4B Board (Street Improvement Economic Development Corporation)
Regular MeetingBedford, TX · July 16, 2019
Minutes
STATE OF TEXAS §
COUNTY OF TARRANT §
CITY OF BEDFORD §
The Board of Directors of the City of Bedford Street Improvement Economic Development
Corporation, Bedford, Texas, met at 6:00 p.m. at Bedford City Hall, 2000 Forest Ridge Drive,
Bedford, on the 16th day of July 2019 with the following members present:
Roger Fisher President
Tina Penney
Rusty Sartor
Michael Boyter
Mitchell Epstein
Ruth Culver
Douglas Murphy
Constituting a quorum.
Also present were:
Brian Bosshardt City Manager/Executive Director
Clifford Blackwell Assistant City Manager/Treasurer
Kenny Overstreet Public Works Director
Scott Tedford Assistant Public Works Director
Jerry Laverty Street and Drainage Manager
Dean Yanagi Senior Staff Engineer
Amanda Jacobs Assistant City Secretary/Assistant Secretary
CALL TO ORDER
President Fisher called the meeting to order at 6:00 p.m.
APPROVAL OF MINUTES
1. Approval of the minutes of the January 15, 2019 regular meeting.
Motioned by Director Epstein, seconded by Director Sartor, to approve the minutes of the January
15, 2017 regular meeting.
Motion passed 7-0-0. President Fisher declared the motion carried.
NEW BUSINESS
2. Receive the Financial Status Report for Fiscal Year 2019.
Cliff Blackwell, Assistant City Manager/Treasurer, presented information on this item.
Mr. Blackwell stated that there will be no more debt service payments and that the Series 2005 G.O.
Bonds have been paid off from the 4B fund. Sales tax receipts through July 2019 are currently running
7.61%, or $541,193 above last year. The fund balance moving into FY 2020 is $2.99M.
3. Staff report on the status of Fiscal Year 2018/19 projects.
Listed below are the budgeted projects and status for Fiscal Year 2018/2019:
Harwood Road mill and overlay from Central Drive to Martin Drive – Milling was completed by
TexOp Construction, LP in April 2019. Tarrant County Precinct 3 completed the asphalt overlay
in May 2019.
L. Don Dodson mill and overlay from Central Drive to Murphy Drive – Milling was completed by
TexOp Construction, LP in March 2019. Tarrant County Precinct 3 completed the asphalt overlay
in May 2019.
Hospital Parkway mill and overlay from SH183 to Pipeline Road – Milling was completed by
TexOp Construction, LP in March 2019. Tarrant County Precinct 3 completed the asphalt overlay
in May 2019.
Concrete repairs (panels, sidewalks and ADA ramps) – Cam Crete Construction began the
concrete repairs on June 25, 2019. Estimated completion of the project is September 2019.
Crack routing and sealing – Curtco, Inc. completed the crack routing and sealing project in April
2019.
Street light rehabilitation and installation – Staff is working with Oncor Electric Delivery to obtain
a cost estimate for the installation on new street lights on Fox Glen Circle.
Street reclamation, mill and overlay at various locations (Year 1 of the proposed 5-year plan) –
Peachtree Construction began construction on June 25, 2019. Estimated project completion is
September 2019.
Striping and traffic markings – Stripe-A-Zone began the 2019 Pavement Marking Program in
June 2019. Estimated completion of the project is August 2019.
Subgrade repairs – Ace Asphalt completed subgrade and spot repairs in June 2019.
Cheek Sparger Road at Heritage Avenue Signal Light Installation and Roadway Improvement –
The City of Euless entered into a contract with Kimley-Horn and Associates for design of the
project. Estimated completion of the preliminary design is October 2019.
4. Update and discussion on the Safe Routes to School Grant status and pedestrian
crosswalks.
Field Operations Manager David Smyth presented information on this item.
Mr. Smyth stated that by submitting the pedestrian crosswalk project for grant funding, the project can
be increased to include 13 enhanced safety crosswalks, installation of approximately 1,300 linear feet of
10’ hike and bike trail to complete the section from Forest Ridge to Harwood Road at McLain Road, the
completion of missing sidewalk sections at Bedford Road and L. Don Dodson, and the installation of
Americans with Disabilities Act (ADA) approved sidewalk ramps at various locations.
This item will be considered at the August 13, 2019 regular City Council meeting.
5. Discussion and possible action on the addition of a sidewalk along Woodpark Lane from the
walking trail that ends at the TXU easement to Cheek Sparger Road.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated that staff is seeking direction from the Board on the installation of a sidewalk along
Woodpark Lane from the walking trail that ends at the TXU easement to Cheek Sparger Road if the
Safe Routes to School Grant is not funded.
The Board was of the consensus to wait until a decision is made on the Safe Routes to School Grant
funding before moving forward with this project.
6. Staff report on the status of the installation of the traffic signal and roadway improvements at
the intersection of Cheek Sparger Road and Heritage Avenue.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated that in February 2019 the City entered into an interlocal agreement with Tarrant
County and the cities of Euless and Colleyville for the installation of a traffic signal at the intersection of
Cheek Sparger Road and Heritage Avenue. The City of Euless contracted with Kimley Horn and
Associates to complete a traffic study, which showed that additional improvements were necessary to
ease traffic backup. A number of options were presented to staff, including the addition of a forward
through lane, which would add a left turn lane onto Heritage Avenue, two eastbound forward lanes, a
westbound forward lane and a left turn lane onto Woodpark Lane. The preliminary design of the traffic
signal and the roadway improvements should be completed in October 2019 with plans to begin
construction in early in FY 2019-2020.
There was discussion regarding right-of-way for a curb, traffic stacking in the Silverwood Addition and
other options that were presented.
7. Discussion and possible action on participating in improvements to Cheek Sparger Road and
the adjacent walking trail to the south.
Executive Director Brian Bosshardt presented information on this item.
Director Bosshardt stated that he was contacted by the City of Colleyville City Manager to discuss
Bedford’s interested in participating in a project to install a dedicated middle turn lane on Cheek Sparger
Road from ____ to the Tara shopping center.
There was discussion regarding the benefit to Bedford residents, the Board’s interest in pursuing the
project, the Regional Transportation Commission’s interest in intergovernmental projects, and grant
funding.
There was a consensus of the Board to have staff continue exploring the parameters of the project with
the City of Colleyville.
8. Consider approval of the Fiscal Year 2019/2020 budget for the City of Bedford Street
Improvement Economic Development Corporation.
Public Works Director Kenny Overstreet presented information on this item.
There was discussion regarding the proposed items for the FY 2019/20 budget, proposed revenue and
expenditures, mill and overlay locations, paying for projects with cash rather than bond money, mill and
overlay on Brown Trail from Bedford Road to SH 183 and on Forest Ridge Drive from Pipeline Road to
HS 183, funding for traffic signal management software, the transfer of funds to the Utility Repair Fund
for the Economic Development Department, increase of the minor apparatus line item, supplemental
items, a healthy fund balance moving into FY 2019/2020, and a Capital Project in the amount of
$120,000 for a pedestrian crossing warning system is budgeted on the off chance that grant funding is
not awarded making 4B expenditures $4,797,450, and available funds, less expenditures $1,145,633.
Motioned by Director Epstein as amended at $4,797,450, seconded by Director Murphy, to approve the
FY 2019/2020 SIEDC budget
Motion passed 7-0-0. President Fisher declared the motion carried.
ADJOURNMENT
President Fisher adjourned the meeting at 7:56 p.m.
____________________________
Roger Fisher, President
ATTEST:
________________________________
Amanda Jacobs
Assistant City Secretary
Agenda
AGENDA
Street Improvement Economic Development Corporation
Tuesday, July 16, 2019
Bedford City Hall Building A
2000 Forest Ridge Drive
Bedford, Texas 76021
6:00 P.M.
CALL TO ORDER
APPROVAL OF MINUTES
1. Approval of the minutes of the January 15, 2019 regular meeting.
NEW BUSINESS
2. Receive the Financial Status Report for Fiscal Year 2019.
3. Staff report on the status of Fiscal Year 2018/19 projects.
4. Update and discussion on the Safe Routes to School Grant status and pedestrian
crosswalks.
5. Discussion and possible action on the addition of a sidewalk along Woodpark Lane
from the walking trail that ends at the TXU easement to Cheek Sparger Road.
6. Staff report on the status of the installation of the traffic signal and roadway
improvements at the intersection of Cheek Sparger Road and Heritage Avenue.
