CITY OF WALKER
ENGINEERING DEPARTMENT
MEMORANDUM
TO: Building Committee
FROM: Scott Conners, P.E., City Engineer
DATE: September 7, 2022
RE: Library Scoping Discussion
We are attaching a handful of items that should help kickstart our formal initiation of the Walker
Library expansion. The first item is a flow chart that shows the various tasks that we recommend
in order to procure design and construction professionals. This chart can be a loose guide as we
take thoughtful and methodical steps forward in planning for the expansion of our library at the
heart of our city campus.
The second item is a draft Request For Proposals (RFP) that we can use to begin our search for
Architectural / Engineering (A/E) services. This process will be slightly different than our
typical RFP process for securing traditional engineering assistance. The architectural firm will
be the lead firm on the A/E team. The engineers will play a big role but it does not have to be
one of our standard 3 firms. There are numerous firms in the area that are capable of providing
these facility design services. Our challenge will be to find the right firm for our unique
community. This document was drafted in June so the dates within the document will need to be
updated when the Building Committee is ready to begin our search.
We have also provided a few exhibits to help prospective firms get familiar with our site and the
history of the library and campus development. We need to ensure that we have an interactive
and creative design process. In past projects many of our best design features came from staff
members with institutional knowledge and passion for the City. We will want the designers to
look at several creative options and provide enough flexibility to pivot when needed to hybridize
potential design features. Our hope should be to create a timeless design that will accent our
beautiful city campus.
Page 2 of 16
We look forward to engaging with the Building Committee and City Commission as we begin
this exciting journey. Please let me know if you have any questions in advance of our first
session. You can reach me directly at 616-791-6792 or sconners@ci.walker.mi.us.
Cc: Darrel Schmalzel, City Manager
Frank Wash, Assistant City Manager
Page 3 of 16
Walker Library Visioning Flow Chart
Request For Proposals (RFP) Review proposals with Building Construction Management invitees:
Committee. Select 2-3 firms for The visioning and design process
development – Architectural and should follow the proposal from the
Engineering Services interviews. Standard grading criteria to OAK
include: Experience, Project Team, A/E firm. Key components from the
Rockford Construction
Approach and Creativity, Relevant Project RFP will emphasize the community
Pioneer
Budget (Is % of project really fair?) engagement and staff involvement.
Earhardt
Triangle
Initial meeting with Building Beckering
Committee and key infrastructure staff
(Managers, DPW, Engineering &
Library) Post Interview, Building Committee Bi-Monthly updates should be
recommends A/E Firm to City Initial visioning session with A/E firm provided to the Building Committee.
Commission for consideration. to begin exploring various options This should include a report on tasks
within the City campus. A completed along upcoming goals and
representative from the CM should key decision points.
play a minor role in this process to
Refine RFP. Distribute to local A&E
Staff ensure constructability and cost
firms with experience in libraries and Staff re-establishes
coordinates feasibility. Options to creatively
school buildings Building Authority for
contract with include:
Page 4 of 16
purposes of bonding
firm selected by Library construction and • Symmetric addition to
Commission design costs existing library per original
vision.
Distribute RFP and supporting • Multistory Addition to
Follow A/E Proposal Through
Request For Proposals (RFP) existing library.
documents including Fishbeck Needs Bidding.
development – Construction • Scrape and new design
Assessment, campus site plans,
Management Services within parameters of
utility as-builts. Initial list to include:
existing campus area.
Tower Pinkster Titus
C2AE
Fishbeck Initiate same review process for this
Set up bi-weekly progress meetings for
Progressive AE RFP but include one member of the
design team including key staff and a
(others after request to prequalify A/E team to serve on the staff review
representative from the Building
with City Engineer) team.
Committee.
S. Conners 5-16-22
REQUEST FOR PROPOSALS
ARCHITECTURAL AND ENGINEERING SERVICES
CITY OF WALKER
KENT DISTRICT LIBRARY – WALKER BRANCH
Date Drafted:
June 8, 2022
Page 5 of 16
Qualified Architects & Engineers June 8, 2022
RE: Kent District Library – Walker Branch
Architectural / Engineering Services
We are inviting proposals from prequalified Architecture and Engineering (A/E) firms to work
collaboratively with The City of Walker (Walker), Kent District Library (KDL), and a Construction Manager
(CM) to be selected at a future date. The project will include visioning and designing for a new or
upgraded Walker Branch Library. Your firm has been selected as a candidate to provide these services.
