Infrastructure Committee
Regular MeetingRoswell, NM · November 26, 2018
Minutes
Regular Meeting of the Infrastructure Committee
Held in the Conference Room at City Hall
November 26, 2018
Notice of this meeting was given to the public in compliance with Sections 10-15-1
through 10-15-4, NMSA 1978 and Resolution 17-49.
ROLL CALL:
The meeting convened at 4:00 p.m. with Chairman Oropesa presiding and Councilors
Best, Peterson, and Grant being present.
Staff Present:
Louis Najar, Trent Moore, Kevin Dillon, Monica Garcia, Bill Morris, Frank Montoya, Juan
Fuentes, Joe Neeb, Mayor Dennis Kintigh, and Bernadette Lopez.
Guest(s) Present:
Alison Penn and Larry Connolly.
APPROVAL OF AGENDA:
Councilor Grant moved to approve the agenda for the Regular Infrastructure
Committee meeting of November 26, 2018 as presented. Councilor Best
seconded the motion. A voice vote of 4-0 was unanimous, and the motion
passed.
APPROVAL OF MINUTES:
1. October 22, 2018:
Councilor Grant moved to approve the October 22, 2018 Minutes for the Regular
Infrastructure Committee meeting as presented. Councilor Best seconded the
motion. A voice vote of 4-0 was unanimous, and the motion passed.
NON-ACTION ITEM(S):
2. Project Updates Discussion:
Note: Last month’s Project Updates status (10-18-18) was accidently submitted in this
Infrastructure package. The current Project Updates status (11-20-18) was handed out
during the meeting.
Hot Recycling Pavement Maintenance:
Mr. Najar discussed the update.
Pavement Condition Study:
Page 1 of 3
Mr. Najar discussed the update.
Yucca Recreation Center:
Mr. Dillon discussed the update.
Roswell Air Center Repairs:
Mr. Dillon discussed the update.
Convention Center:
Mr. Dillon discussed the update.
RPD Boilers:
Mr. Dillon discussed update. Mr. Najar stated Finance is still working on the funding.
3. Large Diameter Water Lines:
Mr. Najar discussed this item.
REGULAR ITEM(S) (Action):
4. Award ITB19-001 – S. Atkinson Rehabilitation Project:
Councilor Grant moved to send to Consent Agenda to award ITB-19-001 S.
Atkinson Rehabilitation Project to J&H Services from Albuquerque, NM in the
total amount of $1,451,731.68. Mr. Najar discussed this item. Mr. Najar stated the
funding is not available in the account as it was before. Mr. Najar will follow up with
Finance. Councilor Best seconded the motion. A voice vote of 4-0 was
unanimous, and the motion passed.
5. Award ITB19-003 – Montana/Stone Street Realignment Project:
Councilor Grant moved to send to Consent Agenda to award ITB-19-003
Montana/Stone Realignment Project to Abraham’s Construction from
Albuquerque, NM in the total amount of $399,500.81. Mr. Najar discussed this item.
Councilor Best seconded the motion. A voice vote of 4-0 was unanimous, and
the motion passed.
6. Award ITB19-004 – 2019 Annual Maintenance Contract:
Councilor Grant moved to send to Consent Agenda to award ITB-19-004 2019
Annual Maintenance Contract to Bullseye Construction of Artesia, NM and
Abraham’s Construction of Albuquerque, NM. Mr. Najar discussed this item.
Councilor Best seconded the motion. A voice vote of 4-0 was unanimous, and
the motion passed.
Page 2 of 3
7. Award ITB19-005 – N. Main Alley Sewer Replacement Project:
Councilor Grant moved to send to Consent Agenda to award ITB-19-005 N. Main
Alley Sewer Project to Adame Construction from Los Lunas, NM in the total
amount of $118,508.80. Mr. Najar discussed this item. Councilor Best seconded
the motion. A voice vote of 4-0 was unanimous, and the motion passed.
8. Award ITB19-006 – Mescalero Lift Station Project:
Councilor Grant moved to send to Consent Agenda to award ITB-19-006
Mescalero Lift Station to Adame Construction from Los Lunas, NM in the total
amount of $99,745.80. Mr. Najar discussed this item. Councilor Best seconded the
motion. A voice vote of 4-0 was unanimous, and the motion passed.
