Infrastructure Committee
Regular MeetingRoswell, NM · March 22, 2021
Minutes
Regular Meeting of the Infrastructure Committee Held
in the Convention Center
March 22, 2021
Notice of this meeting was given to the public in compliance with Sections 10-15-1
through 10-15-4, NMSA 1978 and Resolution 21-7.
ROLL CALL:
The meeting convened at 4:02 p.m. with Chairman Roebuck presiding, Councilor
Sanchez being present, Councilor Peterson being absent, and Councilor Kennard
participated via GoToMeeting.
Staff Present:
Juan Fuentes, Juan Salas, Abraham Chaparro, Lorenzo Sanchez, Trent Moore, Janie
Davies, Chanel Rey, Kevin Maevers, Jessica Collier, Debbie Reyer, Louis Najar, and
Bernadette Lopez
Guest(s) Present:
Grace Sanchez, Larry Connolly, Ivan Hall, and Linda Gonzales participated via
GoToMeeting
APPROVAL OF AGENDA:
Councilor Kennard moved to approve the agenda. Councilor Sanchez was the
second. A voice vote of 3-0 was unanimous, and the motion passed with
Councilor Peterson being absent and Councilor Kennard participating via
GoToMeeting.
APPROVAL OF MINUTES:
1. February 22, 2021:
Councilor Kennard moved to approve the minutes. Councilor Sanchez was
the second. A voice vote of 3-0 was unanimous, and the motion passed with
Councilor Peterson being absent and Councilor Kennard participating via
GoToMeeting.
NON-ACTION ITEMS
2. Projects Updates Discussion:
Mr. Najar discussed the update for the Hot Recycling and Nova Chip. Mr. Moore
discussed the update for the Carpenter Park, Police Evidence Storage, Library Build
Back, and the Library Roof Projects.
3. Landfill Unit 5-A Update:
Mr. Chaparro discussed the update for this item. Mr. Chaparro stated the Addendum for
Page 1 of 3
the bids were supposed to be received today, and they were not accepted because they
were incomplete. He further stated that some of the bidders were having issues procuring
the liner for the cell. Mr. Chaparro handed out a Bar Graph Tonnage sheet with totals for
the last four years. Chairman Roebuck asked to have the Bar Graph Tonnage sheet sent to
the Committee digitally. Chairman Roebuck inquired about the urgency within the market
for the materials needed for the liner. Mr. Chaparro responded, there is a shortage with
HTPE resin used to build the liner and comes out of Texas; however, due to the
catastrophic weather, they are having issues procuring it. Chairman Roebuck inquired
about a contingency plan if the liner is not available. Mr. Najar responded, there could only
be one contingency plan, either have the liner/plastic and continue with the project, or the
project goes on stand-by at no fault to the contractor, and when landfill unit gets full, the
only alternative would be to ship it out.
4. Mountain View Middle School Waterline:
Mr. Najar stated Chris Thweatt with the Roswell Independent School District contacted him
to build a waterline for Mountain View Middle School. Mr. Najar has discussed this with City
management and as soon as agreements are signed, Engineering will proceed with the
design.
5. Water Billing Issues:
Ms. Davies gave a presentation on the utility issues affecting customers. Chairman
Roebuck expressed his disappointment in the handling of the transition from the old to
new billing system and the stress, duress, and waste of time the customers have
experienced because of the lack of “better planning, leadership, and communication
between departments.” Councilor Kennard inquired how the ball was dropped on this
issue. Ms. Rey responded implementation began in December 2019, testing began in
March 2020 forward, and they went “live” in December 2020. Ms. Rey stated there
were unforeseen circumstances going live and lack of understanding the capabilities
of the system and its process.
FOR THE RECORD: Mr. Najar stated while Finance was giving their presentation, he
received a message form Scott McKitrick with Souder, Miller & Associates and that he
contacted the State of NM Environmental Department where the possibility may exist
to have an Air Space Extension Agreement in which trash can be stacked higher on
closed cells.
6. Bicycle & Pedestrian Plan Update:
Mr. Najar stated he was contacted by members of the Parks & Rec Commission to
discuss ideas for the plan. Mr. Najar informed them there was no funding for this
project, but they could go after state grants for funding. Mr. Najar stated the first step
is to adopt the Bicycle & Pedestrian Master Plan as a guideline in which Mr. Najar will
go before General Services Committee on Wednesday, March 24, 2021 to
recommend and send to City Council.
REGULAR ITEMS (ACTION):
7. Consider Award ITB-21-004 Spring River Trail Rehabilitation:
Councilor Kennard moved to recommend approval to the full City Council, the
award of ITB-21-004 (Rebid) Spring River Trail Rehabilitation Project to
Page 2 of 3
Constructors Inc. in the amount of $159,485.45 to the consent agenda on April
8, 2021. Mr. Najar discussed this item. Councilor Sanchez was the second. A
voice vote of 3-0 was unanimous, and the motion passed with Councilor
Kennard participating via GoToMeeting and Councilor Peterson being absent.
8. Consider Lea/Deming Change Order – Water Repair:
Councilor Kennard moved to recommend approval for ITB-20-002 Lea & Deming
Bridge Repairs Project, Change Order #1 in the amount of $63,121.34 to the
consent agenda on April 8, 2021. Mr. Sanchez discussed this item. Councilor
Sanchez was the second. A voice vote of 3-0 was unanimous, and the motion
passed with Councilor Kennard participating via GoToMeeting and Councilor
Peterson being absent.
9. Consider WWTP Digester Roof Repair:
Councilor Kennard moved to recommend approval of the award of J&J Marquez
Residential and Commercial Building for the WWTP Digester Roof in the
amount of $92,227.40 to the full City Council on April 8, 2021. Mr. Sanchez
discussed this item. Councilor Sanchez was the second. A voice vote of 3-0 was
unanimous, and the motion passed with Councilor Kennard participating via
GoToMeeting and Councilor Peterson being absent.
10. Consider Award RFP-21-004 General Construction Services:
Councilor Kennard moved to recommend approval of the award of RFP-21-004
(2nd Posting) General Construction Services as a multiple-source award to
Facility Build, Holloway Construction, and White Sands Construction to the full
City Council on April 8, 2021. Mr. Moore discussed this item. Councilor Sanchez
was the second. A voice vote of 3-0 was unanimous, and the motion passed
with Councilor Kennard participating via GoToMeeting and Councilor Peterson
being absent.
