Public Works Committee
Regular MeetingWaterford, WI · December 18, 2023
Minutes
VILLAGE OF WATERFORD
Public Works & Utilities Committee Meeting Minutes
Public Works Bldg. 801 Ela Ave
December 18, 2023
Meeting was called to order by Chair Koeller at 4:00 pm.
Present: Fred Koeller, Carl Oberhart, Cindy Mooney
Others present: Mike Sponholtz, Rick Huening, Alysa Robbins, Off. Kiley Donovan, Chief Haffemann,
Asst. Chief Rozena, Zeke Jackson
Minutes: Motion by Oberhart to approve the 11-20-2023 minutes. Second by Goldammer. All aye.
Motion carried.
New Business:
Motion by Koeller to approve proposal to use the new bay to host a monthly craft/farmer
market. Second by Oberhart. All Aye. Motion carried.
Motion by Oberhart to approve purchase of Hot Box as quoted by Midwest Paving Equipment.
Second by Mooney. All aye. Motion carried.
Motion by Oberhart to approve purchase of flashing pedestrian lights and have installed by
DPW. Second by Goldammer. All Aye. Motion carried.
Motion by Goldammer to adjourn at 4: 58 p.m. Second by Oberhart. All aye. Motion carried.
Respectfully submitted by,
Alysa Robbins, Administrative Clerk
Agenda
1
VILLAGE OF WATERFORD
PUBLIC WORKS & UTILITIES COMMITTEE
Waterford Fire Dept - 819 Mohr Ave
December 18, 2023, 4:00 pm
801 Ela Avenue
1. Call to Order
2. Roll Call
3. Comments and Correspondence
4. Public Appearances:
5. Reading and Approval of Min: 11-20-23 PW&U
6. Special Event Permits:
7. Reports: Streets Supervisor, Parks Supervisor, Engineer
New Business
1. Discussions on craft fair proposal at Fire Station 2; consider an appropriate motion for action.
2. Discussions on the purchase of a Hot Box; consider an appropriate motion for action.
3. Discussions on having a flashing pedestrian light for East Main St.; consider an appropriate motion for
action.
Adjournment
Public Notice
Questions regarding the nature of the agenda items or more detail on the agenda items listed above scheduled to be considered by the governmental body
listed above can be directed to Zeke Jackson, Village Administrator at 262-806-1750 or at zjackson@waterfordwi.org. It is possible that members of and
possibly a quorum of members of other governmental bodies of the municipality may be in attendance at the above-stated meeting to gather information;
no action will be taken by any governmental body at the above-stated meeting other than the governmental body specifically referred to above in this
notice. Upon reasonable notice, a good faith effort will be made to accommodate the needs of disabled individuals through sign language interpreters or
other auxiliary aid at no cost to the individual to participate in public meetings. Due to the difficulty in finding interpreters, requests should be made as far
in advance as possible preferably a minimum of 48 hours. For additional information or to request this service, contact the Village Staff at 262-806-1750, or
by writing to the Village Administrator at the Village Administration Building, 123 N. River St, Waterford WI, 53185 Copies of reports and other
supporting documentation are available for review at the Village Administrator’s Office, Administration Building, 123 N. River St, Waterford WI 53185
during operating hours. (8 a.m. – 4 p.m. Monday - Thursday).
Posted: 12/15/2023; 12:00 p.m.
2
VILLAGE OF WATERFORD
Public Works & Utilities Committee Meeting Minutes
Public Works Bldg. 801 Ela Ave
November 20, 2023 - unapproved
Meeting was called to order by Chair Koeller at 4:00 pm.
Present: Fred Koeller, Carl Oberhart, Cindy Mooney
Others present: Mike Sponholtz, Rick Huening, Alysa Robbins
Minutes: Motion by Oberhart to approve the 10-16-2023 minutes. Second by Mooney. All aye. Motion
carried.
Reviewed Special Event Permit Applications for Jingle for Janey and the Christmas Parade. No action
needed.
New Business:
Motion by Koeller to table discussion on painting the bricks on the Main Street Bridge pending
discussion with the State. Second by Oberhart. All Aye. Motion carried.
Discussion about Park Place Townhouse Association’s missing ‘no through’ sign. Being the road
is privately owned by the association they will need to purchase the replacement. No further
action needed.
Discussion on the Rochester impoundment tabled.
