Parks and Recreation Advisory Board
Regular MeetingRoyal Oak, MI · November 6, 2025
Minutes
Minutes
Parks and Recreation Advisory Board
November 6, 2025, 7:00 p.m.
City Hall, Room 122
203 S. Troy Street
Royal Oak, Michigan 48067
Present: Sarah Kindinger
Brigitta Burguess
Tony Rennpage
Sue Wells
Hannah Holliday
Ryan Danescu
Ian McKinney
Brandon Kolo
Brandon Mason
_____________________________________________________________________
1. Meeting Called to Order
Meeting called to order at 7:00 pm.
2. Approval of Agenda
Moved by: Ryan Danescu
Seconded by: Brandon Kolo
Motion to amend to add introductions before public comment
Motion Adopted
3. Approval of Minutes
Moved by: Brandon Kolo
Seconded by: Ryan Danescu
Motion to approve the October 2 minutes
Motion Adopted
4. Introductions
5. Public Comment
1
None.
6. Reports
6.a Staff Report - Nicole McEachern
Administration
Carolyn Marsh has been promoted from part-time A.G.E.
Administrator and Volunteer Coordinator to full-time Senior Center
Administrative Assistant. In this role, Carolyn will oversee customer
service and facility reservations, while supporting a wide range of
administrative and programming duties.
Winter Insights have been mailed out and arrived in mailboxes the
week of October 27. Registration opens 11/11 for Residents, 11/25
for non-res.
Nicole completed Financial Sustainability Certificate Program in
Ann Arbor Oct 21-23, offered by mParks.
We were featured in Royal Oak Review for Lockman Park Ribbon
Cutting and Royal Oak City Lifestyle November Issue.
Recreation
We taking an agreement to Commission on November 10 with the
YMCA and School District to relaunch aquatics programs. This
includes open swim, swim lessons, and water fitness.
We are relaunching the Memorial Tree program for spring plantings
(these are live now). Benches likely opening up in January.
Senior Center is gearing up for AARP Tax Aide appointments
beginning in February. Appointments can be made starting January
6. We are preparing to expand our intake and serve more people
due to Clawson shutting down their tax service.
Senior Center is preparing a guide about area food banks for those
faced with food insecurity.
Indoor Pickleball at the Salter Center is picking up, fielding lots of
calls on hours and information regarding program.
Adult leagues: Softball – season wrapped up last month, starting to
look ahead to spring season. Volleyball – will run to December,
ending before the holidays. Winter Volleyball season will begin after
Jan 1st.
Starting to work with Oakland County on 3 events for 2026-
Marshmallow Drop, DiversAbility Day, and Health and Housing
Summer Fest.
2
Park/Facilities
Salter Center roofing project began this week and is expected to
take 3 weeks. Some programs have been moved to the Senior
Center, other locations inside Salter, or postponed for the duration
of the project (Bounce Volleyball, Video workout group).
Clawson Park Improvements are complete.
Red Run Park playground installation is complete. Just waiting on
DPS to stripe the road.
Memorial Park Netting project began and is expected to be
completed by mid-November.
6.b City Commission Comments
Leprechauns are under new ownership. Mark Sacket is no longer
with the organization, and they have new leadership.
Six electric vehicle charging stations were approved for Senior
Center.
Throne in Centennial Commons is being moved closer to the spray
pad.
Centennial Commons Rink is being set up and will be open by
November 21.
Winter Blast is not returning but there will be 5 different weekend
events in Centennial.
Rehab Board of Appeals is meeting soon to discuss next year's
funding.
Safe Routes to Schools initiative is working to map out routes to
schools and make them safer. They are looking for volunteers.
7. Business
7.a Gunn Dyer Park Improvements - Nicole McEachern and Joseph
Murphy
Moved by: Ryan Danescu
Seconded by: Ian McKinney
Motion to recommend the City Commission approve the Gunn Dyer Park
Improvement Concept Designs as presented.
Motion Adopted
7.b Capital Improvement Plan (CIP) - Nicole McEachern
3
Board requested to do a ranking prioritization process at a future meeting.
Moved by: Hannah Holliday
Seconded by: Ryan Danescu
Motion to recommend the Planning Commission approve proposed
Capital Improvement Plan as presented.
Commissioner Kolo abstained
Motion Adopted
7.c Request to Display Bent Brush - Susan Barkman
Barton South and Pat Paruch, and West Lafayette Parking Structure were
possible options discussed by the board.
8. Items Not on the Agenda
9. Upcoming Events
10. Adjournment
Meeting adjourned at 9:01 pm.
Moved by: Ian McKinney
Seconded by: Hannah Holliday
Motion to adjourn
11. Next Meeting: December 4, 2025
4
Agenda
Agenda
Parks and Recreation Advisory Board
Thursday, November 6, 2025, 7:00 p.m.
City Hall, Room 122
203 S. Troy Street
Royal Oak, Michigan 48067
Anyone planning to attend the meeting who has need of special assistance under the Americans with
Disabilities Act (ADA) is asked to contact the city clerk’s office at 248-246-3050 at least two (2)
business days prior to the meeting.
Pages
1. Meeting Called to Order
2. Approval of Agenda
3. Approval of Minutes 3
4. Public Comment
5. Reports
a. Staff Report - Nicole McEachern
b. City Commission Comments
6. Business
a. Gunn Dyer Park Improvements - Nicole McEachern and Joseph Murphy 8
Staff is seeking feedback on the designs for Gunn Dyer Park. Details
included in attached memo.
