Joint Purchasing Board
Regular MeetingLafayette, IN · March 9, 2017
Minutes
JOINT PURCHASING BOARD
March 9, 2017
The Joint Purchasing Board met on Thursday, March 9, 2017 at 4:00 p.m. in the Board of Public Works and
Safety room, 20 North 6th Street, Lafayette City Hall. Present were: Mayor Roswarski, Cindy Murray, Robert
Plantenga and Tom Murtaugh.
Also present were: Rick Morrissey, City of Lafayette Purchasing Manager
Mr. Murtaugh called the meeting to order.
APPROVAL OF THE MINUTES
Mr. Plantenga moved for approval of the minutes from the December 16, 2016 meeting. Mrs. Murray seconded.
Motion carried.
BID OPENING
2017 Asphalt and Bituminous-Coated Aggregate
CENTRAL PAVING, INC.
Logansport, IN
Joint Purchasing Board
March 9, 2017
Page 2
RIETH-RILEY CONSTRUCTION COMPANY
Lafayette, IN
1. PLANT MIXED - HOT MIX ASPHALT MATERIAL*: 100,000 TONS
(A). FOB PLANT
1. HMA BASE 25 mm $ 33.60 per ton
2. HMA INTERMEDIATE 19 mm $ 34.70 per ton
3. HMA INTERMEDIATE 12.5 mm $ 35.80 per ton
4. HMA INTERMEDIATE 9.5 mm $ 36.75 per ton
5. HMA SURFACE 12.5 mm $ 36.35 per ton
6. HMA SURFACE 9.5 mm $ 36.80 per ton
* ALL MATERIAL TO BE HMA TYPE B WITH PG BINDER 64-22
(B). In place as specified with bidder furnishing all labor, traffic control and equipment. CITY / COUNTY to
furnish trucking. Unit prices listed below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) $ 30.50 per ton
2. TONS PER DAY (201-500) $ 17.50 per ton
3. TONS PER DAY (501-1100) $ 7.75 per ton
4. TONS PER DAY (1101 or MORE) $ 5.25 per ton
(C). In place as specified with bidder furnishing all labor, trucking, traffic control and equipment. Unit prices listed
below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) $ 43.25 per ton
2. TONS PER DAY (201-500) $ 26.25 per ton
3. TONS PER DAY (501-1100) $ 15.20 per ton
4. TONS PER DAY (1101 or MORE) $ 10.15 per ton
BID PRICES ABOVE APPLY TO THE CITY OF LAFAYETTE ONLY.
Prices for the Southwest and Southeast Quadrants (COUNTY ONLY).
SOUTHWEST SOUTHEAST
(per ton) (per ton)
5. TONS PER DAY (0-200) a) $ 46.75 b) $ 46.75
6. TONS PER DAY (201-500) a) $ 30.25 b) $ 29.00
7. TONS PER DAY (501-1100) a) $ 17.00 b) $ 16.00
8. TONS PER DAY (1101 or MORE) a) $ 13.00 b) $ 12.00
Prices for the Northwest and Northeast Quadrants (COUNTY ONLY).
NORTHWEST NORTHEAST
(per ton) (per ton)
9. TONS PER DAY (0-200) a) $ 46.75 b) $ 46.75
10. TONS PER DAY (201-500) a) $ 30.25 b) $ 29.00
11. TONS PER DAY (501-1100) a) $ 17.00 b) $ 15.00
12. TONS PER DAY (1101 or MORE) a) $ 13.00 b) $ 11.30
(D). Patching Material less than full truck load quantities, 2 Ton minimum load.
1. HMA BASE 25 mm $ 38.00 per ton
2. HMA INTERMEDIATE 19 mm $ 39.00 per ton
3. HMA INTERMEDIATE 12.5 mm $ 39.50 per ton
4. HMA INTERMEDIATE 9.5 mm $ 40.50 per ton
5. HMA SURFACE 12.5 mm $ 40.00 per ton
6. HMA SURFACE 9.5 mm $ 40.50 per ton
2. LIQUID ASPHALT – BITUMINOUS MATERIALS: 240,000 GALLONS*
A. FOB LAFAYETTE
Joint Purchasing Board
March 9, 2017
Page 3
1. AE-90, SS-1H $625.00 per ton
2. HFRS – 2 (High Float) No Bid per ton
3. AE – P (Prime) No Bid per ton
4. SS-1H (Contractor to Furnish and apply City only) $995.00 per ton
5. APME No Bid per ton
B. Contractor to furnish and apply liquid asphalt with approved distributors. County to furnish, haul, apply stone
chips and roll.
