Lake Quality Commission
Regular MeetingMaple Grove, MN · February 21, 2024
Minutes
MAPLE GROVE
LAKE QUALITY
COMMISSION MINUTES
February 21, 2024
CALL TO ORDER A meeting of the Lake Quality Commission (LQC) was held on February 21, 2024 in
the Mayor’s Conference Room at the Maple Grove Government Center, 12800
Arbor Lakes Parkway, Maple Grove.
Chairperson Fahrenbruch called the meeting to order at 6:32 p.m.
Commissioners Present:
Becky Fahrenbruch – Chair - Eagle Lake
Sharon Martin-Kotula – Edward Lake
George Schneider – Rice Lake
Brennon O’Callaghan, Vice Chair – Fish Lake
Nancy Bergstrand – Weaver Lake
Joe Ruegsegger – At Large
Steve Lane – Cedar Island Lake
Commissioners Absent:
None
Others Present:
Kristy Janigo, City Council Liaison
Derek Asche, City of Maple Grove
Mark Lahtinen, City of Maple Grove
Diane Spector, Stantec
Katie Kemmitt, Stantec
Tim Evenson – Eagle Lake
OATH OF OFFICE Councilmember Janigo provided the Oath of Office to George Schneider.
APPROVAL OF Minutes of the January 17, 2024 LQC meeting were presented. It was noted by
MINUTES George Schneider he is listed as both present and absent. He was absent.
MOTION TO APPROVE with the requested change by Lane, second by O’Callaghan.
With all in favor the motion was APPROVED.
AREA REPORTS Edward, Sharon Martin-Kotula – Some open water on Edward. The association is
hoping stock fish in 2024 and notes many deer have been roaming the shores.
Mark Lahtinen – Open water on Fish is noted. Last time Fish Lake water level was
able to be taken at this time of year was February 21, 2017.
Rice Lake, George Schneider – The aerator has been shut off and some open water
has been noted. More than 20 swans are enjoying Rice Lake. The association
annual meeting is scheduled for May 7, 2024.
Fish Lake, Brennon O’Callaghan – Ice is still ~8” in the thickest locations. A few
anglers are getting their last ice fishing in for the season. Polar Plunge was a
successful event.
Weaver Lake, Nancy Bergstrand – Small amount of action on the lake but mostly
quiet.
Joe Ruegsegger, At Large – What is left of the ice is beginning to lose strength.
Council Liaison Kristy Janigo – The city has promoted the delisting of Fish Lake on
social media.
Eagle Lake, Becky Fahrenbruch – Not much activity on Eagle. Coyotes have been
seen in the area. Remaining events on Eagle have been canceled due to thin ice.
Cedar Island Lake, Steve Lane – Not much activity on Cedar Island. Quiet for this
time of year.
WATERSHED Diane Spector and Katie Kemmitt of Stantec representing the Shingle, West
UPDATE Mississippi, and Elm Creek watersheds provided an update to the Commission on
watershed related projects and activities. It was noted that in the Elm Creek
watershed Fish Lake was set to be delisted as an impaired water. Also in Elm the
total maximum daily load plan and the watershed plan are scheduled for updates.
In the Shingle Creek and West Mississippi watersheds it was noted that the
Eagle Lake sub-watershed assessment and lake management plan are being
drafted. Proposed management in Eagle is to complete an alum treatment in 2024
and again in 2026 to improve water clarity and meet state mandated goals.
Vegetation management and monitoring will be necessary during this process.
Additionally, a watershed project is being considered to enhance the treatment
of stormwater prior to discharge in Eagle Lake. Asche noted sediment samples
from Cedar Island have been tested and found to have low levels of nutrients
indicating internal loading from sediment is likely low. The city will collect
samples from upstream ponds in the Cedar Island watershed and send them
for testing of water quality parameters.
The West Metro Water Alliance (WMWA) is offering upcoming workshops for
lakeshore restoration and resilient yards in partnership with Metro Blooms. The goal
is to assist home owners with implementing improvements. Technical and financial
assistance is planned to be offered.
2024 LIP PROCESS Asche presented the Lake Improvement Program process including applications for
cost share on projects and deadlines for submittal.
