Public Works & WWTP Committee
Regular MeetingLansdale, PA · April 3, 2024
Minutes
Borough of Lansdale
Public Works Committee Minutes
Meeting of April 3, 2024
Members Present Members Absent
BJ Breish, Chairman
Rich DiGregorio, Councilman (arrived late)
Rachel Bollens, Councilwoman
Greg Rapp, WWTP Superintendent
Jason Van Dame, Code Manager
Tyler Williams, RV Engineers
Mark Bickerton, Pennoni Associates
Minutes from the March 6th Public Works Committee were approved by a vote of 3-0.
1. Public Works Action Items
1.1. East Main Street Streetscape Project - The committee voted to put forth a motion to full Council to award the contract
to Scott Contractors, Inc. in the amount of $3,199,280.75. Tyler also presented two proposals for inspection services for
this project. The committee recommended putting forth a motion to accept one of the inspection services’ proposals.
pending determination of the full-time or part time requirement.
2. WWTP Action Items
2.1. Chemical Feed Automation Project - Change order #3 is for granting a time extension that allows a substantial completion
date of June 12, 2024, and a final completion date to July 12, 2024. There are no costs associated with change order #3.
The committee voted to put forth a motion to full council for approval.
2.2. Whites Road Pumps Station Upgrade Project – The committee voted to post-approve the Environmental Engineering and
Management Associates proposal in the amount $7,500.00. This proposal is for the additional engineering services that
are associated with mold remediation; the mold was discovered during upgrade. The costs associated with the proposal
will be covered by the Merck Increase in Capacity Agreement. They also voted to approve Change Order #2 in the amount
of $88,765.00 for the work associated with remediation of the mold and the repair of the areas impacted by the conditions.
The costs associated with the proposal will be covered by the Merck Increase in Capacity Agreement. Both items will be
sent to full council for their approval.
3. Public Comment – Resident asked for a brief overview of East Main Streetscape Project.
4. Public Works Update
3.1. Ridge Street Outfall Replacement Project – This project is currently out for bid with bids being due on 4/25/24.
3.2. Cherry Street Outfall Replacement Project – Reamstown will begin mobilizing on April 15th.
3.3. Norway Drive Storm Sewer Repair – Project is currently out for bid with bids being due 4/10/24 and the committee
voted to put forth a motion to full council to award this contract pending engineer recommendation within budgeted
scope. Twenty-five replacement trees were included in the bid specifications for this project.
5. WWTP Update
4.1. Aeration Upgrade Project – Mr. Rapp confirmed the LSA grant may be used for the match requirement of the H20 grant.
Project scheduled to be going out to be bid on Monday.
4.2. Ridge Street Pump Station Electrical Upgrades – Payment #2 in the amount of $27,740.00 was made to the contractor.
Majority of equipment has been installed and working to get it connected to SCADA.
Borough of Lansdale
Public Works Committee Meeting
Meeting of April 3, 2024
Continued
4.3. WWTP Chemical Feed Upgrades – Payment #2 in the amount of $8,550.00 was made to the contractor.
4.4. Mr. Rapp gave a short update on process changes and projects. Will be putting out an RFP for hydraulics
shortly. He also mentioned this was the fourth wettest March on record.
6. Other Business Items
5.1. Road Degradation Ordinance - RV Engineers are working on a draft ordinance.
7. Public Comment – Mr. Lee commented on the condition of the alleyways in the Wedgewood/Andover development.
Discussed this matter with the Mayor and made several comments on ideas to cut back on traffic in the alleys with trash tracks
and local residential traffic. He would like to Borough look at paving these alleys.
Meeting adjourned.
One Vine Street
Lansdale, PA 19446
215-368-1691
WWW.LANSDALE.ORG
Agenda
Borough of Lansdale
Public Works Committee Agenda
April 3, 2024
6:30 pm
Borough Council Chambers
Chairperson: BJ Breish
Approval of Minutes
NOTE: The public will have an opportunity to comment on each action item before the committee takes a vote
1. Public Works Action Items
1.1. East Main Street Streetscape Project*
2. WWTP Action Items
2.1. Chemical Feed Automation Project*
2.2. Whites Road Pump Station Upgrade Project*
3. Public Comment
4. Public Works Update
3.1. Ridge Street Outfall Replacement Project
3.2. Cherry Street Outfall Replacement Project
3.3. Norway Drive Storm Sewer Repair
5. WWTP Update
4.1. Aeration Upgrade Project
4.2. Ridge Street Pump Station Electrical Upgrades
4.3. WWTP Chemical Feed Upgrades
4.4. Update on Process Changes and Projects if time permits.
6. Other Business Items
5.1. Road Degradation Ordinance
7. Old Business
8. New Business
9. Public Comment
*Possible Action Item at Business Meeting
One Vine Street
Lansdale, PA 19446
215.368.1691
WWW.LANSDALE.ORG
Get email alerts for Lansdale
A daily email when new agendas and minutes are posted.