1. AE – 90 NO BID per ton
2. HFRS – 2 (High Float) NO BID per ton
3. AE – SP NO BID per ton
4. SS-1H $ 900.00 per ton
5. AE – P (Prime) NO BID per ton
C. Contractor to furnish and apply liquid asphalt with approved distributors, apply stone chips with a mechanical self-
propelled chip spreader and roll with an approved rubber tired roller. County to furnish and haul chips to spreader.
1. AE - 90 NO BID per ton
2. HFRS – 2 (High Float) NO BID per ton
D. Contractor to furnish and apply liquid asphalt with approved distributors and apply stone chips with a mechanical
self-propelled chip spreader. County to furnish and haul chips to spreader and roll.
1. AE - 90 NO BID per ton
2. HFRS – 2 (High Float) NO BID per ton
* Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
AE – P – 250 Gallons / Ton
3. DUST CONTROL – BITUMINOUS MATERIALS: 200,000 GALLONS*
A. FOB – County Storage
1. DUSTLAY NO BID per ton
B. Vendor to furnish one 10,000 gallon portable storage tank.
1. DUSTLAY NO BID per ton
C. Vendor to deliver to specified road site and County to pump off material
1. DUSTLAY NO BID per ton
*Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
4. COLD MIX – FOB PLANT
1. UPM High Performance (2 ton minimum) $125.00 per ton
5. ASPHALT MILLING
Asphalt Milling (up to 2” depth, single mobilization) $2.00 Per Square Yard
Mobilization for asphalt milling, after the first mobilization $1,000.00 Lump Sum, Each
6. 4.75 mm STEEL SLAG SAND SURFACE – FOB PLANT
4.75 mm Steel Slag Sand $65.00 per ton
Joint Purchasing Board
March 9, 2017
Page 4
MARATHON PETROLEUM COMPANY, LLC
Indianapolis, IN
1. PLANT MIXED - HOT MIX ASPHALT MATERIAL*: 55,000 TONS
A. FOB PLANT
1. HMA BASE 25 mm NO BID per ton
2. HMA INTERMEDIATE 19 mm NO BID per ton
3. HMA INTERMEDIATE 12.5 mm NO BID per ton
4. HMA INTERMEDIATE 9.5 mm NO BID per ton
5. HMA SURFACE 12.5 mm NO BID per ton
6. HMA SURFACE 9.5 mm NO BID per ton
* ALL MATERIAL TO BE HMA TYPE B WITH PG BINDER 64-22
B. In place as specified with bidder furnishing all labor, traffic control and equipment. CITY / COUNTY to furnish
trucking. Unit prices listed below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) NO BID per ton
2. TONS PER DAY (201-500) NO BID per ton
3. TONS PER DAY (501-1100) NO BID per ton
4. TONS PER DAY (1101 or MORE) NO BID per ton
C. In place as specified with bidder furnishing all labor, trucking, traffic control and equipment. Unit prices listed
below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) NO BID per ton
2. TONS PER DAY (201-500) NO BID per ton
3. TONS PER DAY (501-1100) NO BID per ton
4. TONS PER DAY (1101 or MORE) NO BID per ton
BID PRICES ABOVE APPLY TO THE CITY OF LAFAYETTE ONLY.
Prices for the Southwest and Southeast Quadrants (COUNTY ONLY).
SOUTHWEST SOUTHEAST
(per ton) (per ton)
5. TONS PER DAY (0-200) a) NO BID b) No Bid
6. TONS PER DAY (201-500) a) NO BID b) No Bid
7. TONS PER DAY (501-1100) a) NO BID b) No Bid
8. TONS PER DAY (1101 or MORE) a) NO BID b) No Bid
Prices for the Northwest and Northeast Quadrants (COUNTY ONLY).
