CONSERVATION COMMISSION
LOWELL, MASSACHUSETTS
October 27, 2021
Note: These minutes are not completed verbatim. For further detail, video recordings are available at
the Pollard Library, second floor reference desk or online at www.LTC.org.
Due to the COVID-19 pandemic, this meeting was held both in person and virtually using Zoom.
Members Present: Louisa Varnum, Brad Buitenhuys, William Lovely (Zoom), Perry Downs, Kevin Dillon
(Zoom), Weston Standish (Zoom), Stephen Laput
Members Absent: None
Others Present: Fran Cigliano, Senior Planner
CALL TO ORDER
Meeting called to order at 7:01 PM
ORDER OF BUSINESS
NEW BUSINESS
CONTINUED BUSINESS
Notice of Intent
Chantho Mo
138 Martin Street
Lowell, MA 01854
Project Location: 138 Martin Street 01854
The applicant is seeking to construct an addition to a single-family home within the 100 year floodplain.
The applicant has proposed to demolish an existing addition at the rear of the property and construct a
larger addition. The applicant has requested to withdraw their application without prejudice.
On Behalf:
None
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
None
Motion:
P. Downs motioned to allow the applicant to withdraw their application without prejudice. S. Laput
seconded the motion and it passed unanimously, (6-0).
Enforcement Order
Westminster Preservation LP
60 Columbus Circle
New York, NY 10023
Violation Location: 1276 Pawtucket Boulevard, 01854
The violator engaged in brush and soil removal along the bank of the Merrimack River in order to create
their own beach. They are also storing a floating dock, a chair, and a kayak along the river.
On Behalf:
None
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum explained that this is a riverbank violation that caused a great deal of erosion. Caused by an
unknown person. They have remediated the violation a second time. It is a difficult location with a steep
steep bank. She is satisfied with what they have tried to do. Doesn’t see a reason to keep the violation
open. It will be spring before we see results. W. Standish and W. Lovely concurred with L. Varnum’s
comments.
Motion:
W. Standish motioned to rescind the EO, seconded by P. Downs. The motion passed unanimously, (6-0).
Request for Determination of Applicability
Sovann Kong
51-57 Shirley Avenue
Lowell, MA 01854
Project Location: 51-57 Shirley Avenue, 01854
A Request for Determination of Applicability has been filed by Sovann Kong to remove brush. The
proposed work will take place within the 100-year Floodplain.
On Behalf:
None
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum said that this is a sensitive site. The Commission is unsure of the legality since we have an
outstanding denial at this same location. F. Cigliano confirmed that we are still waiting for Law to issue
an opinion.
Motion:
W. Lovely motioned to continue to the 1/11 meeting, seconded by K. Dillon. The motion passed
unanimously, (6-0).
Request for Determination of Applicability
MS Red Realty
401 Broadway Road
Dracut, MA 01826
Project Location: 81 Old Ferry Road, 01854
A Request for Determination of Applicability has been filed by MS Red Realty to remove existing
pavement and replace with new pavement to grade. The proposed work will take place within the 100-
year flood plain.
On Behalf:
Matt Hamor, Applicant’s Engineer
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum asked whether any additional area would be paved. M. Hamor confirmed no. M. Hamor
confirmed that they are taking out the existing asphalt and replacing. L. Varnum, P. Downs, and W.
Lovely commented that they do not see any issues with the proposal.
Motion:
W. Lovely motioned and K. Dillon seconded the motion to issue a Negative III Determination. The
motion passed unanimously, (6-0).
NEW BUSINESS
Request for Determination of Applicability
City of Lowell
375 Merrimack Street
Lowell, MA 01851
Project Location: 7 Chambers Street 01852
RDA to remove a dead tree within the 100-ft buffer zone to Meadow Brook.
On Behalf:
Sandy Swaile, Design Planner
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
S. Swaile said that they would like to take down a dead tree. L. Varnum asked if the stump will remain. S.
Swaile said yes. L. Varnum commented that the roots will help hold the bank together and stabilize the
slope.
Motion:
P. Downs motioned to issue a Negative III Determination. W. Lovely seconded the motion and it passed
unanimously, (6-0).
