues. Other remnants were discovered of old foundations
and structures (storm structures) requiring removal to include an old
retaining wall. Many obstructions and obstacles were discovered during
excavation activities for the project.
The fiber optic installation was an added cost because the fiber optic system
was installed many years ago often reusing old conduit at that time. The
system was not installed correctly requiring rerouting of the fiber to
reposition it away from other utilities installed as part to the project.
Although a cost was incurred, the fiber optic system in the project area is
now installed correctly and should have a lifespan of many years without
service interruptions. Additionally, staff was able to identify the location of
the fiber optic system in the project area because the location was
undetermined prior to the project.
Schedule 74 commercial and private conversions throughout the project site
begins with the typical installation of all main utilities followed by
installation of dry utilities, such as power and other utility purveyors. The
project encountered conflicts when construction activities based on PSE
plans encountered challenges in setting the required vaults and identifying
locations for the equipment, as well as rerouting of the mainline trench to
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 3
avoid contact with other utilities. The issue resulted in a cascading affect as
any design change for sewer or water can affect other components
constructed later in the process. Connections into existing buildings both
commercial and residential encountered some difficulties, as well as the final
connection to a former restaurant recently acquired by the City. Existing
antiquated and non-conforming connection points at the restaurant required
additional work to bring the connection point to current standards to
complete the final connection.
City storm pond modifications were required because infiltration rates were
lower than required. Additional investigation identified poor soil strata in
parts of the pond. Staff developed a remediation plan to address the issue
by excavating the pond an additional 18 inches to increase the storage of the
pond and the required infiltration rate. Additionally several smaller
infiltration areas will be added inside the pond.
The original plan did not call for repaving Lee and Linda Streets. However,
because of design changes on Lee Street and the poor condition of an
asbestos watermain, the contractor was concerned about damaging the line
during construction. Staff completed some redesigns, which increased the
utility cuts within the roadway necessitating a repaving rather than patching
the roadway. Repaving extends the life of the road and avoids infiltration of
water through pavement cuts. Extra work on Linda Street included
extending the roadway improvements to the end of Linda Street.
During the work on the sewer main along Capitol Boulevard at the southern
terminus of the project site, an existing manhole in poor condition, the
discovery of a utility trench filled with concrete, and the presence of a gas
line impacted the ability to connect the sewer at that location necessitating
the extension of the sewer line by approximately 180 feet south to connect
to a manhole in better condition. The extension of the sewer main resulted
in the removal of the concrete panels under Capitol Boulevard. The City
benefitted from the additional work as the Capitol Boulevard Corridor Plan
includes plans to upgrade the sewer main along the corridor with a portion
of the sewer main replaced as part of the project, as well as removal of the
concrete panels. Although the work resulted in an increase in the cost, it
was a net benefit to the City.
Manager Lindauer explained that the examples represented the major
changes in addition to other smaller issues that contributed to the increase in
the cost of the project.
Councilmember Althauser questioned the electrical upgrade of the
restaurant building if the City owns the building. Manager Lindauer advised
that PSE is unable to serve a property that has an outdated electrical
connection point.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 4
Director Hicks explained that within the purchase and sale agreement the
City negotiated with the future purchasers of the property, the City is
required to connect the property to all utilities. He believes the new owners
plan to retain the building and repurpose its use. It is possible that the work
completed as part of the project will be changed in order to serve the new
use. However, the City is responsible for reconnecting utility services to the
property.
Councilmember Jefferson asked about the major reasons for the cost
increase. Manager Lindauer commented on the difficulty of identifying any
one item attributing to the cost overrun. Any time a project change occurs,
it tends to incur a cost implication, which could be minimal or major. All
changes add up. For undergrounding utility work on an old roadway, the
outcome was acceptable as costs will be incurred when trenching and
replacing utilities because of the uncertainty of what might exist in the
ground. Most unanticipated costs for roadway projects are associated with
underground work.
Manager Lindauer reported the additional costs will be paid through the
Capital Facilities Plan (CFP) for Transportation, Water, Sewer, and Storm.
The majority of the cost will be allocated to the Transportation and Storm
CFPs with some costs allocated to Water and Sewer CFPs as applicable.
Staff will quantify the costs and allocate the costs to each CFP.
Councilmember Althauser requested information on the specific amounts of
the overruns between the different CFPs. Manager Lindauer explained that
the costs have not been allocated between the different CFPs; however, the
majority of the cost would be allocated to the Transportation CFP followed
by the Storm CFP for the pond costs with the majority of the costs for sewer
attributed to the sewer extension. Costs to the Water CFP would be minimal.
When staff calculates pay applications for the contractor, all units are
segregated into different categories identifying the amount for allocation to
each CFP.
Councilmember Althauser commented that the initial project approval also
include a contingency, which likely would cover some of the overrun.
Director Hicks affirmed that when the budgeting was completed for the
Transportation CFP, staff included additional funding because the bidding
environment continues to be extremely unpredictable in terms of inflation,
cost of materials, and labor. The Transportation CFP is fully funded with
sufficient budget to cover additional costs. Additionally, the project was the
City’s most complex project ever undertaken. Staff was prepared for the
potential of overruns.
Councilmember Althauser asked about the potential of affecting sewer
projects with the increased costs incurred by the project. Director Hicks
affirmed the possibility as utility capital funds are somewhat constrained in
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 5
capacity to absorb additional costs because of large projects. Director Smith
is working with Director Niemeyer to consider financing for completing
some large utility projects.
