Finance Committee
Regular MeetingOconomowoc, WI · April 2, 2024
Minutes
City of Oconomowoc
Joint Finance/Utility Committee Meeting
Meeting Minutes
April 02, 2024 - 7:10 PM
Aldermen Present: Finance - Charles Schellpeper, Karen Spiegelberg, Andrew Moroni and Utility - Kevin Ellis, Matt
Mulder
Absent: Utility – Matt Rosek
Also Present: Robert Magnus, Jennifer Aultman Kloth, Chris Douglas, Eric Boettcher, Lucas Caine, Diane Coenen,
Jason Herzog, Laurie Sullivan-Murray, Scott Osborn, Brad Timm
Finance Chairman Schellpeper and Utility Acting Chairman Ellis called the Joint Finance/Utility Committee Meeting to
order at 7:10 PM and appropriate meeting notification was confirmed.
Committee Business
a Consider/recommend Resolution 24-R3183 Authorizing a Budget Amendment to Increase the
2024 Water Meter Budget
Finance Committee: Motion to recommend Resolution 24-R3183 authorizing a budget
amendment to increase the 2024 Water Meter Budget made by Schellpeper and seconded by
Moroni.
Motion carried 3-0-0.
Utility Committee: Motion to recommend Resolution 24-R3183 authorizing a budget amendment to
increase the 2024 Water Meter Budget made by Mulder and seconded by Ellis.
Motion carried 2-0-0.
Adjourn
Finance Committee: Motion to adjourn made by Spiegelberg and seconded by Moroni.
Motion carried 3-0-0.
The meeting adjourned at 7:21 PM.
Utility Committee: Motion to adjourn made by Ellis and seconded by Mulder.
Motion carried 2-0-0.
The meeting adjourned at 7:21 PM.
__________________________________
Minutes taken by Diane Coenen, City Clerk
Aldermen Spiegelberg, Secretary and
Mulder, Acting Secretary
1
Joint Finance/Utility Committee Meeting - April 02, 2024
Agenda
City of Oconomowoc
Joint Finance/Utility Committee Meeting
Finance: Schellpeper, Chairman / Spiegelberg, Secy /
Moroni
Utility: Rosek, Chairman / Ellis, Secy / Mulder
Tuesday, April 02, 2024 - 7:10 PM
City Hall - Conference Room 3
174 E. Wisconsin Ave. Oconomowoc, WI 53066
Notice: If a person with a disability requires that the meeting be accessible or that materials at the
meeting be in an accessible format, call the City Clerk’s office at least 48 hours in advance to request
adequate accommodations. Tel: (262) 569-2186
1 Call to order and confirmation of appropriate meeting notification
2 Committee Business
a Consider/recommend Resolution 24-R3183 Authorizing a Budget Amendment to Increase
the 2024 Water Meter Budget
3 Adjourn
________________________________
Diane Coenen, City Clerk
City of Oconomowoc
Notice is hereby given that a majority of the Common Council will be present at the above scheduled meeting to gather information
about a subject over which they have decision-making responsibility. This constitutes a meeting of the Common Council pursuant to
State ex rel. Badke v. Greendale Village Board, 173Wis. 2d 553, 494 N.W. 2d 408 (1993) and must be noticed as such, although the
Common Council will not take any formal action at this meeting.
1
MEMORANDUM
DEPARTMENT - WATER UTILITY
Date: April 2, 2024
To: Mayor, Common Council, and Utility Committee
From: Kevin Kaari, Utility Manager
Laurie Sullivan-Murray, Finance Director
Scott Osborn P.E., Water Superintendent
Re: Consider/Act on Resolution 24-R3183 Budget Amendment for Additional Water Meters
RELATES TO THE STRATEGIC PLAN
Strategic Goal- II – Improve and Maintain our Infrastructure/Facilities
BACKGROUND
The approved 2024 water meter budget is $125,000. However, water meter needs have increased due to the
number of planned developments, the backlog of meters on our meter resolution list (meters not working, leaks,
complaints, and repairs), and Lead Service Line (LSL) replacements. Our revised projected 2024 capital meter
estimate, for these categories, is $200,000, a $75,000 increase. See attached spreadsheet.