1. Introduction
Key Contact: Scott Conners, PE
City Engineer
City of Walker
(616) 791-6792
sconners@walker.city
All questions regarding this Request for Proposals (RFP) should be submitted in writing to Mr.
Scott Conners at sconners@walker.city. Questions must be in writing to ensure that we can
provide comprehensive documented answers. Questions should be submitted before July 21st in
order to be considered prior to the due date for A/E consultant proposals.
2. Project Information
Following a Spaces Needs Study that was completed in January of 2019, the City of Walker has
recognized the need for a new or expanded library to serve the residents of Walker and west
Michigan. The Library would be staffed by the Kent District Library but owned and operated by
Walker.
The existing Walker Branch Library is approximately 8000 sq-ft in size. After reviewing the Space
Needs Study and considering many other issues, Walker is proposing to expand to approximately
25,000 sq-ft. The new design should allow for a logical expansion of approximately 15,000 sq-ft at a
future date.
The existing Walker Branch Library sits on the middle of the Walker campus. It is strategically
located between City Hall and the Public Safety/59th District Court building. When the library was
originally constructed in 1990 there was space allocated for a future expansion that would roughly
double the square footage with a similar and adjacent footprint. The city would like to have this
original expansion considered as part of the A/E consultant effort.
The City wishes to consider the following options for expansion:
• Expand the library as shown in the 1990 campus site plan.
• Multistory expansion of the existing facility
• Raze building and propose new structure that will fit within the existing architecture of the
Walker municipal campus.
Page 6 of 16
The City hopes for a collaborative and creative design process where many stakeholders are
engaged to help look for qualities to retain or add to the library. Additional parking is available
northeast of the existing library. This parking area may used for parking or it may be used to
reconfigure the library away from the covered walkway. The walkway itself may also become
integrated into the new design, as we did with our expansion of the City Hall and Commission
chambers. This campus interconnectivity could take different shapes during the creative process of
discovery. A clean slate design might include an open community space where the covered
walkways is removed in favor of a plaza. Examples of creativity should be a key component of A/E
proposals.
The City will hire a Construction Management (CM) firm to oversee construction and become an
integral part of the project team. The CM will assist the A/E and staff team during the design phase.
Their role will be to assist with estimating proposed costs and construction feasibility. As the project
transitions to construction the CM will take on the larger role while the A/E remains on the team, but
with a support role to assist in answering questions and responding to Requests For Information
(RFI).
The City of Walker, in conjunction with a Building Committee will be developing a bond program to
fund the library project. At this time, the final scope of work is not yet defined. For the purposes of
this proposal, assume a construction project value of $10M-$15M, including project soft costs.
a. Preliminary Project Timeline
A/E Pre-Design & Visioning November 2022 – June 2023
A/E Design Phase Services July 2023 – July 2024
Construction Admin Phase Services March 2023 - September 2025
Final schedule to be developed in conjunction with the project team, based on the A/E
proposal selected for the project.
Project Architect/Engineer Role
The scope of services is defined in this RFP and the AIA B132 – 2009 Owner-Architect, Construction
Manager as Advisor and AIA A232-2009, General Conditions of the Contract. A modified, mutually
agreeable version of this contract is intended to be negotiated between the successful AE and City of
Walker. The selected AE will be responsible for the following minimum services:
a. Pre-design & Visioning
i. Conceptual planning
ii. Preparation and presentation of up to 3 conceptual layouts within the municipal
campus
iii. Participation in all stakeholder engagement and community meetings
iv. Provide assistance in the procurement of a Construction Management firm.
v. Other items as detailed in A/E proposal
b. Design services
i. Site planning and design services
ii. Code reviews
Page 7 of 16
iii. ADA – Accessibility Design
iv. Architectural Services
v. Civil Engineering services
vi. Structural Engineering services
vii. HVAC / Electrical, plumbing engineering
viii. Information technology Infrastructure
ix. Facility furnishing – Coordinate budget and plan for a hybrid of new and existing
(salvaged) furnishings.
