City Council
Regular MeetingMount Vernon, WA · June 9, 2021
Minutes
City of Mount Vernon
City Council Meeting Minutes
June 9, 2021
Mayor Boudreau called the meeting to order at 7:00 p.m.
Present: Councilmembers Beaton, Brocksmith, Carías, Hudson, Hulst,
Molenaar and Morales
Staff Present: City Attorney Rogerson, Finance Director Volesky, Project Development
Manager Donovan, Development Services Director Phillips, Capital Programs
Manager Bullock, Engineering Services Manager Chesterfield, Police Chief
Cammock, Parks and Enrichment Services Director Berner, Library Director
Huffman and Human Resources Director Keator
Citizens Present: 2
CONSENT AGENDA
A. Approval of May 26, 2021 Regular Council Meeting Minutes
B. Approval of June 4, 2021 payroll checks numbered 110767 – 110788, direct
deposit checks numbers 82496 – 82728, and wire transfers numbered 980 –
984 in the amount of $941,542.
C. Approval of June 9, 2021 Claims numbered 14029 – 14030, 14037 and
14044 – 114187 in the amount of $669,835.39.
Councilmember Beaton moved to approve Consent
Agenda Items A-C. Motion seconded by
Councilmember Hudson. Motion carried 7-0.
REPORTS
A. Public Works and Library – see committee minutes for details.
Public Safety – see committee minutes for details.
B. Community Comments – none
C. Councilmember Comments
• Councilmember Hudson congratulated the 2021 Mount Vernon High School
graduates.
• Councilmember Hulst asked any citizen reporting an issue to Council via
email to provide specifics so that their concern may be addressed.
Mount Vernon City Council
June 9, 2021
Page 2 of 4
• Councilmember Morales congratulated the 2021 Mount Vernon High
School graduates.
D. Mayor’s Report
• Mayor Boudreau briefly explained the Skagit PUD Micro-Hydro System
Project and directed citizens to the Skagit PUD website for additional
information.
• Congratulated the 2021 Mount Vernon High School graduates.
E. Committee Agenda Requests - none
NEW BUSINESS
A. Interlocal Agreement with Skagit County for Economic Development
Grant: Mr. Donovan presented an interlocal agreement with Skagit
County in which the city receives a $100,000 grant for improvements to
the City owned historic Lincoln Theatre. The funding will be used to
improve the flow of patron traffic in the lobby and expand restroom
facilities. Mayor Boudreau thanked Lincoln Theatre Executive Director
Roger Gietzen for writing and submitting the grant application on behalf of
the City.
Councilmember Hulst moved to authorize the Mayor
to enter into an interlocal agreement Skagit County
for Improvements to the Historic Lincoln Theatre.
Motion seconded by Councilmember Morales.
Motion carried 7-0.
B. Planning Commission Appointment: Mr. Phillips requested approval of the
appointment of James Fikkert to the Mount Vernon Planning Commission.
Councilmember Molenaar moved to approve the
appointment of James Fikkert to the Mount Vernon
Planning Commission. Motion seconded by
Councilmember Beaton. Motion carried 7-0.
Mayor Boudreau performed the swearing in of James Fikkert.
C. Schedule Public Hearing for Adoption of 2022-2027 Six-Year Transportation
Improvement Program: Mr. Bullock requested approval to set the Public
Hearing date for the adoption of the 2022-2027 Six-Year Transportation
Improvement Program for June 23, 2021.
Mount Vernon City Council
June 9, 2021
Page 3 of 4
Councilmember Beaton moved to approve the
public hearing date of June 23, 2021 for the
approval of the 2022-2027 Six-Year Transportation
Improvement Program. Motion seconded by
Councilmember Molenaar. Motion carried 7-0.
D. Agreement Amendment, PBS Environmental, Inc.: Mr. Bullock requested
approval of Amendment 1 to the agreement with PBS Engineering and
Environmental, Inc. to include construction management services for the
Freeway Drive Project in the amount of $203,290.
Councilmember Hulst move to authorize the Mayor
to enter into Amendment 1 of Agreement 3903 with
PBS Engineering and Environmental, Inc. in the
amount of $203,290. Motion seconded by
Councilmember Hudson. Motion carried 7-0.
E. Interlocal Agreement with Skagit County for Economic Development Grant:
Mr. Huffman requested approval of an Interlocal Agreement with Skagit
County to provide funding for the Library Commons Project in the amount
of $500,000.
Councilmember Morales moved to authorize the
Mayor to enter into an interlocal agreement with
Skagit County for the Library Commons Project in
the amount of $500,000. Motion seconded by
Councilmember Carías. Motion carried 7-0.
The meeting was convened into Executive Session at 7:25 p.m. for a period of
twenty-five minutes to discuss with legal counsel matters pertaining to collective
bargaining. No action will be taken following the session.
The meeting was adjourned at 7:50 p.m.
SUBMITTED BY:
Becky Jensen, City Clerk
Mount Vernon City Council
June 9, 2021
Page 4 of 4
ATTEST:
Doug Volesky, Finance Director
APPROVE:
Jill Boudreau, Mayor
Agenda
CITY OF MOUNT VERNON
CITY COUNCIL MEETING
AGENDA
June 9, 2021, 7:00 p.m.
Police Court Campus
(Public health measures will be required of all persons in attendance.
Masks and social distancing are required.)
To virtually attend the meeting, the public may:
1. Call the conference line: 1-888-924-9240; Access Code: 3366211 (please ‘mute’
your phone, if possible, to minimize distractions)
2. Watch the meeting live on TV10: Comcast/Xfinity Channel 10
3. Watch the meeting live, online:
https://www.youtube.com/channel/UCUob_hcQUmd4S93YkletdrA
I. OPENING CEREMONIES
A. Call to Order
B. Pledge of Allegiance
C. Roll Call of Councilmembers
II. CONSENT AGENDA
A. Approval of May 26, 2021 Regular Council Meeting Minutes
B. Approval of June 4, 2021 payroll checks numbered 110767 – 110788, direct deposit
checks numbers 82496 – 82728, and wire transfers numbered 980 –
984 in the amount of $941,542.34
C. Approval of June 9, 2021 Claims numbered 14029 – 14030, 14037 and
14044 – 114187 in the amount of $669,835.39
III. REPORTS
A. Committees
1. Public Works and Library
2. Public Safety
B. Community Comments
(This is an opportunity for Mount Vernon residents to address their City Council. Please limit comments
to 3 minutes or less. Under normal circumstances, the Mayor and Council will not respond immediately
to Community Comments. If you would like someone to follow-up with you regarding the topic of your
comments, please leave your name and contact information on the form at the entrance of the Council
Chambers.
Public comments will also be accepted via email to council@mountvernonwa.gov. The comments will
be read aloud into the record during the public comment portion of the agenda. All comments must be
received by 4:00 p.m. on June 9, 2021.)
