Utility Commission
Regular MeetingLittle Chute, WI · April 16, 2013
Minutes
MINUTES OF THE WATER COMMISSION MEETING – APRIL 16, 2013
Call to Order
The Water Commission meeting was called to order at 6:00 P.M. by Kevin Coffey, Chair
Roll Call
PRESENT: Kevin Coffey, Chair
Mark Gloudemans
Jason Wegand
Tim Wegand
EXCUSED: Tim Bevers
ALSO PRESENT: President Vanden Berg, MCO Rep. Jerry Verstegen, Village Administrator Charles
Kell, Public Works Director Roy Van Gheem, Finance Director Teri Matheny, Village Clerk Vicki
Schneider
Public Appearance for Items Not on the Agenda
None
Approval of Minutes
Water Commission Minutes of February 19, 2013
Moved by Commissioner Gloudemans, seconded by Commissioner J. Wegand to approve the
minutes of February 19, 2013 as presented. All Ayes – Motion Carried
Update on Private Wells
J. Verstegen reported that some of the well owners he has talked to do not put their wells online until
June so June is going to be the annual anniversary date for permit renewal. J. Verstegen stated that he
has not had any conflicts with the well owners he has contacted but he hasn’t yet talked to some of the
larger commercial well owners. Letters will be sent to well owners about the annual permitting and a
second notice letter will be sent if there is no response. Decisions on particular unique situations with
wells will have to be made by the Commission and he will bring that information forward at the June
meeting. The Building Inspector is willing to assist with the private well inspections and permitting.
C. Kell reported that the Locks Authority may be coming forward to ask for approval to install wells for
the Lock Tender houses at Heesakker Park and the Cedar Locks as they do not want to connect to the
water service because it is a long way for them to run water main connections. They are planning to use
these facilities as overnight hostiles. C. Kell stated that staff has informed them that new wells are not
allowed but the Locks Authority has asked about an appeals process. Discussion took place.
Commissioner’s stated their position is that they will not allow new wells to be constructed and C. Kell
stated he will report the Commissions’ position to the Locks Authority. J. Verstegen pointed out that
wells are also not allowed for potable water. The Commission will be kept updated on this issue.
Progress Reports
MCO Operations Update
J. Verstegen provided a handout of an updated report for March. Items reported:
The main breaker at Well #1 is failing and the breaker is 20+ years old and it keeps tripping. It is likely
that it will need to be replaced and the replacement cost is estimated to be between $9,000 and $18,000.
A replacement power source has been ordered for Booster #1 and it will be installed tomorrow.
The crew is spending the bulk of their time on the Main St. project therefore no meters were changed in
March.
Valve repairs were done as well as a hydrant replacement on Randolph Drive.
Water Commission Meeting Minutes – April 16, 2013 – Page 2
The apartment units on Elm Dr. are going with individual meters for each apartment so there will be 70
new installs of lead meters and there has been a large meter install for the Green Stone Credit Services
building.
Hydrant flushing is taking place between April 15 and April 25th.
J. Verstegen reported on water quality issues on Riverside Dr. and Wabush Ave. A contractor hit an
unmarked water main which caused bad water conditions in this area. Customers were contacted and
their meters were read so a credit could be applied to their bills as the customers flushed during the
night. The high volume flushing in this area is going to be postponed until the Main St. project is
completed and the property owners in this area will be notified of this.
Private well permitting will take place as time allows as the crew is working on the Main St. project
daily.
Director of Public Works
R. Van Gheem reported on the status of the Main Street project noting that the sanitary main is basically
completed and crews are working on both ends of the street performing the water main replacements.
Sanitary laterals are also being replaced. This is a valuable project that will help with I & I issues as
cross connections are being discovered and corrected with this project. The response for replacement of
copper laterals has been good.
Also reported:
Bids were opened for the 2013 asphalt paving project and this includes work for some water main
replacement on Elm Drive between Buchanan Street and Ceil Street, Harding Street between Hoover
Avenue and Coolidge Avenue, Sheridan Court, Wisconsin Court, Woodland Court. R. Van Gheem
provided a handout of the bid tab and noted the Village Board would be awarding the bid at their
meeting tomorrow night.
Stony Ridge Apartments utility projects taking place next week.
The project for Pine Street remains on the agenda for this year as well as the possibility of the Buchanan
interceptor project and he will keep the Commission updated on the status of these projects.
Finance Director
T. Matheny provided Commissioners with a copy of the PSC annual report that was recently submitted
to the PSC and she noted that the utility had a very good year with almost $500,000 in earnings.
Also reported: Currently working on the audit and in May or June she wants to look at the debt
commitment taken out for the Main St. project because the debt payments will kick in next year.
Look at a simplified rate case study this year after the audit is complete. She will report back on this
issue.
The Budget and CIP status were reviewed.
Meter inventory will be conducted with assistance from J. Verstegen.
PSC reports available on the PSC website.
Water loss is at 12% and that is nothing to worry about from a PSC standpoint.
PSC closed their PILOT investigation for now. T. Matheny will include the PSC document that shows
the testimony given regarding PILOT in next month’s packet.
Approval of Vouchers
Moved by Commissioner Coffey, seconded by Commissioner T. Wegand to approve and
authorize payment of the vouchers in the amount of $121,740.86 and draw from their respective
funds. All Ayes – Motion Carried
Water Commission Meeting Minutes – April 16, 2013 – Page 3
Unfinished Business
None
Items for Future Agenda
PSC Rate Case Study Update
Water loss report in 2014
Adjournment
Moved by Commissioner T. Wegand, seconded by Commissioner Gloudemans adjourn the
meeting at 7:22 p.m. All Ayes - Motion Carried
VILLAGE OF LITTLE CHUTE
By: Kevin Coffey, Chair
Attest: Vicki Schneider, Village Clerk
Agenda
AGENDA
VILLAGE OF LITTLE CHUTE WATER COMMISSION MEETING
PLACE: Little Chute Village Hall, President's Room
DATE: Tuesday, April 16, 2013
TIME: 6:00 p.m.
A. Call to Order
B. Roll Call
C. Public Appearance for Items Not on the Agenda
────────────────────────────────────────────────────────────────────
1. Approval of Minutes
Water Commission Meeting Minutes of February 19, 2013
2. Update on Private Wells
3. Progress Reports
a. MCO Operations Update
b. Director of Public Works
c. Finance Director
4. Approval of Vouchers
5. Unfinished Business
6. Items for Future Agenda
7. Adjournment
Requests from persons with disabilities who need assistance to participate in this meeting or hearing should be made with as much advance notice as
possible to the Clerk's Office at 108 West Main Street, (920) 788-7380 ext. 204. Prepared: April 10, 2013
Get email alerts for Little Chute
A daily email when new agendas and minutes are posted.