x. Permitting
b. Construction Phase A/E Services
i. Participate in post-bid interviews
ii. Submittal review
iii. Participate in regular project team meetings
iv. Review pay applications as necessary
v. Remain available to clarify drawings / respond to RFI’s
vi. Assist in closeout and punch list development and documentation
RFP Submission
a. RFP Schedule
i. Request for proposal issued August 1, 2022
ii. Questions due via email August 18, 2022
iii. Proposal due August 26, 2022 – 11 a.m.
iv. Interview(s) September
v. A/E Selection October 10, 2022 – 7 p.m.
b. Pre-Proposal Meeting
A mandatory pre-proposal meeting will be held on August 9, 2022 at 10:00 a.m. at the
existing Walker Branch of the Kent District Library. Walker staff will be there to familiarize
the prospective A/E firms with the site and it’s relationship to the municipal campus.
c. Submission Instructions
RFP responses must be submitted in an organized manner. Each copy should address the
distinct sections as listed in Part 5: Proposal Format.
Proposals shall be submitted to the office of Scott Conners, P.E. at 4243 Remembrance
Road, NW, Walker MI, 49534, before 11 a.m., in the following quantities:
• Ten (10) hard copies of technical proposal
• One (1) electronic copy of technical proposal, emailed to sconners@walker.city
d. Evaluation Criteria
The City of Walker reserves the right to select the design firm that provides the best value
as displayed through this RFP response and interview. The criteria for evaluation
includes, but is not limited to:
Page 8 of 16
i. Experience delivering projects of similar scope, size, and under similar contract types
and conditions with successful outcomes.
ii. Proposed key team members who will work well with the City team and have a track
record of success on similar projects.
iii. Demonstrated experience with innovate and creative design. Experience
incorporating libraries, school, and public institutions within an existing campus or
existing facilities.
iv. Value of professional services, including fee proposals.
.
Proposal Format - Technical Proposal
Each proposal shall include cover page, cover letter, and responses to the following sections:
e. Company Background
Provide a brief overview of your firm including location of home office, year founded,
ownership structure, annual volume and website address.
f. Experience & References
Identify recent library or school projects of similar size and scope for which your firm has
provided design services under AIA B132 contract in similar fashion to the program Walker
is considering. Please include references for at least 3 relevant projects completed in the
past five (5) years. Provide a reference for each client and relevant team members from
your firm who completed referenced work.
g. Project Team
Provide an organizational chart for your proposed project team. Include resumes for your
key team members, highlighting recent and relevant experience and expertise. Also
describe what services you intend to deliver through “in house” staff and what you
subcontract to consultants.
h. Design Approach
Summarize your approach to design services, specific to Walker and our Walker Branch
Library project. Identify key factors such as conceptual design, design phase processes,
milestone checks, and communication with client and team members.
i. Differentiators)
Highlight specific qualities that you believe will bring value to Walker and this project.
j. Fee Proposal
Provide a professional services cost estimate including soft costs. Ensure that the
proposed fee includes professional services to investigate and propose necessary
technology and furnishings. Keep in mind that the City is not looking for the lowest fee.
We are looking for an appropriate level of professional services to ensure a quality project
and an experienced project team.
Page 9 of 16
k. Endorsement
The proposal should be signed and dated by a principle in the firm.
