HPMPO Technical Coordinating Committee (TCC)
Regular MeetingHigh Point, NC · March 15, 2016
Minutes
Attachment 1
MINUTES
TECHNICAL COORDINATING COMMITTEE
March 15, 2016
TCC MEMBERS PRESENT: Greg Venable, Guy Cornman, Chuck George, Bryan
Fulbright, Carrie Spencer, Darius Sturdivant, Jen Britt, Roger Jones, Diane Hampton, Ed
Lewis, Marc Allred, Angela Wynes, Chuck Smith, Mark McDonald, and Mark Kirstner
TAC MEMBERS PRESENT: Joe Geigle (FHWA)
OTHERS PRESENT: Kelly Larkins (Piedmont Triad RPO), Anna Leonard (Piedmont
Triad Regional Council, John Hanes (High Point), Vicki Embry (High Point)
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Mark McDonald called the meeting to order.
ACTION ITEMS
Item 1: Consideration of the February 16, 2016 TCC Meeting Minutes.
The minutes were approved.
Motion by: Guy Cornman
Seconded by: Bryan Fulbright
Vote:
For: Unanimous
Against: None
Item 2: Recommendation to the TAC for approval of the Self Certification
process.
Every year, prior to adoption of the Unified Planning Work Program, the MPO is
required to certify its planning process and its compliance with various federal
regulations including the Clean Air Act, the Civil Rights Act, the Americans with
Disabilities Act, and the federal transportation authorizing legislation. The certification
states that the MPO is in compliance with all federal requirements and is carrying out its
planning process in the appropriate manner. The resolution is a necessary prerequisite for
adoption of the UPWP.
Motion by: Mark Kirstner
Seconded by: Guy Cornman
1
Attachment 1
Vote:
For: Unanimous
Against: None
Item 3: Recommendation to the TAC for approval of the 2016-2017 Unified
Planning Work Program.
The UPWP is the MPO’s annual budget and work plan. It lists the planning tasks that staff
expects to perform and the work products that we expect to produce during the fiscal year.
Our fiscal year runs from July 1st through June 30th of next year. The work program consists
of three major divisions: surveillance of change, long-range planning, and administration.
Each major division includes several line items under which the MPO can perform work.
Each line item includes explanatory text describing the customary work items for the line
item, the rationale for performing the work, how much money we plan to spend on the line
item and the work products that the MPO expects to produce during the upcoming year. The
UPWP also includes a series of tables showing the sources of the funds used, the amount of
federal funds used, the amount of the local match, and total expenditures for each line item
from each funding source. The public had at least thirty (30) days to review and comment
on the UPWP. No public comments were received. Greg stated that a change was made
to the funding amounts. As a result of a carryover from this fiscal year to next fiscal year
some additional funding was added to the planning study. The MPO originally budgeted
$280,000 for special studies and $70,000 local match for a total of $350,000. We had
$200,000 in there originally but we are carrying over $150,000 that we had programmed
for this fiscal year. Jamestown will possibly be using some of those funds. The MPO is
also going to be conducting a bike plan. Greg stated that if there are any additional
studies that the jurisdictions would like done they can be looked at.
Motion by: Bryan Fulbright
Seconded by: Guy Cornman
Vote:
For: Unanimous
Against: None
Information Items
Item 4: SPOT 4.0
Greg stated that the MPO’s prioritization process was approved.
MPO Reports
Item 5: NCDOT Division Reports
Division 7
Ed Lewis reported that the projects in Division 7 are moving along.
2
Attachment 1
Division 8
Darius Sturdivant reported that there are several resurfacing projects that are scheduled to
start in April. The Prospect St. bridge replacement project over Business 85 is 36%
complete. The SPOT safety project to update the traffic signal at NC 62 and Finch Farm
Rd. is expected to be completed by the middle of April. The Archdale Rd. widening
project has been segmented in the segments A & B. The Randolph County (segment A)
portion from Robbins Country Rd to the Guilford County line is funded. The remaining
segment (segment B) from the Randolph County line to Main St. is unfunded. There has
been discussion about down scoping the project to a 3 lane project.
Division 9
Diane Hampton reported that the US 52/I-85 Business project is expected to be
completed by the end of March. The bid opening for the turn lane at Hickory Tree Rd.
and Mendenhall Rd. has taken place and they are awaiting documents for award. There
was a public meeting in January on the Business 85 crossover between Thomasville and
Lexington. Some suggestions for modifications were received and are being reviewed.
Item 5: Triad Air Awareness
No one was present.
Item 6: NCDOT Transportation Planning Branch
No one was present.
Item 7: Hitran
Angela had nothing to report.
Item 8: PART
Mark Kirstner reported information on the Commuter Dash which is a transportation
demand management program and project that takes place yearly to raise awareness
about the different forms of transportation. The 5K race will take place in Triad Park this
year. PART’s service on route 4 was recently modified through some funds from the
Burlington/Graham MPO. This route was originally set up to provide medical trips from
the Triad area to Chapel Hill and Duke. Due to the modifications and the addition of a
connection with Triangle Transit in Mebane ridership has gone from 300 a month to over
1200 a month. The UNC hospital in Chapel Hill offers their employees free transit. Now
that High Point has a UNC owned hospital Mark would like Angela and the MPO staff to
look into whether this is something that can be provided to the other UNC branches.
Discussion
Greg stated that there will be a two of presentations at the TAC meeting on March 22.
DOT voting will take place after the TAC meeting is adjourned. The TAC meeting will
start at 9:00 am instead of 10:00 to give the TAC members time to vote.
There was no other business. The meeting was adjourned.
3
Agenda
HIGH POINT URBAN AREA MPO
TECHNICAL COORDINATING
COMMETTEE (TCC)
Agenda for the March 15, 2016 TCC Meeting
2:00 PM
***Third Floor Conference Room***
High Point Municipal Building - City Hall
211 S. Hamilton Street, High Point
Action Items
1. Consideration of the February 16th TCC meeting minutes. (Mark McDonald) Page 1
2. Recommendation to the TAC for approval of the Self Certification process. (Greg
Venable) Page 5
3. Recommendation to the TAC for approval of the 2016-2017 Unified Planning Work
Program (UPWP). (Greg Venable) Page 11
Information Items
4. SPOT 4.0 update (Greg Venable) Page 13
MPO Reports
4. NCDOT Division Reports
Division 7 (Mike Mills / Ed Lewis) Page 15
Division 8 (Brandon Jones / Darius Sturdivant) Page 20
Division 9 (Pat Ivey / Diane Hampton) Page 21
5. Triad Air Awareness Report (Lorelei Elkins) Page 24
6. NCDOT Transportation Planning Branch Report (Wayne Davis)
7. Hitran Report (Angela Wynes)
8. PART Report (Scott Rhine) Page 25
TCC
Meeting
Meeting Date 3/15/2016 Agenda Item No. 1
Action Requested Approve
Section Tab
Consideration of the February 16th TCC meeting minutes. (Mark McDonald)
Information Summary Attachments Yes No
The complete meeting minutes are in your packet as Attachment 1.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
1
Attachment 1
MINUTES
TECHNICAL COORDINATING COMMITTEE
February 16, 2016
TCC MEMBERS PRESENT: Greg Venable, Guy Cornman, Chuck George, Bryan
Fulbright, Carrie Spencer, Heidi Galanti, Darius Sturdivant, Jen Britt, Roger Jones, Scott
Rhine, Diane Hampton, Jeff York, Lorelei Elkins, Jason Miller,
TAC MEMBERS PRESENT: Joe Geigle (FHWA)
OTHERS PRESENT: John Hanes (High Point), Gwen Ford (High Point)
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Greg Venable called the meeting to order.
ACTION ITEMS
Item 1: Motion to move SPOT discussion to last agenda item in meeting.
Motion by: Guy Cornman
Seconded by: Jeff York
Vote:
For: Unanimous
Against: None
Item 2: Consideration of the January 26, 2016 TCC Meeting Minutes.