Request for Determination of Applicability
Lowell National Historic Park
67 Kirk Street
Lowell, MA 01852
Project Location: 91 Pevey Street 01851
The applicant is seeking permission to engage in soil boring along the Upper Pawtucket Canal Walkway.
On Behalf:
David Lieb, National Park Service – Historic Architect
Gordon Edington, VHB
Mike Ciance, Terracon
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum asked the applicant to confirm how close to the canal wall the test pits would be drilled. M.
Ciance said within 20 ft. of the canal wall. W. Lovely asked about a contingency plan in the event that
they discover contaminated material. M. Ciance said that they are aware this is possible and that they
do have a plan in place.
Motion:
B. Buitenhuys motioned to issue a Negative III Determination. The motion was seconded by P. Downs
and passed unanimously, (7-0).
Request for Determination of Applicability
Boys and Girls Club of Greater Lowell
647-679 Middlesex Street
Lowell, MA 01851
Project Location: 647-679 Middlesex Street 01851 (Boys and Girls Club of Greater Lowell)
The applicant is seeking to construct an addition within the 100-ft. Buffer Zone to the Pawtucket Canal.
On Behalf:
Joe Hungler, Boys and Girls Club
Cassandra Koutalidis, Applicant’s Engineer
Rich Feldman, Applicant’s Engineer
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum commented that she loves that they are making a garden where a parking lot once was. They
are adding pervious surfaces and plants. They have a fairly complicated drainage situation. C. Koutalidis
expanded on the stormwater system and said that they had been working closely with Mike Stuer from
the Lowell Regional Wastewater Utility.
W. Standish said that he feels like an NOI would be more appropriate for this project than an RDA. W.
Lovely said that he feels that the work doesn’t feel significant enough to warrant an NOI application. C.
Koutalidis said that they would be happy to attach special conditions to a DOA.
W. Lovely said that the resource they are protecting is already somewhat altered by manmade activities.
Stuff can get into the canal – they want to make sure that the work that is done does not impact the
resource. The applicant is not proposing work directly over the canal. He feels like, in this case, the
proposal is better than current conditions since they are proposing to reduce paving and improve
natural landscaping. He is open to the applicant’s suggestion of specifying conditions under the Negative
III Determination. W. Standish added that the applicant has already done the work for an NOI; he just
wants the work to be reviewed by MassDEP.
R. Feldman added that they will be installing erosion controls. He would appreciate working with the
Commission. Their budget is challenging as a non-profit. B. Buitenhuys agrees that the filing should be
reviewed as an RDA. P. Down said that since this is an improvement from current conditions, it could be
reviewed as an RDA. L. Varnum commented that it is not a hard site to keep an eye on.
W. Lovely asked what to include as special conditions. L. Varnum said no stockpiling of loose materials
on site – anything loose that could blow or wash away and get into the canal or slope. W. Lovely and B.
Buitenhuys suggested a 50 ft. setback for stockpiling of materials.
Motion:
W. Lovely motioned to issue a Negative III Determination with the following conditions:
1) Adopt Standard Lowell Order of Conditions
2) Any stockpiling of material in connection with the project shall be stored at least 50 ft. from
the canal wall so as to avoid erosion into the canal.
B. Buitenhuys seconded the motion and it passed (6-1) with W. Standish voting in opposition.
Request for Determination of Applicability
Gervais Lincoln
24 Reiss Avenue
Lowell, MA 01851
Project Location: 24 Reiss Ave Lowell, MA 01851
The applicant is seeking to construct a 4,081 square foot addition to the existing car dealership and to
restripe the existing paved parking area. The proposed work is approximately 75 feet from the nearest
point of the wetland. The applicant notes that the wetland may actually be a drainage channel rather
than a protected wetland.
On Behalf:
Brian Milisci, Applicant’s Engineer
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum commented that this is a fairly low impact project. She does not have a lot of concerns. W.
Standish said he had no concerns.
Motion:
B. Buitenhuys motioned and P. Downs seconded the motion to issue a Negative III Determination. The
motion passed unanimously, (7-0).