C. Councilmember Comments
D. Mayor’s Report
E. Committee Agenda Requests
Mount Vernon City Council Agenda
June 9, 2021, Page 2 of 2
IV. UNFINISHED BUSINESS
None
V. NEW BUSINESS
A. Interlocal Agreement with Skagit County for Economic Development Grant
(Staff is requesting approval of an interlocal agreement with Skagit County in which the City receives
$100,000 for Improvements to the Historic Lincoln Theatre)
(required action – motion)
(staff contact – Peter Donovan)
B. Planning Commissioner Appointment
(Staff is requesting approval of the appointment of James Fikkert to the Mount Vernon Planning
Commission)
(required action – motion)
(staff contact – Chris Phillips)
C. Schedule Public Hearing for Adoption of 2022-2027 Six-Year Transportation
Improvement Program
(Staff is requesting approval of a Public Hearing date for the adoption of the 2022-2027 Transportation
Improvement Program.)
(required action – motion)
(staff contact – William Bullock)
D. Agreement Amendment, PBS Engineering and Environmental Inc.
(Staff is requesting approval of Amendment 1 to the agreement with PBS Engineering and
Environmental, Inc. for the Freeway Drive Improvements Project.)
(required action – motion)
(staff contact – William Bullock)
E. Interlocal Agreement with Skagit County for Economic Development Grant
(Staff is requesting approval of interlocal agreement with Skagit County for grant funding for the Library
Commons Project.)
(required action – motion)
(staff contact – Isaac Huffman)
COMMITTEE MEETINGS
Public Works and Library 6:00 p.m.
Next Ordinance 3834
Next Resolution 995
AGENDA ITEM: A
DATE: June 9, 2021
TO: Mayor Boudreau and City Council
FROM: Peter Donovan, Project Development Manager
SUBJECT: INTERLOCAL AGREEMENT WITH SKAGIT COUNTY FOR GRANT FUNDING
RECOMMENDED ACTION:
Motion
INTRODUCTION/BACKGROUND:
The City of Mount Vernon applied for Skagit County’s Economic Development Grant funding, for the
purpose of making improvements to the “front of house” area of the City-owned, historic Lincoln
Theatre. The improvements will be made within the current footprint of the property, and expand
restroom facilities while enhancing the flow of patron traffic throughout the lobby area.
FINDINGS/CONCLUSIONS:
Skagit County Commissioners selected the City’s Lincoln Theatre Project to receive $100,000 in its 2021
Economic Development Grant Funding cycle.
RECOMMENDATION:
Staff recommends that the Council authorize the Mayor to enter into this interlocal agreement with
Skagit County in the amount of $100,000; for improvements to the historic Lincoln Theatre.
ATTACHED:
Draft Interlocal Agreement with Skagit County
City Application for Economic Development Grant funds
INTERLOCAL COOPERATIVE AGREEMENT
BETWEEN
SKAGIT COUNTY AND CITY OF MOUNT VERNON
FOR FRONT OF HOUSE RENOVATIONS
THIS INTERLOCAL AGREEMENT is entered into this _____ day of
_________________, 2021 between Skagit County, Washington (the “County”) and City
of Mount Vernon, a Washington Municipal Corporation (the “Recipient”) pursuant to the
authority granted by Chapter 39.34 RCW, INTERLOCAL COOPERATION ACT, and in
consideration of the mutual benefits do hereby agree as follows:
1. Purpose: The purpose of the contract is to distribute economic development funds
pursuant to RCW 82.14.370.
2. Scope of Work: Recipient will use the funds distributed under this agreement
pursuant to the intent and purpose of RCW 82.14.370. Further, Recipient is to use such
funds for the Public Facility Project described in Recipient’s Economic Development
Applications submitted to the County which are attached to this document as Exhibit “A”.
3. Payment: County will compensate Recipient a maximum of $100,000, chargeable to
GL expenditure code # 342 58502414109. Recipient shall submit an invoice describing the
use of funds to be distributed by the County and the County upon receipt of appropriate
documentation shall distribute a portion of the awarded funding as determined by the County
Contract Representative described in Paragraph 6.1 of this Contract. However, such
payments shall not occur more often than monthly, through the County voucher system. The
County Contract Representative has the sole discretion of determining what appropriate
documentation is required in order for Recipient to receive a distribution of funds under this
Agreement.
4. Recipient agrees that in the event the county or other state or federal agency finds
that the funds distributed pursuant to this agreement violate any state or federal laws
including but not limited to the primary purpose for which funds pursuant to this
agreement are being given, Recipient agrees to return the funds provided by County
under this agreement to County including any penalties and interest, and agrees to hold
County harmless and indemnify County for distributing such funds contrary to state or
federal law. Further, in the event that funds provided to Recipient under this agreement
are used for a purpose other then what was originally described in its application of funds,
then Recipient agrees to return such funds to the County upon demand.
5. The parties agree that Recipient is an independent contractor and not an employee,
or agent of Skagit County. Recipient hereby agrees not to make any representations to any
third party or to allow such third party to remain under the misimpression that Recipient is
an employee, independent contractor, or agent of Skagit County. All payments made
hereunder and all services performed shall be made and performed pursuant to this
Agreement. Recipient will defend, indemnify and hold harmless the County, its officers,
agents or employees from any loss or expense, including but not limited to settlements,
judgments, setoffs, attorneys’ fees or costs incurred by reason of claims or demands
because of breach of the provisions of this paragraph. Further the Recipient represents that
all employees and sub-contractors are covered under Industrial Insurance in compliance
with R.C.W. Title 51.
6. Administration: The following individuals are designated as representatives of the
respective parties. The representatives shall be responsible for administration of this
Agreement and for coordinating and monitoring performance under this Agreement. In the
event such representatives are changed, the party making the change shall notify the other
party in writing.
6.1 The County's representative shall be the Budget and Finance Director:
Trisha Logue
1800 Continental Place, Suite 100
Mount Vernon, WA 98273
6.2 Recipient's representative shall be the Project Development Manager:
Peter Donovan
910 Cleveland Avenue
Mount Vernon, WA 98273
All notices and payments mailed by regular post (including first class) shall be deemed to
have been given on the second business day following the date of mailing, if properly mailed
and addressed. Notices and payments sent by certified or registered mail shall be deemed
to have been given on the day next following the date of mailing, if properly mailed and
addressed. For all types of mail, the postmark affixed by the United States Postal Service
shall be conclusive evidence of the date of mailing.
7. Defense & Indemnity Agreement: The Recipient agrees to defend, indemnify and
save harmless the County, its appointed and elective officers and employees, from and
against all loss or expense, including but not limited to judgments, settlements, attorney's
fees and costs by reason of any and all claims and demands upon the County, its elected
or appointed officials or employees for damages because of personal or bodily injury,
including death at any time resulting therefrom, sustained by any person or persons and on
account of damage to property including loss of use thereof, whether such injury to persons
or damage to property is due to the negligence of the Recipient, its subcontractors, its
elected officers, employees or their agents, except only such injury or damage as shall have
been occasioned by the sole negligence of the County, its appointed or elected officials or
employees. It is further provided that no liability shall attach to the County by reason of
entering into this contract, except as expressly provided herein. Recipient insurance shall
be primary. Any insurance or self-insurance maintained by the County, its officers, officials,
employees or volunteers shall be excess of Recipient’s insurance and shall not contribute
to it.
8. This Agreement shall become effective upon execution of Resolution No.
R20210098. Work on the project shall be substantially complete and contract shall expire
November 30, 2021. For the purposes of this paragraph, the term “substantially complete”
shall mean “when the contract work has progressed to the extent that the Recipient has full
use and benefit of the facilities, both from the operational and safety standpoint, and only
minor incidental work, replacement of temporary substitute facilities, or correction or repair
remains to physically complete the total contract.” Upon termination of this Agreement, all
property acquired by the Recipient shall remain the Recipient’s property, with no obligation
to pay the County therefore.