Motion by Koeller recommend updated Engineering Work Order on the East Main Street
Reconstruction Project to the Village Board for approval. Second by Oberhart. All aye. Motion
carried.
Motion by Koeller to approve maintenance invoice from All-Pro to replace stacks on heaters at
the Public Works Building. Second by Oberhart. All Aye. Motion carried.
Motion by Oberhart to adjourn at 4: 59 p.m. Second by Koeller. All aye. Motion carried.
Respectfully submitted by,
Alysa Robbins, Administrative Clerk
3
VILLAGE OF WATERFORD
PUBLIC WORKS AND UTILITY MEETING
For additional information: http://www.waterfordwi.org
Meeting Date: December 2023
Public works:
• Crew has been busy working with Mike getting the parks ready for winter
• Crew installed hockey rink at Whitford Park
• Crew helped with Christmas parade detour and closures
• Crew loaded fireworks for Christmas parade
• Plow trucks ready for winter
• Will start pre treating roads with brine when snow is predicted
• Chipseal project in Fairview is closed out
• Personnel update
Utilities:
• Fiber has been installed at tower 1 for AMI project and for SCADA upgrade
• Meter reading is completed billing goes out this week
• The Expediters were in and grouted leaks found during annual televising
Rick Huening
Public Works/Utilities Supervisor
Name: i:\1. 2017 agendas\board\2017_04\02a br 2017 bridenhagen.docx Created: 4/13/2017 4:46 PM Printed: 4/14/2017 2:38 PM Author: Robert
Kufrin Last Saved By: Zeke Jackson Revision: 2
4
5
6
7
8
9
10
11
12
13
14
VILLAGE OF WATERFORD
PUBLIC WORKS AND UTILITY M EETING
Facilities and parks update
Meeting Date: December 2023
Facilities
-Ongoing general maintenance, cleaning and repairs of the Library, Village Hall, DPW, Park facilities and other various
facilities projects. Managing various contractors, performing PM on the HVAC, fire protection and alarm systems.
-Rescheduled the pavilion remodeling project at Whitford park to spring.
-Planning for the December 14 Park Bathroom and concession stand installation. Working of the final plumbing layout and
foundation construction, coordinating installation, crane rental, road closure, and final plumbing and electrical hook up
details.
-Daily inspections and project management at the 10 Club Park construction project, Final work at the park being completed
for the year, though some small items will remain and will be completed in spring.
Parks
-Ongoing preparation for the new ice rink installation, rubber mats around the rink, electrical hook ups, new lighting and
poles around the rink, new ramps, and working with the Lions club in planning the skate rentals, etc.
-Setting up the hockey rink (existing ice rink) at Whitford park.
-Working on new park signs, rinks signs, rink operations for the upcoming season.
-Winter project planning
Facilities and Parks supervisor.
Mike Sponholtz
15
Firefighter Kiley Donovan
To whom it may concern,
After attending the budget meeting on November 21st I was inspired to
formulate a plan to raise money for the fire department. A way to engage with the
community, bring them into the firehouse, and to raise funds. I am proposing that we
begin hosting an indoor craft fair / farmers market this winter. It would bring the
community together, seeing as there is not a consistent farmers market held. We
would be able to bring various businesses in from Waterford as well as our
surrounding areas. It would not only bring together our community, it would build a
stronger connection to our neighbors. Below is an outline of ways money would be
bought in.
● There would be a $25 “suggested donation to WFD” for the use of the space.
● The fire department would supply various concession items for sale.
● The community would be welcome to tour the station, and see inside of our
various apparatus
● The fire department is currently designing various clothing items with a
specialized logo which will be available for purchase by the community.
Thank you for taking the time to read through this, and for considering our
proposal. If there is any further questions or concerns please feel free to reach me at
the following:
Cell: (262)391-5078
Email: kileyedonovan@gmail.com
16
QUOTATIO
N
2129 W. MORGAN AVENUE MILWAUKEE, WI 53221 PHONE (414) 281-6400 FAX (414) 281-6404
Customer Information: Date: 12/5/23
Village of Waterford NOTE: Quotation is good
for 30 days from the above
date. Prices quoted are for
EMAIL: quantities shown only.