9. 2019 Infrastructure Meeting Dates:
Councilor Grant moved to accept the 2019 Infrastructure meeting dates as
presented. Mr. Najar discussed this item. Councilor Best seconded the motion. A
voice vote of 4-0 was unanimous, and the motion passed.
OTHER BUSINESS (Non-Action):
10. Public Comments:
Mr. Connolly expressed his gratitude for the pothole that was fixed in front of All
American Cleaners.
ADJOURN:
The meeting adjourned at 4:43 p.m. The next scheduled meeting is January 28, 2019.
Page 3 of 3
Agenda
ROSWELL INFRASTRUCTURE COMMITTEE AGENDA
Monday, November 26, 2018 at 4:00 p.m.
City Hall Large Conference Room
425 N. Richardson Ave., Roswell, New Mexico 88201
Committee Chair: Juan Oropesa
Committee Vice Chair: George Peterson
Committee Members: Caleb Grant, Jeanine Corn Best
Staff Coordinator: Louis Najar
A. Call to Order
B. Roll Call
C. Approval of the Agenda
D. Approval of Minutes
1. October 22, 2018 1-3
E. Non-Action Items
2. Project Updates Discussion 4 - 10
3. Large Diameter Water Lines 11
F. Regular Items (Action Items)
4. Award ITB-19-001 – S. Atkinson Rehabilitation Project 12 - 17
5. Award ITB-19-003 – Montana/Stone Street Re-alignment Project 18 - 20
6. Award ITB-19-004 - 2019 Annual Maintenance Contract 21 - 24
7. Award ITB-19-005 - N. Main Alley Sewer Replacement Project 25 - 27
8 Award ITB-19-006 – Mescalero Lift Station Project 28 - 30
9. 2019 Infrastructure Meeting Dates 31 - 32
Other Business (Non-Action)
10. Public Comments
G. Adjourn (Next Meeting: January 28, 2019) No need for December meeting?
Notice of this meeting has been given to the public in compliance with Sections 10-15-1 through 10-15-4 NMSA 1978
and Resolution 18-55.
NOTICE OF POTENTIAL QUORUM – A quorum of the City Council may or may not attend, but there will not be
debate by the City Council.
If you are an individual with a disability who is in need of a reader, amplifier, qualified sign language interpreter, or
any other form of auxiliary aid or service to attend or participate in the hearing or meeting, please contact Human
Resources at 575-624-6700 at least one week prior to the meeting or as soon as possible. Public documents
including the agenda and minutes can be provided in various accessible formats. Please contact the City Clerk at
575-624-6700 if a summary or other type of accessible format is needed.
Printed and posted: 11/21/18
Regular Meeting of the Infrastructure Committee
Held in the Conference Room at City Hall
October 22, 2018
Notice of this meeting was given to the public in compliance with Sections 10-15-1
through 10-15-4, NMSA 1978 and Resolution 17-49.
ROLL CALL:
The meeting convened at 4:00 p.m. with Chairman Oropesa presiding and Councilors
Best, Peterson, and Grant being present.
Staff Present:
Joe Neeb, Louis Najar, Trent Moore, Kevin Dillon, Aaron Holloway, Monica Garcia,
Ryan Porter, and Bernadette Lopez.
Guest(s) Present:
Alison Penn, Elena Mendoza, and Larry Connolly.
APPROVAL OF AGENDA:
Councilor Grant moved to approve the agenda for the Regular Infrastructure
Committee meeting of October 22, 2018 as presented. Councilor Best seconded
the motion. A voice vote of 4-0 was unanimous, and the motion passed.
APPROVAL OF MINUTES:
1. September 24, 2018:
Councilor Grant moved to approve the September 24, 2018 Minutes for the
Regular Infrastructure Committee meeting as presented. Councilor Best
seconded the motion. A voice vote of 4-0 was unanimous, and the motion
passed.
NON-ACTION ITEM(S):
2. Project Updates Discussion:
ITB-18-007 S. Union & S. Washington:
Mr. Najar discussed the update.
RPD Boilers:
As a safety concern, Mr. Najar informed the committee of the Roswell Police
Department boilers in need of repair/replacement that was discovered on Friday,
Page 1 of 3 1
October 19, 2018. Facility Maintenance staff is working on getting quotes. This item
will be discussed at a later committee meeting and possibly council at a later date.
Convention Center:
Mr. Dillon discussed the update.
Yucca Recreation Center:
Mr. Dillon discussed the update.
Remote Read Water Meters:
Mr. Dillon discussed the update.
