Public Works, Sewer and Water
Regular MeetingVerona, WI · September 22, 2025
Minutes
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday, September 22, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order Meeting called to order by Beth Tucker Long at 5:30 pm
2. Roll Call Beth Tucker Long, Chris Weiss, Melissa Kellor, also present Bryan Manning-Public Works Director,
Michael Trotter-Assistant Public Works Director, Carla Fischer-City Engineer AECOM
3. Public Comment None
4. Approval of the Minutes: September 8, 2025. Moved by Melissa Kellor and seconded by Chris Weiss to
approve the minutes. Motion passed 3-0
5. Discussion and Possible Action: Inspection Service Agreement JT Engineering,
Dreger Development Apex 2. Moved by Beth Tucker Long and seconded by Chris Weiss to
recommend approval of the Inspection Services Agreement JT Engineering Dreger Development
for a sum not to exceed $89,720.00 Motion passed 3-0
6. Discussion and Possible Action: Inspection Service Agreement KL Engineering, Avalon
Ridge Development. Moved by Chris Weiss and Seconded by Mellisa Kellor to recommend approval of
the Inspection Services Agreement KL Engineering, Avalon Ridge Development for a sum not to exceed
$113,337.60 Motion passed 3-0
7. Discussion and Possible Action Change order #1 US 18 151 Aux Lane budget for Design
Services AE COM Project number 60718474 Reduction Epic Moved by Beth Tucker Long and
seconded by Mellisa Kellor to approve Change order #1 US 18 151 Aux Lane budget for Design Services AE
COM Project number 60718474 Epic reducing contract time and materials with a not to exceed amount
of $850,000.00 Therefore, the total authorized compensation, inclusive of this change order is
$2,070,000.00 Motion passed 3-0
8. Discussion and Possible Action Change Order #1 Project West Rd/Hyper Drive budget for
design Services AE COM Project number 60731271 Increase Epic Moved by Mellisa Kellor and
Seconded by Beth Tucker Long to approve Change order #1 Project West Rd/Hyper Drive budget for Design
Services AE COM Project number 60731271Epic Increasing contract time and materials with a not to exceed
amount of $850,000.00 Therefore, the total authorized compensation including the change order is
$3,730,100.00 Motion passed 3-0
9. Discussion and Possible Action: Project #2022-109 North Booster Station Rohde
Brothers Change Order request #3 Moved by Chris Weiss and seconded by Mellisa Kellor to
approve Project 2022-109 North Booster Station Rohde Brothers change order request #3 for a sum
not to exceed $844.20 to be paid in pay request #12 Motion passed 3-0
10. Discussion and Possible Action: Project #2022-109 North Booster Station Rohde
Brothers pay request #12 Moved by Mellisa Kellor and seconded by Beth Tucker Long to approve
Project 2022-109 North Booster Station Rohde Brothers final pay request #12 for a sum not to exceed
$19,459.08 Motion passed 3-0
11. Staff Report:
12. Adjourn Move by Chris Weiss and seconded by Mellisa Kellor to Adjourn Motion passed 3-0
Beth Tucker Long -Chairperson
September 18, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
Agenda
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday, September 22, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order
2. Roll Call
3. Public Comment
4. Approval of the Minutes: September 8, 2025.
5. Discussion and Possible Action: Inspection Service Agreement JT Engineering, Dreger
Development Apex 2
6. Discussion and Possible Action: Inspection Service Agreement KL Engineering, Avalon Ridge
Development
7. Discussion and Possible Action Change order #1 US 18 151 Aux Lane budget for Design Services
AE COM Project number 60718474 Reduction Epic
8. Discussion and Possible Action Change Order #1 Project West Rd/Hyper Drive budget for design
Services AE COM Project number 60731271 Increase Epic
9. Discussion and Possible Action: Project #2022-109 North Booster Station Rohde Brothers
Change Order request #3
10. Discussion and Possible Action: Project #2022-109 North Booster Station Rohde Brothers pay
request #12
11. Staff Report:
12. Adjourn
Beth Tucker Long - Chairperson
POSTED: September 18, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
City of Verona
111 Lincoln Street
Verona, WI 53593
(608) 845-6495
veronawi.gov
PUBLIC WORKS, SEWER & WATER COMMITTEE-
DATE: Monday, September 8, 2025 TIME: 5:30 PM
LOCATION: VERONA CITY HALL
ROOM D122
111 LINCOLN STREET
VERONA, WI 53593
1. Call to Order Meeting called to order by Beth Tucker Long at 5:30 pm
2. Roll Call Beth Tucker Long, Chris Weiss, Melissa Kellor, also present Bryan Manning-Public Works
Director, Michael Trotter-Assistant Public Works Director, Carla Fischer-City Engineer AECOM
3. Public Comment None