The minutes were approved.
Motion by: Guy Cornman
Seconded by: Diane Hampton
Vote:
For: Unanimous
Against: None
Item 3: Recommendation to the TAC for approval of the amendments to the
2016-2025 MTIP.
There are four STIP additions and one STIP modification that are being recommended for
TAC approval. Scott Rhine from PART has some projects that he would like to include in
the amendment to the TAC. There are two projects on the list for replacement buses that are
1
2
Attachment 1
using funding from NCDOT not the MPO. The first projects funding originated from FTA
section 5339 funding which will be transferred into the 5307 program for FTA grant
purposes. Funding for the second project will go directly through NCDOT which will go
through partner direct. These grant funds need to be recorded in the local TIP. There are
also two projects on the list that are being funded through CMAQ funds which came through
the HP MPO “Call for Projects” and have already been approved by HP MPO. The first
project is to implement a new Palladium circulator in North High Point beginning in 2017.
The funds will be an 80/20 split. The second project is for a replacement bus.
Motion by: Roger Jones
Seconded by: Diane Hampton
Vote:
For: Unanimous
Against: None
MPO Reports
Item 4: NCDOT Division Reports
Division 7
No one was present. Report is in the packet.
Division 8
Darius Sturdivant reported that the Project St. Bridge Replacement over Business 85 is
34% complete. There are two SPOT safety traffic signal upgrade projects. One is at the
intersection of NC 62 and Finch Farm Rd. and the other is Trinity Rd. and Archdale Rd.
The signal at Trinity Rd. and Archdale Rd. is complete and operational. The restriping at
NC 62 and Finch Farm Rd. has been delayed due to weather. The Board of
Transportation just approved funds for the I-73 Pavement Rehabilitation Project. There
are also two bridge replacement projects and another pavement rehabilitation project on
the list. Greg brought up the fact that at the scope meeting for the Archdale Rd. there was
some concern about the traffic numbers being low for the type of widening to be done.
There was some discussion about to get together with the staff working on the Surrett Dr.
Project and conduct a combined feasibility study.
Division 9
Diane Hampton reported that utility relocation is underway for the replacement bridge
project over Business 85. There are several bridge projects and resurfacing projects. The
Hickory Tree Rd. left turn land project is currently advertised for bid. The widening of
NC 8 which will tie into the interchange project in Lexington will be let in 2019.
Item 5: Triad Air Awareness
Lorelei Elkins reported that there are a couple of grant opportunities from the NC Clean
Energy Technology Center at NC State. She encouraged everyone to take a look at a
2
3
Attachment 1
webinar series, Advancing a Sustainable Highway System. The registration is open for
the NC Breathe Conference taking place in Charlotte on April 8. The conference deals
mainly with the medical implications of poor air quality.
Item 6: NCDOT Transportation Planning Branch
No one was present.
Item 7: Hitran
No one was present.
Item 8: PART
Scott Rhine reported that the phase two Freight Planning kickoff took place last week.
The first phase was inventory of the region and the second phase will be on model design
structure and the third phase will be on travel diary. The purpose of the freight phase is
to incorporate a tour based model into the travel demand model. We will be the first in
NC to have this tour base freight travel demand model. The first phase was started with
Federal Highway funds. There are some new vanpool vehicles in the PART fleet. PART
has been working with Division 9 on the Business 40 closure project. PART just kicked
off an analysis of Davidson County Transportation with regard to growth.
Information Items
Item 9: Discussion on the prioritization process for the High Point MPO and
the SPOT 4.0 Schedule.
Greg Venable discussed the prioritization process and reviewed the SPOT 4.0 schedule.
Discussion
There was no other business. The meeting was adjourned.
3
4
TCC
Meeting
Meeting Date 3/15/2016 Agenda Item No. 2
Action Requested Recommendation
Section Tab
Consideration of HPMPO Self Certification process. (Greg Venable)
Information Summary Attachments Yes No
Every year, prior to adoption of the Unified Planning Work Program, the MPO is
required to certify its planning process and its compliance with various federal
regulations including the Clean Air Act, the Civil Rights Act, the Americans with
Disabilities Act, and the federal transportation authorizing legislation. The certification
states that the MPO is in compliance with all federal requirements and is carrying out its
planning process in the appropriate manner. The resolution is a necessary prerequisite for
adoption of the UPWP. Staff is requesting a recommendation to the TAC to approve the
self-certification process. A copy of the resolution is included in your packet.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
5
Metropolitan Planning Organization Self-Certification
As part of the planning process the MPO is required to regularly certify that it is complying with
federal regulations pertaining to transportation planning, the environment, and access to decision-
making. The certification requirement is found in 23 CFR Part 450.335 which states in part:
. . . “(a) The State and the MPO shall annually certify to the FHWA and the FTA that the planning process is
addressing the major issues facing the area and is being conducted in accordance with all applicable
requirements of:
(1) Section 134 of title 23, U.S.C., section 8 of the Federal Transit Act (49 U.S.C. app. 1607) and this part;
(2) Sections 174 and 176 (c) and (d) of the Clean Air Act (42 U.S.C. 7504, 7506 (c) and (d));
(3) Title VI of the Civil Rights Act of 1964 and the Title VI assurance executed by each State under 23
U.S.C. 324 and 29 U.S.C. 794;
(4) Section 1003(b) of the Intermodal Surface Transportation Efficiency Act of 1991 (Pub. L. 102–240)
regarding the involvement of disadvantaged business enterprises in the FHWA and the FTA funded planning
projects (sec. 105(f), Pub. L. 97–424, 96 Stat. 2100; 49 CFR part 23); and
(5) The provisions of the Americans with Disabilities Act of 1990 (Pub. L. 101–336, 104 Stat. 327, as
amended) and U.S. DOT regulations “Transportation for Individuals with Disabilities” (49 CFR parts 27, 37,
and 38).”
In addition, the following checklist should help guide the MPOs as they review their processes
and programs for self-certification.
The self certification checklist below summarizes the requirements for self certification and
indicates that the High Point MPO is meeting the USDOT’s planning requirements.
Item Regulatory Reference Status
1 Is the MPO properly designated by agreement between the Governor and Yes
75% of the urbanized area, including the central city, and in accordance in
procedures set forth in state and local law (if applicable)? [23 U.S.C. 134
(b); 49 U.S.C. 5303 (c); 23 CFR 450.306 (a)]
2 Does the policy board include elected officials, major modes of Yes
transportation providers and appropriate state officials? [23 U.S.C. 134 (b);
49 U.S.C. 5303 (c); 23 CF R 450.306 (i)]
3 Does the MPO boundary encompass the existing urbanized area and the Yes
contiguous area expected to become urbanized within the 20-yr forecast
period? [23 U.S.C. 134 (c), 49 U.S.C. 5303 (d); 23 CFR 450.308 (a)]
4 Is there a currently adopted Unified Planning Work Program (UPWP)? 23 Yes
CFR 450.314
Is there an adopted prospectus
Are tasks and products clearly outlined
Is the UPWP consistent with the LRTP
Is the work identified in the UPWP completed in a timely fashion
6
Item Regulatory Reference Status
5 Does the area have a valid transportation planning process? 23 CFR Yes
450.322
Is the transportation planning process continuous, cooperative and
comprehensive
Is there a valid LRTP
Did the LRTP have at least a 20-year horizon at the time of adoption
Does it address the 8-planning factors
Does it cover all modes applicable to the area
Is it financially constrained
Does it include funding for the maintenance and operation of the system
Does it conform to the State Implementation Plan (SIP) (if applicable)
Is it updated/reevaluated in a timely fashion (at least every 4 or 5 years)
6 Is there a valid TIP? 23 CFR 450.324, 326, 328, 332 Yes
Is it consistent with the LRTP
Is it fiscally constrained
Is it developed cooperatively with the state and local transit operators
Is it updated at least every 4-yrs and adopted by the MPO and the
Governor
7 Does the area have a valid CMS? (TMA only) 23 CFR 450.320 Yes
Is it consistent with the LRTP
Was it used for the development of the TIP
Is it monitored and reevaluated to meet the needs of the area
8 Does the area have a process for including environmental mitigation Yes
discussions in the planning process? SAFETEA-LU
9 Does the planning process meet the following requirements of 23 CFR Yes
450.316 (2) (3), EO 12898?