Roswell Air Center Repairs:
Mr. Dillon discussed the update.
Land Acquisition:
Mr. Najar discussed item.
3. Large Diameter Water Lines:
Mr. Najar discussed this item. Councilor Peterson voiced his concern for the street to
be cleaned up.
4. WWTP & Sewer Concerns:
Mr. Najar discussed this item. Mr. Najar discussed issues with the sewer line in North
Pizza Hut’s parking lot, and with no new money in the Wastewater account, money will
be requested at mid-year budget.
REGULAR ITEM(S) (Action):
5. Water Meter Tampering Ordinance & Resolution:
Councilor Grant moved to send to full City Council Ordinance 18-06. Mr.
Holloman discussed the update. Mr. Najar stated this was also going before the Legal
Committee. Councilor Best seconded the motion. A voice vote of 4-0 was
unanimous, and the motion passed.
6. 2018 CDBG Project Support Resolution:
Councilor Grant moved to send to full City Council Resolution 18-xx for support
of funding awarded to the City, CDBG Project No. 18-C-NR-I-03-G-14 for repairs to
the Boys and Girls Club of Roswell. Mr. Najar discussed this item. Councilor Best
Page 2 of 3 2
seconded the motion. A voice vote of 4-0 was unanimous, and the motion
passed.
OTHER BUSINESS (Non-Action):
7. Public Comments:
The Infrastructure Committee agreed to not have a meeting in December unless it is
necessary, in which December 17, 2018 would be the meeting date.
ADJOURN:
The meeting adjourned at 4:27 p.m. The next scheduled meeting is November 26,
2018.
Page 3 of 3 3
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Project Updates – Infrastructure Committee open discussion
BACKGROUND: Committee will be given opportunity for Q&A on any project.
Project Dashboard report is part of the committee packet.
FINANCIAL
CONSIDERATION: None at this time.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: Not Applicable.
4
City of Roswell Projects Status
Updated 10/18/2018
Category: Grant and Legislative Projects
Yucca Recreation Center 15-L-1115:
SCOPE: Plan, design, repair, improve, and construct the Yucca Recreation Center.
ESTIMATED COST: $ 250,000 $ 20,434,770.93
FUNDING SOURCE: Capital Outlay City Funds Original Budget
BUDGET: Total Budget: $ 20,684,770.93 $ 20,000,000.00
Total Encumbrance: $ (20,595,210.26)
Total Change Orders: $ (374,668.00)
Current Balance: $ 89,560.67
PROJECT SCHEDULE: September 9, 2014 - (Rec Center Jan 2019) (Aquatics May 2019)
EST. COMPLETION: Unknown
PROJECT STATUS: Admin Phase I 100%
Design 100%
Admin Phase II 100%
Construction 52%
Closeout 0%
The Aquatics section is still continuing. We are moving forward with the Aux parking lot. The shot crete is complete on the outdoor pool.
The finish coat will be applied once the concrete deck is poured. The casting slab is pour at the indoor pool location that will be used for the
tilt-up walls for the Aquatics. Sheet rock is going up in the admin space and the Lobby is getting done. The roofing TPO is complete in the
north low roof and the decking is getting installed over the Gym area. Big walls for the Aquatics Side are up. TPO on the Gym is about 50%
complete. Translucent panels are all installed.
Dec-15 Jun-16 Jan-17 Jul-17 Feb-18 Sep-18
Phase % Complete
Design RFP
Design RFP 100% Programming Phase
Programming Phase 100%
Schematic Phase
Schematic Phase 100%
100% Design Development Phase
Design Development Phase
Construction Documents Phase 100% Construction Documents Phase
Construction RFP 100% Construction RFP
Construction 52% Construction
Substantial Completion 0% Substantial Completion
Project Closeout 0%
Project Closeout
Roswell Air Center Repairs
SCOPE: Repair Partial Roof of Dean Baldwin
ESTIMATED COST: $ 5,600,000.00
FUNDING SOURCE: DFA Grant Funds, City, State & Federal
BUDGET Total Budget: $ 5,600,000.00
Total Encumbrance: $ 4,533,000.00
Total Change Orders: $ -
Current Balance: $ 1,067,000.00
PROJECT SCHEDULE: Unknown
EST. COMPLETION: Unknown
PROJECT STATUS: Grant A2402 is complete and closedout ($488,000). We are currently waiting to complete Bays #1 & #2 all other areas
have been completed. Recieved Executed Grant Agreement for the additional $1,485,000. Still waiting on Executed
Grant Agreement for $900,000 (State Funds). The fire alarm system is currently being installed. Roof Work to start back
the week of 7/23/18. We are at about 65% on Bay #2. Bay #2 is complete Bay #1 is scheduled to start 11/15/18 -
1/7/2019. Working with Kazal on Fire Suprression getting Waide to carry under their CES contract.