4. Approval of the Minutes: August 25, 2025. Moved by Chris Weiss and seconded by Melissa Kellor to
approve the minutes. Motion passed 3-0
5. Discussion and Possible Action: Project 2023-112 Legion Street-Westlawn Project, Parisi
Construction Inc. Pay request #2 Move by Beth Tucker Long and seconded by Chris Weiss to approve
Pay request # 2 Project #2023-112 Legion Street-Westlawn Project, Parisi Construction Inc for a sum
not to exceed $206,402.28 Motion passed 3-0
6. Discussion and Possible Action: Recommend awarding Construction Inspection Services
contract for SSM Health Clinic. Move by Chris Weiss and seconded by Melissa Kellor to recommend
awarding a contract for Construction Inspection Services for SSM Health Clinic, subject to final review
and approval by the Director of Public Works and City Attorney. Motion passed 3-0
7. Discussion and Possible Action: Recommend awarding contract for Project 2025-101
Pavement rehabilitation and sidewalk improvements -Edward Street Moved by Beth Tucker Long
and seconded by Melissa Kellor to award contract for Project #2025-101Pavement rehabilitation and
sidewalk improvements-Edward Street to Wolf Paving Inc for a sum not to exceed $443,100.00
Motion passed 3-0
8. Staff Report:
9. Adjourn Move by Chris Weiss and seconded by Melissa Kellor to adjourn at 6:27 pm
Beth Tucker Long - Chairperson
POSTED: September 4, 2025
POSTED: Verona City Hall
Verona Public Library
Miller’s Market
All agendas are posted on the City website at: veronawi.gov
WRITTEN COMMENTS: You can send comments to the Public Works, Sewer & Water Committee on any matter, either on or not on the
agenda, by emailing bmanning@veronawi.gov or in writing to Public Works, Sewer & Water Committee, 410 Investment Court, Verona, WI,
53593.
Notice: If you need an interpreter, materials in alternative formats, or other accommodation to access the meeting, please contact the City
Clerk at (608) 845-6495 at least 48-hours preceding the meeting. Every reasonable effort will be made to accommodate your request.
Notice is hereby given that a majority of the City Council may be present at the meeting of the Public Works, Sewer & Water Committee to
gather information about a subject over which they have decision-making responsibility. The City Council and any other standing
committees will not take formal action at this meeting.
Meeting Date: September 22, 2025
PW/S&W Committee Memo
Public Works/Sewer & Water Committee
Listed below is an explanation of the items on the Public Works/Sewer & Water Committee
agenda.
Item (5) Discussion and Possible Action Inspection Services Agreement JT Engineering,
Dreger Development
Recommended Motion: Move to recommend approval of the Inspection Services
Agreement JT Engineering, Dreger Development for a sum not to exceed $89,720.00
Item (6) Discussion and Possible Action Inspection Services Agreement KL Engineering,
Avalon Ridge Development
Recommended Motion: Move to recommend approval of the Inspection Services
Agreement KL Engineering, Avalon Ridge Development for a sum not to exceed
$113,337.60
Item (7) Discussion and Possible Action: Change order #1 US 18 151 Auxiliary Lane budget
for Design Services AE COM Project number 60718474 Reduction Epic
Recommended Motion: Move to approve Change order #1 US 18 151 Auxiliary Lane budget
for Design Services AE COM Project number 60718474 Epic reducing contract time and
materials with a not to exceed amount of $850,000.00 Therefore, the total authorized
compensation, inclusive of this change order is $2,070,000.00
Item (8) Discussion and Possible Action: Change order #1 Project West Rd/Hyper Drive
budget for Design Services AE COM Project number 60731271 Increase Epic
Recommended Motion: Move to approve Change order #1 Project West Rd/Hyper Drive
budget for Design Services AE COM Project number 60731271Epic Increasing contract
time and materials with a not to exceed amount of $850,000.00
Therefore, the total authorized compensation including the change order is $3,730,100.00
Item (9) Discussion and Possible Action: Project #2022-109 North Booster Station Rohde
Brothers Change Order Request #3
Recommended Motion: Move to approve Project 2022-109 North Booster Station Rohde
Brother change order request #3 for a sum not to exceed $844.20 to be paid in pay request
#12
Page 1 / 2
Meeting Date: September 22, 2025
PW/S&W Committee Memo
Item (10) Discussion and Possible Action: Project #2022-109 North Booster Station Rohde
Brothers final pay request #12
Recommended Motion: Move to Approve Project #2022-109 North Booster Station Rohde
Brothers final pay request #12 for a sum not to exceed $19,459.08
Staff Report
Page 2 / 2
CONTRACT AGREEMENT
BETWEEN
JT ENGINEERING, INC.