7. Discussion and possible action on participating in improvements to Cheek Sparger
Road and the adjacent walking trail to the south.
8. Consider approval of the Fiscal Year 2019/2020 budget for the City of Bedford Street
Improvement Economic Development Corporation.
ADJOURNMENT
CERTIFICATION
I, the undersigned authority, do hereby certify that this Notice of Meeting was posted on the outside window in a display cabinet at the
City Hall of the City of Bedford, Texas, a place convenience and readily accessible to the general public at all times, and said Notice
was posted by the following date and time: Friday, July 12, 2019 at 5:00 p.m., and remained so posted at least 72 hours before said
meeting convened.
_____________________________________________ ___________________________
Michael Wells, City Secretary Date Notice Removed
(Auxiliary aids and services are available to a person when necessary to afford an equal opportunity to participate in City functions and activities. Auxiliary aids
and services or accommodations must be requested in writing to the City Secretary’s Office a minimum of seventy-two hours (72) hours prior to the scheduled
starting time of the posted meeting. Requests can be delivered in person or mailed to the City Secretary’s Office at 2000 Forest Ridge Drive, Bedford, TX 76021,
or emailed to citysecretary@bedfordtx.gov. Some requests may take longer due to the nature, extent and/or availability of such auxiliary aids, services or
accommodations.)
PRESENTER: Amanda Jacobs, Assistant City Secretary DATE: 07/16/19
Minutes
ITEM:
Consider approval of the following 4B Street Improvement Economic Development Corporation
minutes:
a) January 15, 2019
DISCUSSION:
N/A
ATTACHMENTS:
January 15, 2019 minutes
STATE OF TEXAS §
COUNTY OF TARRANT §
CITY OF BEDFORD §
The Board of Directors of the City of Bedford Street Improvement Economic Development
Corporation, Bedford, Texas, met at 6:00 p.m. at Bedford City Hall, 2000 Forest Ridge Drive,
Bedford, on the 15th day of January 2019 with the following members present:
Roy W. Turner President
Tina Penney
Rusty Sartor
Michael Boyter
Mitchell Epstein
Roger Fisher
Constituting a quorum.
Also present were:
Brian Bosshardt City Manager/Executive Director
Clifford Blackwell Assistant City Manager/Treasurer
Kenny Overstreet Public Works Director
Scott Tedford Assistant Public Works Director
Jerry Laverty Street and Drainage Manager
Dean Yanagi Senior Staff Engineer
Amanda Jacobs Assistant City Secretary/Assistant Secretary
CALL TO ORDER
President Turner called the meeting to order at 6:00 p.m.
APPROVAL OF MINUTES
1. Approval of the minutes of the June 25, 2018 regular meeting.
Motioned by Director Boyter, seconded by Director Epstein, to approve the minutes of the June 25,
2018 regular meeting.
Motion passed 7-0-0. President Turner declared the motion carried.
NEW BUSINESS
2. Consider and act upon the appointment of a President, Vice President, Treasurer, and
Secretary to the Street Improvement Economic Development Corporation.
The following nominations were made and approved:
President – Roger Fisher
Vice President – Rusty Sartor
Treasurer – Cliff Blackwell, Assistant City Manager
Secretary – Michael Boyter
3. Receive the Financial Status Report.
Cliff Blackwell, Assistant City Manager/Treasurer, presented information on this item.
Mr. Blackwell stated that there will be a principal and interest payment of $40,800 for Debt Service
made on February 1, 2019. Sales tax receipts through December are running 8.93 percent, or
$143,932, above year-to-date sales tax receipts this fiscal year.
4. Staff report on the status of Fiscal Year 2017/2018 projects.
Listed below are the projects and their status for Fiscal Year 2017/2018:
• Bedford Court East reconstruction – The contractor completed the punch list items in December
2018. Staff is waiting for the contractor to resolve two resident claims prior to accepting the project.
• Rankin Drive reconstruction from Forest Ridge Drive to Brook Hollow Park – The project is delayed
until the construction on the drainage channel wall is completed.
• Bedford Road asphalt mill and overlay from Somerset Terrace to Brown Trail – Completed May
2018.
• Martin Drive asphalt mill and overlay from Cummings Drive to Cheeksparger Road – Completed
May 2018.
• Bobwhite Drive, Blue Jay Court, Eagle Drive, Hawk Lane, Warbler Drive and Wren Court asphalt
mill and overlay – The contractor has completed the mill and overlay, but prior to the final walk
through, staff identified multiple transverse cracks that have developed. The contractor and staff
are investigating what may be causing cracks in the new asphalt.
• Loma Alta Addition asphalt mill and overlay – The contractor has completed the mill and overlay,
but prior to the final walk through, staff identified multiple transverse cracks that have developed.
The Contractor and staff are investigating what may be causing cracks in the new asphalt.
• Shady Lane asphalt mill and overlay from Shady Brook Drive to Shady Grove Drive – The
contractor has completed the mill and overlay, but prior to the final walk through, staff identified
multiple transverse cracks that have developed. The contractor and staff are investigating what
may be causing cracks in the new asphalt.
• Briarhaven Drive asphalt mill and overlay from Forest Ridge Drive to McLain Road – The
contractor has completed the mill and overlay, but prior to the final walk through, staff identified
multiple transverse cracks that have developed. The contractor and staff are investigating what
may be causing cracks in the new asphalt.
• Spargercrest Drive asphalt mill and overlay from Forest Ridge Drive to McLain Road – The
contractor has completed the mill and overlay, but prior to the final walk through, staff identified
multiple transverse cracks that have developed. The contractor and staff are investigating what
may be causing cracks in the new asphalt.
• Shady Turf asphalt mill and overlay from Schumac Lane to Hialeah Path – The contractor has
completed the mill and overlay, but prior to the final walk through, staff identified multiple
transverse cracks that have developed. The contractor and staff are investigating what may be
causing cracks in the new asphalt.
• Hialeah Path mill and overlay from Schumac Lane to Shady Turf Drive – The contractor has
completed the mill and overlay, but prior to the final walk through, staff identified multiple
transverse cracks that have developed. The contractor and staff are investigating what may be
causing cracks in the new asphalt.
• Concrete panel repair/replacement at various locations – The contractor has completed the
sidewalk portion of the contract. Due to multiple weather and scheduling delays on this project,
the concrete panels and ADA ramps have not been completed. With the winter months here, and
concrete work requiring warmer weather, the remainder of the contract will not be completed.
• Crack routing and sealing various locations – Project was completed in May 2018.
• Sidewalk and handicap ramp repairs at various locations – The contractor has completed the
sidewalk portion of the contract. Due to multiple weather and scheduling delays on this project,
the concrete panels and ADA ramps have not been completed. With the winter months here, and
concrete work requiring warmer weather, the remainder of the contract will not be completed.
• Street light rehabilitation and installation at various locations – No new street light installations
occurred this fiscal year. After staff investigated all requests received, it was determined that the
street light installation did not meet the required criteria. After discussing the street light upgrades
with Oncor personnel, Public Works staff were informed that this is considered a maintenance
item and is Oncor’s responsibility.
• Striping and traffic markings at various locations – City staff received bids for this project on June
26, 2018. The majority of the bid items were for the installation of bike lanes on Cummings Drive.
All bids for the project were rejected after staff determined that Tarrant County would install the
new bike lanes.
• Pedestrian crossing warning system installation at the 3300 block of Martin Drive, Brown Trail at
Carolyn Drive and the update of the pedestrian crossing warning system in the 3400 block of
Central Drive with in-lane lighting – Staff was unable to locate a contractor that installs in-lane
lighting and there is only one vendor who still sells the products needed. This discovery was too
late to be completed in the 2017/2018 fiscal year.
5. Staff report on Fiscal Year 2018/2019 projects.
Listed below are the projects and their status for Fiscal Year 2018/2019:
• Harwood Road mill and overlay from Central Drive to Martin Drive – The project is scheduled to
begin in March 2019. The Interlocal Agreement with Tarrant County will be presented to the City
Council for consideration on February 5, 2019.
• L. Don Dodson Drive mill and overlay from Central Drive to Murphy Drive – The project is
scheduled to begin in March 2019. The Interlocal Agreement with Tarrant County is scheduled for
City Council consideration on February 5, 2019.
• Hospital Parkway from SH183 to Pipeline Road – The project is scheduled to begin in March 2019.