City Hall Annex Roof A2403
SCOPE: Replace the City Hall Annex Roof
ESTIMATED COST: $ 105,000.00
FUNDING SOURCE: DFA Grant Capital Outlay
BUDGET Total Budget: $ 105,000.00
Total Encumbrance: $ (105,000.00)
Total Change Orders: $ -
Current Balance: $ -
PROJECT SCHEDULE: Unknown
EST. COMPLETION: 98%
PROJECT STATUS: Executed Grant Agreement Received 8/30/2017. 95% Complete waiting on Invoice and file for Riembursement. Work is
complete waiting on final factory inspection for Warranty and Final Invoice. Warranty is received waiting on final
invoice.
Accountability. Communication. Excellence. Integrity. Teamwork. 5
Roswell Fire Stations Roofs & Infrastructure A2404
SCOPE: Replace Roofing of Station #1 and Additional Repairs
ESTIMATED COST: $ 195,000.00
FUNDING SOURCE: DFA Grant Capital Outlay
BUDGET Total Budget: $ 195,000.00
Total Encumbrance: $ (175,534.00)
Total Change Orders: $ -
Current Balance: $ 19,466.00
PROJECT SCHEDULE: Unknown
EST. COMPLETION: 98%
PROJECT STATUS: Executed Grant Agreement Received 8/31/2017. PO Issued and work in progress. Work stopped to go to Dean Baldwin.
Station 1 is complete. Currently awaiting direction from the Fire Chief on remaining direction on Station #2. To
complete #2 we will need about $25,000. Submited Change Order to cover Station #2 roof. Currently waiting to
schedule the work. Work scheduled for #2 to start week of 6/25. Fire Station #2 is complete just waiting on final invoice
to closeout.
Roswell Roads Improvements A2551
SCOPE: Continue the Improvements to Washington and Union
ESTIMATED COST: $ 300,000.00
FUNDING SOURCE: DFA Grant Capital Outlay
BUDGET Total Budget: $ 300,000.00
Total Encumbrance: $ (20,316.00)
Total Change Orders: $ -
Current Balance: $ 279,684.00
PROJECT SCHEDULE: Under Construction
EST. COMPLETION: 4/1/2019
PROJECT STATUS: Agreement executed. Phase I ADA completed. ITB-18-007 was awarded to J&H Services Inc. Milling has commenced
on S. Washington.
Entryway Signs:
SCOPE: Plan, design, and install 5 entryway signs.
ESTIMATED COST: $ 600,000
FUNDING SOURCE: Lodger's Tax
BUDGET: Total Budget: $ 600,000.00
Total Encumbrance: $ 323,864.00
Total Change Orders: $ 7,959.69
Current Balance: $ 268,176.31
EST. COMPLETION: December 2016
PROJECT COMPLETION: 80%
PO issued 11/30/15. Final designs being considered at 3/3/16 Finance Committee. Design approval at the April 14th council meeting. City
has finalized the Change Order and the process has begun. Currently in Fabrication (Production). Install Planned to start seek of 4/17/17.
Install Complete of signs. Site work is in process. Issuing Change Order for remaining 2 signs. Awaiting for budget review for final numbers
prior to proceeding. Awaiting on Change order to complete install.
Garden Bridge:
SCOPE: Replace bridge on Garden Ave.
BUDGET: $ -
FUNDING SOURCE: City
EST. COMPLETION: October 2016
PROJECT STATUS: 10%
Preliminary survey and site review completed. Project on Hold Awaiting Funding.
Country Club/Main Traffic Signal:
SCOPE: Upgrade traffic signals at Country Club and Main.
BUDGET: $ -
FUNDING SOURCE: City
EST. COMPLETION: July 2016
PROJECT STATUS: 10%
Preliminary survey and site review completed. Appraiser has been contracted to assist with right of way acquisitions. Engineering has met
with utility companies concerning any relocations. Waiting on apprailsal report from McCelland.