PART # DESCRIPTION UNIT PER QUANTIT TOTAL
PRICE Y
Spaulding 4 ton Asphalt $25,500.00
Trailer
Hydraulic Dump Hopper $5,100.00
Manual Top and Rear Door
Diesel Burner $1,475.00
Oil Jacketed $7,000.00
2 LED Strobes $950.00
Solvent Tank $300.00
5 Piece Tool Holder $250.00
IF YOU HAVE ANY QUESTIONS CONCERNING THIS SUBTOT $40,575.00
QUOTATION, AL
PLEASE CONTACT MIKE BAIER FREIGHT $1,400.00
PHONE (414) 405-6511 SALES N/A
EMAIL: MBAIER@SHERWININDUSTRIES.COM TAX
TOTAL $41,975.00
17
Midwest Paving Equipment, Inc.
757 DuPage Blvd Suite 2387
GLEN ELLYN, IL 60137 US
(630) 453-0772
Estimate
ADDRESS SHIP TO ESTIMATE # 1688
Village of Waterford Village of Waterford DATE 11/09/2023
801 Ela Avenue 801 Ela Avenue EXPIRATION DATE 01/09/2024
Waterford, WI 53185 Waterford, WI 53185
ACTIVITY QTY RATE AMOUNT
5D4TR 1 46,936.00 46,936.00
4-Ton Falcon Asphalt Recycler & Hot Box Trailer
DUAL BURNER
12-Volt Battery
Triple Wall Construction and Fully Insulated
Automatic Temperature Control
Diesel Burner VIP Technology - Voltage Indicator and
Protector
Controller Automatically Prevents Burner(s) from
Operating
Below Burner Manufacturer's Required Voltage
One-Piece, Seamless Ceramic Combustion Chamber
Tandem Axle Trailer Frame - 2" x 6" x 1/4" Tubular
Steel
Independently Certified 92% Fuel Efficiency
Diamond Tread Plate Hopper Access Platform
Electric Brakes w/ Safety Breakaway
Conspicuity Tape
Falcon Smart Control package includes VIP, 7-day
timer, fuel level gauge, hour meter, voltmeter, and
temperature gauge
Included Options:
Battery Charger Package
Single diesel burner
Dump Box (12-Volt Electric Over Hydraulic)
Standard frame – 16’
LED Lighting Upgrade - Two Red Stop/Tail/Turn
Lights and
One Amber Strobe Per Side
LED night work lights
Strobe Warning Light
Upgrade to ST235/80R 16" Tires - Load Range E
Release agent basket
18
ACTIVITY QTY RATE AMOUNT
24 hour timer
3 position tool holder
Paint 1 0.00 0.00
Color Falcon Red
Trailer Plug 1 0.00 0.00
RV plug Round Plug 7 Flat pins
Steel Surcharge 1 1,750.00 1,750.00
Steel Surcharge
Freight 1 1,113.00 1,113.00
Midland, MI to Waterford, WI
Options 1 0.00 0.00
NJP0067 1 309.00 309.00
Step (to Hopper Access Platform)
Subtotal: 50,108.00
Warranty 1 0.00 0.00
Two Year Factory, Lifetime Frame Warranty
Falcon CCMFG 1 0.00 0.00
5 Year Combustion Chamber Maintenance Free
Guaranty
Manual 1 0.00 0.00
Operator, Parts and Service Manual
Training 1 0.00 0.00
On-site Operation and Service Training
Discount -1 4,724.00 -4,724.00
PCA Contract #OD-362-22
Disocunt
Discount -1 4,427.00 -4,427.00
MPE DEMO DISCOUNT 2022 Model
VIN 1F9P41724NM339170
Discount -1 1,113.00 -1,113.00
MPE will cover freight for Demo Unit Only.
Why a FALCON? 1 0.00 0.00
Why Falcon?