The Interlocal Agreement with Tarrant County is scheduled for City Council consideration on
February 5, 2019.
• Concrete repairs (panels, sidewalks and ADA ramps) – The projected bid date is March 2019.
• Crack routing and sealing – The agreement was approved by the City Council on January 8, 2019.
The projected start date is February 2019.
• Street light rehabilitation and installation – New street lights will be installed after customer
requests are received and the location meets the required criteria.
• Street reclamation, mill and overlay at various locations (Year 1 of the proposed 5-year plan) –
The projected bid date is April 2019.
• Striping and traffic markings – The projected start date is summer 2019.
• Subgrade repairs – The agreement was approved by the City Council on January 8, 2019. Work
will begin prior to the mill and overlay of Harwood Road, L. Don Dodson Drive and Hospital
Parkway.
• Cheeksparger Road at Heritage Avenue – City of Bedford staff is currently working on an interlocal
agreement with the City of Euless and the City of Colleyville for the installation of the signal light
and roadway modifications.
6. Consider approval of an amended Fiscal Year 2018/2019 budget for the City of Bedford Street
Improvement Economic Development Corporation.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated several projects were budgeted in FY 2017/2018 that were not completed before
the end of fiscal year, leaving the 4B budget with a high fund balance of $3,680,942, and requests
that the Board authorize payment for the following projects:
• Bedford Court East: Reliable Paving completed the project by December 2018; however, staff is
waiting for them to resolve two home-owner claims, prior to accepting the project as complete.
The amount outstanding for the construction is $115,494.74.
• 2018 Concrete Contract: Reliable Paving has completed the sidewalk portion of the contract. Due
to multiple weather and scheduling delays, the concrete panels and ADA ramps have not been
completed yet. The remainder of the contract will not be completed until the summer, when the
weather is much warmer. The amount outstanding for this project is $390,210, which is
approximately $213,553.44 for work that is completed and $176,656.56 for the remainder of the
project. This will give staff funds necessary to complete concrete panel replacements with the
2019 Concrete Contract, since none were replaced with the 2018 Concrete Contract.
• Street Assessment: Fugro Roadware is compiling the final report for the street assessment. The
amount outstanding for the contract is $47,647.50.
• Pedestrian Crosswalks: Staff was unable to fund the pedestrian crosswalk project because no
contractor was available at the time to install in-lane lighting nor sell the products needed for
installation; however, staff requests authorization to spend the unused $120,000 in conjunction
with the amount budgeted for FY 2018/2019. This will provide total funding in the amount of
$240,000 for the installation of pedestrian crosswalks, where needed.
• Striping and Traffic Markings: All bids for the 2018 Pavement Markings contract were rejected last
year, so no paved striping occurred in FY 2017/2018; however, staff requests authorization to
spend the unused $120,000 in conjunction with the amount budgeted for FY 2018/2019. This will
provide total funding in the amount of $240,000 for the installation of striping and traffic markings.
There was discussion to not fund the pedestrian crosswalks, making the total requested amount
$811,742.
Motioned by Director Epstein, seconded by Director Boyter to approve authorizing the unspent
portions of the 4B Street Improvement Economic Development Corporation projects to be paid from
fund balances.
Motion passed 7-0-0. President Turner declared the motion carried.
7. Discussion on the Tarrant County 45th Community Development Block Grant.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated every two years, the City of Bedford is eligible to pursue HUD funding through
the Tarrant County Community Development Division for qualifying areas in the City, Census qualified
areas must meet low to moderate income household criteria, and staff has determined Bedford Court
East, between Hurst City Limit and Brown Trail, meets the program criteria. There is the potential to
receive up to $155,000 for this project and applications are due on January 31, 2019.
Mr. Overstreet stated that the project would include the removal and replacement of existing
deteriorated asphalt pavement and replacing it with 6” concrete and 6” curbs on Bedford Court East,
beginning at the west side of Brown Trail and to the Hurst city limit. The project also includes the
removal and reconstruction of two valley gutters, one fire hydrant relocation, and adjusting sewer
manholes and water valves to the new street grade.
The Board approved moving this item forward for Council consideration at the January 22, 2019
regular meeting.
8. Staff report on the installation of the traffic signal at the intersection of Cheek Sparger Road
and Heritage Avenue.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated that in the SIEDC Fiscal Year 2018/2019 approved budget, funds were allocated
for the installation of a traffic signal at the intersection of Cheek Sparger Road and Heritage Avenue.
The project will contain street markings to support the installed traffic signal. This project will be a joint
effort between Tarrant County and the cities of Colleyville, Euless, and Bedford, with each party
supplying a share of the total cost of installation.
Staff agreed to accept responsibility for the maintenance and operation of the traffic signal, given its
proximity to the Bedford traffic signal at Rio Grande. To support this request, the City of Bedford will
also maintain a portion of Cheek Sparger Road, approximately 50 feet east of Woodpark Lane to the
concrete pavement, and approximately 300 feet west of Woodpark Lane to Silverwood Lane.
The Board approved moving this item forward for Council consideration at the February 8, 2019
regular meeting.
9. Discussion and possible action on the removal of the barricade on Woodpark Lane that closes
the road to through traffic between Cummings Drive and Cheek Sparger Road.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated during the planning of the Walmart store along SH 121 and Cheek Sparger
Road, residents from the homes behind the site expressed concerns about increased traffic flow along
Woodpark Lane. It was decided to install a barricade across the roadway where it intersects the TXU
easement.
There was a consensus of the Board to leave the barricade, to move forward with the interlocal
agreement with plans to remove the barricade after the completion of the SH 121 construction and
hold public meetings with the neighbors.
10. Discussion and possible action on pedestrian crosswalks.
Public Works Director Kenny Overstreet presented information on this item.
Mr. Overstreet stated that in-lane lighting is no longer being used and cities are moving to other types
of crosswalk warnings. Pedestrian presence sensors are no longer recommended as blowing trash or
debris can cause the warning system to activate.
There was a consensus of the Board to have staff continue to research options and present
recommendations to the Board at a future meeting.
ADJOURNMENT
President Turner adjourned the meeting at 6:57 p.m.
____________________________
Roger Fisher, President
ATTEST:
________________________________
Amanda Jacobs
Assistant City Secretary
Clifford Blackwell, CGFO
PRESENTER: 4B SIEDC Treasurer
DATE: 07/16/19
Staff Report
ITEM:
Receive the Financial Status Report for Fiscal Year 2019.
DISCUSSION:
Attached, is the 4B Street Improvement EDC Financial Status Report for the months ending June 30,
2019.
Please note the following:
1. There will be no more debt service payments from this fund. The Series 2005 G.O. Bonds
have been paid off from the 4B SIEDC fund.
2. Sales tax receipts through July 2019 are currently running 7.61%, or $541,193 above last year
on the year-to-date basis.