9. The Recipient shall not assign any interest in this Contract and shall not transfer any
interest in same without prior written County consent.
10. The Recipient will secure, at his own expense, all personnel required in performing
said services under this Contract. Recipient shall be personally liable for applicable payroll,
Labor and Industries premiums, and all taxes, and shall hold the County harmless from any
claims related thereto.
11. Right to Review: This contract is subject to review by the State Auditor's office. The
County or its designee shall have the right to review and monitor the financial components
of this project. Such review may include, but is not limited to, on-site inspection by County
agents or employees, and inspection of all records of other materials, which the County
deems pertinent to the Agreement and its performance. Recipient shall preserve and
maintain all financial records and records relating to this project under this Agreement for 3
years after contract termination, and shall make them available for such review, within Skagit
County, State of Washington, upon request.
12. Acknowledgement of Funding: All books, informational pamphlets, press releases,
research reports, articles, requests for information, signs or other public notices developed
for or referring to the activities or programs funded by this agreement shall include the
statement, “This project received funding from Skagit County,” or similar language
acknowledging Skagit County’s funding contribution. Further, Recipient shall notify the
County (or Administrative Services) no later than two weeks before a dedication ceremony
or public event for any activities or programs funded by this agreement. Recipient shall also
make efforts to verbally acknowledge the County’s contributions to the Recipient at all
dedication ceremonies or other public events relating to any programs or projects funded by
this agreement.
13. Prevailing Wages: If Prevailing Wages are applicable to the work provided under the
Agreement then Recipient shall submit a “Statement of Intent to Pay Prevailing Wages” prior
to submitting first application for payment. Each statement of intent to pay prevailing wages
must be approved by the Industrial Statistician of the Department of Labor and Industries
before it is submitted to the County. Unless otherwise authorized by the Department of Labor
and Industries, each voucher claim submitted by a Recipient for payment on a project
estimate shall state that the prevailing wages have been paid in accordance with the pre-
filed statement or statements of Intent to Pay Prevailing Wages on file with the public
agency.
14. Nondiscrimination: During the performance of this contract, the Recipient shall
comply with all federal and state nondiscrimination statutes and regulations. These
requirements include, but are not limited to:
a. Nondiscrimination in Employment: The Recipient shall not discriminate
against any employee or applicant for employment because of race, color, sex, religion,
national origin, creed, marital status, age, Vietnam era or disabled veterans status, or the
presence of any sensory, mental, or physical handicap. Such action shall include, but not
be limited to, the following: Employment, upgrading, demotion, or transfer, recruitment or
recruitment selection for training, including apprenticeships and volunteers. This
requirement does not apply, however, to a religious corporation, association, educational
institution or society with respect to the employment of individuals of a particular religion to
perform work connected with the carrying on by such corporation, association, educational
institution or society of its activities.
15. Compliance with Applicable Law: The Recipient and all subcontractors of
Recipient shall comply with, and the Department is not responsible for determining
compliance with, any and all applicable federal, state, and local laws, regulations, and/or
policies. This obligation includes, but is not limited to, nondiscrimination laws and/or
policies; the Americans with Disabilities Act (ADA); Ethics in Public Service (RCW 42.52);
Covenant Against Contingent Fees (48 C.F.R. Sec. 52.203-5); safety and health
regulations. In the event of the Recipient’s or a subcontractor’s noncompliance or refusal
to comply with any law or policy, the Department may rescind, cancel, or terminate the
contract in whole or in part. The Recipient is responsible for any and all costs or liability
arising from the Recipient’s failure to so comply with applicable law.
16. Venue and Choice of Law: In the event that any litigation should arise concerning
the construction or interpretation of any of the terms of this Agreement, the venue of such
action of litigation shall be in the Superior Court of the State of Washington in and for the
County of Skagit. This Agreement shall be governed by the laws of the State of
Washington.
17. No Separate Legal Entity: It is understood and agreed that this Agreement is solely
for the benefit of the parties hereto and gives no right to any other party. No joint venture
or partnership is formed as a result of the Agreement.
18. Termination of Contract for Cause
a. If, through any cause, the Recipient shall fail to fulfill in a timely and proper
manner its obligations under this contract or if the Recipient shall violate any of its
covenants, agreements, or stipulations of this contract, the County shall thereupon have
the right to terminate this contract and withhold the remaining allocation if such default or
violation is not corrected within thirty (30) days after submitting written notice to the
Recipient describing such default or violation. Further, in the event Recipient fails to
expend funds under this contract in accordance with State or Federal laws and/or the
provisions of the agreement, the County reserves to right to recapture funds expended to
Recipient in an amount equal to the extent of the noncompliance.
b. The County may unilaterally terminate all or part of this contract, or may
reduce its scope of work and budget, if there is a reduction in funds by the source of
those funds, and if such funds are the basis for this contract.
19. Termination for Public Convenience: The County may terminate the contract in
whole or in part whenever the County determines, in its sole discretion, that such termination
is in the best interests of the County. Whenever the contract is terminated in accordance
with this paragraph, the Recipient shall be entitled to payment for actual work performed at
unit contract prices for completed items of work. An equitable adjustment in the contract
price for partially completed items of work will be made, but such adjustment shall not
include provision for loss of anticipated profit on deleted or uncompleted work. Termination
of this contract by the County at any time during the term, whether for default or
convenience, shall not constitute a breach of contract by the County. If sufficient funds are
not appropriated or allocated for payment under this contract for any future fiscal period, the
County will not be obligated to make payments for services or amounts incurred after the
end of the current fiscal period. No penalty or expense shall accrue to the County in the
event this provision applies.
20. Nonassignability: Neither this contract, nor any claim arising under this contract,
shall be transferred or assigned by the Recipient.
21. Taxes: All payments accrued on account of payroll taxes, unemployment
contributions, any other taxes, insurance or other expenses for the Recipient or its staff
shall be the sole responsibility of the Recipient.
City of Mount Vernon
Signature
(Date )
Print Name
Title
Mailing Address:
910 Cleveland Avenue
Mount Vernon, WA 98273
Telephone No.
360-336-6207 Fed. Tax ID #
91-6001260
Contractor Lic. #. N/A
DATED this _____ day of _______________, 2021.
BOARD OF COUNTY COMMISSIONERS
SKAGIT COUNTY, WASHINGTON
Lisa Janicki, Chair
Peter Browning, Commissioner
Attest: Ron Wesen, Commissioner
Clerk of the Board
For contracts under $5,000:
Authorization per Resolution R20030146
Recommended: County Administrator
Department Head
Approved as to form:
Civil Deputy Prosecuting Attorney
Approved as to indemnification:
Risk Manager
Approved as to budget:
Budget & Finance Director
Exhibit A
AGENDA ITEM: B
DATE: June 9, 2021
TO: Mayor Boudreau and City Council
FROM: Chris Phillips, Development Services Director
SUBJECT: APPOINTMENT OF JAMES FIKKERT TO THE PLANNING COMMISSION
RECOMMENDED ACTION:
Staff requests that Council confirm the Mayor’s appointment of James Fikkert to the Planning
Commission
INTRODUCTION/BACKGROUND:
James Fikkert has Master’s Degree in Urban Planning, has worked in the development/construction
private sector, and has volunteered countless hours serving the local community on a variety of issues
that include low income housing solutions, small business initiatives and a variety of redevelopment
proposals. He will serve on the Planning Commission from today to which expires on 31 December 2023.