OTHER BUSINESS (Non-Action):
11. Department Reports:
No discussion was held on the reports.
12. Public Comments:
Mr. Connolly commented on the water billing issues.
Linda Gonzales of 637 E. Apple St., Roswell, NM 88201, stated she’s had a lot of
billing problems in which she was repeatedly billed for the same amount each month
when she had paid it previously. Ms. Gonzales asked what the plan was to fix the
faulty system. No response was given from the Committee, nor the Finance
Department staff.
ADJOURN:
The meeting adjourned at 5:01 p.m. The next scheduled meeting is April 26, 2021.
Page 3 of 3
Agenda
ROSWELL INFRASTRUCTURE COMMITTEE AGENDA
Monday, March 22, at 4:00 p.m.
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Committee Chair: Jacob Roebuck
Committee Vice Chair: Margaret Kennard
Committee Members: George Peterson, Savino Sanchez
Staff Coordinator: Louis Najar
A. Call to Order
B. Roll Call
C. Approval of the Agenda
D. Approval of Minutes
1. February 22, 2021 1-2
E. Non-Action Items
2. Project Updates Discussion 3 - 12
3. Landfill Unit 5-A Update 13
4. Mountain View Middle School Waterline 14
5. Water Billing Issues 15 - 29
6. Bicycle & Pedestrian Plan Update 30 - 31
F. Regular Items (Action Items)
7. Consider Award ITB-21-004 Spring River Trail Rehabilitation 32 - 34
8. Consider Lea/Deming Change Order – Water Repair 35 – 38
9. Consider WWTP Digester Roof Repair 39 - 41
10. Consider Award RFP-21-004 General Construction Services 42 - 43
G. Other Business (Non-Action)
11. Department Reports 44 - 60
12. Public Comments
H. Adjourn (Next Meeting: April 26, 2021)
Notice of this meeting has been given to the public in compliance with Sections 10-15-1 through 10-15-4 NMSA 1978
and Resolution 21-7.
NOTICE OF POTENTIAL QUORUM – A quorum of the City Council may or may not attend, but there will not be
debate by the City Council, and no action will be taken.
If you are an individual with a disability who is in need of a reader, amplifier, qualified sign language interpreter, or
any other form of auxiliary aid or service to attend or participate in the hearing or meeting, please contact Human
Resources at 575-624-6700 at least one week prior to the meeting or as soon as possible. Public documents,
including the agenda and minutes, can be provided in various accessible formats. Please contact the City Clerk at
575-624-6700 if a summary or other type of accessible format is needed.
Printed and posted: 3.18.2021
THE PUBLIC IS ENCOURAGED TO PARTICIPATE ELECTRONICALLY THROUGH THE GOTO MEETING
APPLICATION AND NOT PHYSICALLY ATTEND DURING THE PANDEMIC.
TO ATTEND THE INFRASTRUCTURE COMMITTEE BY GO-TO-MEETING
Infrastructure Committee
Mon, March 22, 2021 4:00 PM - 6:00 PM (MDT)
Please join my meeting from your computer, tablet or smartphone.
https://global.gotomeeting.com/join/929161493
You can also dial in using your phone.
United States: +1 (571) 317-3122
Access Code: 929-161-493
New to GoToMeeting? Get the app now and be ready when your first meeting starts:
https://global.gotomeeting.com/install/929161493
Help Desk – 500-0587
Regular Meeting of the Infrastructure Committee Held
in the Convention Center
February 22, 2021
Notice of this meeting was given to the public in compliance with Sections 10-15-1
through 10-15-4, NMSA 1978 and Resolution 21-7.
ROLL CALL:
The meeting convened at 4:01 p.m. with Chairman Roebuck presiding, Councilor
Peterson, Councilor Kennard, and Councilor Sanchez being present.
Staff Present:
Juan Fuentes, Juan Salas, Abraham Chaparro, Lorenzo Sanchez, Trent Moore, Becky
Hicks, Louis Najar, and Bernadette Lopez
Guest(s) Present:
Grace Sanchez and Larry Connolly
APPROVAL OF AGENDA:
Councilor Kennard moved to approve the agenda. Councilor Peterson was the
second. A voice vote of 4-0 was unanimous, and the motion passed.
APPROVAL OF MINUTES:
1. January 25, 2021:
Councilor Kennard moved to approve the minutes. Councilor Peterson was
the second. A voice vote of 4-0 was unanimous, and the motion passed.
NON-ACTION ITEMS
2. Projects Updates Discussion:
Mr. Najar discussed the update on the Boys & Girls Club gym floor. Chairman Roebuck
pointed out that the Boys & Girls Club Pool hours and days of operation are still on the
building wall when the pool has been closed for years. Mr. Najar responded they will
check into it.
3. Water Conservation Plan:
Mr. Sanchez discussed the update for this item. Chairman Roebuck asked for a broader
description of what the Water Conservation Plan covers. Mr. Sanchez briefly read aloud
some of the objectives in the Water Conservation Plan Proposal. Councilor Peterson
stated he would like to see citations issued for wasting water. Mr. Sanchez stated they
address the calls received regarding wasting water immediately and collaborate with the
Code Enforcement Department.
4. 2021 Sewer Manhole Rehabilitation Project:
Page 1 of 2 1
Mr. Sanchez discussed the update for this item. Councilor Kennard inquired about the cost
of each manhole rehab of $5,000. Mr. Najar responded the cost is approximately $4,500 but
historically, around $5,000.
REGULAR ITEMS (ACTION):
5. Consider Asset Management Plan Resolution:
Councilor Kennard moved to recommend Resolution 21-13 Water Utility Asset
Management Plan to the City Council at the March 11, 2021 City Council Meeting.
Mr. Najar discussed this item. Councilor Peterson was the second. A voice vote of
4-0 was unanimous, and the motion passed.