Suggested Motion Language - Motion to recommend the City
Commission approve the Gunn Dyer Park Improvement Concept
Designs as presented.
b. Capital Improvement Plan (CIP) - Nicole McEachern 13
Staff is seeking feedback on the Parks and Recreation Capital
Improvement Plan. Details included in attached memo.
Suggested Motion Language - Motion to recommend the Planning
Commission approve proposed Capital Improvement Plan as presented.
c. Request to Display Bent Brush - Susan Barkman 23
Details included in attached memo.
7. Items Not on the Agenda
8. Upcoming Events
9. Adjournment
10. Next Meeting: December 4, 2025
Page 2 of 24
Minutes
Parks and Recreation Advisory Board
October 2, 2025, 7:00 p.m.
City Hall Commission Chambers Room 121
203 South Troy Street
Royal Oak, MI 48067
Present: Sarah Kindinger
Brigitta Burguess
Tony Rennpage
Hannah Holliday
Ryan Danescu
Ian McKinney
Brandon Kolo
Absent: Sue Wells
_____________________________________________________________________
1. Meeting Called to Order
Meeting called to order at 7:00 pm.
2. Approval of Agenda
Motion to add a public comment to 6 A.
Moved by: Ryan Danescu
Seconded by: Tony Rennpage
Motion Adopted
3. Approval of Minutes
Motion to approve the September 4, 2025 Minutes.
Moved by: Ryan Danescu
Seconded by: Tony Rennpage
Motion Adopted
4. Public Comment
1
Page 3 of 24
1. Joe Vukich spoke as fields director for Royal Oak Football Club to bring
attention to issues at Normandy Oaks Park soccer fields with condition of
the fields. Asked board members to visit the soccer fields.
2. Joe Williams, Royal Oak resident and former Southfield Parks and
Recreation employee reported that Normandy Oaks Park suffered grass
damage from a fungal disease in May 2022, prompting a soil test that
revealed poor soil chemistry. They recommended adding magnesium,
conducting regular soil tests at premium fields, and applying fertilizer three
to five times annually, while also noting issues with irrigation head
placement. The Michigan State Turf Grass Institute was suggested as a
helpful resource, and ROYSA was acknowledged for contributing to
Quikstad and helping maintain the fields.
5. Reports
5.a Staff Report – Nicole McEachern
Administration
We selected Jes Alger as our full-time Parks and Recreation Clerk.
Jes will oversee customer service, while supporting a wide range of
administrative and programming duties to ensure smooth daily
operations. Jes Alger has 15 years of experience in parks and
recreation, specializing in aquatics, athletics, and archery. Jes is a
Certified Parks and Recreation Professional (CPRP). She has
worked with Parks and Recreation Departments at Oak Park,
Independence Township, and West Bloomfield
We have Erin Junge joining our Parks and Recreation team as a
new part-time clerk on a temporary basis. Erin will provide
additional coverage to the Recreation Counter, answer main line
phone calls, and tackle administrative and programming tasks.
She will work approximately 20 hours per week. Before relocating
to the east side last month, Erin spent nearly three years with the
City of Portland as the Recreation Coordinator, where she
managed youth and adult sports leagues, oversaw the Daddy
Daughter Dance, and contributed to improving program operations
and communications. Erin is a Certified Parks and Recreation
Professional (CPRP) and holds a Master’s degree in Recreation
Management. She is well-versed in RecDesk software.
Doruk Dogan is being promoted from part-time Chef to full-time
Senior Center Chef. In this role, Doruk will supervise the
Congregate Meal Program, oversee Dinner and Luncheon Events,
Cooking Classes, the Community Gardens, Bee Hives, and more.
Doruk is ServSafe Food Safety Certified.
Interviews for the Administrative Assistant positions for the Senior
Center are underway.
2
Page 4 of 24
Winter Insight publication process is underway.
Recreation
Salter Center open pickleball begins the week of Monday, October
20th with options for play M-F. Outdoor pickleball will be closing
sometime late October.
We are in final stages of developing an agreement with the YMCA
and School District to relaunch aquatics programs. This includes
open swim, swim lessons, and water fitness. Our goal is to finalize
agreements prior to November.
ROFC Season will wrap up at our parks 11/8.
ROSL beginning to discuss 2026 field use and plans.
Adult leagues:
o Softball will run through October, with playoffs to end the
season.
o Volleyball will run to December, ending before the holidays.
o Winter Volleyball season will begin after Jan 1st.
Park/Facilities
Senior Center had its grand reopening and ribbon cutting on Friday,
September 26.
Salter Center roofing project has been awarded. Project is
estimated to be completed in the fall.
Clawson Park Improvements are on track for substantial
completion in October.
Red Run Park playground replacement begins Monday, October 6
and is expected to take 3 weeks.
Memorial Park Netting project anticipated to start October 22.
5.b City Commission Comments - Commissioner Kolo
New charging stations are coming to the Senior Center.
The three throne bathrooms have been well received. They cost
$6,000 per month.
We have a new DDA Director dedicated to the downtown.
Farmers Market received recognition from the Governor for being
100 years old.