ATTACHMENTS:
Financial Status Report for FY2019
Street Improvement Economic Development Corporation
FYE September 30, 2019
Annual Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep REV projected
Budget 2018 2018 2018 2019 2019 2019 2019 2019 2019 2019 2019 2019 YTD over/(under)
*estimate*
Revenue:
Sales Tax $ 2,700,000 $ 238,142 $ 272,983 $ 226,835 $ 212,179 $ 288,736 $ 222,766 $ 198,384 $ 298,798 $ 230,896 $ 817,401 $ 3,007,121 $ 307,121
Special Sales Tax $ - - - - - - - - - - - - - - $ -
Interest Income $ 30,000 2,815 4,157 8,811 4,665 5,881 10,026 4,878 6,101 23,667 71,001 $ 41,001
Other (Xfer In: Street and Drainage) $ - - - - - - - - - - - - - - $ -
Total $ 2,730,000 $ 240,957 $ 277,140 $ 235,645 $ 216,844 $ 294,618 $ 232,793 $ 203,262 $ 304,899 $ 230,896 $ - $ - $ 841,068 $ 3,078,122 $ 348,122
Expenditures: *estimate* EXP projected
(over)/under
Supplies $ 54,300 $ 552 $ 1,282 $ 875 $ 1,122 $ 4,004 $ 4,322 $ 748 $ 4,281 $ 419 $ - $ - $ 26,394 $ 44,000 $ 10,300
Maintenance 605,720 804 2,525 7,780 12,853 19,043 14,040 15,508 573,010 15,236 - - 59,643 720,444 $ (114,724)
Contract Services 2,139,720 - 143,597 27,202 79,073 - - 123,614 151,758 - - - 1,742,354 2,267,600 $ (127,880)
Debt Service 69,350 - 1,620 749 41,516 1,377 1,462 1,631 2,108 477 - - 18,409 69,350 $ 0
Contingency(GIS) 60,000 - 19,185 - - 16,667 - - - - - - 24,148 60,000 $ 0
Capital Outlay 438,300 - 318,300 - - 112,967 - - - - - - 168,321 599,588 $ (161,288)
Total $ 3,367,390 $ 1,356 $ 486,510 $ 36,607 $ 134,564 $ 154,058 $ 19,824 $ 141,503 $ 731,158 $ 16,132 $ - $ - $ 2,039,269 $ 3,760,981 $ (393,591)
Excess (deficiency) of
revenue over expenditures $ (637,390) $ 239,601 $ (209,370) $ 199,039 $ 82,280 $ 140,560 $ 212,968 $ 61,759 $ (426,259) $ 214,764 $ - $ - $ (1,198,201) $ (682,859) $ 45,469
Beginning Fund Balance $ 3,680,942 $ 3,680,942 $ 3,920,543 $ 3,711,173 $ 3,910,211 $ 3,992,491 $ 4,133,051 $ 4,346,019 $ 4,407,778 $ 3,981,520 $ 4,196,284 $ 4,196,284 $ 4,196,284 $ 3,680,942
Ending Fund Balance $ 3,043,552 $ 3,920,543 $ 3,711,173 $ 3,910,211 $ 3,992,491 $ 4,133,051 $ 4,346,019 $ 4,407,778 $ 3,981,520 $ 4,196,284 $ 4,196,284 $ 4,196,284 $ 2,998,083 $ 2,998,083
Available Fund Balance (9-30-2019) $ 2,998,083 Based on Budgeted Revenue & Expenditures
Required Reserve 2019 -
S:\DEPTDATA\COUNCIL\AGENDFRM\4B - SIEDC\2019\July 16, 2019\SIEDC Financial Report 2019.xlsx
Street Improvement Economic Development Corporation
FYE September 30, 2019
Annual Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep REV projected
Budget 2018 2018 2018 2019 2019 2019 2019 2019 2019 2019 2019 2019 YTD over/(under)
*estimate*
Revenue:
Sales Tax $ 2,700,000 $ 238,142 $ 272,983 $ 226,835 $ 212,179 $ 288,736 $ 222,766 $ 198,384 $ 298,798 $ 230,896 $ 817,401 $ 3,007,121 $ 307,121
Special Sales Tax $ - - - - - - - - - - - - - - $ -
Interest Income $ 30,000 2,815 4,157 8,811 4,665 5,881 10,026 4,878 6,101 23,667 71,001 $ 41,001
Other (Xfer In: Street and Drainage) $ - - - - - - - - - - - - - - $ -
Total $ 2,730,000 $ 240,957 $ 277,140 $ 235,645 $ 216,844 $ 294,618 $ 232,793 $ 203,262 $ 304,899 $ 230,896 $ - $ - $ 841,068 $ 3,078,122 $ 348,122
Expenditures: *estimate* EXP projected
(over)/under
Supplies $ 54,300 $ 552 $ 1,282 $ 875 $ 1,122 $ 4,004 $ 4,322 $ 748 $ 4,281 $ 419 $ - $ - $ 26,394 $ 44,000 $ 10,300
Maintenance 605,720 804 2,525 7,780 12,853 19,043 14,040 15,508 573,010 15,236 - - 59,643 720,444 $ (114,724)
Contract Services 2,139,720 - 143,597 27,202 79,073 - - 123,614 151,758 - - - 1,742,354 2,267,600 $ (127,880)
Debt Service 69,350 - 1,620 749 41,516 1,377 1,462 1,631 2,108 477 - - 18,409 69,350 $ 0
Contingency(GIS) 60,000 - 19,185 - - 16,667 - - - - - - 24,148 60,000 $ 0
Capital Outlay 438,300 - 318,300 - - 112,967 - - - - - - 168,321 599,588 $ (161,288)
Total $ 3,367,390 $ 1,356 $ 486,510 $ 36,607 $ 134,564 $ 154,058 $ 19,824 $ 141,503 $ 731,158 $ 16,132 $ - $ - $ 2,039,269 $ 3,760,981 $ (393,591)
Excess (deficiency) of
revenue over expenditures $ (637,390) $ 239,601 $ (209,370) $ 199,039 $ 82,280 $ 140,560 $ 212,968 $ 61,759 $ (426,259) $ 214,764 $ - $ - $ (1,198,201) $ (682,859) $ 45,469
Beginning Fund Balance $ 3,680,942 $ 3,680,942 $ 3,920,543 $ 3,711,173 $ 3,910,211 $ 3,992,491 $ 4,133,051 $ 4,346,019 $ 4,407,778 $ 3,981,520 $ 4,196,284 $ 4,196,284 $ 4,196,284 $ 3,680,942
Ending Fund Balance $ 3,043,552 $ 3,920,543 $ 3,711,173 $ 3,910,211 $ 3,992,491 $ 4,133,051 $ 4,346,019 $ 4,407,778 $ 3,981,520 $ 4,196,284 $ 4,196,284 $ 4,196,284 $ 2,998,083 $ 2,998,083
Available Fund Balance (9-30-2019) $ 2,998,083 Based on Budgeted Revenue & Expenditures
Required Reserve 2019 -
S:\DEPTDATA\COUNCIL\AGENDFRM\4B - SIEDC\2019\July 16, 2019\SIEDC Financial Report 2019.xlsx
PRESENTER: Kenneth Overstreet, Public Works Director DATE: 07/16/19
Staff Report
ITEM:
Staff report on the status of Fiscal Year 2018/2019 projects.
DISCUSSION:
Listed below are the budgeted projects and status for Fiscal Year 2018/2019:
• Harwood Road mill and overlay from Central Drive to Martin Drive – Milling was completed by
TexOp Construction, LP in April 2019. Tarrant County Precinct 3 completed the asphalt
overlay in May 2019.
• L. Don Dodson mill and overlay from Central Drive to Murphy Drive – Milling was completed
by TexOp Construction, LP in March 2019. Tarrant County Precinct 3 completed the asphalt
overlay in May 2019.
• Hospital Parkway mill and overlay from SH183 to Pipeline Road – Milling was completed by
TexOp Construction, LP in March 2019. Tarrant County Precinct 3 completed the asphalt
overlay in May 2019.
• Concrete repairs (panels, sidewalks and ADA ramps) – Cam Crete Construction began the
concrete repairs on June 25, 2019. Estimated project completion is September 2019.
• Crack routing and sealing – Curtco, Inc. completed the crack routing and sealing project in
April 2019.
• Street light rehabilitation and installation – Staff is working with Oncor Electric Delivery to
obtain a cost estimate for the installation on new street lights on Fox Glen Circle.
• Street reclamation, mill and overlay at various locations (Year 1 of the proposed 5-year plan)
– Peachtree Construction began construction on June 25, 2019. Estimated project completion
is September 2019.
• Striping and traffic markings – Stripe-A-Zone began the 2019 Pavement Marking Program in
June 2019. Estimated project completion is August 2019.
• Subgrade repairs – Ace Asphalt completed subgrade and spot repairs in June 2019.
• Cheek Sparger Road at Heritage Avenue Signal Light Installation and Roadway Improvement
– The City of Euless entered into a contract with Kimley-Horn and Associates for design of
the project. Estimated completion of the preliminary design is October 2019.
ATTACHMENTS:
N/A
David Smyth, Field Operations Manager
PRESENTER: Kenneth Overstreet, Public Works Director
DATE: 07/16/19
Staff Report
ITEM:
Update and discussion on the Safe Routes to School Grant status and pedestrian crosswalks.
DISCUSSION:
The Public Works Department submitted a preliminary application to the Texas Department of
Transportation (TxDOT) on April 11, 2019 for a Safe Routes to School (SRTS) grant. The SRTS
program is funded at 100% for approved projects, with no required matching funds from the City.
The submitted request for SRTS funding included the following projects, for an estimated project
cost of approximately $850,000.