Page 2 of 6 Accountability. Communication. Excellence. Integrity. Teamwork. 6
Remote Read Water Meters:
SCOPE: Upgrade meter reading system.
BUDGET: $ 19,853,557
FUNDING SOURCE: Joint Utility Revenue Bond Ordinance 16-22
EST. COMPLETION: Nvember 2018
PROJECT STATUS: 80%
12/8/16 City Council approved 8-1 Resolution 16-80 Vendor Selection. City Council approved 9-0 Ordinance 16-22 Joint Water & Sewer
Improvement Revenue Bonds Final Reading 1/12/17. Contract Signed #2017-003 Signed 2/1/2017. Physical Network installation is
planned on starting 8/23/2017 As of 10/12/18 18,800 meters have been installed. Currently workig on getting the interface software
going. We are also expanding the network coverage to increase accuracy by adding 3 additional collection routers.
Feb-17 Jun-17 Sep-17 Dec-17 Mar-18 Jul-18
Phase % Complete
1st Meter Order
1st Meter Order 100% Network Installation
Network Installation 90%
Pilot Meter Installation
Pilot Meter Installation 100%
Troubleshooting
Troubleshooting 95%
2nd Material Order 100% 2nd Material Order
Ramp-up Installation 100% Ramp-up Installation
Production Installation 95% Production Installation
3rd Material Order 100%
3rd Material Order
Final Material Order 100%
Final Material Order
Ramp-Down Production Install 10%
Cleanup / Punch List 0% Ramp-Down Production Install
Close-Out 0% Cleanup / Punch List
Close-Out
Land Acquisition:
Funding pulled / Pending Funding Availability
Convention Center
SCOPE: Design Remodel Addition Original Budget
BUDGET: $ 8,116,506 $ 7,448,160.00
Encumbrance $ (7,835,797)
FFE $ (250,000)
Change Orders $ (393,503)
Remaining Bal $ 30,709
FUNDING SOURCE: Hotel Convention Center Fee & Revenue Bond
EST. COMPLETION: October 2018
PROJECT COMPLETION: 75%
PO Issued and Sent 8/15/16. Kick-off meeting 9/14. Design team performed site evaluation 10/5. Presented design at 5/11/17 Council
Meeting. Rfp was pushed out to be due 8/10/2017 due to lack of General Contractor Participation. RFP recommendation approved 8/24/17
for $6,326,640.63. Pre-Con Meeting 9/26/17. Getting things prepped the existing side of the facility is at 75% complete. The north
addition is sitting at about 75%. Completed addressing the existing facility emergency lighting issues due to lack of maintenance.
Phase May-16 Sep-16 Dec-16 Mar-17 Jun-17 Oct-17 Jan-18 Apr-18 Aug-18
% Complete
Design RFP
Design RFP 100%
Programming Phase
Programming Phase 100%
Schematic Phase
Schematic Phase 100%
Design Development Phase
Design Development Phase 100%
Construction Documents Phase
Construction Documents Phase 100%
Construction RFP 100% Construction RFP
Construction 75% Construction
Substantial Completion 0% Substantial Completion
Project Closeout 0% Project Closeout
Edgewood Small Diameter Waterline Project
SCOPE: Replacement of small diameter waterlines in the Edgewood Neighborhood.
BUDGET: $ -
FUNDING SOURCE: 2016 City Budget
EST. COMPLETION: Summer 2019
PROJECT COMPLETION: 90% Plans
Survey complete.Plans 90% complete. This project to incorporate (2) 36" diameter valves at (3rd & Garden) & (Cherry & Garden). Design is
currently undergoing review by Engineering Department.
Page 3 of 6 Accountability. Communication. Excellence. Integrity. Teamwork. 7
48" Waterline Project
SCOPE: Replace 4,500' of 48" Waterline on Country club Rd.
BUDGET: $ 2,926,227
FUNDING SOURCE: EPA Water Loan (75% forgiveness) 2016 City Budget
EST. COMPLETION: May 2018
PROJECT COMPLETION: 100%
PROJECT COMPLETE. Performing internal audit & awaiting NMED final audit.
Union Avenue - 19th to Country Club
SCOPE: Pavement Rehab
BUDGET: $ 2,700,000
FUNDING SOURCE: 2017 Capital Projects
EST. COMPLETION: 7/1/2018
PROJECT COMPLETION: 98%
ITB 17-014 Advertise June 25th open bids August 8th. Council awarded project on 9/14/17. Contractor performing punchlist and needs to
finish street lighting & pavement markings.