3
Page 5 of 24
6. Business Items
6.a Gunn Dyer Park Improvements and Future CDBG Funded Park
Projects
Staff is seeking feedback from the Parks and Recreation Advisory Board
on the 30% design for Gunn Dyer Park. Feedback is also requested from
the Board regarding prioritization for future CDBG funded park projects.
Details included in attached memo. Staff presented overview of memo.
Gunn Dyer Park Feedback: Board members expressed interest in using
bid alternates to save costs, especially on concrete alternatives for
pathway and reduced parking options. Item will be brought back to the
November meeting for further discussion.
Public Comment on Gunn Dyer:
David Prout, Sandlot League- Fully supports the project for multiple sports
and playground use. The park is heavily used up to six days a week but
has drainage issues and serves 30 to 35 teams of kids aged 8 and under.
John Linz, Royal Oak Football Club - Supports park improvements and
sees this as a chance to show commitment to better facilities. Suggests
delaying the playground phase due to its high cost.
Joe Vukich, Royal Oak Football Club - Notes that third and fourth grade
games are 7 versus 7, and fitting an 11 versus 11 field may be difficult due
to space needed for corner kicks and out-of-bounds play.
Joe Williams, Royal Oak Football Club- Says this is one of the city’s worst
drained parks and needs attention.
6.b Capital Improvement Plan (CIP)
Staff presented overview of projects recommended for 26-27 Fiscal Year.
Board members provided the following feedback:
Board suggested that Madison Heights would be a good model for a
Master Plan Update.
7. Items Not on the Agenda
8. Upcoming Events
9. Adjournment
Adjourned 9:15 pm.
Resolution Number: Motion to adjourn
Moved by: Hannah Holliday
Seconded by: Brigitta Burguess
4
Page 6 of 24
Motion Adopted
10. Next Meeting: November 6, 2025
5
Page 7 of 24
Royal Oak Parks and Recreation
203 S Troy Street
Royal Oak, MI 48067
248.246.3180
MEMORANDUM
DATE: October 28, 2025
TO: Parks and Recreation Advisory Board
FROM: Nicole McEachern, Parks and Recreation Director
Joseph Murphy, Planning Director
SUBJECT: Gunn Dyer Park Improvements
Feedback Requested for Gunn Dyer Park Improvements
Staff is requesting feedback from the Parks and Recreation Advisory Board on the 30%
design plans for Gunn Dyer Park. This project is funded through Community Development
Block Grant (CDBG) funds. Nowak & Fraus Engineers (NFE) submitted the lowest bid for
survey, design, and construction inspection services.
At the October 2 Board meeting, staff presented a concept that exceeded the available
budget and asked the Board to help identify priorities. Based on that input, staff worked with
NFE to develop two revised design options for the Board’s consideration. Both incorporate
the ability to safely accommodate U6, U8, U10, or U12 soccer fields along with a U8 ball
diamond.
The tables below outline the differences between these two concepts. Staff recommends
moving forward with the bid process using both options, with specific elements included as
bid alternates. A bid alternate is a pricing option in a construction bid that allows the project
owner to decide whether to include or exclude certain features. This approach provides
flexibility to adjust the project scope based on available funding.
Page 8 of 24
Concept A – Estimated $874,000
Proposed walking surfaces are 100% concrete. Larger raised playground. 2 parking
areas.
Category Description Cost
Overall Site Improvements 2 parking areas (grading, base, pavement) $62,000
All walkways incl. concrete path + NE parking $38,000
Site grading with berm $20,000
Baseball Diamond/Fields More pavement (bleacher to parking, 6") $19,000
Playground Improvements Adjacent seating areas – Concrete, 4" $13,000
Machine grading (berm) $0
Larger play area (EWF mulch) $12,000
Railing $2,000
Other Mobilization + Contingency $90,000
Page 9 of 24
Concept B – Estimated $816,000
Less concrete surfacing. Slightly smaller playground. 1 parking area.
Category Description Cost
Overall Site Improvements 1 parking area (grading, base, pavement) $41,000
All walkways incl. crushed stone pathway $29,000
Site grading – no berm $12,000
Baseball Diamond/Fields Less pavement (bleacher to parking) $13,000
Playground Improvements Adjacent seating areas – Crushed stone $4,500
Machine grading: excavation required $6,000
Smaller play area (EWF mulch) $9,500
No railing $0
Other Mobilization + Contingency $84,000
Page 10 of 24
BACKGROUND
Nearly every five years, the U.S. Department of Housing & Urban Development (HUD)
provides communities across the country with data sets to determine which census block
groups within their jurisdiction have a relatively greater percentage of low- to moderate-
income residents compared to averages. The data helps determine potential activities that
will indirectly benefit those living in qualifying census block groups.
On June 6th,2024 HUD released its notice and related data based on the results of the
American Community Survey 2016-2020 5-year estimates. A new map illustrates qualifying
census block groups.
It’s worth noting that prior data was based on the results of comprehensive decennial census
efforts. The new data is based on samplings over time, pooled together, weighted, and
processed as a whole dataset.
In prior years, the city expended Community Development Block Grant (CDBG) funds on
capital improvements within qualifying census block groups. Based on the service area of the
activity, it’s presumed under HUD regulations to indirectly benefit all residents living in the
qualifying census block group. Area benefit activities have included improvements to public
infrastructure like street trees, sidewalks, crosswalks, roads, street lighting, fire hydrants,
neighborhood scale park features such as playground equipment, exercise equipment, ball
fields, and walking paths, etc.