6. Consider Landfill Professional Services – Construction Unit 5A:
Councilor Kennard moved to send the professional services agreement in the
amount of $162,316.06 to the Finance Committee on March 4, 2021. Mr. Chaparro
discussed this item. Chairman Roebuck asked if the cell would be open in time. Mr. Najar
responded he believed so, contingent upon Souder, Miller & Associates completing the
plans and getting them approved by N.M.E.D. The project will be phased to allow opening
of partial unit prior to completing the entire project. Councilor Peterson was the
second. A voice vote of 4-0 was unanimous, and the motion passed.
7. Digester Roof Repair:
Councilor Kennard moved to recommend approval to award Speir Construction,
LLC roofing repairs for the WWTP Digester Roof estimated in the amount of
$153,470.64 to consent agenda on March 11th City Council Meeting. Mr. Sanchez
discussed this item. Councilor Peterson was the second. A voice vote of 4-0 was
unanimous, and the motion passed.
OTHER BUSINESS (Non-Action):
8. Department Reports:
Mr. Najar discussed the South Main Pedestrian Light by the old Payless Shoe store.
9. Public Comments:
Mr. Connolly thanked the committee members for their service.
ADJOURN:
The meeting adjourned at 4:44 p.m. The next scheduled meeting is March 22, 2021.
Page 2 of 2 2
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Project Updates – Infrastructure Committee open discussion
BACKGROUND: Initiated by: Louis Najar
Committee will be given opportunity for Q&A on any project.
Project Dashboard report is part of the committee packet.
Please note project updates report;
Facilities Department
Engineering Department.
FINANCIAL
CONSIDERATION: None at this time.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: None, this is opportunity for Committee to ask questions.
3
City of Roswell Projects Status
Updated 3-16-21
Capital Projects & Facilities
Year
2019 Carpenter Park Splash Pad
SCOPE: Construction of a Splash Pad at Carpenter's park
ESTIMATED COST: $ 450,000
FUNDING SOURCE: CITY SHARE: $3,936.33
$ 314,907 DFA/GRANT #: 19-D2949 Legislative Appropriation
$ - OTHER:
BUDGET: Total Budget: $ 450,000
Total Payments: $ 3,936
Encumbered $ 322,779
Total Change Orders: $ -
Current Balance: $ 127,221
PROJECT CODE NO.: FAC20.001
PURCHASE ORDER NO. 22100111
GL #: 26014311-817504
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 100%
Design Development Phase 100%
Construction Documents Phase 100%
RFP, ITB, CES, Proposal 100%
Construction 95%
Substantial Completion 0%
Project Closeout 0%
Vendor CES/Waide
Notes: Estimated Completion 21-Apr
In Design Phase with Vortex / 3/17/20: design 100%; received proposal from vendors. Will take to Infrastructure Committee end of March and Council in
April. Construction start date first of May (estimated). NOO 1 Approved. Segregated account has been developed and funds transferred. Presenting to
Infrastructure Committee on April 27, 2020. Construction started 11/2020. 12/7/20 Construction on hold as construction crew and plumbing crew in COVID-
19 isolation. 12/28/20 - Construction has resumed.1/18/21 - Concrete pads have been poured. Infrastructure is complete. 2/12/21 - Installation of seating
and top out electrical to commence the week of 2/15/21, weather permitting. 3/16/21 - Seating installation is complete and the electrical top out is 75%.
Features to be installed April 2021.
Year
2019 McBride Veteran's Cemetery
SCOPE: Construction of Honor guard and family shelter
ESTIMATED COST: $ 516,000
FUNDING SOURCE: $ - CITY SHARE: 0
$ 516,000.00 DFA/GRANT #: D2950 - Legislative Appropriation
$ - OTHER:
BUDGET: Total Budget: $ 516,000
Total Payments: $ 42,416 A&E
Encumbered $ 42,416
Total Change Orders: $ -
Current Balance: $ 473,584
PROJECT CODE NO.: FAC20.002
PURCHASE ORDER NO. 194140 GL #: 26014311-817504 Public Works
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 50%
Design Development Phase 100%
RFP, ITB, CES, Proposal 0%
Construction 0%
Substantial Completion 0%
Project Closeout 0%
Vendor
Notes: Estimated Completion 0%
In Design with Huitt-Zollars 3/17/20: Awaiting on topographical map from Engineering. Proposal for AE available on 03/07/20. Conceptual design received
and under review with General Services and Veteran's group.12/16/20. 12/21/20 - Revised conceptual design for presentation to GS on 1/27/21. 2/12/21-
Conceptuals approved by council on 2/11/21, proceeding to complete schematic phase. 3/16/21 Schematic Phase is 50% complete.
Year
4
2020 Library Restroom Build Back
SCOPE: Replace existing scale system with more modern above ground scale system.
ESTIMATED COST: $ 288,265
FUNDING SOURCE: FY21/ Insurance $ 135,776 CITY SHARE:
$ - DFA/GRANT #:
Insurance Claim $ (152,489) OTHER:
BUDGET: Total Budget: $ 288,265
Total Payments: $ -
Encumbered $ 282,334.00
Total Change Orders: $ -
Current Balance: $ 288,265.00
PROJECT CODE NO.:
PURCHASE ORDER NO. 22100607 GL #: 26014311 - 817504
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 100%
Design Development Phase 100%
RFP, ITB, CES, Proposal 100%
Construction 60%
Substantial Completion 0%
Project Closeout 0%
Vendor CES/Holloway
Notes: Estimated Completion
Construction permit delayed 10/26/2020. Revised construction drawings, permit received, submittals reviewed and signed. Construction began the week of
12/21/2020. 1/18/21 - Wall paint and patching is continuing, bathroom reconfigure and repairs has started. Wall patching 90% complete. Patched area and
painting 90% complete. Plumbing rough-in 100% ready for state inspection. New restroom access starting 2/15/21, weather permitting. 3/16/21- All rough-
in plumbing and electrical is complete, and both have received and passed State of NM inspection. Framing to close off existing entry at 90%. New mold-
proof wall sheeting has commenced.
