Public Works, Sewer and Water
Regular MeetingVerona, WI · January 14, 2013
Minutes
CITY OF VERONA
MINUTES
PUBLIC WORKS/SEWER & WATER COMMITTEE
MONDAY, JANUARY 14, 2013
1. The meeting was called to order by Chairperson William McGilvray at 5:30 p.m.
2. Roll Call: Present: William McGilvray, Clark Solowicz. Excused: Richard Streich. Also present:
Bob Gundlach, City Engineer, Bill Burns, City Administrator, Mayor Jon Hochkammer, Ron
Rieder, Public Works Director.
3. MOVED by McGilvray, seconded by Solowicz, to approve the minutes of the November 12, 2012
meeting of the Public Works/Sewer and Water Committee. Motion carried 2-0.
4. MOVED by McGilvray, seconded by Solowicz, to approve the Professional Services Agreement
for 2013 Storm Water Services not to exceed $10,000.00. Motion carried 2-0.
5. MOVED by McGilvray, seconded by Solowicz, to approve the Professional Services Agreement
for Construction Related Services of the Lincoln Street Culvert and Channel Modifications Project
not to exceed $11,900.00. Motion carried 2-0.
6. MOVED by McGilvray, seconded by Solowicz, to approve Change Order #1 for Well #5
Construction and Testing in the amount of $10,326.00. Motion carried 2-0.
7. MOVED by McGilvray, seconded by Solowicz, to approve Change Order #2 for Well #5
Construction and Testing. The result of this Change Order is no change to the contract amount.
Motion carried 2-0.
8. Discussion regarding the December 20, 2012 blizzard: Ron Rieder reported that the City
submitted costs related to the storm to Dane County Emergency Management in the amount of
$63,628.00.
9. Discussion regarding 2013 construction projects: 2013 Street Rehabilitation Project is expected to
be bid in February and awarded in March with an anticipated start date in April. Lincoln Street
Culvert and Channel Modifications Project is expected to be bid in March and awarded in April
with an anticipated start date in June. 2013 Surface Treatment Project is scheduled to be bid in
April and awarded in May with an anticipated start date of June. The Booster Station and Ground
Reservoir have been awarded and are slated to begin in March with a completion date of August
31, 2013. Engineering for the Lincoln Street Reconstruction Project will not begin until March
with construction to begin in August. Status of the Epic Campus TIA was discussed; a draft of the
report should be completed in February.
10. MOVED by McGilvray, seconded by Solowicz, to adjourn. Motion carried 2-0. Time: 6:25 p.m.
William McGilvray
Chairperson
Agenda
CITY OF VERONA
PUBLIC WORKS/SEWER & WATER COMMITTEE
MONDAY, JANUARY 14, 2013 – 5:30 P.M.
VERONA CITY HALL
AGENDA
1. Call to order.
2. Roll call.
3. Approval of the minutes of the November 12, 2012 meeting of the Public Works/Sewer and Water
Committee.
4. Discussion and possible action regarding a Professional Services Agreement for Construction Related
Services for 2013 Storm Water Services.
5. Discussion and possible action regarding a Professional Services Agreement for Construction Related
Services for the Lincoln Street Culvert and Channel Modifications Project.
6. Discussion and possible action regarding Change Order #1 for Well #5 Construction and Testing.
7. Discussion and possible action regarding Change Order #2 for Well #5 Construction and Testing.
8. Discussion and possible action regarding the December 20 and 21, 2012 snow event.
9. Discussion and possible action regarding 2013 construction projects.
10. Adjourn.
William McGilvray
Chairperson
POSTED: Verona City Hall
Verona Public Library
Miller=s Market
ALL AGENDAS ARE POSTED ON THE CITY=S WEBSITE AT www.ci.verona.wi.us
IF YOU NEED AN INTERPRETER, MATERIALS IN ALTERNATIVE FORMATS, OR OTHER
ACCOMMODATION TO ACCESS THE MEETINGS, PLEASE CONTACT THE CITY CLERK AT 845-6495