Public Works, Sewer and Water
Regular MeetingVerona, WI · March 10, 2025
Minutes
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: MONDAY March 10, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order Meeting called to order by B. Tucker Long at 5:34 pm.
2. Roll Call: Beth Tucker Long, Brandon Braithwaite, Spencer Harrison
Also present: Carla Fisher (AECOM), Bryan Manning – Public Works Director,
Michael Trotter - Assistant Public Works Director
3. Public Comment. None
4. Approval of the Minutes: February 24, 2025.
Moved by Spencer Harrison and seconded by Brandon Braithwaite to approve the minutes
Motion Carried 3-0.
5. Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers pay
request #8 Staff and contracted inspectors have verified the quantities and recommend approval
of the pay request. Moved by Brandon Braithwaite and seconded by Spencer Harrison to
approve pay request #8 in the amount of $248,326.97
6. Discussion and Possible Action: Range Trail and Highway CTH M Streetlight Installation
No Action Taken
7. Staff Report:
8. Adjourn Moved by Spencer Harrison and seconded by Brandon Braithwaite to adjourn at 5:49pm
Beth Tucker Long - Chairperson
POSTED: March 6, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees w ill not take formal action at this meeting.
Agenda
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: MONDAY March 10, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order
2. Roll Call
3. Public Comment.
4. Approval of the Minutes: February 24, 2025.
5. Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers pay
request #8
6. Discussion and Possible Action: Range Trail and Highway CTH M Streetlight Installation
7. Staff Report:
8. Adjourn
Beth Tucker Long - Chairperson
POSTED: March 6, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: MONDAY, February 24, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order Meeting called to order by B. Tucker Long at 5:34 pm.
2. Roll Call: Beth Tucker Long, Brandon Braithwaite, Spencer Harrison
Also present: Carla Fisher (AECOM), Bryan Manning – Public Works Director,
Michael Trotter - Assistant Public Works Director
3. Public Comment. None
4. Approval of the Minutes: February 10, 2025.
Moved by Spencer Harrison and Brandon Braithwaite seconded by to approve the minutes
Motion Carried 3-0.
5. Discussion and Possible Action: Project #2022-109 North Booster Station-Rohde Brothers
change order request #1- Staff explained additional cost due to request from city to install a new
flow meter and relocate an existing gas line. Moved by Brandon Braithwaite and seconded by
Spencer Harrison to approve Change order #1 Project 2022-109 in the amount of $3503.00
6. Discussion and Possible Action: Project #2022-110 Well 6 WQ Study - Well #6 Reconstruction
and Liner Installation - Water Well Solution -Staff explained that this is the next step in rehabbing
the well and moving the project forward. Moved by Beth Tucker Long and seconded by Spencer
Harrison to recommend approval of the contract for Well #6 reconstruction and Liner Installation-
Water Well Solutions in the amount not to exceed $378,500.
7. Discussion and Possible Action: Range Trail and Highway CTH M Streetlight Installation- No
Action Taken
8. Staff Report:
9. Adjourn Moved by Beth Tucker Long and seconded by Brandon Braithwaite to adjourn. (6:09 pm)
Motion Carried 3-0.
Beth Tucker Long - Chairperson
POSTED: February 20, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
Meeting Date: March 10, 2025
PW/S&W Committee Memo
Public Works/Sewer & Water Committee
Listed below is an explanation of the items on the Public Works/Sewer & Water Committee
agenda.
Item (5) Project #2022-109 North Booster Station-Rohde Brothers Pay Request #8
Staff and contracted inspectors have verified the quantities and recommend approval of the pay
request.
Recommended Motion:
Recommend approval of pay request #8 for Project #2022-109 in the amount of $248,326.97
Item (6) Discussion and Possible Action Range Trail and CTH M Streetlight Installation
Discuss options for lighting crosswalk on CTH M at Range Trail
Recommended Motion:
Recommend research for options including cost for improving lighting of the intersection and
crosswalk located at Range Trail and CTH M.
Page 1 / 1
Owner: City of Verona, Wisconsin
Project: North Pump Station and Electrical System Updates
Project No.: 2022-109.1 Contract: 2022-109.1
Contractor: Rohde Brothers, Inc.
W5745 Woodchuck Ln
Plymouth, WI 53073
Estimate Prepared By: Brian Marquardt
Name
Project Manager
Title
2/20/2025
Date
SUMMARY
ORIGINAL CONTRACT AMOUNT 581,100.00
APPROVED CONTRACT REVISION AS OF 3,503.00
ADJUSTED CONTRACT AMOUNT 584,603.00
REQUEST THIS ESTIMATE
TOTAL COMPLETED TO DATE 465,601.00
PREVIOUS REQUESTS FOR PAYMENT 213,407.91
TOTAL EARNED THIS REQUEST 252,193.09
RETAINAGE 5% 3,866.12
CURRENT PAYMENT DUE 248,326.97
AECOM
Name
February 25th, 2025
Date
City of Verona
Name
Date
Owner's approval
Date
REQUEST FOR PAYMENT
PROJECT NAME: Verona North Pump Station DATE: 2/20/2025
ADDRESS: 7049 Cross Country Road, Verona, WI 53593
CONTRACT FOR: HVAC, Plumbing, Mechanical
Project 24025 Contract # 2022-109.1 Invoice #
REQUEST NUMBER: 8 PERIOD FROM: 2/1/2025 TO: 2/28/2025
ORIGINAL CONTRACT AMOUNT 581,100.00
APPROVED CONTRACT REVISION AS OF 3,503.00
ADJUSTED CONTRACT AMOUNT 584,603.00
TOTAL COMPLETED TO DATE 465,601.00
PREVIOUS REQUESTS FOR PAYMENT 213,407.91
TOTAL EARNED THIS REQUEST 252,193.09
RETAINAGE 5% 3,866.12
CURRENT PAYMENT DUE 248,326.97
SUBCONTRACTOR Rohde Brothers, Inc.
