Public Works Committee
Regular MeetingTumwater, WA · June 6, 2024
Minutes
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 6, 2024 Page 1
CONVENE: 8:00 a.m.
PRESENT: Chair Eileen Swarthout and Councilmember Michael Althauser.
Excused: Councilmember Angela Jefferson.
Staff: City Administrator Lisa Parks, Water Resources & Sustainability Director
Dan Smith, Transportation & Engineering Director Brandon Hicks, Engineering
Services Manager Bill Lindauer, Transportation Engineer I Bernie Gertje, Deputy
City Clerk Marnie McGrath, and Administrative Assistant Bonnie Hale.
APPROVAL OF
MINUTES:
PUBLIC WORKS
COMMITTEE,
MAY 9, 2024:
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to approve
the minutes of May 9, 2024, as published. A voice vote approved the motion.
AUTHORITY TO Manager Lindauer reported the request is to approve the solicitation for bids for
SOLICIT BIDS the Linwood Avenue Sidewalk, Susitna Lane to 2nd Avenue project.
AND
RECOMMEND The project was included in the Capital Facilities Plan and listed in the State
AWARD FOR Transportation Improvement Program (STIP). Funding was received from the
THE LINWOOD Transportation Improvement Board. The main goals are to provide multimodal
AVENUE improvements to the area along Linwood Avenue for bike mobility, pedestrian
SIDEWALK, mobility, and traffic calming and safety features. A roadway maintenance
SUSITNA LANE component is included in the project to upgrade the roadway.
TO 2ND AVENUE
PROJECT: Manger Lindauer displayed a project illustration identifying the project site. Most
of the project is limited to the Linwood corridor with some work along G Street for
curb returns and sidewalk improvements to 6th and 7th Avenue to expand pedestrian
continuity. The project is adjacent to Michael T. Simmons Elementary School, the
Tumwater School District Office, and the North End Fire Station.
Councilmember Althauser questioned whether there would be any improvements
in the area of Lake Park Drive. Manager Lindauer advised that infill is included in
the project scope with new sidewalk added in some locations. That portion of the
sidewalk located on the south side and west of Lake Park Drive will include a new
portion of sidewalk.
Manager Lindauer reported roadway improvements include asphalt grinding and
inlay of the entire roadway and repairing distressed areas in the road. The scope
also includes sidewalk reconstruction of failing sidewalk or sidewalk not meeting
ADA compliance. Some portions of new sidewalk will be added to provide
continuity for pedestrians through the project site to benefit the school. Curb bulb-
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 6, 2024 Page 2
outs will be installed at several intersections for traffic calming and reduction in
vehicle speeds. Lake Park Drive intersection improvements include correcting the
alignment to assist drivers as they approach Linwood Avenue to execute a left or
right turn safely. The project includes some channelization and curbing to align
the approach to some extent. The project also includes minor storm drainage
improvements by adding storm drainage enhancements and upgrading any surface
grates within the project limits. The scope includes reinstallation of all surface iron
with contract collars to prolong the life and pavement markings and select signage
throughout the project site.
The project site is heavily traveled with close proximity to the elementary school,
fire station, and neighborhoods. Traffic control by the contractor includes one lane
closure on either the north or south side to accommodate construction activities.
One side will be closed but two-way traffic will be maintained with one lane
alternating during construction of curb bulb-outs. The paving operation will
require one-lane alternating to accommodate paving on each side of the roadway.
Councilmember Althauser asked about coordination with the fire department for
access to respond to emergency calls. Manager Lindauer explained that all
emergency vehicles have full priority during closures of a lane of traffic through
the construction site. The project is similar to the Israel Road project that involved
close coordination between the fire station and the contractor to ensure emergency
vehicle access was maintained.
Staff contacted the fire department and the school to review the project scope. The
intent is to complete a majority of the work before school opens in September. The
school and school district are aware of coordination plans. The project includes a
number of adjacent property owners who have placed personal items within the
public right-of-way, such as plants, fences, and other improvements installed over
time. Those right-of-ways are required for the project. Staff identified all impacts
and plans to outreach and coordinate with each property owner to remove items
from the right-of-way.
The estimated construction cost range is $1,150,000 to $1,450,000. Funding was
provided by the Transportation Improvement Board ($371,250 in fuel tax) and
another $22,500 for project design. The Tumwater Transportation Benefit District
and the Transportation CFP will split remaining costs. The anticipated
construction schedule calls for the release of the construction bid in June 2024 with
construction beginning in mid-July through October 2024 with the project
substantially completed by October 2024. A majority of the work would likely be
completed in August.
Chair Swarthout questioned the street side selection from the section from Lake
Park Drive to Susitna lane. That area is located along the tree side, appears to lack
sufficient land, and slopes along the area. Manager Lindauer affirmed the street
side includes an existing one-foot asphalt shoulder and several feet of a flat area
sloping to a change in elevation. The design team was aware of the conditions
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 6, 2024 Page 3
from a design perspective. The area also includes existing older maple trees that
might be affected. Staff is working with the Community Development Department
on whether removal of trees might be required and the appropriate species of any
replacement trees.