Secondly, we have a planned mandatory mass meter replacement project starting in 2026. The last time the
Water Utility did a mass meter replacement was in 2006. Chapter 185.61 (1) of the Wisconsin Public Service
Commission (PSC) requires “All meters used for measuring the quantity of water delivered to a customer shall be
in good working condition.” To comply with the PSC, the City of Oconomowoc Water Utility follows the
Wisconsin PSC Code requirement in section 185.76(6) of replacing water meters for services 1” or smaller after 20
years of being in-service versus testing all those meters and repairing them every 10 years. As of the date of this
memorandum, we have over 2500 meters to replace by 2026.
We were originally planning to purchase the meters and contract all the labor and administration for the mass
meter replacement project in 2026. However, to reduce the supply chain risk for procuring over 2500 meters and
to level out the large expenditures associated with this program over three years, the Water Utility recommends
starting to purchase the meters this year. Our plan is to purchase 800 meters per year for the next 3 years. We
also recommend starting the replacement of these meters with our own crews, when available, saving the utility
money associated with future contracted labor expenditures. The additional budget needed for purchasing these
meters in 2024 is $285,000. The balance of meters remaining to be exchanged in 2026, will still need to be
contracted out to meet the PSC requirement.
We verified with our water meter vendor that the meters are available to meet our 2024 goals.
ADDITIONAL ANALYSIS
We contacted the Wisconsin PSC regarding the need for a Construction Authorization for the Mass Meter
Replacement project. This is how they responded.
1
2
“Generally speaking, water meter replacement projects no longer require construction approval by the Public
Service Commission (Commission). The Commission stopped reviewing meter projects in 2021 with the
adoption of Wis. Act 86.”
FINANCIAL IMPACT
The proposed 2024 budget amendments to #602-573-7000 WO#224001 includes the following:
1. Add $75,000 to the current 2024 water meter budget for known projects this year.
2. Add $285,000 to allow for 800 additional water meters for the mass meter replacement project starting
in 2024. This will allow Water Utility staff to begin scheduling and replacing meters this year.
The total recommended budget amendment request is for an additional $360,000, with funds coming from
Water Reserves, for a total amended budget amount for water meters of $485,000 in 2024.
Adjustments to the 2024-2028 Long Term Financial Plan (LTFP) and future financial plans will be reflected during
the LTFP Planning and the Budget Workshops that will take place during the normal budgeting process.
Staff recommends the budget amendment to increase the 2024 water meter budget to include $75,000 for
additional meters due to planned growth and replacement of meters on the meter resolution list and an
additional $285,000 to start procuring and installing replacement meters associated with the PSC required 20-
year mass meter replacement project.
SUGGESTED COMMITTEE RECOMMENDATION
Motion to recommend to the Common Council approval of the proposed budget amendments for additional
water meters of $360,000, with funds coming from Water Reserves, for a total amended budget amount for
water meters of $485,000 in 2024.
SUGGESTED COUNCIL MOTION
Motion to adopt Resolution 24-R3183.
Z:\Interim Utility Manager\2024 Watermeters\Background Memo for 2024 Water Meter Budget Amendment Final.docx
2
3
RESOLUTION NO. 24-R3183
RESOLUTION AUTHORIZING A BUDGET AMENDMENT TO INCREASE
THE 2024 WATER METER BUDGET
WHEREAS, water meter needs for 2024 have increased due to the number of planned
developments, LSL replacements and the backlog on the meter resolution list; and
WHEREAS, the Water Utility proposes to phase in the water meter purchases for the
2026 mandatory mass meter replacement project requiring the replacement of
approximately 2500 meters; and
WHEREAS, to accomplish the proposed plan the Water Utility will need a budget
amendment to purchase the additional meters as follows:
1. Add $75,000 to the current 2024 water meter budget for known projects this
year.