FINDINGS/CONCLUSIONS:
The requirements of MVMC Chapter 2.60 have been satisfied with the recommended appointment of
James Fikkert to the Planning Commission.
RECOMMENDATION:
Confirm the Mayor’s appointment to the Planning Commission.
ATTACHED:
Planning Commission Resume
AGENDA ITEM: C
DATE: April 14, 2021
TO: Mayor Boudreau and City Council
FROM: William Bullock, PE – City Engineer
SUBJECT: SCHEDULE PUBLIC HEARING: ADOPTION OF THE 2022-2027 SIX-YEAR
TRANSPORTATION IMPROVEMENT PROGRAM
RECOMMENDED ACTION:
Set a public hearing date for the adoption of the Mount Vernon 2022-2027 Six-Year
Transportation Program (TIP).
INTRODUCTION/BACKGROUND:
State law, RCW 35.77.010, requires that each year the City adopt a six-year Transportation
Improvement Program (TIP). The TIP is designed to identify the schedule, costs, and financial
plan associated with capital projects the City intends to complete during the next six years. The
adopted financial plan must detail conceptual project costs and demonstrate that funding for
the TIP is feasible, although it may include projections of local funds, grants, loans or other
potential sources that are not yet secured.
FINDINGS/CONCLUSIONS:
The draft TIP will be presented for discussion, highlighting the projects slated for years 1-3 and
new projects added to the program during the latest planning cycle. Any modifications to the
draft TIP will be made and brought forward in a final version for adoption at the June 23, 2021
public hearing.
RECOMMENDATION:
Staff recommends a motion to authorize the Mayor to direct staff to schedule a Notice for
public hearing on April 28, 2021 for the consideration and adoption of the 2022 -2027 Mount
Vernon Six-Year Transportation Improvement Program.
ATTACHED:
1. Public Hearing Notice
2. 2022-2027 TIP Project List
CITY OF MOUNT VERNON, WASHINGTON
NOTICE OF PUBLIC HEARING
2022-2027 SIX-YEAR TRANSPORTATION IMPROVEMENT PROGRAM
NOTICE IS HEREBY GIVEN that the City Council of the City of Mount Vernon will hold a
public hearing regarding the proposed 2022-2027 Six-Year Transportation Improvement
Program on June 23, 2021. The public hearing will be held at City Council Chambers, 1805
Continental Place, Mount Vernon WA, beginning at 7:00 p.m. or as soon thereafter as possible.
Copies of the proposed Six-Year Transportation Improvement Program are available for review
at the Public Works Department at 1024 Cleveland Ave, Mount Vernon, or by calling William
Bullock at 360-336-6204.
Dated this 9th day of June, 2021.
Doug Volesky,
City Clerk
Publish: Skagit Velley Herald June 11 & June18, 2021
Mount Vernon 2022-2027 Six Year TIP Project List
City Wide - Local Street Improvements
City Wide - Signal Maintenance Program
City Wide - Sidewalk Gap Program
ADA Sidewalk Transition Program
Library Commons Project
Hoag/Laventure Intersection Improvements
College Way Separated Rail Crossing
Minor Intersection Enhancements
Riverside Drive Improvements- 2
Fowler Trail Connection
30th Street Improvements
Riverside Drive Improvement - 1
Laventure Road Widening
Fir Street Widening
15th Street Sidewalk Improvements
30th Street Improvements - 2
River Dike Trail System - Phase 1
Broad Street Improvements
Martin Road Improvements
Laventure/Blackburn Intersection Improvement
Blackburn Road Widening -1
Kincaid Street Corridor Improvements
Hickox/I-5 Interchange Completion
18th Street/Blackburn Intersection Improvements
Blackburn Road Extension
30th Street Extension
Skagit River Pedestrian Bridge
AGENDA ITEM: D
DATE: June 9, 2021
TO: Mayor Boudreau and City Council
FROM: William Bullock, PE – City Engineer
SUBJECT: PROFESSIONAL SERVICES AGREEMENT AMENDMENT:
CONSTRUCTION MANAGEMENT: FREEWAY DRIVE IMPROVEMENTS PROJECT
RECOMMENDED ACTION:
Staff recommends amending the Professional Services Agreement with PBS Engineering and
Environmental (PBS) for contract management services for the Freeway Drive Improvements Project.
INTRODUCTION/BACKGROUND:
This project accomplishes five main improvements to Freeway Drive: adds sidewalk on the west side and
bike lanes on both sides, establishes new storm water facilities, enhances corridor street lighting,
improves intersection channelization, and rehabilitates the pavement. A key highlight of these upgrades
is the new and continuous pedestrian connection from Lions Park (and downtown) to College Way.
Federal funding (STBG program) was prioritized through Skagit Council of Governments; total award
amount of $2,170,000 (Design - $260,000 and Construction - $1,910,000); additional construction
funding allocated to the project will come from the stormwater fund ($310,000) and TBD ($99,000).
FINDINGS/CONCLUSIONS:
PBS is currently under contract for design services of the Freeway Drive project which is now ready to
bid for construction. Staff recommends amending the current contract with PBS to include construction
management services (i.e. full time inspection, contractor administration, testing coordination, change
orders, etc).
RECOMMENDATION:
Motion to authorize the Mayor to execute a contract amendment with PBS Engineering and
Environmental, Inc. to provide construction management services on the Freeway Drive Improvements
Project in an amount not to exceed $203,290.00.
ATTACHED:
1. Contract, Scope and Fee
2. Vicinity Map
May 27, 2021
Bill Bullock, PE
City of Mount Vernon
1024 Cleveland Avenue
Mount Vernon, Washington 98273
Via email: billb@mountvernonwa.gov
Regarding: Amendment 1 to Freeway Drive, Cameron Way to College Way Project
Mount Vernon, Washington
Project No. TS-2020-006
Federal Aid #STPUS-7333(001)
PBS Project 45033.000
Dear Bill:
PBS Engineering and Environmental Inc. (PBS, Consultant) is pleased to submit this proposal to the City of Mount
Vernon (City) to provide additional services for the Freeway Drive, Cameron Way to College Way project in Mount
Vernon, Washington. Amendment 1 is necessary for new tasks related to construction management and
inspection services, as described below under Task 1300, Task 1400, and Task 1500.
SCOPE OF WORK
PBS proposes the following scope of work for the Freeway Drive, Cameron Way to College Way project’s
construction management and inspection services.
TASK 100. PROJECT MANAGEMENT
Additional project management time related new tasks and additional invoicing for extended schedule.
Subtask 110. Contract Administration, Invoicing, and Progress Reports
Consultant will provide general oversight of the construction management services, including monitoring budget,
schedule, and scope of work for these services. Consultant will provide monthly invoicing with progress reports.
Consultant will coordinate with the contractor’s project manager and City of Mount Vernon throughout the
construction duration of the project.