The city’s parks system has been the recipient of CDBG investments. Over the past twelve
years, the city commission has authorized $7.2 million of the city’s CDBG funds on park
improvements. Parks will undoubtable compete for future CDBG funds.
Within the city’s recreation master plan, each of the city’s parks are classified by their size
and service area into three primary categories: mini-parks, neighborhood parks, and
community parks. Depending on the scale of the park and its amenities, the document
outlines the suggested service area below.
park type amenity service area
mini-park ¼ mile or less
neighborhood park ¼ - ½ mile
community park ½ - 3 miles
Typical park improvements include new or improved playground equipment, fitness
equipment, pathways, limited parking, ball fields, tennis courts, drainage improvements,
landscaping, etc. These facilities dominate the city’s mini-parks and neighborhood parks.
Community scale parks are larger in scale and often include facilities intended to serve a
larger population. Their area benefit is designed to serve more than just those living in the
immediate neighborhood.
Page 11 of 24
Many of park facilities are outdated or deteriorated and need to be replaced. The city’s
recreation master plan identifies system-wide and park-specific actions. The document also
establishes a goal to increase and diversify access to parks. It recognizes the need to
enhance pedestrian and cyclists’ access to the parks and recreation facilities.
Federal regulations require that CDBG-funded public facilities and improvements benefit
those living in qualified census block groups that are primarily residential in nature. The
funded activity must have a service area boundary that does not extend beyond the census
block group boundary.
In recent past, staff have been asked to research the eligibility of expending CDBG funds on
improvements in community scale parks. Representatives from HUD have affirmed various
ineligible projects based on the service area of the park. Staff suggest that recommended
improvements be limited to known eligible projects. Numerous mini-parks and neighborhood
parks are in need of improvements that will benefit those living in the immediate
neighborhood. Community scale parks within the qualifying census block groups include
Cummingston Park, Memorial Park, Quickstad Park, and Worden Park. Different funding
sources should be researched for improvements at these community scale parks.
The following parks are geographically located within qualifying census block groups and
would have eligible projects based on service area:
Neighborhood Parks: Gunn Dyer Park, Miller Park, Upton Park
Mini Parks: Westwood Park, Rotary Park
Page 12 of 24
Royal Oak Parks and Recreation
203 S Troy Street
Royal Oak, MI 48067
248.246.3180
MEMORANDUM
DATE: October 27, 2025
TO: Parks & Recreation Advisory Board
FROM: Nicole McEachern, Director of Parks and Recreation
SUBJECT: Parks & Recreation Capital Improvement Plan 2026-2032
Staff prepared an updated Capital Improvement Plan (CIP) totaling $28.5 million in estimated
investments for parks infrastructure. The plan emphasizes rehabilitating and replacing existing
infrastructure, driven by aging amenities and limited funding. In short, staff recommend focusing on
caring for what we already have.
2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
$ 1,596,000 $2,762,000 $4,670,000 $4,564,000 $6,839,000 $8,060,000
A detailed spreadsheet of proposed park projects is attached. Please note, proposals for recreational
facilities are not being presented to the Board at this time.
Staff has growing concern over deferred maintenance across the city’s 51 parks and multiple
recreation sites. Without intervention, the backlog of repairs could lead to difficult decisions, including
the removal of amenities or, in extreme cases, divestment of park land.
Page 13 of 24
Suggested motion language
No formal action is required from the Advisory Board at this time, though members may choose to
pass a motion endorsing the draft CIP. Suggested motion language is provided to facilitate this option.
Motion to recommend the Planning Commission approve proposed Capital Improvement Plan
as presented.
Background
The CIP is a strategic planning tool used by city governments to schedule, finance, and implement
infrastructure projects over multiple years. While the CIP guides budgeting decisions, it does not
determine final budget allocations. Development of the parks and recreation CIP was informed by the
Recreation Master Plan and the Sustainability and Climate Action Plan. The Parks and Recreation
Advisory Board discussed CIP at their September and October 2025 meetings.
The CIP process occurs prior to the operating budget process as the CIP will be used to develop the
capital portion of the budget. Approval of the CIP by the Planning Commission does not signify final
approval or funding of any project contained within the plan. Rather, by approving a CIP, the Planning
Commission acknowledges that they agree that the projects present a reasonable interpretation of the
upcoming needs / wants for the city and comply with the City’s master plan. Generally, the projects
contained in the first year of the plan will be requested in next year’s department requested budget
and potentially advance to the manager’s recommended and/or city commission’s approved budget
should funding be available
Page 14 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Currently the lighting at Memorial Park athletic fields is manually operated, requiring a
Parks and
Memorial Park staff member to be physically onsite to turn it on and off. The retrofit will allow staff to
Parks & Recreation
TBD Lighting Controls $ 15,000 create automated schedules and remotely operate the lights through a software
Grounds Millage
Retrofit application. This will improve overall efficiency and reduce staff labor associated with
operating the lights.
The Recreation Master Plan highlights the desire for more bicycle infrastructure (racks
and repair stations) in city parks to enhance Royal Oak's nonmotorized network.
Parks and
Bicycle Racks and Priority parks include Wagner, Realtor, Grant, VFW, Lockman, Meininger, Upton, and
Parks & Recreation
2026-22 Repair Stations in $ 17,000 Worden East. Department of Public Service staff would install the items. Project would
Grounds Millage
Parks cover the cost of 4 installations completed in-house. Supports S-CAP Action 2.1.6.