NORTHWEST NORTHEAST
(per ton) (per ton)
9. TONS PER DAY (0-200) a) No Bid b) No Bid
10. TONS PER DAY (201-500) a) No Bid b) No Bid
11. TONS PER DAY (501-1100) a) No Bid b) No Bid
12. TONS PER DAY (1101 or MORE) a) No Bid b) No Bid
D. Winter Mix Patching Material
CM-300HP No Bid per ton
E. Patching Material less than full truck load quantities, 2 Ton minimum load.
1. HMA BASE 25 mm No Bid per ton
2. HMA INTERMEDIATE 19 mm No Bid per ton
3. HMA INTERMEDIATE 12.5 mm No Bid per ton
4. HMA INTERMEDIATE 9.5 mm No Bid per ton
5. HMA SURFACE 12.5 mm No Bid per ton
6. HMA SURFACE 9.5 mm No Bid per ton
2. LIQUID ASPHALT – BITUMINOUS MATERIALS: 240,000 GALLONS*
(A). FOB LAFAYETTE
Joint Purchasing Board
March 9, 2017
Page 5
1. AE-90, SS-1H $362.40 per ton
2. HFRS – 2 (High Float) No Bid per ton
3. AE – P (Prime) No Bid per ton
4. SS-1H (Contractor to Furnish and apply City only) No Bid per ton
5. APME No Bid per ton
(B). Contractor to furnish and apply liquid asphalt with approved distributors. County to furnish, haul, apply stone
chips and roll.
1. AE – 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
3. AE – SP No Bid per ton
4. SS-1H No Bid per ton
5. AE – P (Prime) No Bid per ton
(C). Contractor to furnish and apply liquid asphalt with approved distributors, apply stone chips with a mechanical
self-propelled chip spreader and roll with an approved rubber tired roller. County to furnish and haul chips to
spreader.
1. AE - 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
(D). Contractor to furnish and apply liquid asphalt with approved distributors and apply stone chips with a
mechanical self-propelled chip spreader. County to furnish and haul chips to spreader and roll.
1. AE - 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
* Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
AE – P – 250 Gallons / Ton
3. DUST CONTROL – BITUMINOUS MATERIALS: 200,000 GALLONS*
A. FOB – County Storage
1. DUSTLAY No Bid per ton
B. Vendor to furnish one 10,000 gallon portable storage tank.
1. DUSTLAY No Bid per ton
C. Vendor to deliver to specified road site and County to pump off material
1. DUSTLAY No Bid per ton
*Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
ASPHALT MATERIALS, INC.
Indianapolis, IN
1. PLANT MIXED - HOT MIX ASPHALT MATERIAL*: 55,000 TONS
A. FOB PLANT
1. HMA BASE 25 mm NO BID per ton
2. HMA INTERMEDIATE 19 mm NO BID per ton
3. HMA INTERMEDIATE 12.5 mm NO BID per ton
4. HMA INTERMEDIATE 9.5 mm NO BID per ton
5. HMA SURFACE 12.5 mm NO BID per ton
6. HMA SURFACE 9.5 mm NO BID per ton
* ALL MATERIAL TO BE HMA TYPE B WITH PG BINDER 64-22
B. In place as specified with bidder furnishing all labor, traffic control and equipment. CITY / COUNTY to furnish
trucking. Unit prices listed below are to be added to the material prices listed in item (A).
Joint Purchasing Board
March 9, 2017
Page 6
1. TONS PER DAY (0-200) NO BID per ton
2. TONS PER DAY (201-500) NO BID per ton
3. TONS PER DAY (501-1100) NO BID per ton
4. TONS PER DAY (1101 or MORE) NO BID per ton
C. In place as specified with bidder furnishing all labor, trucking, traffic control and equipment. Unit prices listed
below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) NO BID per ton
2. TONS PER DAY (201-500) NO BID per ton
3. TONS PER DAY (501-1100) NO BID per ton
4. TONS PER DAY (1101 or MORE) NO BID per ton
BID PRICES ABOVE APPLY TO THE CITY OF LAFAYETTE ONLY.
Prices for the Southwest and Southeast Quadrants (COUNTY ONLY).
SOUTHWEST SOUTHEAST
(per ton) (per ton)
5. TONS PER DAY (0-200) a) NO BID b) No Bid
6. TONS PER DAY (201-500) a) NO BID b) No Bid
7. TONS PER DAY (501-1100) a) NO BID b) No Bid
8. TONS PER DAY (1101 or MORE) a) NO BID b) No Bid
Prices for the Northwest and Northeast Quadrants (COUNTY ONLY).
