City Council
Regular MeetingSan Bruno, CA · May 28, 2024
Agenda
CRESTMOOR RESIDENTIAL PROJECT AT
300 PIEDMONT AVENUE
CITY COUNCIL MICHAEL SMITH
MAY 28, 2024 COMMUNITY DEVELOPMENT
AGENDA
I. Objective
II. Background
III. Analysis
IV. Recommendation
2
OBJECTIVE
1. Review and certify an EIR
2. Review and approve
General Plan amendments
3. Approve an amendment to
the Zoning Map
4. Review and approve
entitlement request for 300
Piedmont Ave.
3
BACKGROUND
4
BACKGROUND
Location: 300 Piedmont
Ave. (former Crestmoor HS
Site)
Owner: San Mateo Union
High School District
Applicant: SummerHill
Homes LLC
BACKGROUND
Site Photos
BACKGROUND
Council Resolution
2022-04
• January 11, 2022
• General Plan policy
OSR-8
• 12 acres of
recreational space
at Crestmoor
• District objected
BACKGROUND
Settlement Agreement
City initiated General
Plan Amendments
Contemplates the
amount of land
dedicated to City
Contemplates location
of bio-retention area
Rescind Council
resolution 2022-04
BACKGROUND
Residential Project
• Construct 155 two-story
single-family homes
• 24 below market rate
(BMR) units (15%+)
BACKGROUND
Planning Approvals:
• Vesting Tentative Tract Map
• Planned Unit Permit
• Architectural Review Permit
• Density Bonus Request
• Tree Removal Permit
• Affordable Housing Plan
• General Plan Amendment
• Zoning Map Amendment
BACKGROUND
Site Plan Approach
• Clustered homes
• Dedication of 6.91
acres, 5.3 acres for
future park
• Additional 12.24 acres of
natural open space on
sloped area
BACKGROUND
BACKGROUND
Planning Commission Review on May 7th
Recommended Certification of EIR and Approval of Project
Resolutions attached to the staff report
ANALYSIS
14
ANALYSIS
Vesting Tentative Tract Map
• 171 parcels
• 155 single-family
parcels
15
ANALYSIS
Planned Unit Permit
1. Clustering of development
2. Lots less than 5,000 SF
3. Reduced setbacks
4. 15’ front setback
5. 20’ garage setback
6. 4’ side setback
16
Architectural Review Permit
1. Two neighborhoods
ANALYSIS 2. High-quality design
3. 21 different exterior styles
4. Landscaped front yards
5. Earth-tone color palette
17
Architectural Review Permit
1. Color palette
ANALYSIS 2. Materials
3. Scale
4. Building form
18
ANALYSIS
Affordable Housing Plan
• 15%+ affordable for sale units (24 units)
• 10% moderate-income
• 5% low-income
• Deed restricted for 55 years
• Units mixed throughout subdivision
• Indistinguishable from market-rate units
19
ANALYSIS
Density Bonus
Concession
• Utility
Undergrounding
20
GENERAL PLAN AMENDMENTS
21
ZONING MAP AMENDMENT
22
ENVIRONMENTAL REVIEW
• Information for
decisionmakers
and the public
• Mitigation and
alternatives
• Public
Participation
23
EIR PROCESS
Draft EIR
Scoping/NOP of Scoping Meeting: Circulation:
EIR: April 10, 2023 April 18, 2023 October 20 –
December 5, 2023
Planning
Draft EIR Public
Final EIR: April 9, Commission
Meeting: October
2024 Recommendation:
26, 2023
May 7, 2024
24
ENVIRONMENTAL REVIEW
• Aesthetics • Hydrology and Water Quality
• Air Quality • Land Use/Planning
• Biological Resources • Noise and Vibration
• Cultural and Tribal Cultural • Population and Housing
Resources • Public Services
• Energy • Recreation
• Geology and Soils • Transportation
• Greenhouse Gas Emissions • Utilities and Service Systems
• Hazards and Hazardous • Wildfire
Materials
25
KEY IMPACTS
IDENTIFIED
• Construction-
related impacts
• Operation-
related impacts
• Vehicle miles
traveled and
greenhouse gas
emissions
• EIR prepared
26
TRANSPORTATION/ VMT
Significance Threshold: Project's Estimated
Regional Average VMT
15% Below Today's Average VMT per
per Resident (Today)
Regional Average Resident
• 14.6 • 12.4 • 14.7
TDM Mitigation Measure (Mitigation Measure TRA-2)
• TDM Marketing Program
27
ALTERNATIVES
28
No Project Alternative
Alternative 1: Increased
Density with ADUs with
Open Space and
Recreation
Alternative 2: Reduced
Density with Open
Space and Recreation
29
TRAFFIC
• Traffic volume not a metric
for significance under
CEQA.