13 safety enhanced crosswalks (Exhibit A)
Approximately 1,300 linear feet of 10’ Hike & Bike Trail to complete the section from Forest
Ridge to Harwood Road at McLain Road (Exhibit B)
Completion of missing sidewalk sections at Bedford Road and L. Don Dodson (Exhibit C)
Americans with Disabilities Act (ADA) approved sidewalk ramps in various locations
On June 18, 2019, TxDOT responded stating that the project has been approved for submittal of a
detailed application, which is due by August 15, 2019. Staff is currently working on the basic design
submittals and the detailed application. This item will be presented to Council for consideration at
the August 13, 2019 regular Council meeting. This is a mandatory step of the detailed application
process.
ATTACHMENTS:
Exhibit A
Exhibit B
Exhibit C
EXHIBIT A
Original Locations
Grant Submittal Locations
EXHIBIT B
EXHIBIT C
Bedford Road
L. Don Dodson
PRESENTER: Kenneth Overstreet, Public Works Director DATE: 07/16/19
Staff Report
ITEM:
Discussion and possible action on the addition of a sidewalk along Woodpark Lane from the walking
trail that ends at the TXU easement to Cheek Sparger Road.
DISCUSSION:
The City of Bedford currently has a walking trail along the TXU easement extending from Forest Ridge
Drive to Woodpark Lane that is traveled by many residents and visitors by bicycle or walking. The
trail ends on Woodpark Lane behind Walmart Supercenter and a short distance from Glade Parks and
the Euless walking trail. There is currently not a sidewalk on Woodpark Lane for the safe passage of
pedestrians between the end of the walking trail and Cheek Sparger Road. Individuals traveling to
the businesses and walking trails in this area must walk down a steep grassy area or walk in the road
on Woodpark Lane.
The addition of a sidewalk on the east side of Woodpark Lane would allow for the safe passage of
individuals traveling to the businesses in the area and accessing the walking trails in both the City
of Bedford and the City of Euless. After initial assessment, it appears there is sufficient right-of-way
for the installation of a sidewalk at this location. At this time, staff does not have a cost estimate for
this potential project.
Staff is seeking input from the Street Improvement Economic Development Corporation (SIEDC)
Board on the proposed addition of a sidewalk along Woodpark Lane to connect the walking trail and
the sidewalks located on Cheek Sparger Road.
ATTACHMENTS:
Map
July 3, 2019 Woodpark Lane Sidewalk
PRESENTER: Kenneth Overstreet, Public Works Director DATE: 07/16/19
Staff Report
ITEM:
Staff report on the status of the installation of the traffic signal and roadway improvements at the
intersection of Cheek Sparger Road and Heritage Avenue.
DISCUSSION:
During the January 15, 2019 SIEDC Board meeting, staff presented an update on the status of the
Interlocal Agreement (ILA) between Tarrant County and the cities of Colleyville, Euless, and Bedford
for the installation of a traffic signal at the intersection of Cheek Sparger Road and Heritage Avenue.
On February 26, 2019, the City Council approved resolution 19-19 allowing the City Manager to enter
into the Interlocal Agreement for the traffic signal installation.
The City of Euless contracted with Kimley-Horn and Associates, Inc. (KHA) to complete the traffic
signal design. One of the steps in the design process was the completion of a traffic study. The traffic
study showed the improvements to the intersection that were proposed by the participants, would
cause a backup in the eastbound lanes with the amount of traffic turning northbound onto Heritage
Avenue.
The engineering firm presented staff with five options to improve the roadway to avoid this issue.
After reviewing the various options presented, staff felt adding an additional forward through lane
was the best option to facilitate efficient and effective management of vehicle traffic through the
intersection. The proposed roadway improvement would add a left turn lane onto Heritage Avenue,
two eastbound forward lanes, a westbound forward lane and a left turn lane onto Woodpark Lane.
Currently, when an individual is turning left on Heritage Avenue, vehicles back up and block the
intersection of Cheek Sparger Road and Silverwood Lane. An additional eastbound forward lane
would assist in facilitating traffic flow movement through the intersection. It would also assist
individuals entering and exiting Silverwood Addition.
The Public Works Director presented these findings to the City Council on June 25, 2019 requesting
approval for the City Manager to expend funds and enter into an interlocal agreement between the
City of Bedford and the City of Euless, Texas to designate a fiscal agent for the engineering, design,
construction, management and costs of roadway improvements at the intersection of Heritage
Avenue, Woodpark Lane and Cheek Sparger Road. The item was approved by City Council.
It is anticipated the preliminary design of the traffic signal and the roadway improvements would be
completed October 2019 and the construction is anticipated to begin early next fiscal year (FY
2019/2020).
Design for the project will be paid out of the Fiscal Year 2018/2019 approved budget line item for the
traffic signal installation and the construction cost is being presented in the proposed Fiscal Year
2019/2020 budget.
ATTACHMENTS:
Road Improvement Map
PRESENTER: Brian D. Bosshardt, City Manager DATE: 07/16/19
Staff Report
ITEM:
Discussion and possible action on participating in improvements to Cheek Sparger Road and the
adjacent walking trail to the south.
DISCUSSION:
The City Manager was contacted by the City of Colleyville to discuss Bedford’s interest in
participating in a joint project to improve Cheek Sparger Road and the adjacent walking trail to the
south. They are proposing to build a middle turn lane, while keeping the two lanes of thru
travel. Colleyville has indicated there is the potential for grant money to assist in the cost
of the improvements. Staff is requesting input from the Street Improvement Development
Corporation (SIEDC) Board with respect to the City’s interest in participating in such a project.
ATTACHMENTS:
N/A
PRESENTER: Kenneth Overstreet, Public Works Director DATE: 07/16/19
Staff Report
ITEM:
Consider approval of the Fiscal Year 2019/2020 budget for the City of Bedford Street Improvement
Economic Development Corporation (SIEDC).
DISCUSSION:
The proposed Fiscal Year 2019/2020 budget includes base operation and maintenance items and the
following projects:
Concrete repairs (panels, sidewalks and ADA ramps) at various locations.
Crack and joint sealing at various locations.
Pavement markings at various locations.
Street light rehabilitation and installation at various locations.
Subgrade repairs at various locations.
Pedestrian crossing warning system installation.
Mill and overlay at various locations (see attachment for the locations).
Mill and overlay on Brown Trail from Bedford Road to SH183 (milling would be completed by
a contractor and the overlay would be completed by Tarrant County Precinct 3).
Mill and overlay on Forest Ridge Drive from Pipeline Road to SH183 (milling would be
completed by a contractor and the overlay would be completed by Tarrant County Precinct
3).
Bedford Court East reconstruction from Brown Trail to Hurst city limits (partially funded by
SIEDC funds, bond funds and Community Development Block Grant (CDBG)).
Cheek Sparger Road at Heritage Avenue roadway improvements.
Cheek Sparger Road at Heritage Avenue signal installation (joint project with the cities of
Euless, Colleyville and Tarrant County).
Additionally, supplemental items included in the proposed budget are a dump truck replacement,
street sanders replacement and traffic signal equipment.
A financial analysis concludes that the fund balance will accommodate the recommended budget.
ATTACHMENTS:
SIEDC Budget Line Items
Proposed Revenue and Expenditure Worksheet
Proposed Supplementals
Mill and Overlay Locations
City of Bedford
Street Improvement Economic Development Corporation
Proposed Revenue and Expenditures
Fiscal Year Ending September 30, 2019
Projected Fund Balance October 1, 2019 $ 2,998,083
Revenue:
Sales Tax $ 2,900,000
Special Sales Tax -
Interest Income $ 45,000
Total Revenue $ 2,945,000
Required Reserve $ -
Available Funds $ 5,943,083
Expenditures
Supplies 57,100
Maintenance 773,210
Contract Services 2,526,380
Debt Service 285,960
Contingency 60,000
Design/Engineering/Construction 580,000
Capital Outlay * 394,800
Total Expenditures $ 4,677,450
Available Funds Less Expenditures $ 1,265,633
Projected Fund Balance, September 30, 2020 $ 1,265,633
* Includes proposed capital items (dump truck replacement, street sanders replacement and
traffic signal equipment).
