Village President, Barb Dickmann, called the meeting to order at 7:30 p.m.
Village Clerk, Mary Kay Baumann, gave the Statement of Public Notice.
Members: Barb Dickmann-present, Dan Sauer-present, David Maglio-present (via phone), Mike Krocka-
absent, Michael Gielow-absent, Joe Caban-present, and Scott Fischer-present
Others Present: Dawn Wagner, Mary Kay Baumann, Chief Goetz, Lt. Rob Meyer, Ray deBruijn, Vicki Lee,
Officer R. Ramthun, Officer E. Ramthun, Laurie Miske, Officer Joe & Carol Holeva, and
Mark Jaeger-Ozaukee Press
PLEDGE OF ALLEGIANCE
CITIZEN COMMENTS AND QUESTIONS
None.
APPROVE MINUTES OF JANUARY 3, 2017 MEETING
Fischer/Caban made a motion to approve the January 3, 2017 minutes as presented. Motion carried.
COMMUNICATIONS
REPORT FROM THE VILLAGE PRESIDENT
Dickmann read and presented Cindy Douglas with a proclamation for Adult Crossing Guard Week.
Dickmann thanked Douglas for her service to the Village for the past 27 years.
REPORT FROM THE VILLAGE ADMINISTRATOR
Wagner thanked Douglas for her service.
PUBLIC HEARING - TO HEAR COMMENTS REGARDING THE VILLAGE OF SAUKVILLE’S INTENT TO EXERCISE
ITS POLICE POWER IN ACCORDANCE WITH §66.0703 WIS. STATS. AND CHAPTER 5 OF THE VILLAGE
CODE, TO LEVY SPECIAL ASSESSMENTS UPON PROPERTIES WITHIN THE FOLLOWING DESCRIBED
ASSESSMENT DISTRICTS FOR BENEFITS CONFERRED UPON THE PROPERTIES BY THE CONSTRUCTION OF
SANITARY SEWER LATERALS, STORM SEWERS AND STORM SEWER LATERALS, CURB AND GUTTER,
DRIVEWAY APPROACHES, SIDEWALKS AND RELATED IMPROVEMENTS: ALL PROPERTY ABUTTING BOTH
SIDES OF CHURCH STREET FROM TOWER STREET 1500 FEET EAST TO CTH O, AND ALL PROPERTY
ABUTTING BOTH SIDES OF CENTER STREET FROM RAILROAD STREET 550 FEET EAST TO SOUTH DRIES
STREET. (7:30 P.M.)
Sean Sullivan, Project Manager for Ruekert & Mielke, reminded everyone of the 30% and 60% Public
Information Meetings (PIM’s) that were held in 2016.
Sullivan stated that in this meeting, he will review the steps of the project to its completion. Sullivan
stated that he would review the timing of the project as well as the assessments that are being levied.
Sullivan stated that the goal is to remove any fears that residents may have regarding the project and to
help residents understand the value of this project.
Sullivan reviewed the scope of the project:
January 17, 2017
Sullivan reviewed his role in the project and role for this meeting.
Residents were given revised assessments with exhibits as they entered the meeting.
Sullivan stated that invitations to the 30% and 60% PIM’s and assessment roll hearing were sent out to Tax
Key number Addresses, same address as taxes are sent to.
Sullivan stated that his goal in this presentation is to get us all enthusiastic about the project, and answer
any project questions.
Sullivan stated that the 30% informational meeting this past March was a general overview of project. No
real details. The 60% informational meeting this past August gave much more defined design. This
included address specific homeowner concerns.
Sullivan reviewed the Scope of Project/Unique aspects.
This will include new curb and gutter and removal and replacement of failed curb and gutter, new
sidewalk and replacement sidewalk, replace driveway approaches, removal of trees within the Right of
Way (ROW), replace water main and replace water services, replace some storm sewer main and inlets,
provide storm laterals for all properties to the ROW, sanitary sewer lateral pipe bursting into basements
including new clean out, fixing road base and new asphaltic pavement.