NORTHWEST NORTHEAST
(per ton) (per ton)
9. TONS PER DAY (0-200) a) No Bid b) No Bid
10. TONS PER DAY (201-500) a) No Bid b) No Bid
11. TONS PER DAY (501-1100) a) No Bid b) No Bid
12. TONS PER DAY (1101 or MORE) a) No Bid b) No Bid
D. Winter Mix Patching Material
CM-300HP No Bid per ton
E. Patching Material less than full truck load quantities, 2 Ton minimum load.
1. HMA BASE 25 mm No Bid per ton
2. HMA INTERMEDIATE 19 mm No Bid per ton
3. HMA INTERMEDIATE 12.5 mm No Bid per ton
4. HMA INTERMEDIATE 9.5 mm No Bid per ton
5. HMA SURFACE 12.5 mm No Bid per ton
6. HMA SURFACE 9.5 mm No Bid per ton
2. LIQUID ASPHALT – BITUMINOUS MATERIALS: 240,000 GALLONS*
A. FOB LAFAYETTE
1. AE-90, SS-1H $ 365.57 per ton
2. HFRS – 2 (High Float) $ 377.57 per ton
3. AE – P (Prime) No Bid per ton
4. SS-1H (Contractor to Furnish and apply City only) No Bid per ton
5. APME $365.57 per ton
B. Contractor to furnish and apply liquid asphalt with approved distributors. County to furnish, haul, apply stone
chips and roll.
1. AE – 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
3. AE – SP No Bid per ton
4. SS-1H No Bid per ton
5. AE – P (Prime) No Bid per ton
Joint Purchasing Board
March 9, 2017
Page 7
C. Contractor to furnish and apply liquid asphalt with approved distributors, apply stone chips with a mechanical self-
propelled chip spreader and roll with an approved rubber tired roller. County to furnish and haul chips to spreader.
1. AE - 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
D. Contractor to furnish and apply liquid asphalt with approved distributors and apply stone chips with a mechanical
self-propelled chip spreader. County to furnish and haul chips to spreader and roll.
1. AE - 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
* Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
AE – P – 250 Gallons / Ton
3. DUST CONTROL – BITUMINOUS MATERIALS: 200,000 GALLONS*
A. FOB – County Storage
1. DUSTLAY $317.57 per ton
B. Vendor to furnish one 10,000 gallon portable storage tank.
1. DUSTLAY $ 319.97 per ton
C. Vendor to deliver to specified road site and County to pump off material
1. DUSTLAY $ 324.77 per ton
*Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
Joint Purchasing Board
March 9, 2017
Page 8
MILESTONE CONTRACTORS, LP.
Lafayette, IN
1. PLANT MIXED - HOT MIX ASPHALT MATERIAL*: 100,000 TONS
(A). FOB PLANT
1. HMA BASE 25 mm $ 39.55 per ton
2. HMA INTERMEDIATE 19 mm $ 41.50 per ton
3. HMA INTERMEDIATE 12.5 mm $ 43.75 per ton
4. HMA INTERMEDIATE 9.5 mm $ 44.95 per ton
5. HMA SURFACE 12.5 mm $ 44.35 per ton
6. HMA SURFACE 9.5 mm $ 44.95 per ton
* ALL MATERIAL TO BE HMA TYPE B WITH PG BINDER 64-22
(B). In place as specified with bidder furnishing all labor, traffic control and equipment. CITY / COUNTY to
furnish trucking. Unit prices listed below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) $ 26.50 per ton
2. TONS PER DAY (201-500) $ 14.00 per ton
3. TONS PER DAY (501-1100) $ 4.00 per ton
4. TONS PER DAY (1101 or MORE) $ 2.00 per ton
(C). In place as specified with bidder furnishing all labor, trucking, traffic control and equipment. Unit prices listed
below are to be added to the material prices listed in item (A).
1. TONS PER DAY (0-200) $ 46.00 per ton
2. TONS PER DAY (201-500) $ 20.15 per ton
3. TONS PER DAY (501-1100) $ 6.50 per ton
4. TONS PER DAY (1101 or MORE) $ 5.00 per ton
BID PRICES ABOVE APPLY TO THE CITY OF LAFAYETTE ONLY.
Prices for the Southwest and Southeast Quadrants (COUNTY ONLY).