Notice of Intent
Duggan & Sons Construction
572 Boston Road Unit 26
Billerica MA 01821
DEP #206-0808
Project Location: 733 Rogers Street 01852
The applicant is seeking to replace a parking lot and install a new stormwater detention system at 733
Rogers Street. The detention system and parking lot would be within the 100-ft buffer zone to an
adjacent wetland. DEP #206-0808.
On Behalf:
Bill Hall, Civil Design Consultants
Speaking in Favor:
None
Speaking in Opposition:
None
Discussion:
L. Varnum said that she was around the last time this parking lot was paved. Very unusual paving
scheme. There are large areas of pervious pavers. The reason for these pervious pavers is that this was
originally an expansion of the parking area. This is adjacent to a very sensitive small wetland area. It is
sensitive for the entire neighborhood. The flow goes to the northeast, goes under Rogers Street and
heads toward Cawley Stadium, and then connects to the wetlands over there. IT is extremely sensitive
and prone to flooding. I remember this project taking many meetings. The entire parking area would be
sheet flowing into a tiny piece of stream bed. I don’t see the Commission letting that happen. I would
suggest the pavers need a bit of repair. They have been doing their job. I am concerned about the edges
being dug up. It appears snow might have been being plowed into the wetland. I am also concerned
about the high water table. This is a flooding concern for not just this property but for the entire
neighborhood.
B. Hall said that the pavers do get beat up, especially where the pavers meet the pavement, from
plowing. He knows that it is the preference of the applicant to go away from the pavers. Maybe they
could look at an alternative design to pavers.
L. Varnum said that most of the pavers are in better shape than the asphalt.
W. Lovely asked what the current recharge of the pervious paver area is. B. Hall said he is unsure since
they did not do the original design. W. Lovely said it would be helpful to know how much stormwater
management is being addressed through the existing system. W. Lovely asked whether there is enough
separation between the bottom of the new infiltration system and the water table.
B. Buitenhuys said that it sounds like they need more information. They need boring information. W.
Lovely agrees and suggests a continuance. L. Varnum would like to see the applicant clean up around
the wetland border as well, as some of the pavers got pushed down there. She would also like to know
alternatives for snow storage. The Commission does not allow snow to be pushed into resource areas,
even canals, and it appears from the condition of the pavers and the fact that pavers are located down
slope that snow is routinely stored there.
B. Buitenhuys suggested installing granite borders along the edges of the pavers to provide a solid lip. L.
Varnum said she would be interested in a proposal to install pavers across the entire parking area.
Motion:
W. Lovely motioned to continue the petition to the 11/10 Conservation Commission meeting to give the
applicant time to provide the following additional information to the Commission:
1. Confirm the recharge and storage capacity of the current pavers (infiltration);
2. Confirm that 4 ft. of separation between the infiltration system and historic water table
elevation is sufficient to account for seasonal water table fluctuations;
3. Demarcate the preferred snow storage location; and
4. Propose stabilization of the edge of paver areas so that they do not continue to degrade over
time due to snow plows, etc.
The motion was seconded by P. Downs and passed unanimously, (7-0).
OTHER BUSINESS
Minutes
9/22 Meeting Minutes
W. Lovely motioned to approve the minutes with revisions. B. Buitenhuys seconded the motion and it
passed unanimously, (6-0).
10/13/2021 Meeting Minutes
10/13/2021 Executive Session Meeting Minutes
B. Buitenhuys motioned and P. Downs seconded the motion to approve both sets of minutes from
10/13/2021. The motion passed unanimously, (6-0).
Approve Proposed 2022 Conservation Commission Schedule
B. Buitenhuys motioned and P. Downs seconded the motion to approve the proposed 2022 schedule.
The motion passed unanimously, (7-0).
ADJOURNMENT
Agenda
The City of Lowell • Dept. of Planning and Development • Division of Development Services
Lowell City Hall • 375 Merrimack Street • Lowell, MA 01852
P: 978.674.4144 • F: 978.446.7103
www.LowellMA.gov
Christine McCall
Assistant City Manager/DPD Director
R. Eric Slagle
Director of Development Services
October 20, 2021
In accordance with the Massachusetts General Laws Chapter 131, Section 40, and the City of Lowell
Wetland Ordinance Section 280.1-13, the Lowell Conservation Commission will hold a meeting on
Wednesday, October 27, 2021 at 7:00 PM.