Subtask 110 Deliverables
Monthly invoices, progress reports
Project documentation
Subtask 120. Preconstruction and Kickoff Meetings
An initial kickoff/coordination meeting will be conducted with PBS’ project team and City staff to establish
procedures/protocols and communication requirements for the project. Consultant will assist City staff with the
bid opening, award and execution of the construction contract. Consultant will assist the City with coordination of
the preconstruction conference. Consultant will produce an agenda and take meeting notes.
1180 NW MAPLE STREET, SUITE 160, ISSAQUAH, WA 98027 425.654.8775 MAIN 866.727.0140 FAX PBSUSA.COM
City of Mount Vernon
Proposal to Provide Construction Management Services – Freeway Drive, Cameron Way to College Way Project
May 27, 2021
Page 2 of 6
Subtask 120 Assumptions
Coordination and preconstruction meetings will be attended by the PBS project manager and
construction manager, and inspector.
Subtask 120 Deliverables
Preconstruction conference meeting agenda and notes provided to the City and the prime Contractor.
TASK 1300. CONSTRUCTION MANAGEMENT AND ENGINEERING
All project documentation will be maintained on a SharePoint site. Consultant will give City staff access to the
SharePoint site.
Subtask 1310. Record of Materials (ROM)
Consultant will prepare and maintain the project Record of Materials (ROM). The ROM will consist of all the
materials submitted for the project along with each material’s associated plan/specification reference, description,
material approval notes, and material acceptance codes/comments. The ROM will also be used to track material
acceptance testing as outlined in Task 1500.
Subtask 1310 Deliverables
Copy of ROM
Subtask 1320. Material Submittals
Consultant will receive and review material submittals (manufacturer’s certificates of compliance, certificates of
material origin, qualified product list sheets, Buy America certificates, etc.), construction sequence schedules, shop
drawings, and other required items from the Contractor to ensure compliance with contract documents.
Consultant will review the following submittals, including but not limited to material-specific submittals, HMA and
concrete mix designs, landscape items, drainage materials, traffic items, and other items required by construction
contract specifications.
Consultant will receive, review, and maintain material submittals. Upon completion of review, consultant will
transmit the approved submittals to the Contractor.
Subtask 1320 Assumptions
Assumes up to 32 material submittals covering materials as listed in the current engineer’s estimate.
Assumes 3 hour per submittal.
Assumes all pavement marking, signing and traffic loop items are QPL products not requiring approval
testing.
Subtask 1320 Deliverables
Copies of approved material submittals
Copies of written communication with the Contractor
Copy of material submittal log
45033.001
City of Mount Vernon
Proposal to Provide Construction Management Services – Freeway Drive, Cameron Way to College Way Project
May 27, 2021
Page 3 of 6
Subtask 1330. Construction Administration and Engineering
PBS’ construction manager will coordinate with City staff throughout the duration of the project, keep a record of
decisions made, review and recommend solutions to change order requests, maintain material quantities, and
review progress and final pay estimates. Consultant will prepare Weekly Statement of Working Days weekly and
will transmit to the Contractor at the end of each week. Consultant will review the following construction
submittals, including but not limited to traffic control plans, construction schedules, quality control plan, erosion
and pollution control plans, and other items required by construction contract specifications. A half hour weekly
construction coordination meeting will be held in which the Consultant will prepare meeting agenda and minutes.
Subtask 1330 Assumptions
Assumes one review of each document followed by feedback/comments to the Contractor.
Assumes additional review for half of resubmitted documents.
Subtask 1330 Deliverables
Copies of construction submittals provided by the Contractor with approval
Review of Monthly Pay Estimates for review and approval
Copies of written communication
Records of field decisions
Copies of schedules provided by the Contractor
Copies of Weekly Statement of Working Days
Subtask 1340. Request for Information Responses and Change Orders
Consultant will assist the City in response to Requests for Information (RFIs) by the Contractor and provide
supplemental information as needed to maintain the progress of the work. Consultant will provide the City with
draft change order write ups for review, approval, and issuance to the Contractor. The consultant will perform
change management consultation and perform change order coordination between the City and the Contractor.
Subtask 1340 Assumptions
Responses for up to 18 RFIs
Prepare up to five change orders
Formal design plan revisions for owner-initiated change orders are not covered under scope of work.
Subtask 1340 Deliverables
Copies of RFIs to the City staff
Draft change orders to the City for approval and issuance to the Contractor
Subtask 1350. Closeout Documentation
Consultant will compile project closeout documentation and coordinate with the Contractor and the City to obtain
the required documents. Consultant will assemble project documentation and deliver to the City at project
completion.
Consultant and the City staff will perform final inspections and create a punch list. Consultant and the City staff
will establish dates of substantial, physical, and contract completion.
The Consultant will prepare as-builts for the project in pdf red line format for City Archiving. AutoCAD Civil 3D
updated files for project features will be updated as necessary and provided to the City.
45033.001
City of Mount Vernon
Proposal to Provide Construction Management Services – Freeway Drive, Cameron Way to College Way Project
May 27, 2021
Page 4 of 6
Subtask 1350 Deliverables
Copy of construction management (CM) project binder (electronic on CD or USB flash drive).
As-Built Plan Red-Lines for the City of Mount Vernon
TASK 1400. CONSTRUCTION OBSERVATION (INSPECTION)
Consultant will provide an on-site inspector for the 90-day construction schedule for an average of eight hours
per day. Consultant will adequately inspect all items constructed for the project according to the project contract
documents and any applicable contractor submittals or changes to the contract. The inspector will coordinate key
“hold points” with the contractor that require inspection before further construction activity takes place in an
effort to adequately check contractor work for conformance with the contract documents. The inspector will
coordinate all materials testing and third-party coordination as required. The inspector will coordinate field
construction related matters directly with the City of Mount Vernon staff as the project construction point of
contact.
Consultant will prepare inspector daily reports (IDRs) (to include construction progress photos and material
tickets) to document construction and write pay notes for contractor progress payments.
Task 1400 Assumptions
The project duration will be 90 working days. Inspector will work eight hours a day on average.
Inspector will be on site for all the construction operations and at a minimum for key inspection points in the
construction process.
Task 1400 Deliverables
IDRs
Construction progress photos
Material tickets
Pay notes
TASK 1500. MATERIAL TESTING (GeoTest)
Consultant will perform compaction testing to include HMA testing and cement concrete testing. Consultant will
perform additional materials testing in conjunction with the contractor’s construction staging that does not cause
delay to the contractor’s operations. Materials testing will be performed to the WSDOT Standard Specifications,
WSDOT Construction Manual, and WSDOT Materials Manual.
Consultant will also prepare testing reports for all material tests made (laboratory and field).
Task 1500 Assumptions
Full aggregate acceptance sieve analysis and protector testing is required for acceptance testing, including all
grading, surfacing, HMA, and concrete aggregates.
o Gravel Borrow – two tests
o CSTC – two tests
o CSBC – two tests
o Coarse Aggregates for Concrete – two tests
45033.001
City of Mount Vernon
Proposal to Provide Construction Management Services – Freeway Drive, Cameron Way to College Way Project
May 27, 2021
Page 5 of 6
o Fine Aggregates for Concrete – two tests
o HMA - two tests
Field testing of HMA, concrete, surfacing, and backfill will be performed.
o HMA – 8 days of testing (including lab testing)
o Surfacing - 8 days of testing (including lab testing)
o Backfill – 6 days of testing
o Commercial Concrete (Class 3000) – 2 tests
o Concrete for Driveways (Class 4000) – 6 tests
All testing will be done to the contractor’s construction staging and schedule, including testing for corrective
action on previously failed compaction tests.