Expense Budget Worksheet Report
Budget Year 2020
2019 Adopted 2019 Estimated 2020 Budget Office
Account Account Description Budget Amount Proposed
Fund 227 - EDC -4B STREET IMPROVEMENT
Department 45 - PUBLIC WORKS
Division 02 - ADMINISTRATION
SUPPLIES
8105 FUEL AND OIL 10,000.00 10,000.00 10,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Fuel for twenty vehicles and twenty heavy equipment 1.0000 10,000.00 10,000.00
Budget Office Proposed Totals $10,000.00
8106 MINOR APPARATUS 4,000.00 4,000.00 6,800.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Asphalt rakes 1.0000 300.00 300.00
Budget Office Proposed Consumable supplies for tools 1.0000 1,250.00 1,250.00
Budget Office Proposed Diamond saw blades 1.0000 750.00 750.00
Budget Office Proposed Hand tools 1.0000 1,500.00 1,500.00
Budget Office Proposed Power tools 1.0000 1,750.00 1,750.00
Budget Office Proposed Shovels 1.0000 500.00 500.00
Budget Office Proposed Small equipment 1.0000 750.00 750.00
Budget Office Proposed Totals $6,800.00
8130 SIGNS 40,300.00 30,000.00 40,300.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Reflective sheeting 1.0000 16,800.00 16,800.00
Budget Office Proposed Sakrete 1.0000 900.00 900.00
Budget Office Proposed Sheeted sign blanks 1.0000 1,000.00 1,000.00
Budget Office Proposed Sign blanks 1.0000 10,400.00 10,400.00
Budget Office Proposed Sign hardware 1.0000 8,000.00 8,000.00
Budget Office Proposed Sign posts 1.0000 3,200.00 3,200.00
Budget Office Proposed Totals $40,300.00
SUPPLIES Totals $54,300.00 $44,000.00 $57,100.00
MAINTENANCE
8205 MAINTENANCE SIDEWALKS AND CURBS 23,000.00 23,000.00 23,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Concrete and supplies for drive approach and sidewalk repairs 1.0000 23,000.00 23,000.00
Budget Office Proposed Totals $23,000.00
Run by JACKIE HANCOCK on 07/08/2019 15:58:27 PM Page 1 of 5
Expense Budget Worksheet Report
Budget Year 2020
2019 Adopted 2019 Estimated 2020 Budget Office
Account Account Description Budget Amount Proposed
Fund 227 - EDC -4B STREET IMPROVEMENT
Department 45 - PUBLIC WORKS
Division 02 - ADMINISTRATION
MAINTENANCE
8208 MAINTENANCE STREETS AND HIGHWAYS 509,510.00 630,000.00 677,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Asphalt for Brown Trail overlay: Bedford Road to SH 183 1.0000 115,500.00 115,500.00
Budget Office Proposed Asphalt for Forest Ridge overlay: Pipeline Road to SH183 1.0000 475,000.00 475,000.00
Budget Office Proposed Asphalt for small road repairs 1.0000 60,000.00 60,000.00
Budget Office Proposed Base materials 1.0000 10,000.00 10,000.00
Budget Office Proposed Concrete 1.0000 10,000.00 10,000.00
Budget Office Proposed Grass replacement 1.0000 1,500.00 1,500.00
Budget Office Proposed Traffic control 1.0000 4,000.00 4,000.00
Budget Office Proposed Tree removal 1.0000 1,000.00 1,000.00
Budget Office Proposed Totals $677,000.00
8210 MAINTENANCE EQUIPMENT 19,900.00 12,400.00 19,900.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Asphalt zipper teeth replacement 1.0000 2,500.00 2,500.00
Budget Office Proposed Equipment maintenance and repair 1.0000 17,400.00 17,400.00
Budget Office Proposed Totals $19,900.00
8212 MAINTENANCE MOTOR VEHICLES 15,000.00 14,000.00 15,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Vehicle maintenance and repair - SIEDC fund fleet 1.0000 15,000.00 15,000.00
Budget Office Proposed Totals $15,000.00
8212.0001 MAINTENANCE MOTOR VEHICLES ACCIDENT .00 2,734.00 .00
REPAIR
8224 MAINTENANCE TRAFFIC SIGNALS 38,310.00 38,310.00 38,310.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Monitors and load switches 1.0000 3,450.00 3,450.00
Budget Office Proposed Opticom 1.0000 8,650.00 8,650.00
Budget Office Proposed School zone warning system maintenance 1.0000 6,050.00 6,050.00
Budget Office Proposed Signal hardware 1.0000 6,650.00 6,650.00
Run by JACKIE HANCOCK on 07/08/2019 15:58:27 PM Page 2 of 5
Expense Budget Worksheet Report
Budget Year 2020
2019 Adopted 2019 Estimated 2020 Budget Office
Account Account Description Budget Amount Proposed
Fund 227 - EDC -4B STREET IMPROVEMENT
Department 45 - PUBLIC WORKS
Division 02 - ADMINISTRATION
MAINTENANCE
Budget Office Proposed Signal light maintenance 1.0000 13,510.00 13,510.00
Budget Office Proposed Totals $38,310.00
MAINTENANCE Totals $605,720.00 $720,444.00 $773,210.00
CONTRACTUAL SERVICES
8310 CONTRACT LABOR 2,137,720.00 2,265,600.00 2,509,380.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Concrete repairs (panels, sidewalks & ADA ramps) 1.0000 450,000.00 450,000.00
Budget Office Proposed Crack and joint sealing 1.0000 150,000.00 150,000.00
Budget Office Proposed Investment Advisory Services - Valley View Consulting, LLP 1.0000 9,380.00 9,380.00
Budget Office Proposed Mill and overlay at various locations 1.0000 1,400,000.00 1,400,000.00
Budget Office Proposed Milling - Brown Trail from Bedford Road to SH183 1.0000 25,000.00 25,000.00
Budget Office Proposed Milling - Forest Ridge Drive from Pipeline to SH183 1.0000 105,000.00 105,000.00
Budget Office Proposed Pavement markings 1.0000 150,000.00 150,000.00
Budget Office Proposed Street light rehabilitation and installation 1.0000 20,000.00 20,000.00
Budget Office Proposed Subgrade repairs 1.0000 200,000.00 200,000.00
Budget Office Proposed Totals $2,509,380.00
8311 SOFTWARE .00 .00 10,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Centracs maintenance agreement for traffic signal management 1.0000 10,000.00 10,000.00
Budget Office Proposed Totals $10,000.00
8321 RENTALS 2,000.00 2,000.00 7,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Barricade rental 1.0000 5,000.00 5,000.00
Budget Office Proposed Equipment rental 1.0000 2,000.00 2,000.00
Budget Office Proposed Totals $7,000.00
CONTRACTUAL SERVICES Totals $2,139,720.00 $2,267,600.00 $2,526,380.00
DEBT SERVICE & TRANSFERS
8412 PAYING AGENT FEES 300.00 300.00 .00
Run by JACKIE HANCOCK on 07/08/2019 15:58:27 PM Page 3 of 5
Expense Budget Worksheet Report
Budget Year 2020
2019 Adopted 2019 Estimated 2020 Budget Office
Account Account Description Budget Amount Proposed
Fund 227 - EDC -4B STREET IMPROVEMENT
Department 45 - PUBLIC WORKS
Division 02 - ADMINISTRATION
DEBT SERVICE & TRANSFERS
8414.0001 DEBT PRINCIPAL LEASE PYMT 28,250.00 28,250.00 35,960.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Enterprise Round 1 Replacement Annual Payment 1.0000 13,450.00 13,450.00
Budget Office Proposed Enterprise Round 2 Replacement Annual Payment 1.0000 14,800.00 14,800.00
Budget Office Proposed Enterprise Round 3 Replacement Annual Payment 1.0000 7,710.00 7,710.00
Budget Office Proposed Totals $35,960.00
8498 OPERATING TRANSFERS 40,800.00 40,800.00 250,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Transfer to Utility Repair Fund for Development 1.0000 250,000.00 250,000.00
Budget Office Proposed Totals $250,000.00
8499 CONTINGENCY 60,000.00 60,000.00 60,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Emergency repairs: street lights, guardrails, signals, etc. 1.0000 60,000.00 60,000.00
Budget Office Proposed Totals $60,000.00
DEBT SERVICE & TRANSFERS Totals $129,350.00 $129,350.00 $345,960.00
CAPITAL OUTLAY
8530 DESIGN / ENGINEERING .00 50,300.00 .00
8570 CONSTRUCTION .00 110,988.00 580,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Bedford Ct. E. reconstruction: Brown Trail to Hurst city limits 1.0000 245,000.00 245,000.00
Budget Office Proposed Cheek Sparger Road at Heritage Avenue roadway improvements 1.0000 185,000.00 185,000.00
Budget Office Proposed Cheek Sparger Road at Heritage Avenue signal light installation 1.0000 150,000.00 150,000.00
Budget Office Proposed Totals $580,000.00
9104 IMPROVEMENTS OTHER THAN BUILDINGS 120,000.00 120,000.00 120,000.00
Budget Transactions
Level Transaction Number of Units Cost Per Unit Total Amount
Budget Office Proposed Pedestrian crossing warning system 1.0000 120,000.00 120,000.00
Budget Office Proposed Totals $120,000.00
Run by JACKIE HANCOCK on 07/08/2019 15:58:27 PM Page 4 of 5
Expense Budget Worksheet Report
Budget Year 2020
2019 Adopted 2019 Estimated 2020 Budget Office
Account Account Description Budget Amount Proposed
Fund 227 - EDC -4B STREET IMPROVEMENT
Department 45 - PUBLIC WORKS
Division 02 - ADMINISTRATION
CAPITAL OUTLAY