Chair Swarthout questioned why the opposite side of the street was not selected for
the improvements. Manager Lindauer responded that both sides of the street are
encumbered by elevational changes. The south side of the street appeared to be a
better area for the improvements. Eventually, sidewalks will be completed on both
sides of the street.
Chair Swarthout reviewed the recommended action by the committee.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to authorize
staff to: (1) solicit bids for the Linwood Avenue Sidewalk, Susitna Lane to 2nd
Avenue project, (2) recommend City Council award and authorize the Mayor
to sign a Public Works Contract with the lowest responsible bidder and place
on the June 25, 2024, City Council meeting consent calendar with a
recommendation to approve and authorize the Mayor to sign. A voice vote
approved the motion.
GOLF COURSE Director Smith reported the request is an extension of time for the grant received
STORMWATER by the City for stormwater facilities as a component of the golf course parking lot
RETROFIT reconstruction project. The extension would be from January 31, 2024 to October
GRANT 2025 to align the project for the needs of the Parks and Recreation Department and
AGREEMENT its construction window for the parking lot improvements over the next
WITH DEPT OF construction season. The extension of the grant was previously approved by the
ECOLOGY Department of Ecology.
AMENDMENT 1:
The golf course has a number of catch basins discharging directly to the Deschutes
River. The project provides stormwater treatment before discharging to the river.
The project also supports the certification of the golf course as a Salmon Safe golf
course. The certification is scheduled for renewal later in the year with the
committee scheduled to receive a briefing on the recertification of the golf course.
Chair Swarthout asked whether the project is currently in design with no bids
released at this time. Director Smith affirmed the project has not been released for
bidding pending the final design and obtaining permits. The extension enables
additional time to complete that work with construction scheduled in summer 2025.
Chair Swarthout reviewed the proposed action by the committee.
MOTION: Councilmember Althauser moved, seconded by Chair Swarthout, to place the
Golf Course Stormwater Retrofit Grant Agreement with Department of
Ecology Amendment 1 on the July 2, 2024, City Council meeting consent
calendar with a recommendation to approve and authorize the Mayor to sign.
A voice vote approved the motion.
TUMWATER PUBLIC WORKS COMMITTEE
MINUTES OF VIRTUAL MEETING
June 6, 2024 Page 4
ADJOURNMENT: With there being no further business, Chair Swarthout adjourned the meeting
at 8:23 a.m.
Prepared by Valerie L. Gow, Recording Secretary/President
Puget Sound Meeting Services, psmsoly@earthlink.net
Agenda
PUBLIC WORKS COMMITTEE
MEETING AGENDA
Online via Zoom and In Person at
Tumwater City Hall, Council Conference
Room, 555 Israel Rd. SW, Tumwater, WA
98501
Thursday, June 06, 2024
8:00 AM
1. Call to Order
2. Roll Call
3. Approval of Minutes: Public Works Committee, May 9, 2024 & May 23, 2024
4. Authority to Solicit Bids and Recommend Award for the Linwood Avenue Sidewalk, Susitna Ln to
2nd Ave project (Transportation & Engineering Department)
5. Golf Course Stormwater Retrofit Grant Agreement with Dept of Ecology Amendment 1 (Water
Resources & Sustainability)
6. Additional Items
7. Adjourn
Meeting Information
All committee members will be attending remotely. The public are welcome to attend in person, by
telephone or online via Zoom.
Watch Online
https://us02web.zoom.us/j/87877073280?pwd=C_OsVuAGEPM0ySX-R8s5mNFY0xZfeQ.BlVN-
Pu5orVHEcSf
Listen by Telephone
Call (253) 215-8782, listen for the prompts and enter the Webinar ID 878 7707 3280 and Passcode
813524.
Public Comment
The public may submit comments by sending an email to council@ci.tumwater.wa.us, no later than
5:00 p.m. the day before the meeting. Comments are submitted directly to the Committee members
and will not be read individually into the record of the meeting.
Post Meeting
Audio of the meeting will be recorded and later available by request, please email
CityClerk@ci.tumwater.wa.us
Accommodations
The City of Tumwater takes pride in ensuring that people with disabilities are able to take part in, and
benefit from, the range of public programs, services, and activities offered by the City. To request an
accommodation or alternate format of communication, please contact the City Clerk by calling (360)
252-5488 or email CityClerk@ci.tumwater.wa.us. For vision or hearing impaired services, please
contact the Washington State Relay Services at 7-1-1 or 1-(800)-833-6384. To contact the City’s ADA
Coordinator directly, call (360) 754-4128 or email ADACoordinator@ci.tumwater.wa.us.