Task 1500 Deliverables
Field material acceptance test reports
Laboratory material acceptance test reports
REIMBURSABLE EXPENSES
Consultant has included reimbursable expenses for:
Vehicle mileage
AMENDMENT 1 COMPENSATION ESTIMATE
PBS proposes to provide the scope of work on a time-and-materials basis. The following outlines the estimated
costs associated with the scope services.
Task 100. Project Management $11,840
Task 1300. Construction Management and Engineering $55,150
Task 1400: Construction Observation (Inspection) $96,800
Task 1500: Material Testing (GeoTest) $32,200
Reimbursable Expenses $7,300
Total Estimated Costs $203,290
This cost estimate includes all labor, materials, transportation, equipment, and other expenses required to
complete the work described. The total contract amount is not to exceed $203,290. See attached cost estimates
as back up for each line item.
SCHEDULE
PBS will perform the work in accordance with the contractor’s construction schedule.
Please feel free to contact me at 425.654.8769 or joe.hudson@pbsusa.com with any questions or comments.
45033.001
City of Mount Vernon
Proposal to Provide Construction Management Services – Freeway Drive, Cameron Way to College Way Project
May 27, 2021
Page 6 of 6
Sincerely,
Joe Hudson, PE
Senior Engineer/Project Manager
GH:DAS:lc
45033.001
Amendment 1
Freeway Drive, Cameron Way to College Way
Construction Management
City of Mount Vernon, Washington PBS
PBS Engineering and Environmental
(Engineering/Management) PBS SUBCONSULTANTS SUB Construction Management
ENG-
Task and Description PRINCIPAL ENG VIII ENG VII ENG III ENG II PRJ ADMIN III PRJ ADMIN II ADMIN Expense TOTAL GeoTest TOTAL BUDGET AMOUNT
Task 100: Project Management 11,840.00 0.00 11,840.00
Subtask 110: Contract Administration, Invoicing, and Progress Reports 36.00 16.00 8,700.00 0.00 $8,700.00
Subtask 120: Preconstruction and Kickoff Meetings 4.00 8.00 4.00 4.00 3,140.00 0.00 $3,140.00
Task 1300: Construction Management and Engineering 55,150.00 0.00 55,150.00
Subtask 1310: Record of Materials (ROM) 16 28 56 11,980.00 0.00 $11,980.00
Subtask 1320: Material Submittals 16.00 52.00 24.00 12,180.00 0.00 $12,180.00
Subtask 1330: Construction Administration and Engineering 36.00 36.00 10,440.00 0.00 $10,440.00
Subtask 1340: Request for Information Responses and Change Orders 24.00 18.00 24.00 9,390.00 0.00 $9,390.00
Subtask 1350: Closeout Documentation 12.00 40.00 36.00 11,160.00 0.00 $11,160.00
Task 1400: Construction Observation (Inspection) 96,800.00 0.00 96,800.00
Construction Observation 680.00 40.00 96,800.00 0.00 $96,800.00
Task 1500: Material Testing (GeoTest) 0.00 32,200.00 32,200.00
Material Testing 0.00 32,200.00 32,200.00 $32,200.00
Reimbursable Expenses 7,300.00 0.00 $7,300.00
Copies 0.00 0.00 $0.00
Expenses 0.00 0.00 $0.00
Travel 7,300.00 7,300.00 0.00 $7,300.00
0.00 0.00
0.00 0.00 $0.00
0.00 $0.00
TOTAL HOURS 0.00 112.00 40.00 822.00 40.00 16.00 180.00 0.00
HOURLY RATES 230.00 195.00 180.00 135.00 125.00 105.00 95.00 75.00
TOTAL DOLLARS 0.00 21,840.00 7,200.00 110,970.00 5,000.00 1,680.00 17,100.00 0.00 171,090.00 32,200.00 0.00 0.00 32,200.00 203,290.00
PBS Project 45033.000
May 17, 2021
GeoTest Services Inc. Proposal No. 21-268T
Arlington, Bellingham, Oak Harbor
Freeway Drive Corridor Improvements
Mount Vernon, WA
Conceptual Scope & Budget: Construction Civil Testing Services
GeoTest is pleased to submit this cost estimate for the above project. Based on a review of the project plans and our
understanding of the construction duration, we believe that the costs for the scope of work detailed below will be
approximately $25,723.
Understanding that construction schedules and logistics can vary, we recommend an anticipated budget range of $23,000 to
$28,000 . This is a time and materials estimate intended for budgeting purposes. Our costs are a direct reflection of the project
construction schedule.
ASSUMPTIONS
The estimated construction duration is approximately 90 working days. We anticipate that GeoTest's presence will be needed periodically.
BUDGET BY DISCIPLINE
FIELD: CONSTRUCTION SPECIAL INSPECTION & TESTING
EARTHWORK
Perform field in-place density tests for structural fills/backfills at civil area and utilities.
Collect samples for laboratory testing as required.
Detail Visits Hours Unit Rate Total
Density Testing/Soils Inspection 7 8 $78 4,368
Density Testing/Soils Inspection 7 4 $78 2,184
Subtotal $6,552
ASPHALT
Test and inspect asphalt pavement during placement and compaction.
Sampling from production facility.
Detail Visits Hours Unit Rate Total
HMA Asphalt Paving - Compaction Tests 4 8 $78 $2,496
HMA Asphalt Paving - Compaction Tests 4 4 $78 1,248
HMA Asphalt Paving - Compaction Tests Nightwork 3 8 $117 2,808
Asphalt Plant - Sample Pick-Up and Processing 8 3 $78 1,872
Asphalt Plant - Sample Pick-Up and Processing Nightwork 3 8 $117 2,808
HMA Asphalt Paving - Lab Staff Nightwork 3 4 $117 $1,404
Subtotal $8,424
CONCRETE
Continuous inspection during placement, including sampling, slump, air, temperature and taking concrete specimens.
Test concrete for compressive strength.
Detail Visits Hours Unit Rate Total
Sidewalk Curb & Gutter 2 6 $75 $900
Driveways 6 6 $75 $2,700
Sample Pickup and Processing 8 3 $75 1,800
Subtotal $5,400
Page 1 of 2
May 17, 2021
GeoTest Services Inc. Proposal No. 21-268T
Arlington, Bellingham, Oak Harbor
OTHER
Detail Hours Unit Rate Total
Project Manager - Health & Safety, Review, Meetings, Closeout 12 $100 $1,200
Trip Charge (44 rt/mi x 0.60/mi = $26/trip) 52 $26 1,352
Subtotal $2,552
FIELD - Total Estimated Budget Civil Testing $17,528
LABORATORY - CONSTRUCTION MATERIALS TESTING
Laboratory testing in accordance with ASTM, WSDOT and project specification criteria.