Year
2019 Police Evidence Storage
SCOPE: Secure old FACMAN (Facility Maint.) Shop for PD Evidence Storage
ESTIMATED COST: $ 400,000
FUNDING SOURCE: FY20 Budget $ 400,000 CITY SHARE: $400,000
$ - DFA/GRANT #:
$ - OTHER:
BUDGET: Total Budget: $ 400,000
Total Payments: $ -
Encumbered $ 288,012.00
Total Change Orders: $ -
Current Balance: $ 400,000.00
PROJECT CODE NO.:
PURCHASE ORDER NO. 22100607 GL #: 26014311 - 817504
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 100%
Design Development Phase 100%
RFP, ITB, CES, Proposal 100%
Construction 60%
Substantial Completion 0%
Project Closeout 0%
Vendor CES/Waide
Notes: Estimated Completion 21-Jul
Phase one scope: Roof repairs, secure outer structure and alarm. Anticipate purchase order release week of 12/14/20 and construction to begin January
2021. 1/18/21 - Executive level decision needed on camera and access package. Securing building exterior is 90% complete; roofing to start 2/22/21 due
to weather delay on 2/15/21. 3/16/21- Roofing started February 2021 and is approximately 33% complete. Purchase order issued on February 2021 for
Phase I & Phase II for electrical and security upgrade. Estimate start date of April 2021.
Year
2020 Annex Transaction Window
SCOPE: Remove window and install transaction drawer
ESTIMATED COST: $ 25,000
FUNDING SOURCE: Cares Act Funding CITY SHARE:
$ - DFA/GRANT #:
$ - OTHER:
BUDGET: Total Budget:
Total Payments: $ -
Encumbered
Total Change Orders: $ -
Current Balance: $ -
PROJECT CODE NO.:
PURCHASE ORDER NO. GL #:
Page 2 of 4 5
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 100%
Design Development Phase 100%
RFP, ITB, CES, Proposal 100%
Construction 0%
Substantial Completion 0%
Project Closeout 0%
Vendor 0%
Estimated Completion 0%
Notes:
Site surveyed and proposal received 12/20. Pending executive level decision 12-30-20. 1/18/21 - Project placed on hold by Executive team.
Year
2020 316 North Richardson Building
SCOPE: Demo ceiling and flooring for structural inspection. Build back for office space.
ESTIMATED COST: $29,131- Demo and Report $868,160 - Remodel
FUNDING SOURCE: CITY SHARE:
DFA/GRANT #:
$ 29,131 OTHER:
BUDGET: Total Budget:
Total Payments: $ 24,406.00
Encumbered $ 29,131.00
Total Change Orders: $ -
Current Balance: $ 24,406.00
PROJECT CODE NO.:
PURCHASE ORDER NO. 22100949 GL #: 11014013 - 725610
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 0%
Schematic Phase 0%
Design Development Phase 0%
RFP, ITB, CES, Proposal 100% Demo
Construction 95% Demo
Substantial Completion 95% Demo
Project Closeout 0%
Vendor Holloway
Estimated Completion 20-Dec
Notes:
Demo completed 12/20, awaiting asbestos abatement. Remodel pending executive level decision. 1/18/21 Project placed on hold by Executive team
Year
2020 Convention Center Block Wall
SCOPE: Construct block wall around outdoor garden area with access.
ESTIMATED COST: $ 150,000
FUNDING SOURCE: CITY SHARE:
$ - DFA/GRANT #:
$ - OTHER:
BUDGET: Total Budget:
Total Payments: $ -
Encumbered
Total Change Orders: $ -
Current Balance: $ -
PROJECT CODE NO.:
PURCHASE ORDER NO. GL #:
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 100%
Design Development Phase 100%
RFP, ITB, CES, Proposal 0%
Construction 0%
Substantial Completion 0%
Project Closeout 0%
Vendor 0%
Estimated Completion 0%
Notes:
Design completed by DPS during CC construction. Awaiting proposals.12/20. Proposals received and awaiting executive level decision 12/30/20.
1/18/21 - Project placed on hold by Executive team.
Year
2020 Rebuild Dias Convention Center
Page 3 of 4 6
SCOPE: Reconfigure Dias layout
ESTIMATED COST:
FUNDING SOURCE: CITY SHARE:
$ - DFA/GRANT #:
$ - OTHER:
BUDGET: Total Budget:
Total Payments: $ -
Encumbered
Total Change Orders: $ -
Current Balance: $ -
PROJECT CODE NO.:
PURCHASE ORDER NO. GL #:
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 0%
Schematic Phase 0%
Design Development Phase 50%
RFP, ITB, CES, Proposal 0%
Construction 0%
Substantial Completion 0%
Project Closeout 0%
Vendor 0%
Estimated Completion 0%
Notes:
Conceptual design is in progress 12/30/20. 1/18/21 - Met with multiple contractors and are awaiting design and project cost estimate. 2/1/21 - Proposed
Budgetary Numbers where unacceptable, so we are proceeding with alternative options and will advise with a new direction. 3/16/21 - Met with contractor
March 2021. Contractor is designing alternative options for presentation and budgetary numbers.
Year
2021 Library Bondurant Room
SCOPE: Remove exiting Spanish tile roof and replace with metal standing seam.
ESTIMATED COST: $ 50,000
FUNDING SOURCE: FY21 Budget $ 43,073 CITY SHARE:
$ - DFA/GRANT #:
$ - OTHER:
BUDGET: Total Budget:
Total Payments: $ -
Encumbered
Total Change Orders: $ -
Current Balance: $ 43,073.00
PROJECT CODE NO.:
PURCHASE ORDER NO. GL #: 26014312
PROJECT SCHEDULE:
EST. COMPLETION:
PROJECT STATUS: Phase % Complete
Conceptual, Design 100%
Schematic Phase 100%
Design Development Phase 100%
RFP, ITB, CES, Proposal 100%
Construction 0%
Substantial Completion 0%
Project Closeout 0%
Vendor 0%
Estimated Completion April-21
Notes:
2/16/21 - PO requisition entered. Construction to start immediately starting PO approved. 3/16/21- Roofing materials received March 2021. Awaiting
State of NM permit.
Page 4 of 4 7
City of Roswell Projects Status
3/16/2021
Street Projects & Other
Country Club/Main Traffic Signal:
SCOPE: Upgrade traffic signals at Country Club and Main. Final cost $528,668.20
BUDGET: $ 750,000 Legis. Grant $712.5K, City $37.5
FUNDING SOURCE: FY 2019 Special Electronics Budget, PO 22002450, $464,926.84
EST. COMPLETION: Opened to traffic October 1, 2020
PROJECT STATUS: 100%
Project complete, Engineering performing audit of quantities for final change order and payment.