Sullivan spoke regarding lead services - There may be a couple homes with lead services in the 2017 road
project area. The contractor will be re-connecting all water services to the new curb stop at the ROW.
The homeowner is responsible for replacing their lead service from the new curb stop to their house if
they choose. This could possibly be done with the on-site contractor of the project with the cost being
born 100% by the resident. The Village of Saukville performs all required testing as is required by the
DNR. The Consumer Confidence Report is available on the Village’s web-site.
Sullivan references the illegal storm water basement hookups and importance of getting those fixed
during the project.
Sullivan explained the temporary water service. He explained the reason for that method of construction
including speeding up construction and saving money.
Sullivan discussed traffic control and access to the church and school. He added that he had been in
discussions with the church to minimize inconvenience.
Sullivan stated that the infiltration cross walks, per new DNR requirements, are planned. Depending on
cost, they may not be included.
Preliminary Assessment creation:
Sullivan explained estimated quantities and bid prices - 2016 vs 2017
Sullivan reviewed an example assessment (there were large displays of fictitious properties that show all
improvements, Sullivan explained each one)
Sullivan stated that every effort will be made to keep costs down and be as efficient as possible.
Sullivan stated that two factors in keeping costs down is timing of the bidding (out so early in the year)
and Wage Rate elimination.
Sullivan informed the residents that the preliminary assessment that they received had storm sewer main
assessed. This project will NOT assess for storm sewer main.
Sullivan added that the homeowner will only be assessed ACTUAL and EXACT values.
Sullivan stated that the preliminary work that has been done by Village staff has added to the effort to
reduce costs. This included early basement access and providing information to contractors in advance.
Sullivan stated that this is above and beyond normal effort. This early work should result in lower bid
prices.
Sullivan stated that for individual assessments, they were conservative on both quantities and unit prices.
Sullivan used the Sanitary Sewer Lateral as an example.
January 17, 2017
Sullivan stated that the homeowner will not be assessed for replacement sidewalk if it was caused by
street tree roots, etc. Any trees that are removed will be replaced at a later date. The tree replacement
is not part of this project.
Sullivan reviewed the scheduling:
• Project is currently out to bid – in newspaper January 12th and 19th.
• Bids open on January 26th at 10:00 a.m. at Village Hall.
• Recommendation into the Village on January 27th.
• Project is awarded by the Village and a pre-construction meeting is scheduled.
At this pre-construction meeting, schedules are reviewed and specific aspects of the project are
reviewed by all parties involved. Construction should begin in March, but is weather dependent.
• September 1st is Substantial Completion (All work but maybe landscaping and other minor issues)
• October 13th Final completion (All work is done)
Sullivan stated that there will be an On-Site Construction Review Manager - Ask him or her any questions
any time. The eyes and ears of the Village will result in a quality product.
Sullivan stated the sidewalks will be constructed to Village standards. He addressed safety concerns.
Sullivan stated that we have no idea what will happen to the school property.
Sullivan stressed the added curb appeal with the completed project. Residents will basically have all new
infrastructure.
Sullivan asked that the 7 addresses with illegal hook-up meet with him for 5 minutes following the
meeting:
219 Church
227 Center
222 Center
231 Church
247 Church
234 Church
145 Church
Sullivan opened the meeting up for questions from the Board and residents.
Jerome Rychtik, 260 Church St., asked about the water pocketing on the corner by his property. Sullivan
stated that the infiltration crosswalks should eliminate runoff buildup.
Gordon Waddington, St. John XXIII Representative, asked if there was a way to contour the S curve to
alleviate run-off? Sullivan stated again that the infiltration crosswalks should alleviate the majority of
that.
Jerry Jordan, 222 Center St. asked about the Special Assessment payments.
Wagner read the terms of the Special Assessment payments. She read the plan for installment payments
and added that this repayment plan is the same that was used for the Linden St. and Colonial Pkwy
Project in 2014.
At this point, the interest rate would be 3.75% with the first payment due by November 1, 2018.