• Traffic control warrants
attached to Final EIR
• COA for a new stop sign at
Madison Avenue and
Piedmont Avenue to
address the restricted view
ENVIRONMENTAL REVIEW
Statement of Overriding Considerations
• General Plan Implementation
• Neighborhood Safety
• Housing Development
• Enhanced Recreational Facilities
30
PUBLIC COMMENT
31
RECOMMENDATION
32
RECOMMENDATION
1. Adopt a Resolution certifying the FEIR for the project, and statement of
overriding considerations, and a mitigation monitoring and reporting program
for the project.
2. Adopt Resolution approving the General Plan amendments, changing
the land use designation for the dedicated portion of the site from low-
density residential to open space, amend GP policy OSR-8 per the
settlement agreement, and other conforming GP amendments
3. Adopt an Ordinance amending the Zoning Map, to change the zoning for the
dedicated portion of the site from Single-family residential to Open Space
4. Adopt Resolution approving the entitlements for the residential portion of the
project, which includes Vesting Tentative Tract Map, Planned Unit Permit,
Architectural Review Permit, Density Bonus, Tree Removal Permit,
and Affordable Housing Plan
33
34
300 PIEDMONT AVENUE, SAN BRUNO
PROCESS TO DATE
2020 Spring 2020 SMUHSD markets Crestmoor site
2021 Dec 2021 SummerHill enters into purchase agreement w/ SMUHSD
Jan 2022 City of San Bruno adopts Resolution re: GP Policy OSR-8
Mar 2022 • SMUHSD & City of San Bruno enter into Tolling Agreement
regarding Resolution re: GP Policy OSR-8
• SummerHill submitted Preliminary & SB 330 Application
2022 May 2022 SummerHill Community Meeting #1
Aug 2022 Formal Application submitted to City of San Bruno
Nov 2022 • 2nd Submittal to City of San Bruno
• Tolling & Settlement Agreement approved between SMUHSD &
City of San Bruno
Dec 2022 City Council initiated GP Amendment re: OSR-8
PROCESS TO DATE
Feb 2023 • SummerHill Community Meeting #2
• 3rd Submittal to City of San Bruno
Apr 2023 • Project Environmental Review Scoping Meeting
Apr-Aug 2023 • Crestmoor Fields Master Plan - Community Meetings & Study
Sessions
2023
July 2023 4th Submittal to City of San Bruno
Sept 2023 Crestmoor Fields Master Plan - Parks & Rec Hearing
Oct 2023 • Crestmoor Fields Master Plan – City Council Adoption
• Draft EIR Public Hearing | Planning Commission Review
Oct-Dec 2023 DEIR Comment Period
Mar 2024 5th Submittal to City of San Bruno
2024 Apr 2024 Final EIR Published
May 2024 Planning Commission Hearing
EXISTING SITE OVERVIEW
PLANNING APPROACH
Utilize SummerHill’s 20+ years of
Be consistent with City’s General
experience providing
Plan, Zoning and utilize its
Communities of Distinction in
Planned Unit Permit Ordinance
San Bruno (Marisol, Merimont,
to preserve open space
Skyline Ridge)
Be consistent with surrounding Provide public open space land
single-family detached for recreation to San Bruno
neighborhood community
Incorporate neighborhood
Preserve the natural open space
feedback from community
slopes
meetings