9109 MACHINERY .00 318,300.00 .00
9111 MOTOR VEHICLES 318,300.00 .00 .00
CAPITAL OUTLAY Totals $438,300.00 $599,588.00 $700,000.00
Division 02 - ADMINISTRATION Totals $3,367,390.00 $3,760,982.00 $4,402,650.00
Department 45 - PUBLIC WORKS Totals $3,367,390.00 $3,760,982.00 $4,402,650.00
Fund 227 - EDC -4B STREET IMPROVEMENT Totals $3,367,390.00 $3,760,982.00 $4,402,650.00
Net Grand Totals $3,367,390.00 $3,760,982.00 $4,402,650.00
Run by JACKIE HANCOCK on 07/08/2019 15:58:27 PM Page 5 of 5
City of Bedford - Supplemental Funding Request
FY 2019-2020
FUND: Street Improvement Economic Development Corporation
DEPARTMENT: Public Works DIVISION: Administration
REQUEST TITLE: AI-500-085 Series Glance Preempt & Priority FMU TOTAL: $228,800
COUNCIL STRATEGIC FOCUS AREA: Organizational Excellence TYPE: Capital
Request reviewed by appropriate oversight division (if applicable): Not Applicable
Core Service Council Goal/Priority Emerging Safety Need Regulation or Mandate
Resident/Customer Expectation National Standard/Best Practice
DESCRIPTION OF REQUEST
This request is for new field monitoring units (FMU) for the traffic signal boxes. The FMU's will replace the current system that utilizes
the radio system for traffic synchronization that was installed in 2011 that allow the signals to "talk". The system functioned without
incident for approximately six years, but the radio system equipment installed on the water towers and at the Service Center is now
outdated and is no longer functioning as designed. Out of the 26 traffic signals maintained by the City, staff is currently unable to
connect to six and another four have intermittent communications. The cost to upgrade the current system, so it functions correctly, is
over $500,000. The requested new equipment will allow the traffic signals to "talk" again utilizing cellular connectivity.
BENEFITS/COST SAVINGS
Replacing the system that is currently not working properly will allow the traffic signals to communicate for traffic synchronization and
to issue alerts to staff when a signal is not functioning properly. The cost for the new field monitoring units and 10 years of cellular
connectivity is less than the cost of upgrading the current equipment so it functions properly.
CONSEQUENCES OF NOT FUNDING
As the equipment continues to decline, the traffic signals that currently cannot connect will continue to fail communicating for traffic
synchronization and to alert staff of signal failures; as well as others that will also lose connectivity.
SUMMARY OF REQUEST
TYPE FUND DEPT. DIV. ACCT. DESCRIPTION COST
Capital 227 45 02 9110 AI-500-085-02 Series Glance Preempt and Priority Controller $228,800
Grand Total: $228,800
COST/REVENUE COMPARISON FY 20/21 FY 21/22 FY 22/23
TOTAL FUTURE COST
TOTAL FUTURE REVENUE
FUND: Street Improvement Economic Development Corporation DEPT: Public Works
DIVISION: Administration REQUEST: AI-500-085 Series Glance Preempt & Priority FMU
CAPITAL REQUEST
# OF
DESCRIPTION OF CAPITAL MAKE/MODEL COST PER UNIT TOTAL AMOUNT
UNITS
Traffic Signal Components AI-500-085-02 Series Glance Preempt & Priority $8,800.00 26 $228,800
Field Monitoring Unit (FMU)
ADDITIONAL EXPENSES
TOTAL: $228,800
Is requested vehicle/equipment a replacement for an existing unit? (If yes, complete following information) Yes
Unit #: Year Purchased: Maintenance Cost last 24 months:
Age (Years): Odometer:
Disposition of Vehicle:
MAINTENANCE REQUEST
LOCATION OF # OF
DESCRIPTION OF MAINTENANCE COST PER UNIT TOTAL AMOUNT
MAINTENANCE UNITS
TOTAL:
PERSONNEL REQUEST
PAY MANDATED
POSITION TITLE FTE SALARY PENSION INSURANCE OTHER TOTAL
GRADE EXPENSES
TOTAL:
City of Bedford - Supplemental Funding Request
FY 2019-2020
FUND: Street Improvement Economic Development Corporation
DEPARTMENT: Public Works DIVISION: Administration
REQUEST TITLE: Swenson Model STCC Cross Conveyor Sander (2) TOTAL: $15,000
COUNCIL STRATEGIC FOCUS AREA: Economic Vitality TYPE: Capital
Request reviewed by appropriate oversight division (if applicable): Fleet
Core Service Council Goal/Priority Emerging Safety Need Regulation or Mandate
Resident/Customer Expectation National Standard/Best Practice
DESCRIPTION OF REQUEST
The City currently has two sanders that are used to sand roadways for ice/snow events and for accidental spills in the roadway. The
first one was purchased in 2000 with the second sander being purchased in 2005. The current sanders are mounted into the dump
bed and require the unit to be lifted into the back with the front end loader. This does not allow for quick installation and requires one
to be mounted year round while the other is mounted during the winter months. The requested model mounts to the tailgate and can
be mounted on an as needed basis. The requested models are electric rather than the current gasoline engines. This will decrease
down time caused by engine failures on the older models.
BENEFITS/COST SAVINGS
The requested sanders mount to the tailgate and are easier to install than the current sanders and does not limit the use of the truck
during the winter months. The Swenson sanders engine is electric and is more reliable than the gasoline engines in the current
sanders. This is because electric engines are inherently less complex pieces of machinery than the gasoline engines and decrease
maintenance issues. The requested sanders have a higher sand capacity than the current models since the truck bed is used rather
than a hopper. This will decrease the amount of trips back to the Service Center to refill when sanding roadways.
CONSEQUENCES OF NOT FUNDING
The current sanders have gasoline engines causing the engine to break down fairly often. This can delay sanding efforts during winter
ice/snow events. If the current sanders are not replaced, more trips will have to be made to the Service Center to refill the hoppers.
This will cause a delay in response times by City staff during ice/snow events.
SUMMARY OF REQUEST
TYPE FUND DEPT. DIV. ACCT. DESCRIPTION COST
Capital 227 45 02 9110 Swenson Model STCC Cross Conveyor Sander (2) $15,000
Grand Total: $15,000
COST/REVENUE COMPARISON FY 20/21 FY 21/22 FY 22/23
TOTAL FUTURE COST
TOTAL FUTURE REVENUE
FUND: Street Improvement Economic Development Corporation DEPT: Public Works
DIVISION: Administration REQUEST: Swenson Model STCC Cross Conveyor Sander (2)
CAPITAL REQUEST
# OF
DESCRIPTION OF CAPITAL MAKE/MODEL COST PER UNIT TOTAL AMOUNT
UNITS
Sander Swenson Model STCC $7,500.00 2 $15,000
ADDITIONAL EXPENSES
TOTAL: $15,000
Is requested vehicle/equipment a replacement for an existing unit? (If yes, complete following information) Yes
Unit #: Year Purchased: Maintenance Cost last 24 months:
Age (Years): Odometer:
Disposition of Vehicle: Auction
MAINTENANCE REQUEST
LOCATION OF # OF
DESCRIPTION OF MAINTENANCE COST PER UNIT TOTAL AMOUNT
MAINTENANCE UNITS
TOTAL:
PERSONNEL REQUEST
PAY MANDATED
POSITION TITLE FTE SALARY PENSION INSURANCE OTHER TOTAL
GRADE EXPENSES
TOTAL:
City of Bedford - Supplemental Funding Request
FY 2019-2020
FUND: Street Improvement Economic Development Corporation
DEPARTMENT: Public Works DIVISION: Administration
REQUEST TITLE: Peterbilt 348 Tandem Dump Truck TOTAL: $150,000
COUNCIL STRATEGIC FOCUS AREA: Revitalization TYPE: Capital
Request reviewed by appropriate oversight division (if applicable): Fleet
Core Service Council Goal/Priority Emerging Safety Need Regulation or Mandate
Resident/Customer Expectation National Standard/Best Practice
DESCRIPTION OF REQUEST
Request to replace unit #40 with a 15 yard Peterbilt 348 Tandem Dump Truck. The dump truck is used to haul the equipment trailer,
transport asphalt, fill material and spoils for various infrastructure repair projects. There are a limited number of drivers that are able to
drive the current tandem dump truck, causing it to be mainly unusable. The Texas Department of Motor Vehicles requires an
individual to test in the manual transmission vehicle to obtain the proper endorsement to drive the vehicle on the roadway. The
current federal transportation guidelines have made the process of obtaining an automatic transmission commercial drivers license
(CDL) difficult enough to obtain, with the manual transmission endorsement adding another level of difficulty.
