Airport Committee
Regular MeetingMinot, ND · July 28, 2015
Minutes
AIRPORT COMMITTEE
July 28, 2015
Page 1
Members Present:
Hatlelid, Frey, Knudsvig, Larson, Lehner, Rued
Members Absent:
Seymour
Others Present:
City Manager, City Clerk, Clerk Admin, City Attorney, Airport Director, City Assessor, Finance Director, City
Treasurer, City Engineer, Assistant City Engineer, City Planner, Fire Chief, Assistant Fire Chief, Police Chief,
Planning Director, Public Works Director, Assistant Public Works Director, Auditorium/Recreation Director, Public
Information Officer, Alderman Connole, Alderman Hatlelid, Alderman Lehner, Alderman Miller, Alderman
Shomento, Jill Schramm, Mark Lyman, Wanda Staab, Cambrey Frantsvog
To the Honorable Mayor and All Aldermen:
Following are the recommendations from the Airport Committee meeting called to order at 4:23p.m July 28, 2015:
1. The City Council award the ATM Concession contract to First Western Bank & Trust and authorize
the Mayor to sign the agreement.
**********
The above motion by Alderman Lehner, seconded by Alderman Frey and was carried unanimously.
2. The City Council approve a professional services contract relating to rehabilitation of the existing
detention pond in the amount of $233,500 to KLJ and authorize the Mayor to sign the agreement.
**********
The above motion by Alderman Lehner, seconded by Alderman Frey and was carried unanimously.
3. The City Council approve funding for terminal transition consulting services with Chrysalis Consulting
for a not-to-exceed amount of $300,000 and allow the Mayor to sign all documents and paperwork associated
with this change (AIR035).
**********
The above motion by Alderman Lehner, seconded by Alderman Frey and was carried unanimously.
4. Informational – Airport Activities, Reports and Project Updates
**********
The Airport Director stated the Airport had its annual FAA certification which went well. Only one small correction was
indicated. The Fire Department provided great service on the required fire response drill.
Mike Mahoney from KLJ started his report with Taxiway D. The closeout papers are being prepared because of
completion. The SRE Building closeout was submitted on February 11, 2015. The new terminal is now 82% complete
with a change order increase of approximately 3.7%
Committee Member Knudsvig entered at 4:29pm.
AIRPORT COMMITTEE
July 28, 2015
Page 2
He continued, 90% of the future parking lot in front of the terminal is now at the proper subgrade level. Phase I of the
Terminal Apron has its concrete complete. Phase II is complete except for one lane which is in place to accommodate
concrete trucks. Phases III and IV are complete except the one lane of traffic. Phases 1A and 4A have been excavated to
subgrade. Base will be placed on July 29th. Runway 8/26 relocation had its final environmental assessment which will
be signed off on this week. The wildlife hazard analysis had its 11th month survey done. The decision was made to
address the detention pond replacement rather than the proposed dump truck. The Runway 13/31 project is completed
with some project overrun. The master plan will have kickoff meetings between August 3rd and 5th.
5. The City Council approve the change order on Airport Access Road to use concrete rather than asphalt.
**********
The above motion by Alderman Lehner, seconded by Alderman Frey and was carried unanimously.
Mike Mahoney explained the engineering department determined it would be more efficient to complete the Access
Road with concrete verses asphalt although there would be some additional costs.
The City Engineer indicated asphalt has a 20 year life span while concrete has a 30 year life span. It would be a better
option to complete this road with concrete.
There being no further business, the meeting adjourned at 4:50 p.m.
Respectfully submitted,
Lisa Jundt
City Clerk