Public Works Committee
Regular MeetingWaterford, WI · November 21, 2022
Minutes
VILLAGE OF WATERFORD
Public Works & Utilities Committee Meeting Minutes
801 Ela Ave. – DPW Building
November 21, 2022
Meeting was called to order by Chair Koeller at 4:00 pm.
Present: Fred Koeller, Carl Oberhart, Kim Migazzi
Excused: Pat Goldammer, Don Houston
Others present: Mike Sponholtz, Rick Huening, Zeke Jackson, Alyssa Robbins
Minutes: Motion by Oberhart to approve the 10.17.2022 minutes. Second by Migazzi. All aye.
Motion carried.
Special Events: Jingle for Janet Run/Walk & Winter Wonderland Christmas Parade. Motion by
Oberhart to approve both special events. Second by Migazzi. All Aye. Motion carried.
Reports: Streets and Utilities Supervisor Huening spoke on updates in the Department of Public
Works.
Parks Supervisor Sponholtz gave updates on the Department of Parks and Facilities.
New Business:
1- Western Racine County Sewer District requests permission to install an antenna on water
tower #2: Motion by Koeller to allow WRCSD permission to install an antenna on water tower
#2. Second by Migazzi. All Aye. Motion carried.
2- Installation of a 3rd tornado siren at the DPW building: Motion by Oberhart to approve the
installation of a 3rd tornado siren at the DPW building. Second by Migazzi. All aye. Motion
carried.
3-Draft Functional Classification of Roads by the WISDot: Motion by Koeller to approve the Draft
Functional Classification of roads by the WISDot. Second by Oberhart. All Aye. Motion carried.
Motion by Migazzi to adjourn at 4:50 p.m. Second by Oberhart. All aye. Motion carried.
Respectfully submitted by,
Alyssa Robbins, Administrative Clerk
Agenda
1
VILLAGE OF WATERFORD
PUBLIC WORKS & UTILITIES COMMITTEE
November 21st, 4:00 pm
DPW Building, 801 Ela Ave
1. Call to Order
2. Roll Call
3. Comments and
Correspondence
4. Public Appearances:
5. Reading and Approval of Min: 10.17.22 PW&U
6. Special Event Permits: Jingle for Janet, Winter Wonderland Parade
7. Reports: Streets Supervisor, Parks Supervisor, Engineer
New Business
1. Review and discussion on the Western Racine County Sewer Districts request for permission to install
an antenna on water tower #2; consider an appropriate motion for action.
2. Review and discussion on proposal of 3rd tornado siren installation at the DPW building; consider an
appropriate motion for action.
3. Review and discussion on Draft Functional Classification of roads by the WISDot; consider an
appropriate motion for action.
Adjournment
Public Notice
Questions regarding the nature of the agenda items or more detail on the agenda items listed above scheduled to be considered by the governmental body
listed above can be directed to Zeke Jackson, Village Administrator at 262-806-1750 or at zjackson@waterfordwi.org. It is possible that members of and
possibly a quorum of members of other governmental bodies of the municipality may be in attendance at the above-stated meeting to gather information;
no action will be taken by any governmental body at the above-stated meeting other than the governmental body specifically referred to above in this
notice. Upon reasonable notice, a good faith effort will be made to accommodate the needs of disabled individuals through sign language interpreters or
other auxiliary aid at no cost to the individual to participate in public meetings. Due to the difficulty in finding interpreters, requests should be made as far
in advance as possible preferably a minimum of 48 hours. For additional information or to request this service, contact the Village Staff at 262-534-7912, or
by writing to the Village Administrator at the Village Administration Building, 123 N. River St, Waterford WI, 53185 Copies of reports and other
supporting documentation are available for review at the Village Administrator’s Office, Administration Building, 123 N. River St, Waterford WI 53185
during operating hours. (8 a.m. – 5 p.m. weekdays).
Posted: 11/16/2022; 4:00 p.m.
2
1 VILLAGE OF WATERFORD
2 Public Works & Utilities Committee Meeting Minutes
3 Held at the DPW building (Unapproved)
4 October 17th, 2022
5
6 Meeting was called to order by Chair Koeller at 4:00pm.
7 Present: Don Houston, Fred Koeller, Carl Oberhart, Pat Goldammer, Kim Migazzi
8 Others present: Mike Sponholtz, Rick Huening, Zeke Jackson, Jody Beer
9
10 Minutes: Motion by Koeller to approve the 09.19.2022 minutes. Second by Houston. All aye. Motion
11 carried.