MARCH 2024 – PROJECT PLAN
PROJECT BENEFITS
Create 155 single family detached homes compatible with the surrounding
Crestmoor Neighborhood – all family sized at 4-bedroom floor plans
Preserve 20+ acres (50% of the site) of open space including:
• Dedication of 6.9 acres public open space
• Preservation & maintenance of 14 acres of publicly accessible private open
space & private open space
Provide 24 single family homes, all
4-bedroom, at below market rate for Low and Moderate income families
PROJECT BENEFITS
Site currently generates no property taxes. Homes will generate
apprx. $3 million in property taxes annually, including apprx. $400,000
to the City of San Bruno
One-time payment of apprx. $4.9 million in
City Development Impact Fees (DIF)
• One-time payment of $1.9 million in School Development Impact Fees to
San Bruno Park & San Mateo Union High School Districts
Proceeds from sale of project site by SMUHSD are anticipated to fund
much-needed housing offsite for District teachers and staff
ENHANCED STREETSCAPE – COURTLAND DRIVE
NEIGHBORHOOD TOT LOT – NEIGHBORHOOD 2
TOT LOT IMAGERY & PRIVATE STREET LIGHT
NEIGHBORHOOD COMMUNITY SPACE – NEIGHBORHOOD 1
6’ HIGH GOOD NEIGHBOR FENCE
6’ HIGH VIEW FENCE (PRIVATE YARDS BETWEEN HOMES)
6’ HIGH GOOD NEIGHBOR FENCE (SOUTH/WESTERN EDGE AT OPEN SPACE)
W/ LATTICE
(PRIVATE YARDS STREET FACING)
COURTLAND DRIVE
(LOTS 1-12 FRONT YARD RAIL FENCE) 5’ HIGH BLACK VINYL COATED CHAIN LINK FENCE & GATE
(COURTLAND DRIVE AT OPEN SPACE & CHURCH)
NEIGHBORHOOD FENCING
DEFENSIBLE SPACE PLAN
MAINTENANCE EXHIBIT - PROJECT
CITY OF SAN BRUNO - CRESTMOOR FIELDS MASTER PLAN | OCTOBER 2023
VIEW OF NEIGHBORHOOD 1 &
NEIGHBORHOOD COMMUNITY SPACE
NEIGHBORHOOD 1 - STREETSCENE
63 Homes (51 market rate, 12 below market rate)
1,942 SF – 2,316 SF
4 Bedrooms and 2.5 or 3 Baths
9 Exterior Designs
2-Car Garage with 2-Car Driveway
NEIGHBORHOOD 1 – PLAN 1
NEIGHBORHOOD 1 – PLAN 2
NEIGHBORHOOD 1 – PLAN 3
VIEW OF NEIGHBORHOOD 2 &
NEIGHBORHOOD TOT LOT
NEIGHBORHOOD 2 - STREETSCENE
92 Homes (80 market rate, 12 below market rate)
2,158 SF – 2,725 SF
4 Bedrooms and 2.5 or 3 Baths
12 Exterior Designs
2-Car Garage with 2-Car Driveway
NEIGHBORHOOD 2 – PLAN 1
NEIGHBORHOOD 2 – PLAN 2
NEIGHBORHOOD 2 – PLAN 3
NEIGHBORHOOD 2 – PLAN 4
PROJECT SUSTAINABILITY
All-electric residential community including heating, water heating, and
appliances
Each home will include solar panels and energy efficient electric
appliances, windows, and insulation
The community will include drought tolerant and/or native landscaping,
water-conserving irrigation systems including climate-sensitive controllers
in common areas, and biological treatment of stormwater runoff
Each garage will have:
- (1) Level 2 Electric Vehicle (EV) Ready space
- (1) Level 1 EV Ready space
- Space for bicycle parking to allow an alternative mode of transit
TRANSPORTATION DEMAND MANAGEMENT (TDM)
PROGRAM & AMENITIES
Aims to reduce residential Vehicle Miles Traveled (VMT) to 12.4 miles per capita,
consistent with a 15% reduction in VMT