BENEFITS/COST SAVINGS
Reduced maintenance costs due to replacing unit #40 with an automatic transmission. Since the dump truck requires an
endorsement that very few employees have, it will help reduce wait times during larger projects by having the ability to run two trucks
versus one. It will also provide an additional truck should Bedford suffer a catastrophic or severe weather event for debris removal.
CONSEQUENCES OF NOT FUNDING
There is a limited number of drivers that are able to use this truck due to special CDL requirements for a manual transmission.
Maintenance issues are largely due to recurring transmission problems. Due to requirements for use, the division has to reach out to
borrow an additional truck for larger projects. Because of the age of the unit, original parts have become obsolete and must either be
manufactured or the truck retrofitted with an after market equivalent at a higher parts cost.
SUMMARY OF REQUEST
TYPE FUND DEPT. DIV. ACCT. DESCRIPTION COST
Capital 227 45 02 9111 Peterbilt 348 Tandem Dump Truck $150,000
Grand Total: $150,000
COST/REVENUE COMPARISON FY 20/21 FY 21/22 FY 22/23
TOTAL FUTURE COST
TOTAL FUTURE REVENUE
FUND: Street Improvement Economic Development Corporation DEPT: Public Works
DIVISION: Administration REQUEST: Peterbilt 348 Tandem Dump Truck
CAPITAL REQUEST
# OF
DESCRIPTION OF CAPITAL MAKE/MODEL COST PER UNIT TOTAL AMOUNT
UNITS
Tandem Dump Truck Peterbilt 348 $150,000.00 1 $150,000
ADDITIONAL EXPENSES
TOTAL: $150,000
Is requested vehicle/equipment a replacement for an existing unit? (If yes, complete following information) Yes
Unit #: 40 Year Purchased: 1999 Maintenance Cost last 24 months: 6.88
Age (Years): 20 Odometer: 36,080 Miles
Disposition of Vehicle: Auction
MAINTENANCE REQUEST
LOCATION OF # OF
DESCRIPTION OF MAINTENANCE COST PER UNIT TOTAL AMOUNT
MAINTENANCE UNITS
TOTAL:
PERSONNEL REQUEST
PAY MANDATED
POSITION TITLE FTE SALARY PENSION INSURANCE OTHER TOTAL
GRADE EXPENSES
TOTAL:
Fiscal Year 2019/2020
Mill and Overlay at Various Locations
LOCATION A (MAYFAIR HILLS ADDN) 2019 2020 2021 2022 2023 2024
Street Name Route Back Route Ahead PCI Yr 1 PCI Yr 2 PCI Yr 3 PCI Yr 4 PCI Yr 5 PCI Yr 6 Water
April Sound Court Off of Saddlebrook North Saddlebrook North 43.12 40.88 38.66 36.29 33.89 PVC
Autumnwood Court Off of Saddlebrook North Dead End 48.67 47.17 45.24 43.24 41 38.75 PVC
Pleasantview Drive Hurst City Limits Saddlebrook North 49.61 48.11 46.5 44.5 42.42 40.16 PVC
Saddlebrook Drive Shady Lane Stonegate Drive North 47.83 46.1 44.12 42.01 39.74 37.43 PVC
Saddlebrook Drive Stratford Drive Stonega!e Drive North 52.14 50.64 49.16 47.66 43.86 41.74 PVC
Saddlebrook Drive Shady Lane Stratford Drive 61.54 60.04 58.55 57.05 55.54 54.04 PVC
Sugar Tree Court Off of Saddlebrook North Saddlebrook Drive 64.91 63.03 61.34 59.84 58.33 56.83 PVC
Hunters Glen Court Off of Shady Lane Cul-De-Sac 58.93 57.43 55.94 54.44 52.93 51.43 PVC
Windsong Court Off of Saddlebrook North Saddlebrook Drive 36.86 34.49 31.54 28.29 24.06 19.43 PVC
LOCATION B (WHISPERWOOD ADDN) 2019 2020 2021 2022 2023 2024
Street Name Route Back Route Ahead PCI Yr 1 PCI Yr 2 PCI Yr 3 PCI Yr 4 PCI Yr 5 PCI Yr 6 Water
Mulberry Lane Cherry Blossom Lane Chinaberry Drive 47.62 45.82 43.84 41.7 39.42 PVC
Hackberry Lane Cherry Blossom Lane Cottonwood Drive 56.63 55.13 53.64 52.14 50.63 49.13 PVC
Pinewood Street Cherry Blossom Lane Cottonwood Drive 67.65 66.03 64.21 62.34 60.76 59.26 PVC
Walnut Drive Cherry Blossom Lane Cottonwood Lane 58.64 57.14 55.66 54.16 52.64 51.14 DI
Aspenwood Drive Bedford Road Brasher Lane South 55.06 53.56 52.07 50.57 49.06 47.56 DI
Cottonwood Lane Aspenwood Drive End of Pavement 54.16 52.66 51.17 49.67 48.16 46.54 DI
Cherry Blossom Lane Aspenwood Drive Mulberry Lane 57.56 56.06 54.58 53.08 51.56 50.06 DI
Chinaberry Drive Bedford Road Mulberry 68.94 67.31 65.69 63.82 61.94 60.44 DI
LOCATION C (CAMELOT ESTATES) 2019 2020 2021 2022 2023 2024
Street Name Route Back Route Ahead PCI Yr 1 PCI Yr 2 PCI Yr 3 PCI Yr 4 PCI Yr 5 PCI Yr 6 Water
Fox Hollow Drive Huntwich Drive Steeplechase Drive 45.76 43.76 41.63 39.38 37.03 34.65 PVC
Huntwich Drive Brown Trail Fox Hollow Drive 71.32 69.32 67.65 66.03 64.18 62.3 PVC
Buckingham Court Off of Huntwich Drive Huntwich Drive 52.79 51.29 49.81 48.31 46.72 44.72 PVC
Oxford Court Off of Steeplechase Drive Steeplechase Drive 56 54.5 53.02 51.52 50 48.5 PVC
Steeplechase Court Off of Steeplechase Drive Cul-De-Sac 39.96 37.67 35.32 32.64 29.36 25.63 PVC
LOCATION D 2019 2020 2021 2022 2023 2024
Street Name Route Back Route Ahead PCI Yr 1 PCI Yr 2 PCI Yr 3 PCI Yr 4 PCI Yr 5 PCI Yr 6 Water
Red Oak Lane Scenic Hills Drive Cummings Drive 52.81 51.31 49.82 48.32 46.74 44.74 PVC
Scenic Hills Drive Red Oak Lane Cummings Drive 62.56 60.95 59.46 57.96 56.45 54.95 PVC
Hickory Court Off of Cummings Drive Cummings Drive 35.53 32.94 29.72 26.14 21.47 16.63 PVC
LOCATION E 2019 2020 2021 2022 2023 2024
Street Name Route Back Route Ahead PCI Yr 1 PCI Yr 2 PCI Yr 3 PCI Yr 4 PCI Yr 5 PCI Yr 6 Water
Susan Drive Emerald Street 177' E.of Emerald Street 51.5 50 48.52 47.02 45 43 PVC
Susan Drive Crystal Springs State Highway #121 61.1 59.6 58.12 56.62 55.1 53.6 PVC
Susan Drive 177' East of Emerald Street Crystal Springs 56.45 54.95 53.46 51.96 50.45 48.95 PVC
Get email alerts for Bedford
A daily email when new agendas and minutes are posted.