RIAC North Water Line - ITB-18-002
SCOPE: New 14" water in NW portion of RIAC
BUDGET: $ 325,000
FUNDING SOURCE: FY 2018 Water Capital Fund
EST. COMPLETION: 7/1/2018
PROJECT COMPLETION: 100%
Bids were open 12/12/17, will be awarded at City Council, 1/2018. Awarded to Total Contractors on 1/11/18 at $297,730.30. PROJECT
COMPLETE. Internal audit in progress.
RIAC Reservoirs
SCOPE: (2) New Water Towers at RIAC
BUDGET: $ 5,300,000
FUNDING SOURCE: EPA Loan & Water Capital Fund
EST. COMPLETION: 12/31/2019
PROJECT COMPLETION: 15%
Tank Industry Consultants is the design professional services. Design is complete and plans submitted to NMED. Upon approval of plans,
the loan will be executed and project to be advertise for bids. DFA advised on 9/17/2018 that loan proceedings should occur in the next 60
days. Awaiting DFA to proceed with loan closing.
Country Club Reservoirs
SCOPE: Rehabilitate the existing twin 7.5 Million Gallon concrete reservoirs on W. Country Club Rd.
BUDGET: $ 3,000,000 Pending finance review
FUNDING SOURCE: Recycle EPA Loan (Forgiveness Funds) & Water Capital Fund
EST. COMPLETION: On-Hold
PROJECT COMPLETION: 0%
Project funds suspended by council recommendation.
Montana Street Realignment
SCOPE: Takeout 90 Degree "S" curve and soften the curve to make street safe prior to opening of Roswell Recreation Center.
BUDGET: $ -
FUNDING SOURCE: Unknown
EST. COMPLETION: 3/31/2019
PROJECT COMPLETION: 10%
Engineering department has started in-house design of project. Preliminary estimate is $434,000. Design is 100% complete. Scheduled to
advortise Sept 30, 2018 and open bids Nov 13, 2018.
Pavement Assesment / Management RFP, Phase I
SCOPE: Prepare a pavement assesment and priority listing of roadway projects for entire city.
BUDGET: $ 150,000
FUNDING SOURCE: FY 2018 Budget
EST. COMPLETION: 6/30/2018
PROJECT COMPLETION: 5%
Engineering workload dependent. Contract with IMS has been executed, Surbey to begin October 2018. IMS is performing preliinary GIS
coordination.
S. Atkinson Project - McGaffey to 2nd Street
SCOPE: ADA / Sidewalk & Mill & Fill of pavement
BUDGET: $1,158,708 ($990,000 NMDOT Share)
FUNDING SOURCE: FY 2018 Budget
EST. COMPLETION: 6/30/2019
PROJECT COMPLETION: 15%
Plans to ve completed by 7/1/18 for NMDOT review. Plans are comlete. NMDOT approval has been received. Scheduled to advertise Sept
30, 2018 to open bids Nov 13, 2018.
Page 4 of 6 Accountability. Communication. Excellence. Integrity. Teamwork. 8
WWTP Safety Upgrades
SCOPE: Various safety improvements at the WWTP
BUDGET: $ 850,000
FUNDING SOURCE: FY 2018 Budget
EST. COMPLETION: 4/1/2019
PROJECT COMPLETION: 10%
Design by HDR. Contractor Bids open 3/13. Bid came in too high, all bids rejected. Rebid awarded to Roads Construction on 6/14/18.
Contracts have been executed. Rhoads awaiting delivery of materials. Pre-Construction conference held on August 22, 20189. Rhoads
waiting on materials to commence project.
E. 2nd Street - Waterline Replacement Phase I
SCOPE: Replace 4.2 miles of existing 10" AC waterline from Atkinson to the east.
BUDGET: $ 3,000,000 per council approval
FUNDING SOURCE: Water Maintenance & Transmission
EST. COMPLETION: 2/28/2019
PROJECT COMPLETION: 5%
Design RFP is advertising. Council awarded RFP to Bohanan-Houston. Survey crews began work August 20, 2018. Design Team meeting
held 9/11/2018. 30% plans to be complete in October 5th.
