City Council Committee Agendas
Regular MeetingMount Vernon, WA · April 11, 2018
Minutes
Public Works/Library Committee Meeting
April 11, 2018
Attendees Present:
Mayor Boudreau
Council Members: Beaton, Brocksmith, Carias, Hudson, Hulst, Lindquist, Molenaar
Staff Members: Public Works – Bell, Chesterfield; City Attorney Rogerson; Library Director –
Huffman; Fire Chief Brice; Police Chief – Dodd; Project Development Manager –
Donovan; Finance Director – Volesky
1. Approval of Public Works Committee Minutes:
Councilmember Beaton moved to approve the minutes from March 14, 2018; Seconded by
Councilmember Hudson; Carried by all.
2. Library Committee – Isaac Huffman
a) Planning Process for New Library
Isaac presented on the new Community Center Library planning. The planning phase is
underway with a group of site visits complete and focus groups upcoming. Focus groups will
include the Downtown Business Association, Chamber of Commerce, Community Center,
Library users, and many others. The key goals will be to understand how the facility will be
optimally utilized.
Phase 1 of the project will be an environmental study, geotechnical investigation, ALTA
survey and conceptual layouts; Chris Phillips, Development Services, will present a
consultant agreement to Council next Wednesday, April 18, 2018; the agreement will be for
an ALTA survey and an ESA study as well as preliminary geotechnical and archeological
investigations. The agreement will be in Council packets for review along with a conceptual
design packet showing the different types of building options.
Once Phase 1 is complete, Staff can move forward with a feasibility study jointly with Skagit
County and request distressed county funds in the amount of $500.000 towards the project.
b) Summer Reading
Summer reading planning is almost complete with events including; Drumming workshop,
Reading Magic, Read the Book/See the Movie Event (Mr. Popper’s Penguins), and a Teen
Summer Art Series with Wrap-up Paint Party. Staff is also collaborating with Enrichment
Services for Picnic Party Children’s Music Series. The national library theme this year is
“Libraries Rock!”
Emmanuel Baptist Church volunteers weeded the library again this year with grounds
maintenance support. A crew of six, including Pastor Kevin Brow, braved the 40 mph gusting
winds to get the library tulip traffic ready.
March 14, 2018, Public Works/Library Committee Minutes
Page 1 of 4
c) General Updates
The Oculus pilot is going full steam ahead along with the Library’s open data series. It has
been noted that there is a better learning ability than traditional learning as people retain
information more by experiencing it; in fact there is 90% retention in virtual reality learning.
There are upcoming open data workshops scheduled as follows;
• May 2, 2018 – Defining and Identifying Open Data (Mount Vernon Library)
• May 9, 2018 – Locating and Using Open Data (Mount Vernon Library)
• May 16, 2018 – Telling the Story with Open Data (Burlington Library)
• May 23, 2018 – Answering Real World Questions (Burlington Library)
3. Program Coordination Division – Blaine Chesterfield
a) Stormwater Pump Station Mobile Generator
The 100kW mobile generator arrived at the shop facility on March 9, 2018 and will be used
as backup power for Stewart Road, West Mount Vernon, and South Mount Vernon
stormwater pump stations if electricity goes out.
b) Kulshan Pump Station Screen Debris Removal System Update
The Kulshan Pump Station Debris Removal System is currently in the environmental
permitting stages of design. Staff anticipates final design in August 2018 and project out to
bid in September 2018. Components should be ordered in January 2019 with a lead time of
5 to 7 months; the anticipated completion date is September 2019.
c) 2018 Stormwater Management Program & 2017 Annual Report
The 2018 Stormwater Management Program and 2017 Annual Report was submitted to
Department of Ecology on March 28, 2018.
4. Project Updates – Esco Bell
a) N 4th Street/Riverside BNSF Railroad Crossing Improvements
The City has received a $1.4 million grant for these improvements. Staff will be asking
Council for authorization to execute WSDOT’s Local Agency Agreement for Design for
preliminary engineering in the amount of $223,000 for the N 4th Street/Riverside BNSF
Railroad Crossing Improvements. This authorization is required by WSDOT in order to
obligate the funding.
b) Quick Miscellaneous Project Updates
Esco briefed Council on various projects:
• BNSF crews installed H-piles at the floodwall crossing of the mainline track this past
week. Remaining work includes installation of the concrete foundation and panels at the
track. The tracks themselves are already near the 100 year flood level.
• College Way and 30th Street Signal: Field surveying is complete and design is 30%
finished. Right of Way is needed for this project.
March 14, 2018, Public Works/Library Committee Minutes
Page 2 of 4
• Riverside Drive and College Way Signal Improvements: Field surveying is complete, curb
ramp existing condition review is on-going, and justification of flashing yellow turn
arrow is being reviewed. There will be enough funds in the project to modernize the
signals and ADA ramps along both corridors.