12
13 Events: No special event permits were presented to discuss and approve.
14
15 Reports:
16 Streets and Utilities Supervisor Huening spoke on updates in the Department of Public Works.
17
18 Parks Supervisor Sponholtz gave updates on the Department of Parks and Facilities.
19
20 New Business:
21 1- Contract Review: Review and discussion was held regarding 3 year renewal of the All Pro Mechanical
22 contract for HVAC maintenance services. The company will continue to provide service for the Village
23 Hall, Library and DPW at a 3-year cost of $28,791. It will also provide service to the Seidel Building at
24 no charge to the Village. The Committee recommends that the All Pro Mechanical contract for HVAC
25 maintenance services be renewed.
26
27 2- Ten Club Park Improvement Plans: Due to the poor economy and higher interest rates new
28 development is not progressing as forecast. Discussions with other municipalities that have water parks
29 are stating that they are having much trouble (and high cost) with maintaining them. Conduit and
30 electric costs are now at $477,000 which is also more expensive than when the project started. We
31 have to get costs down to be able to keep moving forward and get things done. This is a long term
32 investment that will need funds for future upkeep.
33 a. Discussed seeking out sponsors to help fund the park. The Village has already received
34 donations.
35 b. Renaming the park for a donor, except for one parcel that is named Ten Club Park on the deed
36 and that name must remain. We could use sponsors for the new name of the rest of the park.
37 c. Find what costs the Village can pay and push other costs, such as grading, sidewalks, and
38 landscaping to a later date when the economy and money flow is better.
39 d. Try to finalize and sign contract documents, then prepare change orders.
40 i. Have lighting, poles and conduit wires change-ordered out.
41 ii. Have concrete work amended or not completed until later in the project.
42 e. Continue the current plan in the future.
43 i. Purchase the playstream and lighting.
44 ii. The project needs restrooms as soon as possible. Sponholtz looked into precast concrete
45 restroom structures that are made in Illinois. He did not have the cost of the structure at
46 this meeting, but would continue finding information and cost by the November meeting.
47 f. The original budget was $3.5 million and is now $3.1 million without the guts of the playstream.
48 i. We received only 1 bid that was for$4.8 million. The second RFP netted more than one
49 bid, all at $5.2 million and higher.
50 ii. Perform another RFP when the economy and costs are better.
3
51
52 We need new development and new impact fees to help with the funding for Ten Club Park. We are
53 planning to have new plans in the next 2 to 3 years.
54
55 Motion by Koeller to eliminate wire conduit, light poles and playstream from the plans at this time.
56 Second by Houston. Houston, Koeller, Oberhart and Goldammer – aye. Migazzi – no. Motion carried.
57
58 3-Purchase of Avant loader for snow removal and park maintenance: Huening had a video of the
59 capabilities of this loader. It has turf tires that will not tear up grass when mowing and is articulated to
60 make mowing and plowing easier. It is also energy efficient and environmentally friendly. The total cost
61 is $66,000. This includes the following attachments: forks, snow blower, bucket and rotary broom.
62 The purchase is approved for 2023, but the 2022 budget would be amended to purchase the loader in
63 2022.
64
65 Motion by Migazzi to purchase the Avant loader this year. Second by Goldammer. Goldammer,
66 Koeller, Oberhart, Migazzi – aye. Houston – no. Motion carried.
67
68 Motion by Migazzi to adjourn at 4:50 p.m. Second by Koeller. All aye. Motion carried.
69
70 Respectfully submitted by,
71 Jody Beer, Deputy Clerk
72
73
4
5
6
7
8
9
10
VILLAGE OF WATERFORD
PUBLIC WORKS AND UTILITY MEETING
For additional information: http://www.waterfordwi.org
Meeting Date: November 2022
Public works:
All trucks are set up for the winter plow season
Plow truck DOT inspections and oil changes completed
All snow flake decorations are installed
Asphalt patches completed on Red Coat Ct. in the Fox River Hills subdivision
Road pretreating with brine has begun
Contacted Community Methodist Church to see if they want to buy any Christmas decorations
Update on equipment purchase
Replacement lights for the purple street lights have been delivered waiting for contractor to
change the lights
Sweep All was in filled 3 dumpsters full of leaves. Coming back again this week weather
permitting
Utilities:
All hydrant markers are installed
Well 5 prop meter seal fair causing false flow fair alarms
All seasonal meters are in for the winter
E. Main St has been cleaned televising of main and laterals are currently being done
9 man holes were lined and sealed (pictures are in packet)
Lift stations have been cleaned
DNR sanitary inspection set for December (Wells)
Update on AMI antenna install
Rick Huening
Public Works/Utilities Supervisor
Name: i:\1. 2017 agendas\board\2017_04\02a br 2017 bridenhagen.docx Created: 4/13/2017 4:46 PM Printed: 4/14/2017 2:38 PM Author: Robert
Kufrin Last Saved By: Zeke Jackson Revision: 2
11
12
13
14
15
16
17
18
19
20
21
VILLAGE OF WATERFORD
PUBLIC WORKS AND UTILITY MEETING
Facilities and parks update
Meeting Date: November 21 2022
Facilities
-Ongoing general maintenance, cleaning and repairs of the Library, Village hall, DPW, Parks facilities and other various
facilities projects. Managing various contractors, performing PM on the HVAC, controls, and fire protection systems.