S. Atkinson Project - McGaffey to 2nd Street
SCOPE: ADA / Sidewalk & Mill & Fill of pavement
BUDGET: $1,451,732 ($990,000 NMDOT Share) Close out pending - due to Contractor dispute.
FUNDING SOURCE: FY 2019 Budget Change order was submitted to contractor 12.17.2020
EST. COMPLETION: Work in Dec. 2019 was completd
PROJECT STATUS: 99%
NMDOT & FHWA need to perform project audit of City. City audit complete. Final change order has been submitted to NMDOT for approval. Once
approved by NMDOT, then project can be closed and final payment to contractor, $116,731.60. Project may experience $65k savings.
Lea/Deming Bridge Bids Opened 12.8.2020, Award to Council January 14, 2021
SCOPE: Remove and replace bridge
BUDGET: Balance of Grant - $693,981. Bid Award Cost $1,020,353.00
FUNDING SOURCE: 2019 Legislative Grant $800,000 Low bid received Abraham's Const. $1,100,280.31
EST. COMPLETION: 12/31/2021 City Funds Required $406,299.31
PROJECT STATUS: 5%
RFP for design awarded to Souder Miller & Associates in the amount of $103,018.95
Awaiting contract, bonds and insurance from Abraham's Construction. Once received City can schedule a pre-construction conference and a start date.
Due to City Utility work, the first phase will be reconstruction of Deming and Lea disturbed by utility construction.
N. Atkinson Project - 2nd to Cherry St.
SCOPE: ADA / Sidewalk & reconstruction of pavement Project on hold until Fall 2021 due to funding reallocations.
BUDGET: ($1,ooo,000 NMDOT Share) Current Engr. Estimate $2,048,034.73, Required City funding $1,048,034.73
Design PO #22002226 $62,241.38
Design Survey Performed by Engineering Department
FUNDING SOURCE: FY 20 Budget Capital Improvements
EST. COMPLETION: 12/31/2021
PROJECT STATUS: Design 100%
Plans 100% complete. Final approval by NMDOT in August 2020. Bid in early 2021. The funding of this project is being used to fund pavement
maintenance and other change orders for N. Garden Bridge.
Spring River Trail - Atkinson to Virginia 1st bid rejected. Rebid to open bids on March 9, 2021.
SCOPE: Trail maintenance improvements
BUDGET: ($127,326 NMDOT Share) Current Engr. Budget $150,000
Design PO #22002447 $27,039.20 Bid Received $208,501.08
Design Survey Performed by Engineering Department City Funding Req'd. $22,674
FUNDING SOURCE: FY 20 Budget Capital Improvements
EST. COMPLETION: 7/1/2021
PROJECT STATUS: Design 100%
Plans 100% complete. Final approval by NMDOT in August 2020. 1st bid of $208,501.08 rejected due to overbudget and only 1 bid. Rebid with
adjusted scope of work to open bids March 9, 2021.
N. Main - Pavement Maintenance - COOP PO Approved by Council 12.10.2020
Agreement with NMDOT approved at July 9, 2020 City Council for $215,443
SCOPE: Micro Surface or Nova Chip on Main - Alameda to McGaffey & College to Country Club (Original limits with application)
BUDGET: Estimated Current project funding is $621,789, PO 22101230
Current full width Engineer Estimate $621,789, NMDOT $161,582, Recommended City funding $460,207
FUNDING SOURCE: Current Project Amount $621,789 Current NMDOT agreement
NMDOT Funding $161,582 Current NMDOT agreement
City Portions $53,861 Current NMDOT agreement
City additional $406,346
EST. COMPLETION:
PROJECT STATUS: PO Approved by Council 12.10.2020
Construction tentative for March 2021
8
Hondo River Trail - 2nd to Virginia
SCOPE: Trail maintenance improvements
BUDGET: $129,000 ($110,218 NMDOT Share) NMDOT FY 21, Construction Costs based on 2018 Estimate
FUNDING SOURCE: FY 20 Budget Capital Improvements
EST. COMPLETION: 12/1/2021
PROJECT STATUS: 2%
Engineering has performed survey and began plans. Agreement with NMDOT in place. Engineering Department has plans at 30% design. NMDOT
review for 30% milestone designt inspection was held 12.16.2020
RFP-20-004 On Call Engineering Services
SCOPE: Qualify pool of engineering firms
BUDGET: Budget for projects as needed
FUNDING SOURCE: From Project Budgets
EST. COMPLETION: 2 year pool
PROJECT STATUS: RFP Complete and vendors approved.
Vendors approved are Bohannan Huston Inc; Enprotec Hibbs & Todd; HDR Inc.; JSH Engineering; Smith Engineering; Souder Miller & Associates
CDBG Grant 18-C-NR-I-03-G-14 Boys & Girls Club
SCOPE: Repairs and Upgrades to Boys & Girls Club
ESTIMATED COST: Cost$80K HVAC,
$1,048,123.50 Bid Cost, Current cost $1,060,116.93 due to Change Order 1
FUNDING SOURCE: Federal Grant & FY19 City Budget
BUDGET Bid Cost $ 1,048,123.50
HVACs $ 59,360.00 City Supplied
Professional Services $ 42,595.00 JSH Engineering
SENMCOG $ 15,000.00
Total Change Orders: $ 11,993.43
Total Cost $ 1,177,071.93
PROJECT SCHEDULE: August 2020 - March 30, 2021
PROJECT COMPLETION: 90%
PROJECT STATUS: Project to awarded to White Sands Construction Co. Pre-construction held August 28, 2020. Contractor has commenced,
currently completed is asphalt parking lot, most of concrete sidewalk, electrical. Working on concrete floor polishing, HVAC
and ceiling work. Change order 1 was required to replace damaged cieling insulation in Teen Room, Game Room, Computer
Lab and adjacent bathrooms. This CO 1 = $11,993.43. Change order 2 removal of two gym wood floor layers at a cost of
$6000. Project also found damaged concrete sub-flooring in the original 1960s gymnasion. Change order 3 is gym floor
remediation $34,816.09, and vent fire detectors in City provided HVAC units and ducting at $3,015.35. Change orders do not
include GRT
McGaffey - Atkinson to Garden ON HOLD DUE TO BUDGET
SCOPE: ADA/Sidewalk - Mill & Fill 2800 LF 13500 SY
BUDGET: Estimated $1.3 million 3" Mill & Fill only = $459K
FUNDING SOURCE: Submitted on 2020 Legislative ICIP
EST. COMPLETION:
PROJECT STATUS:
Project is on the year 1 Pavement Condition List. No activity
Project on hold due to lack of funding.