Number of
Detail Notes Method Unit Rate Total
Tests
Soils: Proctor w Sieves (CSBC, CSTC, Grav. Borrow/Bkfill) T99/T180 6 $260 $1,560
Concrete Aggregate: Sieves T27/T11 4 $160 640
Soils: Sand Equivalent (CSBC, CSTC, Grav. Borrow/Bkfill) T176 6 $80 480
Soils: Percent Fracture (CSBC, CSTC) T355 2 $80 160
Concrete Compression Tests 8 sets x 5 ea. 40 $28 1,120
Asphalt Extraction/Gradation T308/T27/T11 11 $285 3,135
Asphalt Rice Density T209 11 $100 1,100
Subtotal $8,195
LABORATORY - Total Estimated Budget Construction Materials Testing $8,195
Total Estimated Budget - Construction Special Inspection & Testing $25,723
Page 2 of 2
Vicinity Map
College Way
§
¦
¨
5 Project Limits
Kulshan Trail
Riverwalk Trail
0 500 1,000 2,000
Feet ±
Freeway Drive
Kulshan Trail
Lions Park
Cameron Way
Riverwalk Trail
536
¥
Downtown
AGENDA ITEM: E
DATE: June 1, 2021
TO: Mayor Boudreau and City Council
FROM: Isaac Huffman, Library Director
SUBJECT: INTERLOCAL AGREEMENT WITH SKAGIT COUNTY
RECOMMENDED ACTION:
Motion
INTRODUCTION/BACKGROUND:
This year the Library Commons Project was awarded a $500,000 economic development
grant. The Rural Distressed Counties sales tax supports this grant program. The program's
goal is to add living wage jobs in Skagit County, which the Mount Vernon Commons Project
will surely do.
Because the grant has specific use requirements, an interlocal agreement between Skagit
County and the City of Mount Vernon is required. A similar interlocal agreement was signed
as part of the Skagit floodwall project.
THE MOUNT VERNON CITY LIBRARY REQUEST COUNCIL TO AUTHORIZE THE
MAYOR TO ENTER INTO A INTERLOCAL AGREEMENT WITH THE SKAGIT COUNTY
FOR GRANT FUNDING
FINDINGS/CONCLUSIONS:
The terms in this agreement align with similar interlocal agreements for receiving funding. It is
recommended that we sign the agreement to receive grant funding.
RECOMMENDATION:
Approve
ATTACHED:
INTERLOCAL COOPERATIVE AGREEMENT FOR GRANT FUNDS
INTERLOCAL COOPERATIVE AGREEMENT
BETWEEN
SKAGIT COUNTY AND CITY OF MOUNT VERNON
FOR MOUNT VERNON LIBRARY COMMONS
THIS INTERLOCAL AGREEMENT is entered into this _____ day of
_________________, 2021 between Skagit County, Washington (the “County”) and City
of Mount Vernon, a Washington Municipal Corporation (the “Recipient”) pursuant to the
authority granted by Chapter 39.34 RCW, INTERLOCAL COOPERATION ACT, and in
consideration of the mutual benefits do hereby agree as follows:
1. Purpose: The purpose of the contract is to distribute economic development funds
pursuant to RCW 82.14.370.
2. Scope of Work: Recipient will use the funds distributed under this agreement
pursuant to the intent and purpose of RCW 82.14.370. Further, Recipient is to use such
funds for the Public Facility Project described in Recipient’s Economic Development
Applications submitted to the County which are attached to this document as Exhibit “A”.
3. Payment: County will compensate Recipient a maximum of $500,000, chargeable to
GL expenditure code # 342 58502334109. Recipient shall submit an invoice describing the
use of funds to be distributed by the County and the County upon receipt of appropriate
documentation shall distribute a portion of the awarded funding as determined by the County
Contract Representative described in Paragraph 6.1 of this Contract. However, such
payments shall not occur more often than monthly, through the County voucher system. The
County Contract Representative has the sole discretion of determining what appropriate
documentation is required in order for Recipient to receive a distribution of funds under this
Agreement.
4. Recipient agrees that in the event the county or other state or federal agency finds
that the funds distributed pursuant to this agreement violate any state or federal laws
including but not limited to the primary purpose for which funds pursuant to this
agreement are being given, Recipient agrees to return the funds provided by County
under this agreement to County including any penalties and interest, and agrees to hold
County harmless and indemnify County for distributing such funds contrary to state or
federal law. Further, in the event that funds provided to Recipient under this agreement
are used for a purpose other then what was originally described in its application of funds,
then Recipient agrees to return such funds to the County upon demand.
5. The parties agree that Recipient is an independent contractor and not an employee,
or agent of Skagit County. Recipient hereby agrees not to make any representations to any
third party or to allow such third party to remain under the misimpression that Recipient is
an employee, independent contractor, or agent of Skagit County. All payments made
hereunder and all services performed shall be made and performed pursuant to this
Agreement. Recipient will defend, indemnify and hold harmless the County, its officers,
Page 1
agents or employees from any loss or expense, including but not limited to settlements,
judgments, setoffs, attorneys’ fees or costs incurred by reason of claims or demands
because of breach of the provisions of this paragraph. Further the Recipient represents that
all employees and sub-contractors are covered under Industrial Insurance in compliance
with R.C.W. Title 51.
6. Administration: The following individuals are designated as representatives of the
respective parties. The representatives shall be responsible for administration of this
Agreement and for coordinating and monitoring performance under this Agreement. In the
event such representatives are changed, the party making the change shall notify the other
party in writing.
6.1 The County's representative shall be the Budget and Finance Director:
Trisha Logue
1800 Continental Place, Suite 100
Mount Vernon, WA 98273
6.2 Recipient's representative shall be the Finance Director:
Doug Volesky
910 Cleveland Avenue
Mount Vernon, WA 98273
All notices and payments mailed by regular post (including first class) shall be deemed to
have been given on the second business day following the date of mailing, if properly mailed
and addressed. Notices and payments sent by certified or registered mail shall be deemed
to have been given on the day next following the date of mailing, if properly mailed and
addressed. For all types of mail, the postmark affixed by the United States Postal Service
shall be conclusive evidence of the date of mailing.
7. Defense & Indemnity Agreement: The Recipient agrees to defend, indemnify and
save harmless the County, its appointed and elective officers and employees, from and
against all loss or expense, including but not limited to judgments, settlements, attorney's
fees and costs by reason of any and all claims and demands upon the County, its elected
or appointed officials or employees for damages because of personal or bodily injury,
including death at any time resulting therefrom, sustained by any person or persons and on
account of damage to property including loss of use thereof, whether such injury to persons
or damage to property is due to the negligence of the Recipient, its subcontractors, its
elected officers, employees or their agents, except only such injury or damage as shall have
been occasioned by the sole negligence of the County, its appointed or elected officials or
employees. It is further provided that no liability shall attach to the County by reason of
entering into this contract, except as expressly provided herein. Recipient insurance shall
be primary. Any insurance or self-insurance maintained by the County, its officers, officials,
employees or volunteers shall be excess of Recipient’s insurance and shall not contribute
to it.
Page 2
8. This Agreement shall become effective upon execution of Resolution No.
R20210093. Work on the project shall be substantially complete and contract shall expire
April 30, 2022. For the purposes of this paragraph, the term “substantially complete” shall
mean “when the contract work has progressed to the extent that the Recipient has full use
and benefit of the facilities, both from the operational and safety standpoint, and only minor
incidental work, replacement of temporary substitute facilities, or correction or repair remains
to physically complete the total contract.” Upon termination of this Agreement, all property
acquired by the Recipient shall remain the Recipient’s property, with no obligation to pay the
County therefore.