SOUTHWEST SOUTHEAST
(per ton) (per ton)
5. TONS PER DAY (0-200) a) $ 49.00 b) $ 44.00
6. TONS PER DAY (201-500) a) $ 23.20 b) $ 22.00
7. TONS PER DAY (501-1100) a) $ 9.15 b) $ 7.00
8. TONS PER DAY (1101 or MORE) a) $ 6.05 b) $ 4.50
Prices for the Northwest and Northeast Quadrants (COUNTY ONLY).
NORTHWEST NORTHEAST
(per ton) (per ton)
9. TONS PER DAY (0-200) a) $ 46.00 b) $ 45.00
10. TONS PER DAY (201-500) a) $ 21.00 b) $ 20.00
11. TONS PER DAY (501-1100) a) $ 7.35 b) $ 6.50
12. TONS PER DAY (1101 or MORE) a) $ 4.50 b) $ 3.75
(D). Patching Material less than full truck load quantities, 2 Ton minimum load.
1. HMA BASE 25 mm $ 39.55 per ton
2. HMA INTERMEDIATE 19 mm $ 41.50 per ton
3. HMA INTERMEDIATE 12.5 mm $ 43.75 per ton
4. HMA INTERMEDIATE 9.5 mm $ 44.95 per ton
5. HMA SURFACE 12.5 mm $ 44.35 per ton
6. HMA SURFACE 9.5 mm $ 44.95 per ton
2. LIQUID ASPHALT – BITUMINOUS MATERIALS: 240,000 GALLONS*
A. FOB LAFAYETTE
Joint Purchasing Board
March 9, 2017
Page 9
1. AE-90, SS-1H No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
3. AE – P (Prime) No Bid per ton
4. SS-1H (Contractor to Furnish and apply City only) $995.00 per ton
5. APME No Bid per ton
B. Contractor to furnish and apply liquid asphalt with approved distributors. County to furnish, haul, apply stone
chips and roll.
1. AE – 90 No Bid per ton
2. HFRS – 2 (High Float) No Bid per ton
3. AE – SP No Bid per ton
4. SS-1H $ 995.00 per ton
5. AE – P (Prime) No Bid per ton
C. Contractor to furnish and apply liquid asphalt with approved distributors, apply stone chips with a mechanical self-
propelled chip spreader and roll with an approved rubber tired roller. County to furnish and haul chips to spreader.
1. AE - 90 $ 805.00 per ton
2. HFRS – 2 (High Float) $ 820.00 per ton
D. Contractor to furnish and apply liquid asphalt with approved distributors and apply stone chips with a mechanical
self-propelled chip spreader. County to furnish and haul chips to spreader and roll.
1. AE - 90 $ 790.00 per ton
2. HFRS – 2 (High Float) $ 805.00 per ton
* Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
AE – P – 250 Gallons / Ton
3. DUST CONTROL – BITUMINOUS MATERIALS: 200,000 GALLONS*
A. FOB – County Storage
1. DUSTLAY NO BID per ton
B. Vendor to furnish one 10,000 gallon portable storage tank.
1. DUSTLAY NO BID per ton
C. Vendor to deliver to specified road site and County to pump off material
1. DUSTLAY NO BID per ton
*Conversion from gallons to ton (All prices quoted in tons):
AE Grade – 240 Gallons / Ton
4. COLD MIX – FOB PLANT
1. CM-300 HP $125.00 per ton
2. SMP Patching Material NO BID per ton
5. ASPHALT MILLING
Asphalt Milling (up to 2” depth, single mobilization) $2.00 Per Square Yard
Mobilization for asphalt milling, after the first mobilization $2,500.00 Lump Sum, Each
6. 4.75 mm STEEL SLAG SAND SURFACE – FOB PLANT
4.75 mm Steel Slag Sand $60.00 per ton
Joint Purchasing Board
March 9, 2017
Page 10
Mrs. Murray moved to take the bids under advisement for further review. Mr. Roswarski seconded. Motion
Carried.
PUBLIC COMMENT
There was none.
With no further business to come before the Board, Mr. Roswarski moved to adjourn. Mrs. Murray seconded.
Motion carried.
Time: 4:05 p.m.
JOINT PURCHASING BOARD
Tom Murtaugh s/s
Vice President
Minutes written by: Mindy Miller 1st Deputy Clerk, City of Lafayette.
An audio recording of this meeting is available in the Lafayette City Clerk’s Office or online at
http://www.lafayette.in.gov/agendacenter.
Get email alerts for Lafayette
A daily email when new agendas and minutes are posted.