McGaffey - Main to Garden ON HOLD DUE TO BUDGET
SCOPE: ADA/Sidewalk - Mill & Fill 2500 LF 12000 SY
BUDGET: Estimated $1.3 million 3" Mill & Fill only = $408K
FUNDING SOURCE: Submitted on 2020 Legislative ICIP
EST. COMPLETION:
PROJECT STATUS:
Project is on the year 1 Pavement Condition List. No activity
9
McGaffey - Wyoming to Union Submitted for 2021 Legislative ICIP
SCOPE: ADA/Sidewalk - Mill & Fill 3000 LF 14,500 SY
BUDGET: Estimated $1.3 million 3" mill & fill only = $493K
FUNDING SOURCE: Submitted for 2021 Legislative ICIP consideration.
EST. COMPLETION:
PROJECT STATUS:
Project is on the year 1 Pavement Condition List. No activity
Project on hold due to lack of funding. Project was selected as top 5 ICIP projects for City of Roswell.
FY 21 - Hot Recycling & Micro-surfacing Pavement Maintenance PO approved by Council on 12.10.2020
SCOPE: Hot Recycle & Micro-surfacing of various streets
BUDGET: Estimated $699,706.77 - Hot Recycling only, hot recycled areas to be Micro-Surfaced, Estimated $513,418.64
FUNDING SOURCE: City Road Fund
EST. COMPLETION: 5/7/2021
PROJECT STATUS: Project ready to go, need verified funding PO 2210103 $478,320.23 for micro surfacing
Streets have been selected by using Pavement Condition Survey and field review by Streets & City Engineer. Hot recycling began March 15, 2021,
scheduled to be completed April 2, 2021. Micro-surfacing scheduled to begin March 30, 2021.
FY 21 - Only Micro-surfacing Pavement Maintenance ON HOLD DUE TO BUDGET
SCOPE: Only Micro-surfacing of various streets
BUDGET: Estimated $ 249,512
FUNDING SOURCE: City Road Fund
EST. COMPLETION: 5/30/2021
PROJECT STATUS: Project ready to go, need verified funding
Streets have been selected by using Pavement Condition Survey and field review by Streets & City Engineer. This work to be resubmitted for budget
year FY 22.
FY 21 - Nova Chip Pavement Maintenance ON HOLD DUE TO BUDGET
SCOPE: Place Nova-Chip pavement maintenance lift (plant mix wearing course) - Portions of N. Atkinson
BUDGET: Estimated $ 445,197
FUNDING SOURCE: City Road Fund
EST. COMPLETION: 5/30/2021
PROJECT STATUS:
This work to be resubmitted for budget year FY 22. This is N. Atkinson that has already been crack sealed by Streets Department.
FY 21 - Mill & Fill Pavement Rehab ON HOLD DUE TO BUDGET
SCOPE: Mill and fill 3" depth of existing streets. Portions of Sunset, N. Garden and S. Washington
BUDGET: Estimated $ 2,365,572
FUNDING SOURCE: Engineering Capital Improvement Fund
EST. COMPLETION: 5/30/2021
PROJECT STATUS:
Streets have been selected by using Pavement Condition Survey and field review by Streets & City Engineer. This project is to address pavement
condition only. These locations will not have any sidewalk/ADA improvements. This work to be resubmitted for budget year FY 22.
Bland/Atkinson Turning Lane ON HOLD DUE TO BUDGET
SCOPE: Build turn lane EBL traffic from S. Atkinson
BUDGET: Estimated cost $100K
FUNDING SOURCE: Special Electronics
EST. COMPLETION:
PROJECT STATUS: Design Complete
This NBL to Bland turning lane could never be constructed due to XCEL power poles. In 2019 a pole was damaged and as such, City requested that
power pole be relocated to allow future constrution of turning lane. Design is complete and awaiting funding. Will be requested in future budget cycle.
E Hobson Road Widening ON HOLD DUE TO BUDGET
SCOPE: Widen Hobson Road from E. Earl Cummings Loop east to YO Crossing Road, with turning lanes at Hobson/Earl Cummings Road.
BUDGET: $65,000
FUNDING SOURCE: Capital Improvements
Road Cores PO 22001555 $431.33 - Completed
Design Services PO 22001652 $64,380.88
Topo Survey Performed by Engineering Department
Geotech Testing Performed by Engineering Department
EST. COMPLETION: Unknown until funded
PROJECT STATUS: Design 100%
This project would be conducive to development and access to Roswell Air Center. Plans are complete and project is ready to be prepared for bids if
funding becomes available
Habitat For Humanity Subdivision Development ON HOLD DUE TO BUDGET
SCOPE: Construct cul-de-sac for Humanity Way Court
BUDGET: Estimated cost $180K
FUNDING SOURCE: Capital Improvement
EST. COMPLETION: Unknown until funded
PROJECT STATUS: Design Complete
The City created a subdivision in 2018 for low income housing. As owner/developer the City needs to construct the cul-de-sac. This to be requested in
future budget cycles.
10
Projects coordinated with Utility Departments
RIAC Reservoirs
SCOPE: (2) New Water Towers at RIAC
BUDGET: Design Complete $ 178,500 PO 180704
Historic Documents $ 10,458 PO 190125 _
Const. Prof. Services $ 612,597 PO 22000643 Steel fabrication inspection, field rebar, coating certified inspection
Const. Contractor $ 6,148,750 PO 22002556 Drinking Water Loan - $5,381,142 Principal - Forgiveness $389,463
Total Cost $ 6,950,304
FUNDING SOURCE: EPA Loan & Water Capital Fund
EST. COMPLETION: Tower 1 Gillis St. January 2021, Tower 2 W. Martin St. August 2021.