2. Add $285,000 to allow for 800 additional water meters for the mass meter
replacement project starting 2024. This will allow the Water Utility staff to begin
scheduling and replacing meters this year.
NOW THEREFORE, BE IT HEREBY RESOLVED that the Common Council authorizes the
budget adjustment of $360,000 for additional meter purchases in 2024 with the funds
coming from Water Reserves.
Note: A budget amendment requires a super majority vote to be approved.
DATED: CITY OF OCONOMOWOC
By: _____________________________
Robert P. Magnus, Mayor
ATTEST:
Diane Coenen, Clerk
4
ESTIMATED WATER METER ALLOCATIONS - 2024
Revised 3/18/24
2024 Water Meter Total # Water Meters Estimated # of Units for Estimated Water
New Development or Project Name
Quantity Needed for Project Development Project Meter Size
UW Credit Union 1 1 1 1.5"
Arrowood Phase 2 & 3 (2024) 25 32 32 3/4"
Arrowood Phase 4 (2025) 0 75 35 3/4"
Norden Range - 1" 7 7 1"
270 Apts
Norden Range - 2" 8 12 2"
Olde Highlander - 3/4" for SF homes (2024) 41 164 164 3/4"
Olde Highlander - 1" (quarter in 2024) 2 7 260 1"
Locklyn Apartments 2 2 46 2"
NE Area Apartments Ph 1 (start in 2024) 1 12 200 2"
Prairie Creek Ridge #8 (half in 2024) 20 52 52 3/4"
Oympia Fields proposed build out - 3/4" 0 4 3/4"
116 Apts / 8 Retail
Oympia Fields proposed build out - 1.5" (start in 2024) 1 10 1.5"
Panera Bread 0 1 1 1.5"
Performance Coatings 1 1 1 2"
Winnesota 1 1 1 1.5"
Pabst Retail (2024) 4 16 16 3/4"
Pabst Retail (2025 start) 0 6 6 1.5"
Pabst 59 - Apartments (start late 2024) 4 4 162 3"
Pabst 59 - Apartments (start in 2025) 0 7 see above 3/4"
Pabst 59 - Innvoation buildings (Wingspan Bldg in 2024) 1 4 4 1.5"
Other Developments/Phases of Past Projects Continued... 25 25 3/4"
Sub-Total (Meters) 144 443
METER RESOLUTION LIST (includes all water meter exchanges due to
leaks, complaints, repairs, and stop reading notices. Includes meters
changed during LSL replacements) 190 3/4"
Total Number of Water Meters 334
WATER METER PRICING SUMMARY -2024
New Developments Size Cost/Meter Meter Quantity Estimated Cost
New water meters for service territory growth 3/4" $ 355 115 $ 40,825
New water meters for service territory growth 1" $ 575 9 $ 5,175
New water meters for service territory growth 1.5" $ 1,660 4 $ 6,640
New water meters for service territory growth 2" $ 1,870 12 $ 22,440
New water meters for service territory growth 3" $ 2,345 4 $ 9,380
New Meter Sub-Total 144 $ 84,460
METER RESOLUTION LIST (includes all water meter exchanges due to
leaks, complaints, repairs, and stop reading notices. Includes meters 5/8", 3/4", 1", 1.5", 2", 3" $ 595 190 $ 113,050
changed during LSL replacements)
Sub-Total 334 $ 197,510
Mass Meter Replacement Project (2550 meters exchanged by 2026) 5/8", 3/4", 1" $ 355 800 $ 284,000
TOTALS 1,134 $ 481,510
Notes:
1. New water meter installs as of 3/18/24 = 32
2. Water meter exchanges as of 3/18/24 = 65
3. NE Area Apartment project not initially approved for 2024 construction with 220 units but revised plans expected with 1 building started
4. Arrowood Phase 2&3 - assumed half developed
5. Olde Highlander - assumed quarter developed
6. Pabst Retail - assumed starting in 2024
7. Pabst 59- Wingspan Blgd in 2024, remaining in 2025
8. Norden Range (assume 75% complete)
9. The meter resolution list cost per meter above includes all meter sizes (cost is estimated)
5