2024 WORK PLAN Asche presented the final LQC work plan based on comments from January. No
further comments were received.
February LIP Process
Watershed Update
Final Work Plan
Data and Ethics Practices, Open Meeting Law Training
March LIP Review and Approval
April Blue Water Science – Lake Monitoring Report
May Edward Lake Tour
June Eagle Lake Tour
July No Meeting – Maple Grove Days
August Fish Lake Tour
September Site visit - South Fork Rush Creek Restoration
October NPDES MS4 Annual Meeting and presentation
November Water Quality Pond Dredging Presentation
December Winter/Holiday Gathering
MOTION TO APPROVE by Schneider, second by O’Callaghan. With all in favor the
motion was APPROVED.
INFORMATIONAL Maple Grove Days is July 13, 2024.
ITEMS
FUTURE March 20, 2024
MEETING:
ADJOURNMENT Meeting adjourned at 7:49 pm.
Agenda
Lake Quality Commission Agenda
February 21, 2024
The Lake Quality Commission (LQC) meeting will commence at 6:30 pm at the Maple Grove
Government Center, 12800 Arbor Lakes Parkway, Maple Grove, MN, 55369.
ITEM ACTION REQUIRED
CALL TO ORDER Call to order by Chairperson Fahrenbruch at 6:30 p.m.
BUSINESS ITEMS
1. Introductions Introduce commissioners and students; five minutes for public
comment
2. Oath of Office Oath of Office for George Schneider
3. Area Reports
4. Approval of Minutes Approve minutes from the January 17, 2024 LQC meeting
Receive presentation on watershed projects from Diane Spector
5. Watershed Update
and Katie Kemmitt of Stantec.
6. Lake Improvement Receive Lake Improvement Program process.
Program
7. Approve Final Work Plan Approve Final 2024 Work Plan
INFORMATIONAL ITEMS
FUTURE MEETINGS: March 20, 2024
ADJOURNMENT
MAPLE GROVE
LAKE QUALITY COMMISSION
DRAFT MINUTES
January 17, 2024
CALL TO ORDER A meeting of the Lake Quality Commission (LQC) was held on January 17, 2024 in
the Mayor’s Conference Room at the Maple Grove Government Center, 12800
Arbor Lakes Parkway, Maple Grove.
Chairperson Fahrenbruch called the meeting to order at 6:30 p.m.
Commissioners Present:
Becky Fahrenbruch – Chair - Eagle Lake
Sharon Martin-Kotula – Edward Lake
George Schneider – Rice Lake
Brennon O’Callaghan, Vice Chair – Fish Lake
Nancy Bergstrand – Weaver Lake
Joe Ruegsegger – At Large
Steve Lane – Cedar Island Lake
Commissioners Absent:
George Schneider – Rice Lake
Others Present:
Kristy Janigo, City Council Liaison
Derek Asche, City of Maple Grove
Mark Lahtinen, City of Maple Grove
Hente Braam – Rice Lake area
OATH OF OFFICE Councilmember Janigo provided the Oath of Office to Brennon O’Callaghan and Joe
Ruegsegger.
APPROVAL OF Minutes of the November 15, 2023 LQC meeting were presented.
MINUTES
MOTION TO APPROVE by O’Callaghan, second by Martin-Kotula. With all in favor
the motion was APPROVED.
AREA REPORTS Edward, Sharon Martin-Kotula – Edward is frozen but the aerators have not
started yet. Acorns are falling from the trees.
Mark Lahtinen – After recent measurements, all lakes are a bit higher than normal
possibly due to the rain in late December.
Rice Lake, Hente Braam – Hoping to start aerator soon and put up the thin ice
signage. The RLIA is considering another carp removal project in the future.
Fish Lake, Brennon O’Callaghan – Fish Lake froze over early to mid-January. The
lake association is meeting on Lake Improvement Program (LIP) projects and
applying for an aquatic invasive species (AIS) grant from Hennepin County.
Weaver Lake, Nancy Bergstrand – The Weaver Lake association is meeting in the
coming weeks to discuss LIP applications.
Joe Ruegsegger, At Large – Fish Lake is about three inches thick. There may be a
beaver dam downstream that needs maintenance in the near future.