Title VI
Are there procedures in place to address Title VI complaints and
does it comply with federal regulation? [23 CFR 200.9 (b)(3)]
Environmental Justice (Executive Order 12898)
Has the MPO identified low-income and minority populations
within the planning area and considered the effects in the planning
process?
ADA
Are there procedures in place to address ADA complaints of non-
compliance and does it comply with federal regulation?
[49 CFR 27.13]
DBE
Does the MPO have a DBE policy statement that expresses
commitment to the DBE program? [49 CFR 26.23]
7
Item Regulatory Reference Status
10 Does the area have an adopted PIP/Public Participation Plan? 23 CRR Yes
450.316 (b)(1)
Did the public participate in the development of the PIP
Was the PIP made available for public review for at least 45-days prior
to adoption
Is adequate notice provided for public meetings
Are meetings held at convenient times and at accessible locations
Is the public given an opportunity to provide oral and/or written
comments on the planning process
Is the PIP periodically reviewed and updated to ensure its effectiveness
Are plans/program documents available in an electronic accessible
format, i.e. MPO website?
11 Does the area have a process for including environmental, state, other Yes
transportation, historical, local land use and economic development
agencies in the planning process? MAP 21
8
RESOLUTION CERTIFYING THE HIGH POINT URBAN AREA
METROPOLITAN PLANNING ORGANIZATION'S TRANSPORTATION
PLANNING PROCESS FOR FY 2016-2017
WHEREAS, the Transportation Advisory Committee has found that the
Metropolitan Planning Organization is conducting transportation planning in a
continuous, cooperative, and comprehensive manner in accordance with 23
U.S.C. 134 and 49 U.S.C. 1607;
WHEREAS, the Transportation Advisory Committee has found the
Transportation Planning Process to be in compliance with Sections 174 and 176
(c) and (d) of the Clean Air Act (42 U.S.C. 7504, 7506 (c) and (d)).
WHEREAS, the Transportation Advisory Committee has found the
Transportation Planning Process to be in full compliance with Title VI of the
Civil Rights Act of 1964 and the Title VI Assurance executed by each State under
23 U.S.C. 324 and 29 U.S.C. 794;
WHEREAS, the Transportation Advisory Committee has considered how the
Transportation Planning Process will affect the involvement of Disadvantaged
Business Enterprises in the FHWA and the FTA funded planning projects (Sec.
105(f)), Pub. L. 97-424, 96 Stat. 2100, 49 CFR part 23);
WHEREAS, the Transportation Advisory Committee has considered how the
Transportation Planning Process will affect the elderly and the disabled per the
provision of the Americans with Disabilities Act of 1990. (Pub. L. 101-336, 104
Stat. 327, as amended) and the U.S. DOT implementing regulations;
NOW THEREFORE, BE IT RESOLVED that the High Point Urban Area
Transportation Advisory Committee certifies the Transportation Planning Process
for the High Point Urban Area Metropolitan Planning Organization on this the
22nd day of March, 2016.
A motion was made by TAC member ____________________ and seconded by
TAC member ____________________ for the adoption of the above resolution,
and upon being put to a vote was duly adopted.
___________________________________
Neal Grimes
Chair, Transportation Advisory Committee
******************************************************************
9
Subscribed and sworn to me this 22nd day of March, 2016.
_________________________________
Notary Public
My commission expires ________________.
10
TCC
Meeting
Meeting Date 3/15/2016 Agenda Item No. 3
Action Requested Recommendation
Section Tab
Consideration of the 2016-2017 Unified Planning Work Program (UPWP). (Greg
Venable)
Information Summary Attachments Yes No
The UPWP is the MPO’s annual budget and work plan. It lists the planning tasks that staff
expects to perform and the work products that we expect to produce during the fiscal year.
Our fiscal year runs from July 1st through June 30th of next year. The work program consists
of three major divisions: surveillance of change, long-range planning, and administration.
Each major division includes several line items under which the MPO can perform work.
Each line item includes explanatory text describing the customary work items for the line
item, the rationale for performing the work, how much money we plan to spend on the line
item and the work products that the MPO expects to produce during the upcoming year. The
UPWP also includes a series of tables showing the sources of the funds used, the amount of
federal funds used, the amount of the local match, and total expenditures for each line item
from each funding source.
The public had at least thirty (30) days to review and comment on the UPWP. Staff is
requesting a recommendation to the TAC for approval of the 2016-2017 UPWP. Copies
of the 2016-2017 UPWP will be handed out at the meeting. A copy of the resolution is
included in your packet.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
11
RESOLUTION APPROVING THE FY 2016-2017 PLANNING
WORK PROGRAM FOR THE HIGH POINT URBANIZED AREA
METROPOLITAN PLANNING ORGANIZATION
WHEREAS, a comprehensive and continuing transportation planning program
must be carried out cooperatively in order to ensure that funds for transportation
projects are effectively allocated to the High Point Urban Area; and
WHEREAS, the MPO has adopted a 25 year Metropolitan Transportation Plan to
the Year 2040 that is fiscally constrained and meets federal requirements for
metropolitan transportation planning; and
WHEREAS, the City of High Point has been designated as the recipient of Federal
Transit Administration Metropolitan Planning Program (Section 5303) funds; and
WHEREAS, members of the High Point Urban Area Transportation Advisory
Committee agree that the Planning Work Program will effectively advance the
transportation planning process for FY 2016-2017
NOW, THEREFORE, BE IT RESOLVED that the Transportation Advisory
Committee hereby endorses the FY 2016-2017 Planning Work Program for the
High Point Urban Area.
A motion was made by TAC member _______________________ and seconded by
TAC member __________________________ for the adoption of the above
resolution, and upon being put to a vote was duly adopted.
________________________
Neal Grimes
Chair, Transportation Advisory Committee
*******************************************************************
Subscribed and sworn to me this 22nd day of March 2016.
_______________________________Notary Public
My commission expires ______________
12
TCC
Meeting
Meeting Date 3/15/2016 Agenda Item No. 4
Action Requested Information
Section Tab
SPOT 4.0 Update (Greg Venable)
Information Summary Attachments Yes No
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
13
TCC
Meeting
Meeting Date 3/15/2016 Agenda Item No. 5-9
Action Requested Information
Section Tab
MPO Reports
Information Summary Attachments Yes No
Agenda Item 5
Division Reports
Agenda Item 6
Triad Air Awareness
Agenda Item 7
Transportation Planning Branch Report
Agenda Item 8
Hitran
Agenda Item 9
PART Report
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
14
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design and bid
document
Install pedestrian improvements on SR 1009 (N. Main Street) at
preparation in Small Construction.