Develop and implement a plan to install and maintain municipal bicycle infrastructure
community-wide.
Parks and
Parks & Park Bench/Picnic Recreation This ongoing program aims to replace existing wooden benches/picnic tables in parks
2025-40 $ 20,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000
Grounds Table Replacement Millage with recycled composite benches/picnic tables.
The Recreation Master Plan highlights the desire for more water fountains in city parks.
Parks and Estimate would cover the cost of 4 installations completed in-house by DPS staff.
Parks & Water Fountains in Recreation Prioritization would be for high-use community parks that currently lack water
2024-58 $ 51,000
Grounds Parks Millage fountains: Myron Zucker Park, Quickstad Park, Red Run Park, Starr Jaycee, VFW Park,
Wagner Park, or Worden Park. Supports S-CAP Action 4.1. Provide safe, accessible
drinking water to all residents.
Maddock Park, with the oldest playground equipment in our system dating back to
1994, is a priority candidate for full replacement to meet current safety and
accessibility standards. The average lifespan of commercial playground equipment
Parks and
ranges from 8 to 15 years.These improvements are outlined in the Recreation Master
Parks & Maddock Park Recreation
TBD $ 53,000 $ 350,000 Plan. The project has opportunity to incorporate sustainable features such as porous
Grounds Improvements Millage
pavement and recycled materials, supporting S-CAP Actions 5.3.4 and 3.2.1, which
promote ecological responsibility and recycling in municipal construction. Design and
bid support from an engineering firm will be included in the first fiscal year, with 15%
of the budget allocated for professional assistance.
Page 15 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Lions Club Park, with playground equipment dating back to 1995, is a priority
candidate for full replacement to meet current safety and accessibility standards. The
swing set was recently removed due to damage during a sewer project. The average
lifespan of commercial playground equipment ranges from 8 to 15 years. To improve
Parks and pedestrian safety and access, the crossing at Hilldale will be upgraded with a striped
Parks & Lions Club Park Recreation crosswalk and ADA-compliant ramp at the park entrance. These proposed changes
TBD $ 53,000 $ 350,000
Grounds Improvements Millage were identified in the Recreation Master Plan. The project has opportunity to
incorporate sustainable features such as porous pavement and recycled materials,
supporting S-CAP Actions 5.3.4 and 3.2.1, which promote ecological responsibility
and recycling in municipal construction. Design and bid support from an engineering
firm will be included in the first fiscal year, with 15% of the budget allocated for
professional assistance.
Fernwood Park (1 acre) requires improvements due to outdated facilities. Public input
for the Recreation Master Plan identified replacement of the play structure (installed
in 1999), maintenance for the sandbox, and additional shade as desired priorities for
Parks and
this park. The swing set was recently removed due to disrepair. Design and bid
Parks & Fernwood Park Recreation
2024-30 $ 90,000 $ 600,000 assistance with an engineering firm would occur in the first fiscal year, with 15%
Grounds Improvements Millage
included for engineering firm assistance. There is opportunity for pourous pavement
and recylced materals for this project to support S-CAP Action 5.3.4. Evaluate the use
of ecologically-friendly materials for park play areas, and 3.2.1. Require contractors to
include recycling as part of their bids for municipal construction projects.
Reconstruction of the existing pickleball courts at Whittier Park is necessary as the
lifespan of the courts is expiring. This is a project funded in the current fiscal year and
will be carried over to next two fiscal years. Design and bid assistance with an
Parks and
engineering firm will occur in the first fiscal year, with construction in the second fiscal
Parks & Whittier Pickleball Recreation
2024-36 $ 500,000 year, with 15% included for engineering firm assistance. There is opportunity for
Grounds Courts Replacement Millage
pourous pavement and recylced materals for this project to support S-CAP Action
5.3.4. Evaluate the use of ecologically-friendly materials for park play areas, and 3.2.1.
Require contractors to include recycling as part of their bids for municipal
construction projects.
Located south of 13 Mile and west of Coolidge, Gunn Dyer Park (2.36 acres) is
Parks & Gunn Dyer Park CDBG Fund challenged by flooding issues. Feedback in the planning process identified the need
2024-48 $ 750,000
Grounds Improvements for better, accessible access to the soccer field. Play structure was removed for safety
concerns. This park is eligible for CDBG funds.
Page 16 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Located on the city’s north end, Upton Park (3.86 acres) has eight pickleball courts.
Parks & Upton Park CDBG Fund The park is challenged by flooding issues and a lack of trees. It was identified as a
2024-45 $ 850,000
Grounds Improvements location for a new pavilion with restrooms. Long-term, the pickleball courts are
recommended to be reconstructed. This park is eligible for CDBG funds.
The Recreation Master Plan highlights the desire for installation of more permanent
restrooms in high trafficked parks. Staff is currently determining which parks make
the most sense for restroom additions. Depending on scope, restrooms can cost
anywhere from $250,000 to $500,000. Prioritization would be for high-use parks.
Design and bid assistance with an engineering firm will occur in the first fiscal year,
Parks and
with construction in the second fiscal year. The total project cost for one unheated
Parks & Recreation
2024-51 Park Restrooms $ 42,000 $ 275,000 $ 44,000 $ 290,000 unisex restroom prefabricated structure with utility connections is estimated at
Grounds Millage
$287,500, with 15% included for engineering firm assistance. Restrooms will create
new ongoing operating costs due to regular cleaning, maintenance, and winterization.