9. The Recipient shall not assign any interest in this Contract and shall not transfer any
interest in same without prior written County consent.
10. The Recipient will secure, at his own expense, all personnel required in performing
said services under this Contract. Recipient shall be personally liable for applicable payroll,
Labor and Industries premiums, and all taxes, and shall hold the County harmless from any
claims related thereto.
11. Right to Review: This contract is subject to review by the State Auditor's office. The
County or its designee shall have the right to review and monitor the financial components
of this project. Such review may include, but is not limited to, on-site inspection by County
agents or employees, and inspection of all records of other materials, which the County
deems pertinent to the Agreement and its performance. Recipient shall preserve and
maintain all financial records and records relating to this project under this Agreement for 3
years after contract termination, and shall make them available for such review, within Skagit
County, State of Washington, upon request.
12. Acknowledgement of Funding: All books, informational pamphlets, press releases,
research reports, articles, requests for information, signs or other public notices developed
for or referring to the activities or programs funded by this agreement shall include the
statement, “This project received funding from Skagit County,” or similar language
acknowledging Skagit County’s funding contribution. Further, Recipient shall notify the
County (or Administrative Services) no later than two weeks before a dedication ceremony
or public event for any activities or programs funded by this agreement. Recipient shall also
make efforts to verbally acknowledge the County’s contributions to the Recipient at all
dedication ceremonies or other public events relating to any programs or projects funded by
this agreement.
13. Prevailing Wages: If Prevailing Wages are applicable to the work provided under the
Agreement then Recipient shall submit a “Statement of Intent to Pay Prevailing Wages” prior
to submitting first application for payment. Each statement of intent to pay prevailing wages
must be approved by the Industrial Statistician of the Department of Labor and Industries
before it is submitted to the County. Unless otherwise authorized by the Department of Labor
and Industries, each voucher claim submitted by a Recipient for payment on a project
estimate shall state that the prevailing wages have been paid in accordance with the pre-
Page 3
filed statement or statements of Intent to Pay Prevailing Wages on file with the public
agency.
14. Nondiscrimination: During the performance of this contract, the Recipient shall
comply with all federal and state nondiscrimination statutes and regulations. These
requirements include, but are not limited to:
a. Nondiscrimination in Employment: The Recipient shall not discriminate
against any employee or applicant for employment because of race, color, sex, religion,
national origin, creed, marital status, age, Vietnam era or disabled veterans status, or the
presence of any sensory, mental, or physical handicap. Such action shall include, but not
be limited to, the following: Employment, upgrading, demotion, or transfer, recruitment or
recruitment selection for training, including apprenticeships and volunteers. This
requirement does not apply, however, to a religious corporation, association, educational
institution or society with respect to the employment of individuals of a particular religion to
perform work connected with the carrying on by such corporation, association, educational
institution or society of its activities.
15. Compliance with Applicable Law: The Recipient and all subcontractors of
Recipient shall comply with, and the Department is not responsible for determining
compliance with, any and all applicable federal, state, and local laws, regulations, and/or
policies. This obligation includes, but is not limited to, nondiscrimination laws and/or
policies; the Americans with Disabilities Act (ADA); Ethics in Public Service (RCW 42.52);
Covenant Against Contingent Fees (48 C.F.R. Sec. 52.203-5); safety and health
regulations. In the event of the Recipient’s or a subcontractor’s noncompliance or refusal
to comply with any law or policy, the Department may rescind, cancel, or terminate the
contract in whole or in part. The Recipient is responsible for any and all costs or liability
arising from the Recipient’s failure to so comply with applicable law.
16. Venue and Choice of Law: In the event that any litigation should arise concerning
the construction or interpretation of any of the terms of this Agreement, the venue of such
action of litigation shall be in the Superior Court of the State of Washington in and for the
County of Skagit. This Agreement shall be governed by the laws of the State of
Washington.
17. No Separate Legal Entity: It is understood and agreed that this Agreement is solely
for the benefit of the parties hereto and gives no right to any other party. No joint venture
or partnership is formed as a result of the Agreement.
18. Termination of Contract for Cause
a. If, through any cause, the Recipient shall fail to fulfill in a timely and proper
manner its obligations under this contract or if the Recipient shall violate any of its
covenants, agreements, or stipulations of this contract, the County shall thereupon have
the right to terminate this contract and withhold the remaining allocation if such default or
violation is not corrected within thirty (30) days after submitting written notice to the
Recipient describing such default or violation. Further, in the event Recipient fails to
Page 4
expend funds under this contract in accordance with State or Federal laws and/or the
provisions of the agreement, the County reserves to right to recapture funds expended to
Recipient in an amount equal to the extent of the noncompliance.
b. The County may unilaterally terminate all or part of this contract, or may
reduce its scope of work and budget, if there is a reduction in funds by the source of
those funds, and if such funds are the basis for this contract.
19. Termination for Public Convenience: The County may terminate the contract in
whole or in part whenever the County determines, in its sole discretion, that such termination
is in the best interests of the County. Whenever the contract is terminated in accordance
with this paragraph, the Recipient shall be entitled to payment for actual work performed at
unit contract prices for completed items of work. An equitable adjustment in the contract
price for partially completed items of work will be made, but such adjustment shall not
include provision for loss of anticipated profit on deleted or uncompleted work. Termination
of this contract by the County at any time during the term, whether for default or
convenience, shall not constitute a breach of contract by the County. If sufficient funds are
not appropriated or allocated for payment under this contract for any future fiscal period, the
County will not be obligated to make payments for services or amounts incurred after the
end of the current fiscal period. No penalty or expense shall accrue to the County in the
event this provision applies.
20. Nonassignability: Neither this contract, nor any claim arising under this contract,
shall be transferred or assigned by the Recipient.
21. Taxes: All payments accrued on account of payroll taxes, unemployment
contributions, any other taxes, insurance or other expenses for the Recipient or its staff
shall be the sole responsibility of the Recipient.
Page 5
City of Mount Vernon
Signature
(Date )
Jill Boudreau
Print Name
Mayor
Title
Approved as to form:
_____________________________
Kevin Rogerson, City Attorney
Attest:
_____________________________
Doug Volesky, Finance Director
Mailing Address:
910 Cleveland Avenue
Mount Vernon, WA 98273
Telephone No. 360-336-6207
Fed. Tax ID # 91-6001260
Contractor Lic. #. N/A
Page 6
DATED this _____ day of _______________, 2021.
BOARD OF COUNTY COMMISSIONERS
SKAGIT COUNTY, WASHINGTON
Lisa Janicki, Chair
Peter Browning, Commissioner
Attest: Ron Wesen, Commissioner
Clerk of the Board
For contracts under $5,000:
Authorization per Resolution R20030146
Recommended: County Administrator
Department Head
Approved as to form:
Civil Deputy Prosecuting Attorney
Approved as to indemnification:
Risk Manager
Approved as to budget:
Budget & Finance Director
Page 7
Exhibit A
Page 8
Page 9
Page 10
Page 11
Page 12
Page 13
Get email alerts for Mount Vernon
A daily email when new agendas and minutes are posted.