Chair Swarthout asked about the anticipated timeline for completion of the
project. Manager Lindauer advised that substantial completion is expected
in July with all components completed enabling full operation of the project
site. The project will be essentially completed in September with final
project completion with the contractor scheduled for the end of the year.
Councilmember Jefferson inquired about the official opening date to
document the project historically. Director Hicks said he plans to follow up
on previous discussions with City Administrator Parks with follow up to the
committee at a future meeting.
Construction Engineer Fletcher reported on the final paving operation
during the first week in June during the night along with all utility valve
adjustments, site cleanup, and landscaping. Once pavement markings are
completed, all lanes of the roundabouts will be open to traffic.
Discussion ensued on the increased safety associated with roundabouts
because of lower vehicle speeds.
Director Hicks responded to questions about the timing of a comprehensive
briefing to the Council on the project and suggested including an update
during a Council meeting at the time of the project’s official opening date
announcement.
Chair Swarthout inquired about the status of repaving Israel Road. Manager
Lindauer explained some of the complications of repaving Israel Road
because of federal funding and the requirement for WSDOT approval. The
project will be released for bid soon, but roadwork would not be initiated
prior to the 4th of July holiday.
Chair Swarthout reviewed the request to the committee.
MOTION: Councilmember Jefferson moved, seconded by Councilmember
Althauser, to place the request to increase the change authority
provided to the Transportation and Engineering Director under
Tumwater Municipal Code 2.14.060 from 10 percent to 20 percent for
the Interstate 5/Trosper Road/Capitol Boulevard Reconfiguration
Project on the June 4, 2024, City Council Consent calendar with a
recommendation to authorize and approve. A voice vote approved the
motion unanimously.
INTERLOCAL Assistant Director Ames briefed the committee on the proposed interlocal
AGREEMENT WITH agreement with the City of Olympia for the Mottman Road Pedestrian and
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 6
CITY OF OLYMPIA Street Improvements project setting the framework for completion of the
FOR THE MOTTMAN project.
ROAD PEDESTRIAN
AND STREET The project, developed several years ago, is a joint project between the City
IMPROVEMENTS of Tumwater and City of Olympia bordering the South Puget Sound
PROJECT: Community College campus on the north side following Mottman Road
from R.W. Johnson Boulevard to the east for approximately 3,700 feet.
One-fourth of the distance is located within the limits of the City of
Tumwater with the remaining project site located in the City of Olympia.
The project improves Mottman Road to a standard serving all modes of
transportation. The road experiences all types of transportation modes
ranging from bicyclists, pedestrians, cars, and trucks. The project adds
sidewalk, bike lanes, channelization, and striping.
Conceptual design for the project has been completed and next steps include
final design, specifications, and a construction cost estimate followed by
permitting and construction. Each component of the project is covered by
the interlocal agreement. The City of Olympia is the lead on the project with
support by Tumwater staff as needed. Construction is scheduled to begin in
2027 with completion in 2028. Preliminary design of Olympia’s project
site indicates that the existing culvert at Percival Creek will not require
replacement; however, if determined the culvert requires replacement and
that the project could be extended. If right-of-way is required for storm
facilities and the City of Olympia encounters difficulties obtaining right-of-
way, it could extend the project by another year as well.
The project is funded by Connecting Washington Program, a legislative
funding source. The project total is $7.6 million with Tumwater’s total of
$1.748 million or 25% of the total. No matching funds are required for the
project. The City of Olympia’s cost is $5.68 million or 75% of the project
cost.
Staff recommends the committee place the interlocal agreement with the
City of Olympia for Mottman Road Improvements Project on the June 4,
2024 City Council consent calendar with a recommendation to approve and
authorize the Mayor to sign the agreement.
Councilmember Althauser asked whether the project would include two
project management teams by both cities. Assistant Director Ames advised
that City of Olympia staff would serve as the project manager for the project.
Staff is working with the City of Olympia to streamline the process to enable
the City of Olympia to receive grant funding directly with any Tumwater
staff time submitted to the City of Olympia for reimbursement from the
grant. The overall plan is for a cohesive process.
MOTION: Councilmember Althauser moved, seconded by Councilmember
Jefferson, to place the interlocal agreement with the City of Olympia
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
May 23, 2024 Page 7
for Mottman Road Improvements Project on the June 4, 2024 City
Council consent calendar with a recommendation to approve and
authorize the Mayor to sign the agreement. A voice vote approved the
motion unanimously.
OTHER BUSINESS: Committee and staff discussed the Public Works picnic scheduled at
Tumwater Historical Park later in the day at 11:30 a.m. and the status of the
move by the Water Resources and Sustainability Department’s to office
space at South Puget Sound Community College.
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the
meeting at 8:54 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, May 23, 2024
8:00 AM
1. Call to Order
2. Roll Call
3. Construction Contract with Active Construction, Inc. for the Interstate 5 / Trosper Road / Capitol
Boulevard Reconfiguration Project, Request for Additional Construction Funds (Transportation &
Engineering Department)
4. Interlocal Agreement with City of Olympia for the Mottman Road Pedestrian and Street
Improvements Project (Transportation & Engineering Department)
5. Additional Items
6. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/85781201471?pwd=U2haZU0vb25NZ2ZiamZHVUR5cUZBUT09
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 857 8120 1471 and Passcode
813524.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.
Get email alerts for Tumwater
A daily email when new agendas and minutes are posted.