43250 Lexington Avenue (WCR, pedestrian signal heads, traffic Spring 2016 Summer 2016 $140,000
progress by City, M.A. w/ City,
islands)
Signal plans
approved
Planning and
I-5712 Design activities STIP, P3.0,
Interchange improvements at I-40/US 421 and SR 1850 (Sandy
50126.2.1 1/19/21 FY 2023 underway, R/W $7,800,000 Coordinate w/
Ridge Road)
50126.3.1 plans complete U-4758
1/18/19
R/W plans being
U-2412A
SR 1486 (Greensboro Road) / SR 4121 (High Point Road), revised - April
34802.2.2 STIP, Programmed
Widening (part on new location) from SR 4228 (Vickrey Chapel FY 2019 FY 2022 2017 completion, $51,900,000
34802.2.6 due to HB97
Road) to I-74/US 311 Bypass R/W Acquisition -
34802.3.3
10% complete
Planning and
U-4758 Design activities
Improvements to Johnson Street/Sandy Ridge Road from Skeet STIP, Coordinate w/
40251.2.1 7/16/19 FY2022 underway, R/W $18,300,000
Club Road to I-40 I-5712
40251.3.1 plans complete
7/21/2017
Central Design in
progress, Public
U-5169
I-74/US 311 and NC 68 (Eastchester Drive) interchange workshop early
45220.2.1 6/19/18 FY 2020 $15,775,000 STIP
improvements 2016, R/W
45220.3.1
plans complete
6/17/16
R/W Certified, System
17BP.7.R.22 Bridge #895 on SR 1486 (Lexington Ave.) over Bouldin Branch 3/17/16 Summer 2016 Project let $577,000 Preservation, M.A.
pending executed
15 Page 1 HPMPO 3-4-16.xlsx
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO
TIP/WBS # Description Let Date Completion Date Status Cost Comments
Design in
B-5358
progress, R/W
46072.1.1 STP funds, LAP,
Replace Bridge #428 on Model Farm Rd over Richland Creek 9/30/16 Summer 2017 plans complete; $1,050,000
46072.2.FD1 City match
City acquiring
46072.3.FD1
R/W
I-5767
Pavement Rehabilitation: I-74/US-311 from 0.7 miles East of I-
53010.3.1/ NHPP - Interstate
40 to the Guilford /Forsyth County Line to SR1300 (E. Green 2/16/16 Summer 2017 Contract awarded $20,600,000
I-5736 Maintenance
Drive)
52018.3.1
I-5821
Design and bid
50464.3.1
package
I-5789 Pavement Rehabilitation: I-85 from 0.4 miles South of I-85 NHPP - Interstate
6/21/16 Summer 2017 submittal to $9,900,000
53029.3.1 Business to South of SR 1009 (S. Main St.) in Archdale Maintenance
Raleigh-85%
I-5738
Complete
52020.3.1
Design and bid
I-5734
package
52010.3.1 Pavement Rehabilitation: I-40 from 1.1 miles East of SR 1556 NHPP - Interstate
5/17/16 Summer 2017 submitted to $9,664,000
I-5762 Gallimore Dairy Rd to Forsyth County Line Maintenance
Raleigh - 100%
53005.3.1
complete
16 Page 2 HPMPO 3-4-16.xlsx
Page 1 of 3
03/04/2016
North Carolina Department of Transportation
Active Projects Under Construction - Guilford Co.
Contract TIP Location Description Contractor Name Resident Engineer Contract Bid Availability Work Start Completion Progress Completion
Number Number Amount Date Date Date Schedule Percent
C200800 R-2309AB US-220 FROM SR-2182 (HORSEPEN CREEK TETRA TECH Lorenz, PE, Kris $96,195,464.51 04/02/2012 05/09/2012 Percent
12/27/2016 94.44 57.00
RD) TO EXISTING NC-68 & US-220 CONSTRUCTION INC
INTERSECTION.
C200800 R-2413C US-220 FROM SR-2182 (HORSEPEN CREEK TETRA TECH Lorenz, PE, Kris $96,195,464.51 04/02/2012 05/09/2012 12/27/2016 94.44 57.00
RD) TO EXISTING NC-68 & US-220 CONSTRUCTION INC
INTERSECTION.
C202648 R-2611 SR-1008 (W MARKET ST) FROM SR-2007 JIMMY R. LYNCH & SONS, Smith, Brian V $17,475,472.75 09/26/2011 09/26/2011 11/01/2014 100.00 97.66
(BUNKER HILL RD) AT COLFAX TO NC-68 INC.
IN GREENSBORO.
C202881 U-2412B SR-4228 (VICKERY CHAPEL RD) TO APAC - ATLANTIC, INC. Ingram, PE, J. Paul $40,094,959.99 10/01/2012 10/05/2012 05/13/2016 99.60 83.79
SR-1424 (HILLTOP RD); GREENS- BORO THOMPSON ARTHUR
WESTERN LOOP INTERCHANGE AT HIGH DIVISION
POINT RD.
C202881 U-2524AE SR-4228 (VICKERY CHAPEL RD) TO APAC - ATLANTIC, INC. Ingram, PE, J. Paul $40,094,959.99 10/01/2012 10/05/2012 05/13/2016 99.60 83.79
SR-1424 (HILLTOP RD); GREENS- BORO THOMPSON ARTHUR
WESTERN LOOP INTERCHANGE AT HIGH DIVISION
POINT RD.
C202923 REPLACEMENT OF 1 BRIDGE IN CASWELL SMITH-ROWE, LLC Ingram, PE, J. Paul $7,292,875.26 04/02/2012 05/01/2012 11/01/2015 100.00 99.34
COUNTY, 3 IN GUILFORD COUNTY, 2 IN
ORANGE COUNTY, & 6 IN ROCKINGHAM
COUNTY.
C203197 U-2524C GREENSBORO-WESTERN LOOP FROM VECELLIO & GROGAN INC Smith, Brian V $122,804,388.50 10/28/2013 10/30/2013 03/14/2018 60.30 41.90
SOUTH OF SR-2137 (OLD OAK RIDGE RD)
TO NORTH OF US-220 (BATTLEGROUND
AVE).
C203237 BRIDGE #217, 259 & 274 ON US-220 AND ASTRON GENERAL Lorenz, PE, Kris $1,274,112.00 06/01/2013 06/14/2013 09/28/2013 100.00 82.31
#1, 136 & 470 ON SR-2254 (WENDOVER CONTRACTING COMPANY
AVE). INC
C203256 U-3615B SR-1820 (SKEET CLUB RD) FROM EAST OF APAC - ATLANTIC, INC. Ingram, PE, J. Paul $30,898,017.15 03/02/2015 05/20/2015 03/29/2019 11.20 2.57
SR-1818 (JOHNSON ST) TO WEST OF THOMPSON ARTHUR
NC-68 (EASTCHESTER DR) IN HIGH POINT. DIVISION
C203290 U-2524BC GREENSBORO W LOOP FROM I-73/I-840 FLATIRON Smith, Brian V $4,955,491.02 07/27/2015 09/08/2015 03/01/2017 27.70 25.92
TO SR-2085 (JOSEPH BRYAN BLVD) CONSTRUCTORS, INC.
INTERCHANGE. BLYTHE DEVELOPMENT
CO JOINT VENT
C203399 U-2525B GREENSBORO EASTERN LOOP FROM FLATIRON Smith, Brian V $111,683,421.13 07/28/2014 08/08/2014 12/28/2018 42.80 51.00
NORTH OF US-70 TO US-29 NORTH OF CONSTRUCTORS, INC.
GREENSBORO. BLYTHE DEVELOPMENT
CO JOINT VENT
C203412 R-2612B US-421 AT SR-3418 (NEELLEY RD) SOUTH BRANCH HIGHWAYS, INC. Lorenz, PE, Kris $13,528,497.85 07/28/2014 08/07/2014 12/28/2016 77.40 66.64
OF GREENSBORO.
C203415 W-5114 NC-68 FROM SOUTH OF SR-2111 (E YATES CONSTRUCTION Ingram, PE, J. Paul $1,819,807.14 06/30/2014 07/01/2014 05/14/2015 99.50 86.80
HARRELL RD) TO SR-4831 (BARTONSHIRE CO., INC.
DR).
C203433 I-5110 FUTURE I-73 FROM EXISTING SR-2085 FLATIRON Smith, Brian V $176,550,000.00 05/07/2014 05/07/2014 04/25/2017 49.84 48.90
(JOSEPH M BRYAN BLVD) / AIRPORT CONSTRUCTORS, INC.
PKWY INTERCHANGE TO SOUTH OF BLYTHE DEVELOPMENT
US-220 NEAR HAW RIVER. CO JOINT VENT
17
Page 2 of 3
03/04/2016
North Carolina Department of Transportation
Active Projects Under Construction - Guilford Co.