Due to funding constraints, we have listed installation of only two restrooms. There is
opportunity for pourous pavement and recylced materals for this project to support S-
CAP Action 3.2.1. Require contractors to include recycling as part of their bids for
municipal construction projects
Residents requested parking improvements on E. Parent Avenue for Lawson Park after
improvements at Lawson Park have increased traffic to the park. The estimate of
General
$70,000 provides ten parking spaces in total, with two being accessible. These
Parks & Fund/Road
2026-24 Lawson Park Parking $ 70,000 improvements were presented to the Commission on October 28, 2024 and were not
Grounds Funds
approved for funding at the time. Note that when concepts for Lawson Park
improvements were presented to residents several years ago, the neighborhood
opposed the installation of a parking area within/around the park.
Replace current trails in Cummingston and Tenhave Woods with ADA-compliant trails
to enhance accessibility and connection to nature. This project was identified in the
Parks and
Nature Areas ADA Recreation Master Plan process. Add trail markings, educational signage, and an
Parks & Recreation
2024-47 Trails (Cummingston $ 75,000 $ 500,000 accessible paved path connecting to the sidewalk. Design and bid assistance with an
Grounds Millage
and Tenhave Woods) engineering firm would occur in the first fiscal year, with construction occurring in the
second fiscal year for a project totaling $575,000, with 15% included for engineering
firm assistance.
Page 17 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Red Run Park (19.7 acres) requires renovations due to flooding issues and aging
amenities. Plans include renovating play structures, athletic fields, and potentially
Parks and adding a skate park. Improvements also cover resurfacing ball diamonds, adding
Parks & Red Run Park Recreation seating, pathways, parking, and a new pavilion with restrooms, enhancing overall
2026-32 $ 300,000 $ 2,000,000
Grounds Improvements Millage accessibility and recreational options. Design and bid assistance with an engineering
firm would occur in the first fiscal year, with construction occurring in the second
fiscal year for a project totaling $2,300,000, with 15% included for engineering firm
assistance.
Maudlin Park, with playground equipment dating back to 1995, is a priority candidate
for full replacement to meet current safety and accessibility standards. The average
lifespan of commercial playground equipment ranges from 8 to 15 years. Additionally,
Parks and the existing path to the play equipment will be renovated and completed to ensure full
Parks & Maudlin Park Recreation accessibility for all users. These upgrades are reflected in the Recreation Master Plan.
TBD $ 58,000 $ 385,000
Grounds Improvements Millage The project has opportunity to incorporate sustainable features such as porous
pavement and recycled materials, supporting S-CAP Actions 5.3.4 and 3.2.1, which
promote ecological responsibility and recycling in municipal construction. Design and
bid support from an engineering firm will be included in the first fiscal year, with 15%
of the budget allocated for professional assistance.
Elks Park (4.32 acres), located adjacent to Normandy Oaks, features several sports
fields and courts but faces flooding and maintenance challenges. Its location and size
offer significant redevelopment potential to complement Normandy Oaks. Public
input highlighted the need for new facilities, including a potential skate park. Design
Parks and
and bid assistance with an engineering firm will occur in the first fiscal year, followed
Parks & Elks Park Recreation
2024-38 $ 240,000 $ 1,600,000 $ - by construction in the second fiscal year. The total project cost is estimated at
Grounds Improvements Millage
$1,840,000, with 15% included for engineering firm assistance.There is opportunity
for pourous pavement and recylced materals for this project to support S-CAP Action
5.3.4. Evaluate the use of ecologically-friendly materials for park play areas, and 3.2.1.
Require contractors to include recycling as part of their bids for municipal
construction projects.
Page 18 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Although Royal Oak has 25 tennis courts, the National Recreation and Park
Association suggests 9 for our population size. The Recreation Master Plan advises
repurposing underutilized and severely damaged courts for green space or other
facilities, recommending the decommissioning of 5-7 tennis courts in disrepair.
Tennis Court
Parks & Possible replacement could include conversion to courts lined for both tennis and
2026-33 Removals/Replaceme Risk Fund $ 500,000 $ 500,000
Grounds pickleball. Tennis Courts located at Red Run and Meininger are in the worst condition
nts
and are recommended for removal in other CIP projects. Elks, Dondero, Myron Zucker,
and Kenwood are in poor condition and should be prioritized for replacement or
removal. The average lifespan of an outdoor tennis court in Michigan is below 20 years
due to the climate.
Westwood Park (1.03 acres) offers two swing sets, two play structures, and a
multipurpose field. It is near William Beaumont Hospital Royal Oak and the Berkley
Parks & Westwood Park CDBG Fund
2024-55 $ 750,000 border. The park is challenged by outdated play equipment and the field requires
Grounds Improvements
maintenance. The spiral slide at Westwood is damaged and closed off for safety
reasons. This park is eligible for CDBG funds.