SIGNED: Brin Marquardt
TITLE: Project Manager
W5745 WOODCHUCK LANE • P.O. BOX 409 • PLYMOUTH, WI 53073-0409
PHONE: (920) 893-5905 • FAX: (920) 893-5908 • EMAIL: rohde@rohdebros.com
PROJECT: Verona North Pump Station
SUBCONTRACTOR: ROHDE BROTHERS INC.
APPLICATION DATE: 12/20/2024
PAYMENT APPLICATION NUMBER: 6
SUBCONTRACTOR SCHEDULE OF VALUES
TOTAL COMPLETED &
WORK COMPLETED
STORED TO DATE
ITEM SCHEDULED PREVIOUS MATL RETAINAGE BALANCE
DESCRIPTION OF WORK
NO. VALUE APPLICATION THIS STORED 5% TO FINISH
(B) %
(A) (C) (D) APPLICATION THIS (I) (J)
(G) (H)
(E) Request
(F)
1 Job Supervision $20,000.00 12,500.00 5,500.00 18,000.00 90.00% 900.00 2,000.00
2 Submittals $10,000.00 9,500.00 500.00 10,000.00 100.00% 500.00 0.00
3 O&M's $5,000.00 0.00 2,000.00 2,000.00 40.00% 100.00 3,000.00
4 Project Closeouts $5,000.00 0.00 2,000.00 2,000.00 40.00% 100.00 3,000.00
5 Permits & Bonds $5,200.00 5,200.00 5,200.00 100.00% 260.00 0.00
6 Mobilization $1,000.00 0.00 1,000.00 1,000.00 100.00% 50.00 0.00
7 Demobilization $1,000.00 0.00 0.00 0.00% 0.00 1,000.00
Procurement
8 Process Pipe, Fittings, & Valves $67,000.00 52,207.91 14,792.09 67,000.00 100.00% 3,350.00 0.00
9 Hangers $5,000.00 2,500.00 2,500.00 5,000.00 100.00% 250.00 0.00
10 LW Allen/Altronex
11 43 21 00 Large Booster Pumps $75,000.00 75,000.00 75,000.00 100.00% 3,750.00 0.00
12 43 21 00 Small Jokcey Pump $25,000.00 25,000.00 25,000.00 100.00% 1,250.00 0.00
14 40 61 14 Instrumentation & Controls $9,766.00 9,766.00 9,766.00 100.00% 1,250.00 0.00
15 40 71 13 Inline Magnetic Flow Meter $10,000.00 10,000.00 10,000.00 100.00% 500.00 0.00
17 Motor Control Center $147,595.00 147,595.00 147,595.00 100.00% 1,280.07 0.00
18 North Booster Station Well-4 RTU Modifications $44,719.00 0.00 0.00% 0.00 44,719.00
Labor Installation
19 Measure & Planning $15,000.00 14,000.00 1,000.00 15,000.00 ######## 700.00 0.00
20 Deliveries $3,000.00 0.00 1,000.00 1,000.00 33.33% 0.00 2,000.00
21 Piping Labor $15,000.00 7,500.00 4,000.00 11,500.00 76.67% 375.00 3,500.00
22 Equipment Setting $15,000.00 0.00 0.00 0.00% 0.00 15,000.00
23 Demolition $5,000.00 0.00 0.00 0.00% 0.00 5,000.00
24 Startup/Commissioning $3,000.00 0.00 0.00 0.00% 0.00 3,000.00
0.00
Page 2 of 3
P:\2024\24025 Verona North Pump Station\Correspondence\Billing\Verona North Pump Station Pay App Master[SOV] 2/20/2025 10:55 AM
Subcontractors 0.00
25 Controls/Power Wiring (Pieper Electric) $68,283.00 0.00 51,500.00 51,500.00 75.42% 0.00 16,783.00
26 Painting (Omni Glass & Paint) $25,537.00 0.00 5,537.00 5,537.00 21.68% 0.00 20,000.00
0.00
Change Orders 0.00
27 CO 1 - Moving piping $3,503.00 0.00 3,503.00 3,503.00 100.00% 0.00 0.00
Totals $584,603.00 213,407.91 252,193.09 0.00 465,601.00 79.64% 14,615.07 119,002.00
Page 3 of 3
P:\2024\24025 Verona North Pump Station\Correspondence\Billing\Verona North Pump Station Pay App Master[SOV] 2/20/2025 10:55 AM
Get email alerts for Verona