• 2018 Street Restoration Locations: This project is expected to go out to bid next week
with $1.5 million worth of work including portions of S 2nd Street, E Section Street, S
Laventure Street, and Warren Street.
• Curb Ramp Replacement Portion of Street Maintenance Work: This project will
modernize ADA ramps in the amount of approximately $350,000. The project is
currently out to bid, with an expected bid opening date of May 1, 2018.
5. Public Works Director Comments – Esco Bell
a) Downtown Flood Protection LOMR Submittal
Now that construction of the City’s Downtown Flood Wall is essentially complete, the City is
able to move forward with FEMA’s Letter of Map Revision (LOMR) to remove the downtown
from the 100 year flood plain. The City’s LOMR information was submitted last week and
received by FEMA on Friday, April 6, 2018. FEMA has 90 days to respond to the submittals.
b) Asset Management
Esco showed information updating Council on Public Works use of new asset management
tools. The software was purchased in 2017; it is simple and user friendly for crews in the
field, easily customizable, maintains records for claims, and reports download easily to
Excel. The program will save a lot of staff time and efforts, improving overall efficiency.
Current uses include utility locates, sidewalk repairs, illicit discharges, citizen work requests,
and drainage investigations/detention pond inspections. Additionally Staff recently
developed and started using the catch basin inspection and reoccurring maintenance
module. Future uses can expand into identifying mowing areas, traffic safety, and sign
inventories.
c) Sidewalk Trip Hazard Removal – New Technique Trial
Esco showed slides demonstrating new technique for removing sidewalk trip hazards. The
crews, in conjunction with the contractor, removed some trip hazards near City Hall last
week prior to the Downtown Tulip Street Fair. Staff will likely recommend utilizing this
method more extensively in the future.
6. Traffic Safety Committee Update – Esco Bell & Mike Love
a) Temporary Speed Hump Pilot Test Update
Esco updated Council on progress of use of a temporary speed hump. Pre-project speed
studies were recently completed showing 85% of the traffic is at 25 mph or below, with the
highest speed at 40 mph. The speed hump itself has been ordered and received and needed
signage is being acquired. Staff will inform and coordinate with the Skagit Highlands HOA
March 14, 2018, Public Works/Library Committee Minutes
Page 3 of 4
before proceeding with installation. The pilot test period will be 3 months and speeds will
also be measured with the humps installed.
7. Safer Grant – Bryan Brice
Chief Brice provided information for Council on the SAFER Grant for the Fire Department. This
36 month long grant was created to provide funding to fire departments to help increase or
maintain the number of trained “front line” firefighters. The grant period is open from March 26
– April 27, 2018; the City will apply for six (6) firefighter positions. As this is not a temporary
hiring pool, but rather utilizing a cost share approach to long term employment, the City will be
responsible for 25% of the cost incurred for the first and second year and 65% for the third year.
Cost sharing will be funded through new BLS integration revenues and is a key component in
criteria based dispatching. EMS is currently working with the 911 Center in implementing
criteria based dispatching to enable the correct resources to be sent to the correct calls. If after
the three years the City is not able to sustain all of the firefighters, those employees will at least
be further trained and very marketable to other jurisdictions.
Meeting adjourned at 7:02 pm
Sherri Pritchard, Public Works Department
March 14, 2018, Public Works/Library Committee Minutes
Page 4 of 4
Agenda
AGENDA
PUBLIC WORKS / LIBRARY COMMITTEE
April 11, 2018 - 6:00 PM
Police / Court Campus – 1805 Continental Place
1. APPROVAL OF MINUTES
2. LIBRARY COMMITTEE TOPICS – Isaac Huffman
a. Planning Process for New Library
b. Summer Reading
c. General Updates
3. PROGRAM COORDINATION DIVISION – Blaine Chesterfield
a. Stormwater Pump Station Mobile Generator
b. Kulshan Pump Station Screen Debris Removal System Update
c. 2018 Stormwater Management Program & 2017 Annual Report
4. PROJECT UPDATES – Mike Love
a. N 4th Street/Riverside BNSF Railroad Crossing Improvements
b. Quick Miscellaneous Project Updates
5. PUBLIC WORKS DIRECTOR COMMENTS – Esco Bell
a. Downtown Flood Protection LOMR Submittal
b. Asset Management
c. Sidewalk Trip Hazard Removal – New Technique Trial
6. TRAFFIC SAFETY COMMITTEE UPDATE – Esco Bell and Mike Love
a. Temporary Speed Hump Pilot Test Update
7. SAFER GRANT – Chief Brice
8. MISCELLANEOUS / FOR THE GOOD OF THE ORDER
COMMITTEE COMMENTS
Attachments:
Public Works Committee March 2018 Meeting Minutes
Get email alerts for Mount Vernon
A daily email when new agendas and minutes are posted.