Contract TIP Location Description Contractor Name Resident Engineer Contract Bid Availability Work Start Completion Progress Completion
Number Number Amount Date Date Date Schedule Percent
C203433 I-5110A FUTURE I-73 FROM EXISTING SR-2085 FLATIRON Smith, Brian V $176,550,000.00 05/07/2014 05/07/2014 Percent
04/25/2017 49.84 48.90
(JOSEPH M BRYAN BLVD) / AIRPORT CONSTRUCTORS, INC.
PKWY INTERCHANGE TO SOUTH OF BLYTHE DEVELOPMENT
US-220 NEAR HAW RIVER. CO JOINT VENT
C203433 R-2413A FUTURE I-73 FROM EXISTING SR-2085 FLATIRON Smith, Brian V $176,550,000.00 05/07/2014 05/07/2014 04/25/2017 49.84 48.90
(JOSEPH M BRYAN BLVD) / AIRPORT CONSTRUCTORS, INC.
PKWY INTERCHANGE TO SOUTH OF BLYTHE DEVELOPMENT
US-220 NEAR HAW RIVER. CO JOINT VENT
C203489 P-5204 SR-2819 (MCLEANSVILLE RD) GRADE TRIANGLE GRADING & Ingram, PE, J. Paul $7,078,936.15 10/27/2014 10/29/2014 02/28/2017 43.00 44.76
SEPARATION OVER NS/NCRR RAILROAD PAVING INC
FROM SR-2826 TO NORTH OF SR-2746.
C203518 B-5119 BRIDGES #349 & #291 OVER US-29/70/220 APAC - ATLANTIC, INC. Julian, Jason R $5,973,735.98 03/02/2015 03/16/2015 02/28/2018 28.00 30.39
ON I-40/85. THOMPSON ARTHUR
DIVISION
C203625 B-4959 BRIDGE #193 OVER BUFFALO CREEK ON R.E. BURNS & SONS CO., Smith, Brian V $957,388.91 03/01/2016 12/07/2015 03/06/2017 0 49.75
SR-2719 (HIGH ROCK RD). INC.
C203627 C-5558 CITY OF HIGH POINT. HAYNES ELECTRIC UTILITY Lorenz, PE, Kris $7,099,452.53 11/30/2015 02/15/2019
CORP.
C203640 REPLACEMENT OF 4 BRIDGES IN HAYMES BROTHERS, INC. Lorenz, PE, Kris $3,124,500.00 06/01/2015 09/02/2015 11/01/2017
GUILFORD COUNTY AND 3 BRIDGES IN
ORANGE COUNTY.
C203641 REPLACEMENT OF 5 BRIDGES IN R.E. BURNS & SONS CO., Kirkman, PE, $5,940,323.00 06/01/2015 06/01/2015 11/01/2018 6.50 17.33
GUILFORD COUNTY AND 5 BRIDGES IN INC. Christopher D
ORANGE COUNTY.
C203715 NC-150 FROM NC-68 TO US-220, AND 20 BLYTHE CONSTRUCTION, Ingram, PE, J. Paul $2,068,055.18 04/15/2016 11/18/2016
SECTIONS OF SECONDARY ROADS. INC.
DG00090 U-2524AB I-73 FROM I-85 TO WENDOVER AVENUE LINEBERRY, INC. Ingram, PE, J. Paul $204,060.50 02/15/2012 02/07/2012 12/15/2014 0 100.00
DG00218 RESURFACE 5.041 MILES OF US 220 APAC - ATLANTIC, INC. Lorenz, PE, Kris $1,376,734.85 04/27/2015 07/09/2015 11/20/2015 100.00 100.00
(WENDOVER AVE.) THOMPSON ARTHUR
DIVISION
DG00219 Resurface SR 3093, SR 3029, SR 2826,SR BLYTHE CONSTRUCTION, Ingram, PE, J. Paul $1,065,598.39 03/30/2015 07/20/2015 11/20/2015 0 80.37
2732 AND SR 2509 INC.
DG00220 BD-5107AB REPLACE BRIDGE #145 ON SR 1340 SMITH-ROWE, LLC Smith, Brian V $347,976.83 03/04/2015 03/04/2015 02/01/2016 99.90 100.00
(HOPKINS ROAD) OVER CANDY CREEK
DG00226 ER-2973 US 421 AND WOODY MILL ROAD MOTS LANDSCAPING & Ingram, PE, J. Paul $81,384.00 02/21/2015 03/09/2015 05/15/2017 100.00 100.00
LAWNS LLC
DG00226 R-2612A(L) US 421 AND WOODY MILL ROAD MOTS LANDSCAPING & Ingram, PE, J. Paul $81,384.00 02/21/2015 03/09/2015 05/15/2017 100.00 100.00
LAWNS LLC
DG00231 REPLACE BRIDGE #238 ON SR 1005 SMITH-ROWE, LLC Kirkman, PE, $1,396,792.10 06/25/2015 06/25/2015 06/15/2017 27.33 16.70
(ALAMANCE CHURCH ROAD) OVER LITTLE Christopher D
ALAMANCE CREEK
DG00235 ER-2973 SR 2085 (BRYAN BLVD) AND I-73 IN STANIEL KEY Ingram, PE, J. Paul $187,000.80 04/09/2015 05/04/2015 10/30/2016 0 36.48
GUILFORD COUNTY AND US 220 IN LANDSCAPING
ROCKINGHAM COUNTY
DG00238 SS-4907AV US 29/70/220 BETWEEN SR 3000 TRAFFIC CONTROL Lorenz, PE, Kris $56,000.00 06/21/2015 06/20/2016
(MCCONNELL ROAD) AND EAST SIDE SAFETY SERVICES, INC.
DRIVE (NON-SYSTEM)
18
Page 3 of 3
03/04/2016
North Carolina Department of Transportation
Active Projects Under Construction - Guilford Co.
Contract TIP Location Description Contractor Name Resident Engineer Contract Bid Availability Work Start Completion Progress Completion
Number Number Amount Date Date Date Schedule Percent
DG00245 ER-2973 VARIOUS INTERCHANGES ALONG I-40 STANIEL KEY Ingram, PE, J. Paul $282,985.15 06/08/2015 07/23/2015 Percent
04/30/2018 90.00 88.52
LANDSCAPING
DG00247 BD-5107Z REPLACE BRIDGE #245 ON SR 3088 DANE CONSTRUCTION, Smith, Brian V $397,647.00 07/06/2015 07/06/2015 04/19/2016 97.30 100.00
(THACKER DAIRY ROAD) OVER BEAVER INC.
CREEK
DG00253 INTERSECTION OF SR 3330 (SOUTHEAST P & S GRADING LLC Lorenz, PE, Kris $585,254.50 07/06/2015 07/10/2015 03/25/2016 99.99 100.00
SCHOOL ROAD) AND SR 3389 (WOODY
MILL ROAD)
DG00256 B-5736 REPLACE BRIDGE #38 ON NC 61 OVER KEYSTONE CONTRACTING Lorenz, PE, Kris $704,800.00 08/03/2015 09/04/2015 05/06/2016 99.60 80.69
BEAVER CREEK CO INC
DG00260 NC 22 FROM THE RANDOLPH COUNTY SHARPE BROTHERS A DIV Lorenz, PE, Kris $1,265,131.67 04/15/2016 11/15/2016
LINE TO NC 62 TO JOINT NORTH OF SR OF VECELLIO & GROGAN,
1486 (LEXINGTON AVENUE) INC.