Page 10 of 16
Page 11 of 16
Original Walker Library Phase II Expansion
Page 12 of 16
Original Walker Library Phase II Expansion – Close Up
Walker Campus Brick Pillar Detail
Page 13 of 16
Page 14 of 16
Original Library Landscaping Layout
OWENS JAMES J
H & D DEVELOPMENT LLC GODFREY STEVEN & SHELLY 2424
COMMAND MICHAEL
4438 2427 NOLAN AVE NW
2402
REMEMBRANCE RD NW NOLAN AVE NW KAKKURI DAN & MARY
CITY OF WALKER KENOWA HILLS PUBL SCHOOL NOLAN AVE NW
2420
4357 4252 MARENTETTE JEFFREY L WISNESKI MELISSA L
NOLAN AVE NW
REMEMBRANCE RD NW 3 MILE RD NW 2421 2412
VANDERWAL ROBERT R NOLAN AVE NW
ALEXIS DR NW
4408
VANDERMYDE DAVID & KRISTIN HOLTROP RONALD J
REMEMBRANCE RD NW DEWALL MICHAEL J 2423 2411
FIre Department 2417 NOLAN AVE NW NOLAN AVE NW
WILSON AVE
ALEXIS DR NW DORATO MICHAEL J & AMY
2419
NOLAN AVE NW CITY OF WALKER
Police Department
RE M 2401
RANDALL AVE NW
EM B VALLONE VITO & JENNIFER
Potential Library Expansion Area 2381
ER
SHMONA ALYOD RANDALL AVE NW
NC
4360
REMEMBRANCE RD NW RA NOBLETT MATTHEW
SHMONA ALYOD D 2369
4360 RANDALL AVE NW
REMEMBRANCE RD NW
JANSHESKI DENNIS J
2355
R A S A INVESTMENTS LLC
CITY OF WALKER Existing Library RANDALL AVE NW
4243
2326 KANAAN ALI
REMEMBRANCE RD NW
WILSON AVE NW 2341
Page 15 of 16
R A S A INVESTMENTS LLC NIJA CORPORATION RANDALL AVE NW
2326 4350 Department of Public Works KERR WILLIAM & ELSA TRUST
WILSON AVE NW
59th District Court
REMEMBRANCE RD NW 2327
RANDALL AVE NW
V
U 11
BURDICK JOANN
GREER KENNETH
2313
2296 RANDALL AVE NW
WILSON AVE NW CITY OF WALKER
DOLCI INVESTMENTS LLC
2311 4151
WILSON AVE NW REMEMBRANCE RD NW
BURDICK JOANN M
D D R REALTY GROUP LLC Walker Ice and Fitness CenterH
HAISMA GERALD
4322 2285
2282 MB
WILSON AVE NW
REMEMBRANCE RD NW
ME RANDALL AVE NW
RE
4300 REMEMBRANCE LLC BOLLMAN JAMES
VADASY SAMANTHA 4300 RA 2271
2228 REMEMBRANCE RD NW NCE City Hall RANDALL AVE NW
WILSON AVE NW
VADASY SAMANTHA
RD RAISANEN THOMAS R & SHELLIE ANN
2228 2257
WILSON AVE NW RANDALL AVE NW
MICHIGAN CONFERENCE ASSOF OF SEVENT KLINE MARK & JENNIFER FAMILY TRUST
2222 2243
WILSON AVE NW RANDALL AVE NW
MICHIGAN CONFERENCE ASSOF OF SEVENTMICHIGAN CONFERENCE ASSOF OF SEVENT
2222 4250
WILSON AVE NW REMEMBRANCE RD NW VEENSTRA LAVERNE &
BROEKEMA KENNETH & SUSAN TRUST 2221
2181 BULL FAMILY TRUST SMITH SUSAN E VELTEMA ADAM & KRISTIN KINNEY AVE NW
ARBOR CT NW 2186 2187 2188
STUBBS MARK T STUBBS MARK T ARBOR CT NW ARBOR TRL NW ARBOR TRL NW
2190 2190 BYRNE RORY & LAUREN STURGIS JEFF PERGIEL MICHAEL
WILSON AVE NW WILSON AVE NW 2174 4200 4036
ARBOR CT NW REMEMBRANCE RD NW EVANSDALE ST NW
City of Walker - Campus Map S. Conners 7-6-22
REGIS Data
±
Potential Library Expansion Area
CITY OF WALKER CITY OF WALKER
Page 16 of 16
4243 4151
REMEMBRANCE RD NW REMEMBRANCE RD NW
Existing Library
NIJA CORPORATION
4350
REMEMBRANCE RD NW
MB
ME
RE
RA
D D R REALTY GROUP LLC NCE
4322 RD
REMEMBRANCE RD NW
4300 REMEMBRANCE LLC
4300
±
REMEMBRANCE RD NW
Walker Library - S. Conners 7-6-22
Area for Replacement or Expansion REGIS Data
Get email alerts for Walker
A daily email when new agendas and minutes are posted.