Dickmann stated that the interest rate was discussed at Finance Committee. The current prime rate is
3.75%. Dickmann asked Sauer to explain his thoughts on the rate.
Sauer stated that residents are assessed for 20% of the project. He would like to see the rate dropped to
2.75% to make it less of a burden for the residents.
January 17, 2017
Ben Boesch, 202 Center St., – asked, what if it isn’t paid back? Wagner stated that it would be put on the
property tax bill and eventually held as a lien against the property.
Tia Boesch, 202 Center St., asked about the storm lateral. Sullivan stated that it would be open cut and
could break up some curb and gutter.
Jean DeGrave, 234 Church St., asked about the mailboxes and telephone poles. Sullivan stated that the
mailboxes would be left in place until the possibility of removal. At that time they would probably install
a temporary group mailbox on Railroad St. WE Energies would have to move any poles if warranted.
Sullivan stated that the trees on Church are not being touched.
Rychtik asked if new trees would be planted between the sidewalk and curb. deBruijn stated yes, on both
streets.
Duwayne Flom, 241 Center St., asked about the sump pump connection. Sullivan stated that the resident
has one (1) year to connect their sump pump.
Flom requested an updated estimate after bids are in.
Sullivan stated that updates can be sent to all affected property owners.
deBruijn, referenced the carriage walks in the terraces. The carriage walks are the concrete extension
between the curb and sidewalk. Sullivan stated that these are slated for removal.
T. Boesch asked why the homeowners are being assessed for the storm laterals that are on Village
property.
Wagner addressed this with the Village Attorney. Wagner referred to the memo prepared by the Village
Attorney (attached).
T. Boesch asked for a copy of the case study to be e-mailed to her and would also like, in writing, a copy
of the benefit to the homeowner.
Flom, noting the reference to other projects, asked if all projects have been applied consistently.
Trustee Caban stated that when the project was completed on his street, they did not have the luxury of
long term repayment of the Special Assessments.
Flom asked if the landscape will be replaced with seed or sod. Sullivan stated that it would be seed. He
added it is a much better product overall.
Flom asked about the plan for tree replacement. deBruijn stated that the trees would be replaced and
they would plant trees specified for smaller areas where warranted.
Rychtik asked how much this would increase property values. Sullivan stated he could not answer
definitively.
DeGrave & Loretta Johnson both asked why we need sidewalks after all these years. Sullivan stated that
it is Village policy on all improvement projects.
Hearing no further questions, President Dickmann requested a motion to close the Public Hearing.
CLOSE PUBLIC HEARING
Sauer/Fischer made a motion to close the Public Hearing. Roll call vote was taken with all in favor.
Motion carried at 8:31 p.m.
ORDINANCES – RESOLUTIONS – PETITIONS
January 17, 2017
Res. #1254 – Final Resolution Authorizing Public Improvements and Levying Special Assessments
Against Benefitted Properties.
Caban/Fischer made a motion to waive the reading of Res. #1254 – Final Resolution Authorizing Public
Improvements and Levying Special Assessments against Benefitted Properties. Motion carried.
Sauer/Caban made a motion to approve Res. #1254 – Final Resolution Authorizing Public Improvements
and Levying Special Assessments against Benefitted Properties with an annual interest rate of 2.75%
effective November 1, 2018. Roll call vote was taken with all in favor. Motion carried.
REPORTS OF VILLAGE BOARD COMMITTEES
Utility Committee
No report.
Public Works Committee
No report.
Public Safety Committee
Sauer reported on the meeting of January 12, 2017.
Sauer stated that the Agreement for Professional Services with EMS Medical Billing Services was reviewed
and recommended to the Finance Committee for approval.
Finance Committee
Dickmann reported on the meeting of January 17, 2017.
Claims for December 2016 in the amount of $213,143.51 were reviewed and approved.
The Investment Report was reviewed.
Res. #1254 was recommended to the Village Board for Public Hearing and approval.
A recommendation was made to the Village Board to approve the Agreement for Professional Services –
Emergency Medical Service Use Fee Billing Services – EMS Medical Billing Associates, LLC.