Council Liaison Kristy Janigo – The City Council continues to implement
environmental initiatives and has approved funding for a future City Forester.
Eagle Lake, Becky Fahrenbruch – Eagle Lake has frozen over and there is one fish
house out at this time. There are lots of eagles. People are expecting the hockey
rinks to come very soon.
ELECTION OF Becky Fahrenbruch was nominated as Chair of the LQC for 2024.
OFFICERS
MOTION TO APPROVE by O’Callaghan, second by Martin-Kotula. With all in favor
the motion was APPROVED.
Brennon O’Callaghan was nominated as Vice-Chair of the LQC for 2024.
MOTION TO APPROVE by Lane, second by Ruegsegger. With all in favor the motion
was APPROVED.
2024 WORK PLAN Asche presented the draft 2024 work plan to LQC and noted that, historically, the
LQC has included Lake Improvement Program (LIP) applications, the required Maple
Grove Municipal Separate Storm Sewer (MS4) annual meeting, and lake tours in the
work program.
After discussion, the LQC made changes to the draft work plan. Revisions will be
completed by staff and provided to LQC for final approval in February. Below is the
plan as revised by LQC. It was noted for Maple Grove Days that Councilmember
Janigo and Commissioner Martin-Kotula plan to attend; our watershed educator
Jessica Sahu Teli plans to attend; and Commissioner Ruegsegger will set up a sign-
up sheet. LQC members should plan to find a substitute if they are unavailable. A
carp harvesting presentation is possible if time allows.
February LIP Process
Watershed Update
Final Work Plan
Data and Ethics Practices, Open Meeting Law Training
March LIP Review and Approval
April Blue Water Science – Lake Monitoring Report
May Edward Lake Tour
June Eagle Lake Tour
July No Meeting – Maple Grove Days
August Fish Lake Tour
September Site visit - South Fork Rush Creek Restoration
October NPDES MS4 Annual Meeting and presentation
November Water Quality Pond Dredging Presentation
December Winter/Holiday Gathering
INFORMATIONAL None.
ITEMS
FUTURE February 21, 2024
MEETING:
ADJOURNMENT Meeting adjourned at 7:35 pm.
LAKE QUALITY COMMISSION
STAFF REPORT
TO: Lake Quality Commission (LQC)
FROM: Derek Asche, Water Resources Engineer
DATE: February 9, 2024
SUBJECT: Watershed Update
Staff from Stantec will attend the February LQC meeting to update the commission on
watershed projects. Topics will include a lakeshore/resilient yards restoration workshop
and alum application with submersed aquatic vegetation management on Eagle and Pike
lakes.
RECOMMENDATION: Receive presentation from the watershed.
Attachment: None
LAKE QUALITY COMMISSION
STAFF REPORT
TO: Lake Quality Commission (LQC)
FROM: Derek Asche, Water Resources Engineer
DATE: February 9, 2024
SUBJECT: Lake Improvement Program (LIP) Process
The LQC annually reviews, and makes recommendations to the City Council, funding for projects
that improve the water quality in our local lakes. Project proposers should consider existing data
and studies, such as sub-watershed assessments as the basis for funding requests. At a minimum,
these projects are typically a partnership between lake associations and the city, but can also
include other partners such as watershed management organizations, Hennepin County, the
Three Rivers Park District, and possibly others.
Funding for water quality monitoring and individual water quality improvement projects (<$750)
is included with the LIP but does not require partnerships or a funding match from lake
associations. Staff has developed guidance for funding amounts (attached).
RECOMMENDATION: None.