DG00261 A PORTION OF SR 1001, SR 1008, SR 3163 APAC - ATLANTIC, INC. Ingram, PE, J. Paul $1,423,221.44 04/15/2016 11/15/2016
AND SR 2851 THOMPSON ARTHUR
DIVISION
DG00262 REPLACE BRIDGE NUMBER 338 ON SR SMITH-ROWE, LLC Lorenz, PE, Kris $562,359.38 02/01/2016 02/01/2016 03/01/2017 9.50 9.36
1859 (BOYLSTON ROAD) OVER WEST
FORK OF DEEP RIVER (TRIBUTARY 1)
DG00265 39 SECONDARY ROADS IN GUILFORD WHITEHURST PAVING CO Julian, Jason R $782,184.98 04/15/2016 08/31/2016
COUNTY AND ONE SECONDARY ROAD IN INC
ROCKINGHAM COUNTY
DG00274 ER-2971G NC 100 FROM STEELE ST. TO BETHEL ST. HOLLINS CONSTRUCTION Ingram, PE, J. Paul $122,953.50 04/01/2016 12/01/2016
AND NC 62 AT BARTLETT YANCEY HIGH SERVICES INC
SCHOOL
DG00275 CONVERT TWO-WAY STOP TO P & S GRADING LLC Ingram, PE, J. Paul $44,050.00 04/01/2016 12/31/2016
FOUR-WAT STOP AT THE INTERSECTION
OF NC 150 AND SR 2702
(OSCEOLA-OSSIPPEE ROAD)
19
DIVISION 8 - ACTIVE PROJECTS (HIGH POINT MPO)
TIP/WBS/ Completion
Description Let Date Status Cost Contractor Comments
Contract # Date
APAC-
Atlantic, INC.
Resurfacing SR 1567, SR 1545, SR 1597, SR 1794, SR 36% Resurfacing scheduled to
DH00175 7/30/15 6/24/16 $1,398,521 Thompson
1850 and SR 1864 Complete continue in Spring 2016.
Arthur
Division
Replace culverts #97 and # 31 on US 311 Business.
Culvert #97 over Sycamore Creek south of SR 1930 91% Country Boy
DH00171 6/9/15 5/11/16 $707,777 Work began 7/7/15
Bronzie Lawson Road and culvert #31 over Bob's Branch Complete Landscaping
north of SR 1527 Marlboro Church Road.
Work began 9/18/15. Work
Asphalt Surface Treatment: SR 1916, SR 2039, SR 1697, 51% Riley Paving
DH00172 6/9/15 Spring 2016 $867,269 scheduled to continue in April
SR 1685 and SR 1536 Complete INC
2016.
SR 1619 Prospect Street - Replace Bridge #136 over US 36% Lee
B-5114 6/16/15 3/15/17 $4,714,965 Work began 8/7/15
29/70/I-85 Business. Complete Construction
I-73 Pavement Rehabilitation from US 311 to 0.6 mi North
APAC-
of SR 1938 Hockett Dairy Road; 7.7 miles - Combined with I-
Atlantic, INC.
5737: I-73 from 1.3 miles north of SR 1504 Spero Road to Work has not Funding approved Jan 2016
I-5763 1/19/16 10/28/16 $ 8,978,000 Thompson
US 311, 2.2 miles) and Combined with W-5601AJ: I- started Start - Spring 2016
Arthur
73/74/US 220 from south of SR 2269 Vision Drive to south
Division
of SR 1712 Pineview Road.
DIVISION 8 - SPOT SAFETY PROJECTS (HIGH POINT MPO)
Project Description Board Approval Date Cost Status
Restriping pavement markings has been
NC 62 at SR 1547 Finch Farm Rd - Upgrade the traffic signal to Flashing delayed due to weather. Signal head
Yellow Arrow (FYA) and restripe the northbound left turn lane to improve the 9/3/2015 $75,000 adjustments to be coordinated with restriping
offset. pavement markings. Project completion
expected within a month.
DIVISION 8 - UPCOMING PROJECTS (HIGH POINT MPO)
TIP/WBS/
Description Let Date Comments Cost
Contract #
Contract awarded - 2/29/16
SR 1603 School Rd - Replace Bridge #84 over Muddy
17BP.8.R.79 Feb-16 Availability Date - 4/4/2016 $728,888
Creek
Completion Date - August 2016
I-85 South of SR 1009 to North of SR 1912 Lunar Drive in
Archdale. Pavement Rehabilitation. Scope of work should
include milling and filling of deteriorating asphalt paved Project let date delayed from Mar 2016 to
I-5738 Apr-16 $7,000,000
shouders, rehabilitation of ramps and rehabilitation of Apr 2016
concrete aprons around drainage structures. Project
combined with I-5821 and I-5789.
ROW is being acquired; Utilities to be
SR 1911 Ashland Street (Archdale) - Replace Bridge #416 relocated; Power is authorized to move;
17BP.8.R.76 Jun-18 TBD
over Dale Creek. Relocation of water lines to be
determined.
DIVISION 8 - AMENDED STIP PROJECT (HIGH POINT MPO)
Will discuss with SPOT and
SR 1577/ SR 1004 Archdale Rd from SR 1567 Robbins
Programming to revise cross section from
Country Rd to US 311 Main Street, widen to multilanes.
4 lane median divided w/ sidewalks and
U-3400 Segment A (FUNDED): From SR 1567 Robbins Country Rd FY 2022 $24,950,000
bike lanes to 3 lanes with sidewalks and
to Guilford Co Line. Segment B (UNFUNDED): From the
bike lanes as supported by HPMPO and
Randolph Co Line to SR 1993 Main Street.
City of Archdale.
20 High_Point_Urban_Area_MPO Div 8 Project Report March 2016
High Point Urban Area MPO
NCDOT Transportation Update
(Davidson County)
Tuesday, March 15, 2016
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects under Construction
Replace Bridge #27 on US 52/NC 8 over US 29/64/70/I- May 1, 2019 Availability date
B-3159 Oct. 20, 2015 (perm. vegetation established $10,164,621 J.T. Russell & Sons, Inc. Utility relocation work is underway
85 Bus. Loop in Lexington October 28, 2019)
April 1, 2016
June 15, 2016 Work start date April 6, 2015. Traffic is now on new structure in
Replace Bridge #38 on SR 1493 (Frye Bridge Rd) over (Perm. vegetation 91.2% Complete final traffic pattern. Only some minor grading work
B-4741 Dec. 16, 2014 $2,333,794 Dane Construction, Inc.
Muddy Creek in Davidson County established (20% ahead of schedule) remains.Road to remain open during construction,with new
Dec. 12, 2016) bridge being built next to existing.
June 15, 2016
(Perm. vegetation 99% Complete Only work on punchlist items remains. Minimal to no impact to
C-4901A NCRR/NS Mainline Bowers to Lake Railroad Roadbed June, 2013 $15,738,016 Blythe Construction, Inc.
established (8% ahead of schedule) vehicular traffic.
Oct. 28, 2016)
Contract Landscaping on I-85 from (SR 1224) Contractor began work on Nov. 3, 2015. Currently planting
I-2304AC/AD (L) Hardgrave Rd in Davidson Co. to (SR2120) Long Ferry Sept. 23, 2015 May 6, 2018 30% Complete $1,281,336 Staniel Key Landscaping trees and shrubs, and mulching plant beds. Selective clearing
Rd in Rowan Co. and landscape grading are complete.
Pavement Rehabilitation of 5.17 miles of I-85 from the
ramps N. of Old Hwy 64 to the concrete pavement south Availability date
I-5740 Feb. 24, 2016 August 31, 2016 $1,069,294 Blythe Construction, Inc. Setting up schedule for preconstruction meeting.
of SR 2010 (E. Holly Grove Rd), which includes milling, April 4, 2016
paving, and pavement markings.
Pavement Rehabilitation, Bridge Preservation, and March 15, 2016
Upgrade to Interstate Standards - US 29/52/70/I-85 Bus. (revised) 99.6% Complete DDRL Project - Contractor should have all pavement
R-4750 From I-85 to south of SR 1147 (Salisbury Rd) and September, 2013 (Perm. vegetation (schedule has been $7,571,155 J. T. Russell & Sons, Inc. markings and rumble strips complete by the end of March.