It’s Versatile
• Recycle leftover asphalt, chunks and millings (a dual
burner unit is required to recycle millings)
• Transport asphalt and keep it hot all day and hold it
overnight
• Heat and re-heat cold patch
It’s Cost-Effective
• When used as a hot box, it eliminates asphalt waste
that
occurs in the back of an unheated truck bed
• When used as a recycler, it recycles leftover asphalt
19
ACTIVITY QTY RATE AMOUNT
and
asphalt chunks torn up from the pavement
• Independently certified 92% fuel efficiency – uses
less
than 3 gallons of fuel per 8-hour shift
It’s Reliable
• VIP Technology (patent pending) – Protects burner
components by automatically preventing burner from
operating with low battery voltage
• A Falcon is designed to allow the burner to run while
in
tow - preventing material from cooling while being
transported
• Heat management system is engineered to provide
even
hopper temperatures – eliminating material scorching
from hot spots and material hardening from cold spots
• Standard 2-year machine warranty and lifetime
frame
warranty
It’s a Falcon
***Leadtime is currently 120 days Leadtime will be verified and SUBTOTAL 39,844.00
adjusted at time of order. TAX 0.00
***DEMO UNIT AVAILABLE FOR IMEDIATE DELIVERY TOTAL
$39,844.00
Accepted By Accepted Date
20
Quote
S66W19444 Tans Drive Date: 12/13/2023
Muskego, WI 53150 Quote #: 1162023-Q
O: 800-956-8213 E: Sales@alertlightingco.com Valid Until: 1/12/2024
C: 262-283-4674
Prepared by: Mike Madia
Quotation For: Waterford Village
ATTN: Rick Huening
SALES PERSON P.O. Number LEAD TIME SHIPPING TERMS
Mike Madia - 2-5 business days UPS SEE TERMS&COND.
ITEM # DESCRIPTION UNIT PRICE QUANTITY AMOUNT
ALC-L.E.D. Pedestrian Sign $ 450.00 2 $ 900.00
LED Pedestrian Sign
$ -
$ -
SUB TOTAL : $ 900.00
ESTIMATED SHIPPING : $ -
TOTAL : $ 900.00
TERMS AND CONDITIONS:
All orders under $1000.00 USD must be pre-pay
Orders over $1000.00 USD can apply for Net 30. If you have any questions about this price quote, please contact:
*Credit references are required for Net 30 terms. Mike Madia @ Sales@alertlightingco.com or by phone
Payment terms granted based upon credit worthiness
Thank you for your consideration in using Alert Lighting Company!
21
22
VILLAGE OF WATERFORD
Engineer’s Report
December 12, 2023
Tetzlaf “The Armory Self Storage” Review – Project No. 222115
We received plans for a self-storage facility north of Gravity Ct in the Mercury
Development.
The public water main extension plans were reviewed, and the owner approval letter was
provided to the developer for submittal to the DNR on 8/9/23.
The Village will not permit construction of the public water main until the recorded
easement is received from the developer.
Neumann Homes Development (Trailside Landing) – Project No. 221632
Single Family development north of Trailside Elementary.
The developers have received an easement from the School District and plan to route the
sanitary sewer down the east side of Milwaukee Street.
Review comments were sent to the developer on 12/5/23.
Pre/3 Multi-Family Development – Project No. 2326172
Pre/3 is the developer, Robert E. Lee is the engineer.
This project is the multi-family project being developed concurrently with the Neumann
Homes single family development.
Review comments were sent to the developer on 11/14/23.
Pro-Health Clinic – Project No. 2325157
We received engineering plans for this project located at Gemini Lots 7 & 10 on 4/11/23.
Our conditional approval recommendation was forwarded to the Village and design
engineer on 05/18/23.
Currently under construction.
East Main Street Reconstruction – Project No. 2325354:
Reconstruct E. Main St. from Milwaukee St. to STH 36 and relay the water main from
Milwaukee St. to 6th St.
The Village received $422,837.87 in WisDOT LRIP money for the road surface portion of
the project.
A Village Resolution is required to establish bicycle facilities as part of the project.
Our design work order was approved by the Village Board on 12/11/23.
We plan to design the project in 2024 and open bids in January 2025.
The WisDOT project funding sundown date is 6/30/27.
Page 1 of 2
P:\WATRF\General\Admin\Monthly Reports\2023\12-2023\12-12-23.docx
23
VILLAGE OF WATERFORD
Engineer’s Report
December 12, 2023
Well 6 Planning – Project No. 180435
This project will replace the capacity of existing Well 1 and Well 3 and allow the Village to
obtain more water from the existing central treatment facility on Cornerstone Crossing.
An Intent to Apply was submitted to the Wisconsin Department of Natural Resources.
The Village will know whether funding, including principal forgiveness, is available in
March of 2024. If funded, plans and specifications need to be submitted prior to June 30,
2024.
Page 2 of 2
P:\WATRF\General\Admin\Monthly Reports\2023\12-2023\12-12-23.docx