Hobbs St - Main to Union
SCOPE: Pavement Rehab
BUDGET: $ 650,000 Pending Finance Review
FUNDING SOURCE: Current FY2018 Capital Projects
EST. COMPLETION: -
PROJECT COMPLETION: 0%
Project is in the cue by engineering department and is next in-line after S. Union & Washington project.
ITB-18-007 S. Union & S. Washington
SCOPE: Mill & Fill / Sidewak
BUDGET: $1.5M
FUNDING SOURCE: Bond Funds Leveraged with Legislative Funds
EST. COMPLETION: 12/31/2018
PROJECT COMPLETION: 5%
Bond Funds with Legilative Appropriation A2551. Remaining bond money $1.138M required to be spent by 12/31/18. J&H
Services began milling & roadway on S. Washington.
Cemetery Roads 18-C2474
SCOPE: Phase 3 and Final Phase
BUDGET: $ 150,000
FUNDING SOURCE: DFA Grant Capital Outlay
EST. COMPLETION: Spring 2019
PROJECT COMPLETION: 2%
City Signed grant agreement. Recieved executed grant agreement. Plans are complete. Work to be done in spring 2019, to allowcemetery
crews time to trim trees in winter to allow access of paving equipment.
Gayle Street 36" Waterline Repair
SCOPE: Repair 36" pressure ups.
BUDGET: $ 800,000
FUNDING SOURCE: Current FY Water Enterprise Fund
EST. COMPLETION: 12/1/2018
PROJECT COMPLETION: 20%
J&H Services awaiting delivery of large diameter valves. Work has commenced & repairs underway.
Hot Recycling Pavement Maintenance
SCOPE: Hot recycle existing pavement 2" depth.
BUDGET: $ 600,000
FUNDING SOURCE: Current FY Road Fund
EST. COMPLETION: 10/31/2018
PROJECT COMPLETION: 100%
Scheduled streets; 1) Airport perimeter Road 2) Jaffa St. - Lea to Sunset 3) Sunset - NBL's (North Bound Lanes) only Brasher to Relief
Route 4) N. Washington - 19th to Country Club. Work is completed.
Slurry Seal & Micro Surfacing
SCOPE: Pavement maintenance overlay
BUDGET: $ 950,000
FUNDING SOURCE: Curent FY Road Fund
EST. COMPLETION: 12//2018
PROJECT COMPLETION: 10%
Page 5 of 6 Accountability. Communication. Excellence. Integrity. Teamwork. 9
IPR Construction completed slurry seal on eastside of RIAC residential. IPR commenced micro surfacing of airport perimeter road "hot
recycled areas".
Page 6 of 6 Accountability. Communication. Excellence. Integrity. Teamwork. 10
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Open Discussion - Large Diameter Water Lines
BACKGROUND: Committee has requested updates on issues and work on large
diameter water lines.
1. Gayle St. repairs approximately 50% complete.
2. McGaffey St. – 2 line stops and 1- 36” butterfly valve will be
required. Pulling an already “on hand” 36” butterfly valve from
Gayle St. to expedite. This will get McGaffey open sooner than
waiting for new 36” butterfly valve. This work to be done by
J&H Services already working on Gayle.
3. A new problem encountered. The pressure relief valves from
the 42” concrete cylinder line at Sunset/Hondo River did not
shut off the week of November 13, 2018. This will require
reconstruction of two pressure relief valves in the concrete
valve. Very same issue encountered at the golf course in 2017.
City crews did reduce flow by working valves by hand.
Condition being monitored by City Crews.
FINANCIAL
CONSIDERATION: None at this time.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: Continue with repairs diligently.
11
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Consider recommendation to award ITB-19-001 S. Atkinson
Rehabilitation Project to J&H Services from Albuquerque, NM in
the total amount of $1,451,731.68.
BACKGROUND: Two bids were received for this project: from Constructors Inc. and
J&H Services. Bid Tabulations and recommendation to award are
attached.
This project is partially funded by NMDOT in the maximum amount
of $990,000. Concurrence to award project to J&H Services was
granted by NMDOT, copy attached.
FINANCIAL
CONSIDERATION: Currently FY 2019 only has $1,170,412 for this project. Review of
funding shortfall will be required. In May 2018, Engineering
anticipated an increase in construction costs, and requested
additional funding with savings of completed projects. This request
did not carry over into FY 2019. Copy of transfer request attached.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: Consider recommendation to award ITB-19-001 S. Atkinson
Rehabilitation Project to J&H Services in the total amount of
$1,451,731.68.