Bridges #43 & #225 over Swearing Creek on US established revised) Working on preliminary punchlist
29/52/70. June 4, 2016)
Grading, drainage, widening, paving, and pavement
Availability date
U-4742NC markings on SR 1508 (Hickory Tree Rd) and SR 1601 Feb. 24, 2016 September 30, 2016 $660,000 TBD Bids have been opened, awaiting documents for award
April 4, 2016
(Mendenhall Rd) in Davidson Co.
Replace Bridge #361 on SR 1837 (Bud Sink Rd) over June 3, 2016
BD-5109L Leonard Creek in Davidson County. Includes Grading, (perm. vegetation Work began Feb. 16, 2016, using an off-site detour. Work on
Dec. 9, 2015 20% Complete $378,498 TCB Builders, LLC
17BP.9.R.63 Drainage, Widening, Structure, Paving, and Pavement established replacing the bridge has begun
Markings. Dec. 31, 2016)
June 23, 2016
Replace Bridge #40 on SR 1298 / I-85 Service Rd (perm. vegetation 45.5% Complete Work began December 7, 2015. Road is closed with off-site
17.BP.9.R.3 October 28, 2015 $830,623 Smith-Rowe LLC
(Grimes Blvd) over Swearing Creek in Davidson County. established (on schedule) detour.
Dec. 9, 2016)
Design Build Project - Bridge #424 (E Center St) work began
on December 7, 2015 and projected will be completed by
Replace (4) bridges in Davidson Co., (1) in Forsyth Co.,
17BP.9.R.34 April, 2012 Oct. 20, 2016 97.1% Complete $12,585,775 Crowder Construction Co. August 22, 2016. Contractor has completed work on drill
(3) in Rowan Co., and (1) in Stokes Co.
shafts. Contractor is working on constructing end-bents, which
will follow by MSE Wall.
Permitting and Express Design Build Contract - Br. #258 over Swearing
DESIGN BUILD - Replace two (2) Bridges in Davidson
design work begun Creek on SR 1272, and Br. #410 over Leonard Creek on SR
17BP.9.R.61 Co., one (1) Bridge in Davie Co., three (3) Bridges in May 19, 2015 June 30, 2019 $10,642,621 Smith-Rowe, LLC
(Anticipate construction work 1844 in Davidson; (1) bridge in Davie; (2) bridges in Rowan;
Rowan Co., and four (4) Bridges in Stokes Co. to begin Summer, 2016) and (4) bridges in Stokes Co.
Permitting and Express Design Build Contract - Br. #86 over First Potts
Mountain Creek
DESIGN BUILD - Replace three (3) Bridges in Davidson design work begun Creek on SR 1158, Br. #95 over Leonard Creek on SR 1838,
17BP.9.R.62 May 19, 2015 September 1, 2018 $4,740,000 Contractors/SEPI
Co. and seven (7) Bridges in Rowan Co. with Culverts (Anticipate construction work and Br. #471 over Unnamed Creek on SR 2416 in Davidson
to begin Spring, 2016)
Engineering
Co. and (7) bridges in Rowan Co.
Milling and resurfacing of 3.8 miles of US 64 from RR Work scheduled to
2016CP.09.01. Division Let contract. Continuation of previous resurfacing
crossing near Decker Rd. to the end of concrete island Aug. 12, 2015 May 20, 2016 begin $1,035,588 J.T. Russel & Sons, Inc.
10291.1 map. Work scheduled to begin after March 15, 2016.
near Linda Pl., just W. of I-85. March 15, 2016
Contract Resurfacing of 2 sections of NC 8, 1 section of
9CR.10291.160, May 25, 2016 Work began August 3, 2015. Work scheduled to resume in
US 64, 1 section of NC 68 and 8 sections of Secondary May 19, 2015 26% Complete $3,755,440 J.T. Russell & Sons, Inc.
9CR.20291.160 (revised) after March 15, 2016.
routes (20.54 miles) in Davidson County.
Davidson County Asphalt Surface Treatment (AST) Preconstruction meeting held Aug. 19, 2015. Work began
9SP.20295.4 Retreatment (58.79 miles) of various Secondary routes June 10, 2015 May 25, 2016 50% Complete $1,455,996 Blythe Construction, Inc. Sept. 22, 2015. Seasonal limitations in force currently, plan to
in Davidson Co. start back in late March, weather permitting.
21
High Point Urban Area MPO/ Piedmont Triad RPO
NCDOT Transportation Update
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects under Development
Bridge Preservation project - Plans are currently being
Bridge Preservation – Bridge #31 on NC 8, Bridges #55 revised. Bridge #55 will be dropped from this contract and
41665.6A TBD TBD $1,600,000 TBD
& 82 on NC 47 in Davidson County completed under another project at a later date. Finalizing
structure plans.
Replace Bridge #46 on SR 1485 (Hampton Rd) over ROW
B-5165 June, 2017 TBD $1,800,000 TBD *Schedule based on Approved 2016-2025 STIP
Muddy Creek FY 2016
Replace Bridge #115 on SR 1711 (Gumtree Rd) over ROW
B-5765 FY 2021 TBD $1,700,000 TBD *Schedule based on Approved 2016-2025 STIP
WSSB RR FY 2019
Replace Bridge #25 on SR 3346 (S. Main St) over ROW
B-5773 FY 2025 TBD $3,250,000 TBD *Schedule based on Approved 2016-2025 STIP
WSSB RR in Lexington FY 2023
Replace Bridge #99 on SR 1810 (Clodfelter Rd) over ROW *Schedule based on Approved 2016-2025 STIP - Project
B-5774 Feb., 2020 TBD $1,200,000 TBD
Brushy Creek March, 2019 accelerated due to additional revenue (HB 97)
Replace Bridge #100 on SR 1810 (Clodfelter Rd) over ROW *Schedule based on Approved 2016-2025 STIP - Project
B-5776 Feb., 2020 TBD $1,800,000 TBD
Abbott's Creek March, 2019 accelerated due to additional revenue (HB 97)
ROW
B-5777 Replace Bridge #58 on NC 109 over US 64 FY 2022 TBD $1,850,000 TBD *Schedule based on Approved 2016-2025 STIP
FY 2021
Replace Bridge #118 on US 29NB/64EB/70EB/I-85 Bus ROW *Schedule based on Approved 2016-2025 STIP - Coordinate
B-5779 FY 2025 TBD $4,061,000 TBD
NB over SR 3346 (N Main St) in Lexington FY 2024 with B-5785
ROW Acquisition in
B-5780 Replace Bridge #17 on NC 47 over Swearing Creek Dec., 2016 TBD $1,400,000 TBD Structure and Geotech design in progress
progress
Replace Bridge #164 and Bridge #168 on US 29/70/I-85 ROW
B-5783 FY 2025 TBD $5,778,000 TBD *Schedule based on Approved 2016-2025 STIP
Bus over NSRR FY 2024
Replace Bridge #121 and Bridge #122 on US 29/70/I-85 ROW *Schedule based on Approved 2016-2025 STIP - Coordinate
B-5785 FY 2025 TBD $4,000,000 TBD
Bus over Leonard Creek FY 2024 with B-5779
ROW
B-5787 Replace Bridge #29 on NC 49 over NC 109 FY 2024 TBD $2,000,000 TBD *Schedule based on Approved 2016-2025 STIP
FY 2023
Extend Sidewalks on SR 3346 (S Main St) and provide Planning/Design/
C-5216 wide paved shoulders on Anna Lewis Dr and Emergency FY 2016 TBD Right of Way in $601,000 TBD *Schedule based on Approved 2016-2025 STIP
Dr. in Lexington progress
Provide wide paved shoulders and construct sidewalks Planning/Design/
C-5217 on Cornelia St and Hillsdie Dr. Bike and Pedestrian FY 2016 TBD Right of Way in $190,000 TBD *Schedule based on Approved 2016-2025 STIP
Improvements on Mize and Biesecker Rds. progress
Pavement Rehabilitation of I-85 from SR 2025 (Squire Planning and Design
I-5793 FY 2018 TBD $6,386,000 TBD *Schedule based on Approved 2016-2025 STIP
Bowers Rd) to 0.3 mi N. of NC 109 in Thomasville in Progress
I-40/US 311 at NC 109 (Thomasville Rd)/Clemmonsville
Rd in Winston-Salem. Convert Half Split Diamond
Interchange at NC 109 to Full Split Diamond ROW
I-5880 FY 2021 TBD $2,875,000 TBD Schedule subject to Approved 2016-2025 STIP
Interchange, and remove Half Split Diamond FY 2020
Interchange and Connector Roads at Clemmonsville
Rd.