Develop a TDM Plan including programs such as:
• Voluntary Travel Behavior Change Program (Coordinator, surveys)
• Travel Behavioral Intervention (on-site annual event)
• Ride-Sharing (carpool matching) Programs (marketing/outreach)
• School Pool Programs (marketing/outreach)
Include an HOA Transportation Alternatives Marketing Program to reduce VMT by at
least 4%, including a Pre-Sale Marketing Program featuring:
• New Owner Trip Reduction Pledge (sales program)
• Pre-sales Trip Reduction Information
• New Owner TDM/Trip Reduction Welcome Packet
• TDM Plan – Purchase Contract/Escrow Disclosures
Provide bicycle parking onsite & bicycle fix-it station
AFFORDABLE HOUSING PLAN
24 SINGLE FAMILY HOMES | 12 PER NEIGHBORHOOD
1,940 SF – 2,150 SF | 4 BEDROOMS + 2.5 OR 3 BATHS
8 HOMES SOLD TO LOW-INCOME HOUSEHOLDS
< 80% OF SAN MATEO CO’S MEDIAN INCOME
16 HOMES SOLD TO MODERATE-INCOME HOUSEHOLDS
< 120% OF SAN MATEO CO.’S MEDIAN INCOME
DEED-RESTRICTED - 55 YEARS
HOMES DISPERSED THROUGHOUT THE COMMUNITY
LOCAL PREFERENCE FOR HOUSEHOLDS THAT LIVE OR WORK IN SAN BRUNO
QUESTIONS? THANK YOU!
PRELIMINARY CONSTRUCTION SCHEDULE
Description Start End Duration
Demolition Feb 2025 May 2025 Apprx. 4 months
Site Work June 2025 June 2026 Apprx. 13 months
Model Homes July 2025 Jan 2026 Apprx. 6 months
Production Homes Oct 2025 Dec 2028 Estimate
Cost Recovery Fee for Temporary
Fireworks Sales
CITY COUNCIL NICK PEGUEROS
MAY 28, 2024 CHIEF FINANCIAL OFFICER
OBJECTIVE
Consider adjustment to the cost recovery fee for
temporary fireworks sales.
2
BACKGROUND
City Council Resolutions 2008-67:
A non-refundable application fee, and
Reimbursement of costs incurred
• 2022 holiday - $66,342
• 2023 holiday - $99,153
2023 holiday cost recovery fee invoices issued – 12/21/23
Meetings with non-profit booth operators:
Review significant increase in costs, year-over-year
Lack of notice to operators of cost increases
AB1403 effective January 1, 2024
3
AB1403 – Effective January 1, 2024
Cost recovery capped at 7% of gross sales
Processing and issuing permits
Inspection of fireworks stands
Public education and awareness campaigns
Safe and sane fireworks enforcement
2023 holiday gross sales = $710,956
7% of gross sales = $49,767
City 2023 costs = $99,153
4
NEXT STEPS FOR 2024 HOLIDAY
No change to operations plans / costs
Cost recovery capped at 7%, consistent with AB1403
Written report on the 2024 holiday:
August – Costs incurred and estimated cost recovery
January – Mid-year budget amendment
5
ANNUAL PROCESS
Pre-holiday
Mid-year report on
past holiday and
upcoming holiday
(January)
Annual Review Post-holiday
Updated legislation; Finance issues cost
recovery invoices
Discussions with booth lower of 7% of gross
operators sales or costs incurred 6
RECOMMENDATION
Adopt a Resolution establishing a cap on the fireworks stand permit
cost recovery fee in the amount of seven percent (7%) of each
permittee’s gross fireworks sales.
2023 Cost Recovery = $49,767
2024 Cost Recovery = Unknown
Waive application fee for past years
7
QUESTIONS
8