STAFF
RECOMMENDATION: Proceed with award of project. City has agreement with NMDOT
to fund this project.
12
13
14
15
16
17
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Consider recommendation to award ITB-19-003 Montana/Stone
Re-Alignment Project to Abraham’s Construction from
Albuquerque, NM in the total amount of $399,500.81.
BACKGROUND: Three bids were received for this project: from Constructors Inc.,
J&H Services and Abraham’s Construction. Bid Tabulations and
recommendation to award are attached.
FINANCIAL
CONSIDERATION: Project is fully funded in current FY 2019 Capital Improvements
budget.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: Consider recommendation to award ITB-19-003 Montana/Stone
Re-Alignment Project to Abraham’s Construction from
Albuquerque, NM in the total amount of $399,500.81.
STAFF
RECOMMENDATION: Proceed with award of project.
18
19
20
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Consider award of ITB-19-004, 2019 Annual Maintenance Contract
to Bullseye Construction of Artesia, NM., and Abraham’s
Construction of Albuquerque, NM.
BACKGROUND: Engineering Department bids out the yearly “Annual Maintenance
Contract”. This contract establishes unit costs for frequently used
items for repairs of roadway, sidewalk, curbing after main breaks.
Also used for construction of civil work on City properties for
sidewalk, drivepads, and such.
Bids were received on November 13, 2018. The two bids were
Bullseye Construction and Abraham’s Construction. Please note
that Abraham’s Construction was the low bidder for 2019 Annual
Maintenance Contract and successfully responded and performed
for all work orders to date. Bid tabs are attached. Under the bid
proposal conditions, this project is awarded to the two lowest
bidders. The 2nd lowest bidder may be used if 1st low bidder can
not respond as required.
FINANCIAL CONSIDERATION:
Each City Department has to request a purchase order utilizing
established unit costs for any work order. Each City Department
utilizing Annual Maintenance Items must have monies available in
their respective budgets.
LEGAL REVIEW: Not Applicable
BOARD AND
COMMITTEE ACTION: Consider award of ITB-19-004, 2019 Annual Maintenance Contract
to Bullseye Construction of Artesia, NM., and Abraham’s
Construction of Albuquerque, NM.
STAFF
RECOMMENDATION: Recommend awards as presented.
21
22
23
24
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Consider recommendation to award ITB-19-005 N. Main Alley
Sewer Project to Adame Construction from Los Lunas, NM in the
total amount of $118,508.80.
BACKGROUND: Three bids were received for this project: from Rhoads Co., AUI Inc.
and Adame Construction. Bid Tabulations and recommendation to
award are attached.
FINANCIAL
CONSIDERATION: Project is funded in current FY 2019 Sewer Budget.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: Consider recommendation to award ITB-19-005 N. Main Alley
Sewer Project to Adame Construction from Los Lunas, NM in the
total amount of $118,508.80.
STAFF
RECOMMENDATION: Proceed with award of project.
25
26
27
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: Consider recommendation to award ITB-19-006 Mescalero Lift
Station Project to Adame Construction from Los Lunas, NM in the
total amount of $99,745.80.
BACKGROUND: Two bids were received for this project: from White Cloud Pipeline
and Adame Construction. Bid Tabulations and recommendation to
award are attached.
FINANCIAL
CONSIDERATION: Project is funded in current FY 2019 Sewer Budget.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: Consider recommendation to award ITB-19-006 Mescalero Lift
Station Project to Adame Construction from Los Lunas, NM in the
total amount of $99,745.80.
STAFF
RECOMMENDATION: Proceed with award of project.
28
29
30
CITY OF ROSWELL
Infrastructure Committee
Large Conference Room, City Hall
425 N. Richardson, Roswell, NM 88201
Monday, November 26, 2018 at 4:00 p.m.
ACTION REQUESTED: To consider presented dates for 2019 Infrastructure Committee
meetings.
BACKGROUND: Committee to discuss and review. See attached letter of
recommended dates presented to City Clerk.
FINANCIAL
CONSIDERATION: None at this time.
LEGAL REVIEW: Not Applicable.
BOARD AND
COMMITTEE ACTION: To consider presented dates for 2019 Infrastructure Committee
meetings.
STAFF
RECOMMENDATION: Proceed as recommended by Infrastructure Committee.
31
32
Get email alerts for Roswell
A daily email when new agendas and minutes are posted.