NC 109 from SR 1756 (Old Greensboro Rd) in Davidson Planning and Design
R-2568C *Post Year TBD $141,000,000 TBD Project to be re-evaluated in during Prioritization 4.0
County to I-40/US 311 in Forsyth County. in Progress
Convert at grade intersection to Interchange on US ROW
R-5737 FY 2021 TBD $15,000,000 TBD *Schedule based on Approved 2016-2025 STIP
29/70/I-85 Bus at SR 1798 (Old Greensboro Rd) FY 2019
Widen NC 8 (Winston Rd) to multi-lanes from 9th St to Planning and Design
U-5757 FY 2019 TBD $1,254,000 TBD *Schedule based on Approved 2016-2025 STIP
SR 1408 (Biesecker Rd) in Lexington in Progress
Widen SR 1508 (Hickory Tree Rd) from US 52/NC ROW
U-5786 FY 2023 TBD $13,794,000 TBD *Schedule based on Approved 2016-2025 STIP
8/Future I-285 to NC 150 FY 2021
Widen NC 150 to multilanes from SR 1493 (Frye Bridge ROW & Utilities *Schedule based on Approved 2016-2025 STIP - New
U-5902B Post Year TBD $33,150,000 TBD
Rd) to Forsyth County Line FY 2024 project programmed due to additional revenue (HB 97)
22 Page 2 Tuesday, March 15, 2016
High Point Urban Area MPO/ Piedmont Triad RPO
NCDOT Transportation Update
Construction
T.I.P. No. Description Let Date Completion Date Status Contractor Comments
Cost
Projects Under Development
Safety Improvements to median crossovers, etc., on I-85
ROW Division Let. Public meeting held Jan. 14, 2016 at Davidson
W-5601CF Business from SR1797 (Evans Rd) to SR 1963 (Moose January , 2017 TBD $600,000 TBD
June 2016 County Community College.
Lodge Rd) in Davidson Co.
Bridge Painting on Bridges #136, 150 in Davidson;#'s
Funding issues. There will be plan revisions and a new letting
17BP.9.P.3 29,32,85,86 in Davie; #'s 53,54,55,78,115,185,297,322 TBD TBD $5,000,000 TBD
date - to be determined.
in Forsyth; and #94 in Rowan County.
Letting date delayed due to funding and other priorities.
Replace Bridge #271 on SR 2501 (S. Main St. Ext./ Lick ROW Acquisition
17.BP.9.R.10 June, 2016 TBD $1,000,000 TBD Coordinating with ALCOA to begin construction. Utility
Creek Ch. Rd) over Lick Creek in Davidson County. in progress.
relocation in progress
Replace Bridge #221 on SR 2324 (Harris Rd) over Lick Plan Preparation 75% Complete; Let date is funding
17.BP.9.R.15 TBD TBD $525,000 TBD
Creek in Davidson County. dependent
Replace Bridge #459 on SR 2160 (Smith Rd) over an
17BP.9.R.33 Nov., 2016 TBD $250,000 TBD Letting date delayed due to funding and other priorities.
unnamed creek in Davidson County.
Replace Bridge #63 on SR 1481 (Welcome-Arcadia Rd) This project will not be pursued at this time. Will be deleted
17BP.9.R.57 TBD TBD $443,000 TBD
over Reedy Creek in Davidson County. from program due to funding rules and bridge condition.
2017.CPT.09.01.1
0291.1 Contract Resurfacing of various sections of Primary and Availability date
April, 2016 October 30, 2016 $3,100,000 TBD Centrally let
2017.CPT.09.01.2 Secondary routes in Davidson County June, 2016
0291.1
Completed Projects
Davidson County Asphalt Surface Treatment (Chip Seal)
9SP.20295.3 April 8, 2015 August 28, 2015 100% Complete $1,555,785 APAC Atlantic, Inc. One year warranty in effect.
Contract
Aug. 15, 2015
Replace Bridge #11 on SR 1155 (Swicegood Rd) over (perm. vegetation
BD-5109V Mar. 11, 2015 100% Complete $572,994 Dane Construction, Inc. Project accepted.
First Potts Creek in Davidson County. established
Dec. 30, 2015)
April 30, 2015
Grade separation on SR 2024 (Upper Lake Rd) over (perm. vegetation DH Griffin Construction
C-4901B March, 2013 100% Complete $4,203,035 ARRA Rail Project - Complete and accepted
Hamby Creek / NCRR established Co., LLC
Nov. 11, 2015)
23 Page 3 Tuesday, March 15, 2016
Triad Air Awareness March, 2016
Air Quality Notes:
Clean air grant
o EPA announced a $26 million funding opportunity for clean
diesel projects
o Qualifying projects need to achieve significant reduction in
diesel emissions in terms of tons of pollution produced by
diesel engines and diesel emissions exposure from fleets
operating in poor air quality areas.
o More Info: http://www.epa.gov/cleandiesel/clean-diesel-
national-grants
Commuter Dash Fun Run
o Triad Air Awareness and Piedmont Authority for Regional
Transportation are partnering to bring you the Commuter
Dash Fun Fun.
o This event at Triad Park will kick-off our Air Quality Season
and help bring attention to clean air transportation options.
o For more information about participation and support,
visit: http://triadcommutechallenge.com/
Air Quality Report:
“Ozone season” begins April 1st
National Air Quality Awareness Week is May 2nd – 6th .The following
topics will be highlighted
o Citizen Science
o Asthma and Air Quality
o Air Quality Around the World
o Air Quality Trends
o Please refer to the AQAW web site for more information
during AQAW. www.airnow.gov/airaware Local
governments are encouraged to participate.
24
Piedmont Authority for Regional Transportation Updates
for the High Point MPO TCC/TAC
March 2016
PART Express Updates
Route 9 Update: Route 9 Business 85 ridership has
doubled since January 11th when the new route
design was implemented.
Route 17/18 Changes Coming Soon: Upcoming
changes for Route 17/18 to serve the VA Hospital in
Kernersville, more information to come!
Connecting Our Communities
Shown Above: PART Express Ridership was 34,227 for January PART recently developed a new 30-second
2016 with a projection of 480,672 for FY 2016. commercial that will air this Spring on WFMY. The
commercial is also available on PART's YouTube
Channel www.youtube.com/partnc
Commuter Dash 5K Run/Walk
Join PART for the Commuter Dash 5K Run/Walk being held
on April 16th at Triad Park in Kernersville. Family friendly
with live music, vendors and food. Guest speaker will be
Dawn Morgan, Town of Kernersville Mayor. Registration is
FREE! www.TriadCommuteChallenge.com
To learn more about PART’s programs and projects, please
visit www.partnc.org
Stay Connected with PART on Social Media!
Page 1 of 2
25
Page 2 of 2
On Board Survey Planned for March Coble Transportation Center
Construction Update
PART is undergoing an On-board Transit Survey Project
which will combine the survey process with customer An update on the Construction of the Howard Coble
satisfaction survey. A process has been developed to Intermodal Transportation Center being constructed in
conduct On-board Transit Survey in-house. Surveying Greensboro. Visit PART YouTube to view
will begin in March. www.youtube.com/partnc
26