Mark Twain Park (7.18 acres), the only dog park in the northwest corner of the city,
charges $40 for residents and $65 for non-residents. Membership covers fence/gate
maintenance, waste management, and landscaping. Potential improvements
identified in the Recreation Master Plan include a shade structure, paved pathway,
Parks and
rain garden, and drainage enhancements. Design and bid assistance with an
Parks & Mark Twain Dog Park Recreation
2024-56 $ 75,000 $ 500,000 engineering firm would occur in the first fiscal year, with construction occurring in the
Grounds Improvements Millage
second fiscal year for a project totaling $575,000 with 15% included for engineering
firm assistance. There is opportunity for pourous pavement and recylced materals for
this project to support S-CAP Action 5.3.4. Evaluate the use of ecologically-friendly
materials for park play areas, and 3.2.1. Require contractors to include recycling as
part of their bids for municipal construction projects
Artificial turf was installed in 2021 at Field #3. The expected lifespan is 8 to 15 years,
Parks and depending on factors like the quality of the turf, usage frequency, and how well it is
Memorial Park Athletic
Parks & Recreation maintained. The turf will need to be replaced as soon as 2029 or as late as 2036
2024-46 Turf Replacement, $ 400,000
Grounds Millage depending on condition. The Joint Operating Agreement with Michigan Red Sox Inc
Field #3
established a refurbishment fund whereby a portion of each year's rental revenue is
deposited to prepare for Field #3 turf replacement.
Page 19 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Rotary Park (0.8 acres) is located directly south of the Royal Oak Golf Course at 13
Parks & Rotary Park CDBG Fund Mile Road between Coolidge and Crooks. Surrounded by nearby apartment buildings,
2024-35 $ 500,000
Grounds Improvements the park has no built amenities but offers a future opportunity for seating or public art.
This park is eligible for CDBG funds.
Miller Park (1.51 acres) is located within walking distance of William Beaumont
Hospital Royal Oak, near Coolidge and 13 Mile. The park has playground equipment
Parks & Miller Park CDBG Fund
2024-32 $ 750,000 $ - and a multipurpose field. It was identified as a location for adult exercise equipment.
Grounds Improvements
The play structure has been updated within the last 10 years. This park is eligible for
CDBG funds.
Maudlin Park, with playground equipment dating back to 1997, is a priority candidate
for full replacement to meet current safety and accessibility standards. The average
lifespan of commercial playground equipment ranges from 8 to 15 years. The project
Parks and has opportunity to incorporate sustainable features such as porous pavement and
Parks & Marks Park Recreation recycled materials, supporting S-CAP Actions 5.3.4 and 3.2.1, which promote
TBD $ 61,000 $ 405,000
Grounds Improvements Millage ecological responsibility and recycling in municipal construction. Design and bid
support from an engineering firm will be included in the first fiscal year, with 15% of
the budget allocated for professional assistance.Design and bid support from an
engineering firm will be included in the first fiscal year, with 15% of the budget
allocated for professional assistance.
Adding lights to soccer fields at Quickstad Park extends playtime into the evening,
increasing usage and accessibility. It supports evening practices and games,
Parks and
enhancing the park’s utility and accommodating community schedules. Lighting also
Parks & Quickstad Park Soccer Recreation
2024-49 $ 90,000 $ 600,000 improves safety and visibility, creating a welcoming environment for all users. Design
Grounds Field Lights Millage
and bid assistance with an engineering firm would occur in the first fiscal year, with
construction occurring in the second fiscal year for a project totaling $690,000, with
15% included for engineering firm assistance.
Wagner Park (14.09 acres) offers picnic areas, playgrounds and an 18-hole disc golf
Parks and course, all shaded by a significant mature tree canopy. Potential improvements
Parks & Wagner Park Recreation include new pathways and updates to the disc golf course. Installed in 2015, the play
2026-23 $ 128,000 $ 850,000
Grounds Improvements Millage structure is will be nearing replacement age by 2030. Design and bid assistance with
an engineering firm will occur in the first fiscal year (estimated 15% of total cost), with
construction in the second fiscal year.
Page 20 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Isabel & Myron Zucker Park (formerly Exchange Park) (14.49 acres), located in the
city's northeast corner, offers various active recreation facilities, including one of
Royal Oak's ten basketball courts. The park faces flooding and maintenance issues.
Public input in the Recreation Master Plan highlighted the need for maintenance, new
Parks and
facilities, and flood mitigation. Design and bid assistance with an engineering firm will
Parks & Isabel & Myron Zucker Recreation
2024-52 $ 300,000 $ 2,000,000 occur in the first fiscal year, with construction in the second fiscal year. The total
Grounds Park Improvements Millage
project cost is estimated at $2,300,000, with 15% included for engineering firm
assistance. There is opportunity for pourous pavement and recylced materals for this
project to support S-CAP Action 5.3.4. Evaluate the use of ecologically-friendly
materials for park play areas, and 3.2.1. Require contractors to include recycling as
part of their bids for municipal construction projects
Memorial Park (18.35 acres) is a community park and features three ball fields, play
structure, and one of five reservable picnic pavilions. Potential improvements include
ADA-accessible bleachers, expanded seating, artificial turf for Fields #1 and #2,
accessible paths, redeveloped restrooms, roofing replacement, updated press box,
Parks and storage facility improvements, new locker rooms, replacing nonfunctional
Parks & Memorial Park Recreation scoreboards, and updated play structure. Design and bid assistance with an
2025-25 $ 450,000 $ 3,000,000
Grounds Improvements Millage engineering firm will occur in the first fiscal year, followed by construction in the
second fiscal year. The total project cost is estimated at $3,450,000, with 15%
included for engineering firm assistance. Improvements at Memorial Park were given a
lower priority by the Parks and Recreation Advisory Board because the park has
already seen substantial recent investments. Artificial turf was installed in 2021 in
Field #3 and replacement for the turf is listed in a separate CIP.