PROJECT STATUS: Time used 75%.
Construction commenced 11.18.19. Tower 1 (Gillis St.) has painting completed. Approximately 85% complete. Tower 2 (W Martin St) painting
complete pain. Approximately 85% complete - finish crews are on the job. Tower 2 should be in service before May 1, 2021. Winds and cold have
delayed operations on Tower 2.
Large Diameter Valve Project
SCOPE: Large Diameter Valve construction
BUDGET: $1,438,96 (Bid) PO 22002823 - Final cost = $1,666,029.46
FUNDING SOURCE: 2019 Legislative Grant $750,000 and Water Enterprise all over $750K
EST. COMPLETION: Completed in Feb. 2021
PROJECT STATUS: 100%
Engineering Department in house design and construction inspection and management.
Work commenced May 4, 2020. Preliminary excavation and pipe measurements performed. Excavations revealed significantly different site
conditions than the old construction plans showed. Change Order 1 addresseded this. Project History: Contractor waited on parts, which were delayed
due to Covid19. During preliminary excavation and verification of pipe review, three of the four sites have significant differing site conditions. Pipe is
not constructed or in postion as per plans. Change order 2 - Final was to reconcile final measured quantities in the amount of $4,588.71. Final
payment in process
Manhole Rehab Project 2020
SCOPE: Rehabilitate 53 sewer manholes.
BUDGET: $204,343.03 award amount Final Cost - $202,294.19
FUNDING SOURCE: FY 20 Budget
EST. COMPLETION: Completed Feb 2021
PROJECT STATUS: Project is Complete
Engineering Department in house design and construction inspection and management.
Contract awarded to Corrosion Resistant Coatings. Contractor began work August 17, 2020. Work is progressing satisfactorily.
WWTP Screw Press Improvements PO for design approved by Council 12.10.2020
SCOPE: Install screw presses at WWTP
BUDGET: Estimated $ 5,500,000 Loan is for design and construction
FUNDING SOURCE: WWTP - Clean Water Loan
EST. COMPLETION: Design March 2021
Construction July 2022
PROJECT STATUS:
RFP process complete and project awarded to HDR for design and future construction professional services. Agreement has been signed by consultant
and City. Design kick off meeting between NMENV, HDR and City was held on 12.16.2020. Design in progress
Manhole Rehab Project 2021
SCOPE: Rehabilitate 49 sewer manholes.
BUDGET: $ 250,000
FUNDING SOURCE: FY 21 Budget
EST. COMPLETION: 3/31/2022
PROJECT STATUS: Plans complete
Engineering Department in house design and also to perform construction inspection and management.
Advertise March 7, 2021, Open bids April 13, 2021 - ITB-21-010
WWTP Dissolved Oxygen Study
SCOPE: Perform study of effluent at WWTP for oxygen values.
BUDGET: $11,325
FUNDING SOURCE: WWTP FY 20
EST. COMPLETION: Study complete Nov. 2020
PROJECT STATUS: 100%
HDR was consulted to do study. Study indicates that Waste Water Treatment Plant will require modifications to meet new EPA requirements. WWTP
is looking over alternatives and will request budget in FY 22
11
Projects coordinated with Other Departments
Cielo Grande All Inclusive Park - Grant 20-E2504 PO for BHI for design services approved by Council 12.10.2020
SCOPE: Design and construct All Inclusive Park and amenities
BUDGET: Grant Amount $ 1,461,000
Design Services $ 150,966 PO 1 _
Const. Bid PO
Other
Total Cost
FUNDING SOURCE: DFA Grant & City Funds possible
EST. COMPLETION: Dec. 2021
PROJECT STATUS: 0%
Engineering assigned this project November 6, 2020. Will team with Parks Department for this project. BHI will be consultant. The current schedule
is to complete design Spring 2021 and construct project by 12.31.2021. Design team kickoff meeting was held Feb. 24, 2021
Cielo Grande Baseball Fields Complex - Grant 20-E2503 PO Approval by Council 1.14.2021 for BHI $526,795 for engineering.
SCOPE: Design and construct baseball field complex
BUDGET: Grant Amount $ 850,000
Design Services Unknown PO 1 _
Const. Bid PO
Other
Total Cost
FUNDING SOURCE: DFA Grant & City Funds possible
EST. COMPLETION: Dec. 2021
PROJECT STATUS: 0%
Engineering assigned this project November 19, 2020. Will team with Parks Department for this project. BHI has began survey of Cielo Grande Sports
Complex area.
12
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Landfill Unit 5A Construction Project Updates – Infrastructure
Committee open discussion
BACKGROUND: Initiated by: Abraham Chaparro
Landfill Unit 5A Construction Project, Bid ITB-21-009 was
advertised for bids on March 7, 2021. Bids to be opened on March
29, 2021 with recommendation going to Finance Committee of
April 1, 2021. Recommendation to award would go to City Council
of April 8, 2021
FINANCIAL
CONSIDERATION: None presented for this project update.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: None, this is opportunity for Committee to ask questions.
13
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Mountain View Middle School Waterline Project Updates –
Infrastructure Committee open discussion
BACKGROUND: Initiated by: Louis Najar
The City has been asked by RISD to build a waterline from S. Main
St. to Mountain View Middle School. Once completed, RISD would
reimburse the City. This line would be a 10 inch water main.
Similar process was used to build waterline to Berrendo
Elementary School.
FINANCIAL
CONSIDERATION: None presented for this project update.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: Once there is a written agreement, Engineering to proceed with
design of project and bidding of project.
14
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Update – Utility Billing Issues and Customer Complaints
BACKGROUND: Initiated by: Janie Davies & Chanel Rey
Timeline and Plan of Correction regarding the Tyler Munis Utility
Billing conversion in December 2020. Committee will be given
opportunity for Q&A. Report is part of the committee packet.
FINANCIAL
CONSIDERATION: None at this time.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: None, this is opportunity for Committee to ask questions.
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Project Updates – Roswell Bicycle & Pedestrian Plan
BACKGROUND: Initiated by: Louis Najar
The Roswell Bicycle & Pedestrian Plan was completed in April 2020.