Sauer/Fischer made a motion to approve the Agreement for Professional Services – Emergency Medical
Service Use Fee Billing Services – EMS Medical Billing Associates, LLC for a 3 year term. Motion carried.
Other Matters:
The Saukville Chamber State of the Community Address will be held Wednesday, February 1st at the
American Legion. Please inform Mary Kay if you are interested in attending.
February 7th will include a Plan Commission Meeting, CDA, Finance and Village Board.
The Mid-Moraine Dinner will be held Wednesday, January 25th. Please inform Mary Kay if you plan to
attend.
REPORTS OF SPECIAL COMMITTEES
Plan Commission
Dickmann reported on the meeting of January 5, 2017.
A request for exterior upgrades to the property located at 261 S. Riverside Drive were reviewed and
approved.
January 17, 2017
A request for exterior color and signage plan changes at the Wal-Mart at 835 E. Green Bay Ave. were
reviewed and approved.
Community Development Authority/Industrial Review Committee
No report.
Library Board
No report.
Mid-Moraine Municipal Association
No report.
OPERATOR’S LICENSE APPROVALS
None.
LIQUOR LICENSE APPROVALS
None.
CITIZEN MATTERS AS NOTICED
None.
ADJOURNMENT
Caban/Krocka made a motion to adjourn. Motion carried at 8:37 p.m.
Mary K. Baumann
Village Clerk
F:\USERS\dclerk\Minutes\Village Board - 2017\Village Board -January 17, 2017.docx
Agenda
THE VILLAGE OF
639 E. Green Bay Avenue • Saukville, WI 53080 • 262-284-9423 • FAX 262-284-9527 • www.village.saukville.wi.us
January 13, 2017
NOTICE
Please take notice that a meeting of the Saukville Village Board will be held on TUESDAY,
JANUARY 17, 2017 at 7:30 p.m. at the SAUKVILLE POLICE DEPARTMENT, 649 E. Green Bay
Ave., Saukville, Wisconsin.
AGENDA
1. Call to Order and Prayer
2. Pledge of Allegiance
3. Statement of Public Notice
4. Roll Call
5. Citizen Comments and Questions
6. Approval of Minutes of January 3, 2017 Meeting
7. Communications
A. Village President Comments
Proclamation – Adult Crossing Guard Week
B. Village Administrator Comments
8. PUBLIC HEARING – to hear comments regarding the Village of Saukville’s intent to exercise its police
power in accordance with §66.0703 Wis. Stats. And chapter 5 of the Village Code, to levy special
assessments upon properties within the following described assessment districts for benefits conferred
upon the properties by the construction of sanitary sewer laterals, storm sewers and storm sewer
laterals, curb and gutter, driveway approaches, sidewalks and related improvements: all property
abutting both sides of Church Street from Tower Street 1500 feet east to CTH O, and all property
abutting both sides of Center Street from Railroad Street 550 feet east to South Dries Street. (7:30
p.m.)
9. Close Public Hearing
10. Ordinances – Resolutions – Petitions
A. Res. #1254 – Final Resolution Authorizing Public Improvements and Levying Special Assessments
Against Benefitted Properties
11. Reports of Village Board Committees
A. Utility Committee
B. Public Works Committee
C. Public Safety Committee
a. Report on meeting of January 12, 2017
D. Finance Committee
a. Report on meeting of January 17, 2017
b. Agreement for Professional Services – Emergency Medical Service Use Fee Billing Services – EMS
Medical Billing Associates, LLC
12. Reports of Special Committees
A. Plan Commission
a. Report on meeting of January 5, 2017
B. Community Development Authority/Industrial Review Committee
C. Library Board
D. Mid-Moraine Municipal Association
13. Operator License Approval
14. Liquor License Approval
15. Citizen Matters as Noticed
16. Adjourn
Dawn Wagner
Village Administrator
Persons with disabilities who may require assistance to attend the meeting should
contact Mary Kay Baumann, Clerk (262)284-9423
Get email alerts for Saukville
A daily email when new agendas and minutes are posted.