Attachment: Staff Guidance on Funding
Lake Improvement Application Form
Individual Water Quality Improvement Project Application Form
LAKE QUALITY COMMISSION
STAFF REPORT
Staff Guidance on Funding
Lake Association
Category of Project Investment City LOC Investment
Internal Phosphorus Sequestering
Alum/Phoslock treatments or similar 20.00 80.00
Aquatic Vegetation Management
Invasive species Management - Curlyleaf/EMW 30.00 70.00
Native Plantings (shoreline restorations, etc…) 30.00 70.00
Algae Reduction Control 30.00 70.00
Boat Launch Inspections/Cleaning Stations (CD3) 30.00 70.00
Dye Treatments 30.00 70.00
Fish Management
Carp Removal 40.00 60.00
Fish Stocking 40.00 60.00
Miscellaneous Activities
Boat Launch Upgrades 50.00 50.00
Consulting/Monitoring Services 50.00 50.00
Aeration 50.00 50.00
Adopt-a-Drain 0.00 100.00
Individual Water Quality Improvement Projects Case by case Case by Case
MAPLE GROVE LAKE IMPROVEMENT PROGRAM
APPLICATION FORM
DUE FEBRUARY 28th, 2024
PROJECT NAME
DATE
Lake
Organization
Contact Person Telephone (H)
Address: (W)
Contractor/Applicator
Address
Telephone
Project Description
Scope of Work (including description of lake area, size of area and expected longevity of project
enhancements)
Meets Objective of
Management Plan?
Yes No
1. Shoreline Buffer
2. Watershed Clean-Up
3. Aquatic Plant Control
4. Water Quality
5. Public Education
6. Fisheries
7. Recreational
8. Algae Control
9. Other
Lake Improvement Program Application – Page 2
For Copper Sulfate treatments, secchi disc readings for water quality, must be taken for one week prior to
and after treatment.
Readings Before Readings After
Date Date
Date Date
Project Cost
Project Cost $
(Attach copy of invoices and permits)
Association Funding $
Other Funding $
Amount of City Funding Requested $
Description of Association in-kind labor and materials:
I declare the stated costs are an accurate reflection of estimated costs to be incurred.
Organization Representative Date
Maple Grove Water Resource Improvement Project Grant
Maple Grove Water Resource Improvement Project Application (Funding is limited and based
on approval from the Lake Quality Commission. Is based on a first come basis, so please get
in your application ASAP)
Name:_____________________________________________
Address:___________________________________________________________________________
Phone:____________________________Email:___________________________________________
Project (check project(s) below):
___ Native shoreline restoration ___ Rain garden (design approved)
___ Bioengineered shoreline ___Native buffer (at least 15 feet wide)
___ Bioengineered slopes greater than 4:1 (H:V) near shore ___
___Consulting services for training for those projects listed above (Note: only covered if a project was
implemented)
___Other (please explain in detail) _______________________________________________________
**Note that lake weed removal will not be covered by this grant
Explain in detail how your project will improve water resource quality (include before and/or after
pictures if available) Use back of form if needed.
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
Estimated Cost of Project (Home owner pays 100% of cost up front, and is then reimbursed up to 50%
of the total cost and $750 maximum). Please save ALL Receipts. You will need to turn them in for
reimbursement.
_______________________
Please send completed form to your Lake Quality Commission Representative.
LQC Use Only:
_____Approved ____ Not Approved
LAKE QUALITY COMMISSION
STAFF REPORT
TO: Lake Quality Commission (LQC)
FROM: Derek Asche, Water Resources Engineer
DATE: February 9, 2024
SUBJECT: FINAL 2024 WORK PLAN
In January of each year, the LQC prepares a draft work plan outlining the topics and subjects for
consideration over the course of the year. Historically, the LQC has included Lake Improvement
Program (LIP) applications, the required Maple Grove Municipal Separate Storm Sewer (MS4)
Annual Meeting, and lake tours in the work program. Additionally, topics of interest, projects,
guest speakers, and/or environmentally relevant issues have been included as well. In February,
the LQC finalizes the work plan. A final work plan based on discussion in January 2024 is provided
as Table 1.
Table 1. FINAL 2024 LAKE QUALITY COMMISSION WORK PLAN
February Watershed Update
LIP Process
Final Work Plan
Data and Ethics Practices, Open Meeting Law Training
March LIP Review and Approval
April Lake Monitoring Report
May Edward Lake Tour
June Eagle Lake Tour
July No Meeting – Maple Grove Days
August Fish Lake Tour
September Site Visit – South Fork Rush Creek Stream Restoration
October NPDES MS4 Annual Meeting and Presentation
November Water Quality Pond Dredging
December Winter/Holiday Gathering
RECOMMENDATION: I recommend the LQC approve their final 2024 Work Plan.