This meeting will occur in-person with the option to join remotely. You can choose to attend in-person
in the City Council Chambers, City Hall, 375 Merrimack Street, Lowell MA 01852; or you can choose to
attend remotely by using one of the following four options to access the meeting:
1. Join using your computer, tablet, or smartphone: https://lowellma.zoom.us/j/82633158424
2. Call (646) 558 8656 and enter the MEETING ID: 826 3315 8424
3. Watch LTC channel 99
4. Watch LTC online at: https://www.ltc.org/watch/channel-99/
Review the project materials online at: https://lowellma.gov/1100/Conservation-Commission
AGENDA
CALL TO ORDER
ORDER OF BUSINESS
CONTINUED BUSINESS
Notice of Intent
Chantho Mo
138 Martin Street
Lowell, MA 01854
Project Location: 138 Martin Street 01854
The applicant is seeking to construct an addition to a single-family home within the 100 year floodplain.
The applicant has proposed to demolish an existing addition at the rear of the property and construct a
larger addition. The applicant has requested to withdraw this application without prejudice.
Enforcement Order
Westminster Preservation LP
60 Columbus Circle
New York, NY 10023
Violation Location: 1276 Pawtucket Boulevard, 01854
The violator engaged in brush and soil removal along the bank of the Merrimack River in order to create
their own beach. They are also storing a floating dock, a chair, and a kayak along the river.
Request for Determination of Applicability
Sovann Kong
51-57 Shirley Avenue
Lowell, MA 01854
Project Location: 51-57 Shirley Avenue, 01854
A Request for Determination of Applicability has been filed by Sovann Kong to remove brush. The
proposed work will take place within the 100-year Floodplain.
Request for Determination of Applicability
MS Red Realty
401 Broadway Road
Dracut, MA 01826
Project Location: 81 Old Ferry Road, 01854
A Request for Determination of Applicability has been filed by MS Red Realty to remove existing
pavement and replace with new pavement to grade. The proposed work will take place within the 100-
year flood plain.
NEW BUSINESS
Request for Determination of Applicability
City of Lowell
375 Merrimack Street
Lowell, MA 01851
Project Location: 7 Chambers Street 01852
RDA to remove a dead tree within the 100-ft buffer zone to Meadow Brook.
Request for Determination of Applicability
Lowell National Historic Park
67 Kirk Street
Lowell, MA 01852
Project Location: 91 Pevey Street 01851
The applicant is seeking permission to engage in soil boring along the Upper Pawtucket Canal Walkway.
Request for Determination of Applicability
Boys and Girls Club of Greater Lowell
647-679 Middlesex Street
Lowell, MA 01851
Project Location: 647-679 Middlesex Street 01851 (Boys and Girls Club of Greater Lowell)
The applicant is seeking to construct an addition within the 100-ft. Buffer Zone to the Pawtucket Canal.
Request for Determination of Applicability
Gervais Lincoln
24 Reiss Avenue
Lowell, MA 01851
Project Location: 24 Reiss Ave Lowell, MA 01851
The applicant is seeking to construct a 4,081 square foot addition to the existing car dealership and to
restripe the existing paved parking area. The proposed work is approximately 75 feet from the nearest
point of the wetland. The applicant notes that the wetland may actually be a drainage channel rather
than a protected wetland.
Notice of Intent
Duggan & Sons Construction
572 Boston Road Unit 26
Billerica MA 01821
Project Location: 733 Rogers Street 01852
The applicant is seeking to replace a parking lot and install a new stormwater detention system at 733
Rogers Street. The detention system and parking lot would be within the 100-ft buffer zone to an
adjacent wetland.
OTHER BUSINESS
Minutes
9/22 Meeting Minutes
10/13/2021 Meeting Minutes
10/13/2021 Executive Session Meeting Minutes
Approve Proposed 2022 Conservation Commission Schedule
ADJOURNMENT