Identified as a priority in the Recreation Master Plan, ADA-compliant crosswalks are
Major and
crucial for ensuring safe park access for all, including people with disabilities. They
Parks & Crosswalks for Safe Local Roads
2026-18 $ 500,000 provide an inclusive environment, promoting equal access and mobility, while also
Grounds Access to Parks Fund
enhancing overall safety for pedestrians. Barton Park North, Dondero, Optimist Park,
Huntington Woods Park were all identified as possible locations for new crosswalks.
Page 21 of 24
Draft 5 Year CIP Parks and Rec
CIP # PROJECT NAME POTENTIAL FISCAL FISCAL FISCAL FISCAL FISCAL FISCAL NARRATIVE
FUNDING YEAR YEAR YEAR YEAR YEAR YEAR
SOURCE(S) 2026-27 2027-28 2028-29 2029-30 2030-31 2031-32
CITY COST CITY COST CITY COST CITY COST CITY COST CITY COST
Based on public input during Recreation Master Plan process, upgrades at Worden
Park (22.67 acres) could include "clovering" ball diamonds for better use of soccer,
lacrosse, and football fields, connecting paths with fitness amenities, lighting
Parks and
upgrades. This is our third largest park and is adjacent to the high school. The park
Parks & Worden Park Recreation
2026-20 $ 675,000 $ 4,500,000 offers baseball, tennis, ice skating, and potential for a community garden, roller
Grounds Improvements Millage
hockey rink, or skate park. Design and bid assistance with an engineering firm will
occur in the first fiscal year, with construction in the second fiscal year. The total
project cost is estimated at $5,175,000, with 15% included for engineering firm
assistance.
Providing Wi-Fi in public parks enhances accessibility, encourages more visitors, and
Parks and
supports digital inclusion. It enables people to stay connected while enjoying outdoor
Parks & Recreation
2024-54 Park Connectivity $ 1,000,000 spaces, making parks more versatile for work, education, and recreation, and
Grounds Millage
fostering community engagement. The focus should be on high volume parks, such as
Starr Jaycee, VFW, Centennial and Normandy Oaks Parks.
The current Master Plan (2023-2027) will be succeeded by the 2028-2032 Plan. A
Parks and consultant will be engaged in fiscal year 2026-2027, with adoption by December 2027.
Parks and Recreation Recreation This Plan outlines future operations, maintenance, and enhancements for Royal Oak’s
2026-35 Study $ 47,000 $ 47,000
5 Year Master Plan Millage parks and recreation facilities. It also forms the basis for grant funding from MDNR and
other agencies. Consultant work spans two fiscal years, totaling approximately
$90,000.
During the Recreation Master Plan process, public input identified a desire for an
Parks and
additional dog park serving the southern area of the city. Dog parks were historically
Feasibility Study for Recreation
2026-7 Study $ 55,000 located in Meininger and Lockman but are no longer operated due to operational
Additional Dog Park Millage
challenges. It is recommended to engage a consultant to evaluate the feasibility and
desirability of adding an additional dog park.
Parks and The Recreation Master Plan identified a need for cultural programming, such as
Feasibility Study for Recreation outdoor concerts. While some parks can temporarily host these activities, no
2026-35 Study $ 55,000
Outdoor Amphitheater Millage permanent facility exists. Conduct a feasibility and locational study for constructing
an outdoor amphitheater to meet this demand.
During the Recreation Master Plan process, residents and stakeholders expressed a
Parks and strong desire for a community pool and an indoor recreation facility. To address this,
Feasibility Study for
Recreation conduct a feasibility study for the pool, potentially collocated with a new community
2026-21 Study Community Center $ 75,000
Millage center. This includes investigating public/private partnerships, determining priority
with Indoor Pool
within city needs, identifying the best accessible location, and developing a
conceptual site plan, and cost estimates for financing and development.
Page 22 of 24
Office of the City Manager
203 South Troy Street
Royal Oak, MI 48067
www.romi.gov
Request to Display Bent Brush
by Richard Gage
Members of the Parks and Recreation Advisory Board:
Local artist Richard Gage has reached out to the us to see if Royal Oak would be interested in
displaying the piece Bent Brush as a long term installation. He is interested in getting the piece
displayed but not planning to sell it, nor does he want to see it to the city. You can get a sense
of the scale of this piece https://youtu.be/uMON-KH_l_w?si=RR-O2KvlJYWk6g8D
The Commission for the Arts heard about the piece and is supportive of displaying it perhaps in
a park location. Staff suggested Barton Park South as a potential location as it is noted in the
Parks Master Plan that an art installation would be good in that area.
The board is open to other locations as well. Staff thought about Pat Paruch Park. Pat was a
long-term Commission representative on the Commission for the Arts. The piece that is
currently located in the park is placed through the Art Explored program, so it is not necessarily
a long-term piece.
Staff would like to get feedback from the Parks and Recreation board to see if you are
agreeable to Barton Park (shown below for reference) or another park location.
Page 23 of 24
If agreeable, we would begin working on specific site location and a contract with the artist and
putting the item before the City Commission for approval.
Susan Barkman
Deputy City Manager
Page 24 of 24
Get email alerts for Royal Oak
A daily email when new agendas and minutes are posted.