-Completed the annual inspection and repairs of the library flat roof. Ongoing work on keeping the HVAC running correctly.
-Finishing up the Village security upgrade.
-Winterized the park bathrooms and Pavilion plumbing. Reorganizing storage buildings at the park.
-Set up/take down and clean up for the haunted house and elections at Village Hall
-Working on Whitford park building improvement plans.
-Completed the repairs to the damaged area at the Whitford park baseball storage facility
Parks
-Ongoing maintenance, mowing, weeding, spraying, watering and mulching of all Village properties
-Removed problem trees at Whitford park, removed asphalt, added topsoil and sod. created a path from the pavilion to the
new concrete we added at the bathroom entrance
-Put up the Ice Rink outer shell, Including the cables and rink lights.
-With the help of our entire crew, we took down the Bandshell tent at Village Hall and brought it to the manufacturer for
cleaning and repairs. Picked up the New band shell tent.
-Continuing upgrade work at Whitford park. The Much needed improvements are looking good.
-Set up/cleanup Waterfeared Halloween event.
-Preparing for the Christmas parade events and Holiday events and decorations in the parks.
-Starting work on planning banner poles at 3 more locations around the Village.
-Completed fall clean up and debris removal at the Village hall landscape beds, Including the beds at the municipal parking
lot as well as other areas.
-Leaf Removal at Ten Club Park and Village Hall
Facilities and Parks supervisor.
Mike Sponholtz
22
VILLAGE OF WATERFORD
Engineer’s Report
November 14, 2022
Cornerstone Crossing Multi-Family Development – Project No. 220511
The development by PRE/3, LLC. includes four multi-family buildings on 5.01 acres located
on Cornerstone Crossing.
The public utilities are installed but have not been fully tested and accepted by the Village.
Mercury Business Park Storage – Project No. 220549
The development by Dave Chavez includes two storage buildings on 1.30 acres located on
Gravity Court.
The public watermain serving the site is complete.
The developer has requested an additional parking area in addition to the approved plans.
We are currently waiting for engineering plans to review.
2022 LRIP Project - N. Milwaukee Street Resurfacing – Project 210605.90/.40
This project involves the resurfacing of N. Milwaukee Street between E. Main Street and
the north Village limits.
The Village was awarded $22,837.87 from WisDOT LRIP funding to be used for the N.
Milwaukee St. resurfacing project.
The project is substantially complete.
The contractor milled and repaved the area that holds water north of 5 th St. The area will
be restriped in the spring when temperatures are higher for paint to cure properly.
Danielson St. & Augusta Paving / Whitford Park Paving – Project No. 221301
The Village has requested that Danielson St and Augusta be resurfaced this year.
Danielson St., Augusta, and Whitford Park are being bid together in separate sections with
the possibility to choose which section is built as part of the contract.
The bid by Stark Pavement Corp ($674,320.15) was approved by the Village on 9/12.
The contractor has completed Danielson St.
Augusta and Whitford Park will be done in the spring. The bid prices will not increase for
Augusta and Whitford Park.
Tetzlaf “The Armory Self Storage” Review – Project No. 222115
We received plans on 10/6/22 for a self-storage facility north of Gravity Ct in the Mercury
Development.
The plans and calcs are currently being reviewed.
Well 6 – Intent to Apply (ITA)
An intent to apply (ITA) application has been submitted for low interest money through
the WDNR; this ITA does not commit the Village to use the funding; it may simply allow
them a lower interest rate and longer repayment terms if the project qualifies for the
funding.
Page 1 of 2
P:\WATRF\General\Admin\Monthly Reports\2022\11-2022\11-14-22.docx
23
VILLAGE OF WATERFORD
Engineer’s Report
November 14, 2022
Neumann Homes Development – Project No. 221632
Neumann Homes is interested in developing the area north of Trailside Elementary on the
east and west sides of N. Milwaukee.
We are working with the developer’s engineer to provide water and sewer service to the
property.
Gemini Lots 7&10 CSM – Project No. 222271
ProHeath Care is interested in constructing a clinic on Cornerstone Court across from the
lift station.
Baxter & Woodman is currently working on a CSM to combine Lots 7&10 and provide an
access easement to the adjacent pond.
Space Squared Self Storage Review – Project No. 220614
We received plans on 10/14/22 for a self-storage facility at the corner of STH 83 and Park
Dr.
The plans and calcs are currently being reviewed.
Page 2 of 2
P:\WATRF\General\Admin\Monthly Reports\2022\11-2022\11-14-22.docx
24
25
26
27
28
29
Get email alerts for Waterford
A daily email when new agendas and minutes are posted.