Parks & Recreation Commission met on March 15, 2021 and
recommended that General Services Committee of March 24, 2021
forward adoption of the plan by Resolution.
By adopting plan, then projects addressed, recommended or as a
result of guidelines from the PLAN could submit for federal and
state funds.
FINANCIAL
CONSIDERATION: None at this time.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Open discussion for this Committee.
STAFF
RECOMMENDATION: Proceed with adoption of Roswell Bicycle & Pedestrian Plan for
groups to begin application process and as a guide for improving
pedestrian and bicycle use.
30
31
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Consider award of ITB-21-004 (Rebid) Spring River Trail
Rehabilitation project to Constructors Inc., in the amount of
$159,485.45 which includes GRT.
BACKGROUND: Initiated by: Louis Najar
This project does have funding participation in the amount of
$127,306 from the NMDOT. This leaves a balance of $32,179.45
required for City match.
1st time Bids were opened on January 12, 2021. One bid was
received from Constructors Inc. of Carlsbad, NM, in the amount of
$208,501.08. This bid was rejected, and project was rebid.
Project bid items were revised and project was rebid. The Rebid
was opened for bids on March 9, 2021. Two bids were received.
Constructors Inc. was deemed qualified bid, with a bid amount
including GRT of $159,485.45
FINANCIAL
CONSIDERATION: This project will be funded by NMDOT project agreement $127,306
and Capital Improvement funds of $32,179.45. This project was
approved for current FY 21 budget.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Consider award of ITB-21-004 (Rebid) Spring River Trail
Rehabilitation project to Constructors Inc., in the amount of
$159,485.45, and recommend to City Council of April 8, 2021.
STAFF
RECOMMENDATION: Proceed with award as presented.
32
33
34
35
36
37
38
39
J & J Marquez Residential and Commercial Building Estimate
Name/Address
City of Roswell
WasteWater Treatment
2306 E College Blvd,
Roswell, NM 88203
575-625-2388
Date Estimate No. Project
03/10/21 10 Water Treatment
Item Description Quantity Cost Total
Standard Remove the two asphalt roofs from existing roof. 85,527.75 85,527.75T
Timberline Remove insulation. Scrap asphalt and clean.
Remove pipe flashing. Clean all curbs for fans and
turbos. Remove steal walking pads. Apply primer
onto concrete decking. Install 1 inch ISO insulation
and secure with foam. Install Vercico 60 mil white
TPO rubber and secure with bonding glue. Wrap all
fan and turbo curbs. Install new pipe flashing.
Install TPO metal drop edging around the building
and weld rubber into metal drop edging. Reinstall
the steal walking pads. Rubber walkig pads will be
an extra charge.
Includes Price includes City permit, cleaning and dumping of 0.00 0.00
all material.
Includes JM 15 This includes the standard 15 year warranty on 0.00 0.00
year Vercico materials.
Not Responsible Not Responsible for damage to gas or electric lines 0.00 0.00
for during repairs.
Guaranteed Work does not include damages resulting from act 0.00 0.00
Work of other trades, material defect, weather or any
other unforeseen acts of nature.
Warranty Work 2 This includes a 2 year contractors workmanship 0.00 0.00
year only guarantee
Down Payment 1/2 down payment required before job is started 0.00 0.00
required
THANK YOU FOR YOUR BUSINESS Total
Page 1
40
J & J Marquez Residential and Commercial Building Estimate
Name/Address
City of Roswell
WasteWater Treatment
2306 E College Blvd,
Roswell, NM 88203
575-625-2388
Date Estimate No. Project
03/10/21 10 Water Treatment
Item Description Quantity Cost Total
Sales Tax Roswell 7.8333% 6,699.65
THANK YOU FOR YOUR BUSINESS Total $92,227.40
Page 2
41
CITY OF ROSWELL
INFRASTRUCTURE COMMITTEE
MEETING ROOM A – ROSWELL CONVENTION CENTER
912 MAIN, ROSWELL, NM 88201
MONDAY, MARCH 22, 2021 AT 4:00 P.M.
ACTION REQUESTED: Consider award of RFP-21-004 (2nd Posting) General Construction
Services as a Multiple-Source award to all three contractors for
various citywide construction projects.
BACKGROUND: Initiated by: Frank Moore
An RFP was issued to make available a pool of contractors for
performing construction services for various citywide projects for
each fiscal year. Three proposals were received as follows,
Facility Build of Albuquerque, NM
Holloway Construction of Roswell NM
White Sands Construction of Alamogordo, NM
All three contractors are deemed qualified for a multiple source
award and establish a contractor pool.
FINANCIAL
CONSIDERATION: Each project to be funded from the appropriate department
budget for each fiscal year.
LEGAL REVIEW: Not applicable.
BOARD AND
COMMITTEE ACTION: Consider award of RFP-21-004 (2nd Posting) General Construction
Services as a Multiple-Source award to Facility Build, Holloway
Construction and White Sands Construction and recommend to
City Council of April 8, 2021.
STAFF
RECOMMENDATION: Consider a Multiple-Source award of RFP-21-004 (2nd Posting)
General Construction Services as presented.
42
43
CITY OF ROSWELL
Infrastructure Committee
Meeting Room A – Roswell Convention Center
912 N. Main, Roswell, NM 88201
Monday, March 22, 2021 at 4:00 p.m.
ACTION REQUESTED: Non-Action Departmental Reports
(Informational for Meeting Packets)
BACKGROUND: Compiled by: Louis Najar
Department Reports Listing: (Alphabetical listing)
Central Control/Source of Supply -
Engineering Report Annual Maintenance Support
Engineering Report Community Development Support
Fleet Maintenance
Solid Waste Departments – (Not submitted)
Special Electronics
Streets Department
Water Maintenance & Transmission –
WWTP & Sewer
FINANCIAL
CONSIDERATION: Not applicable for this agenda item.
LEGAL REVIEW: Not applicable for this agenda item.
BOARD AND
COMMITTEE ACTION: Informational for meeting packets from departments associated
with Infrastructure Committee.
STAFF
RECOMMENDATION: Not applicable for this item.
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
Get email alerts for Roswell
A daily email when new agendas and minutes are posted.