AND
THE CITY OF VERONA
This Contract Agreement is made and entered into this 15th day of September 2025 by and between THE CITY OF
VERONA, hereinafter referred to as the CITY, and JT Engineering, Inc. 281 W. Netherwood Road, Suite 1, Oregon, WI
53575, hereinafter referred to as the CONSULTANT.
The CONSULTANT acknowledges by endorsement of this Contract Agreement that:
(a) CONSULTANT has the expertise and has a thorough knowledge of the professional services required to complete the
proposed work and is qualified to render such professional services
(b) CONSULTANT shall comply with all applicable laws, regulations, and orders in the performance of the work
(c) the work shall be performed in a manner consistent with that level of care, quality and skill ordinarily exercised by others
performing similar work under similar circumstances.
The parties agree as follows:
CONSULTANT shall furnish Construction Inspection Services to the CITY for the Project as described below.
CONSULTANT shall furnish the Basic Services as outlined in the attached scope of services if contract is executed by
September 22nd, 2025 and is expected to be completed by December 31st 2025, unless mutually agreed by CONSULTANT
and CITY to extend work beyond this date.
For all Basic Services, the CITY agrees to compensate CONSULTANT as follows:
Specific hourly rates, inclusive of fees for equipment needed to complete the work and mileage to/from work site, to be used
for hours in which the CONSULTANT’s employees are directly engaged in performing the work or services required by this
contract:
Employee Classification Hourly Rate(1)
Project Engineer $133.00
Project Engineer-Mid $149.00
Project Engineer-Senior $164.00
Project Manager $170.00
Project Manager-Senior $205.00
Project Administrator $210.00
Accountant $150.00
(1) Rates are good until October 1, 2026, and shall be updated annually on October 1 thereafter.
Compensation for all services provided by the CONSULTANT under the terms of this contract shall not exceed $89,720.00
based on the estimated working schedule attached.
Section I – BASIC SERVICES
1.1 Basic Services
The Basic Services to be performed under this Contract include construction inspection services as identified in the attached
scope of services commentary.
Section II – RESPONSIBILITIES
2.1 CITY’s Responsibilities
2.1.1 Assist and cooperate with the CONSULTANT in completing the work in a timely and effective manner.
JT ENGINEERING, INC -1-
2.1.2 Make available to the CONSULTANT drawings, specifications and data which the CONSULTANT considers
pertinent to the CONSULTANT’s responsibilities hereunder, all of which the CONSULTANT may rely upon in
performing services hereunder except as may be specifically provided otherwise in writing.
2.1.3 Give prompt written notice to the CONSULTANT whenever the CITY observes or otherwise becomes aware of
any development that affects the scope, timing, or performance of services of the CONSULTANT.
Section III – TIME SCHEDULE
3.1 Authorization
Unless otherwise directed by the CITY, the CONSULTANT shall commence the performance of the Basic Services upon
execution of this Contract by both parties which shall constitute Authorization to Proceed.
3.2 Expeditious Performance
The CONSULTANT recognizes that the services under this Contract are to be performed as expeditiously as practical after
Authorization to Proceed. Every reasonable effort will be made to substantially complete the Basic Services within the
period described above.
Section IV – INVOICES AND PAYMENT
4.1 Invoices
Invoices shall be submitted once a month or upon completion of services, whichever occurs earlier, for services provided
under Section 1.
4.2 Payment
4.2.1 The CITY shall pay the CONSULTANT based on the monthly invoices, with total payment not to exceed the total
contract amount.
4.2.2 It is expressly understood and agreed by both parties that the CONSULTANT will be paid by the CITY within 30
days after receipt of the invoice provided by the CONSULTANT. The CITY agrees to process the
CONSULTANTS invoices promptly.
Section V – CHANGES
5.1 Written Authorization
THE CITY or CONSULTANT may, at any time, by written order, make changes in the services or work to be performed
within the general scope of this Subcontract.
5.2 Equitable Adjustment
If such changes cause an increase or decrease in the CONSULTANTS cost of, or time required for, performance of any
services under this Contract, an equitable adjustment shall be made, and this Contract shall be modified in writing
accordingly.
Section VI – DISPUTES
6.1 Resolution Procedure
Except as this Contract otherwise provides, in all claims, counter-claims, disputes, and other matters in question (Dispute)
between the CITY and CONSULTANT arising out of or relating to this Contract or the breach of it, the CITY and
CONSULTANT will negotiate a resolution of the Dispute at a reasonable time and location set by the CITY and
CONSULTANT. Should negotiation be unsuccessful, mediation of the Dispute by a third party shall follow. Mediation shall
be conducted in Dane County, WI, unless the CITY and CONSULTANT agree to another location. CONSULTANT and the
CITY agree that those disputes not settled by mediation will be decided by binding arbitration, unless the CITY or
CONSULTANT elect to have said Dispute resolved in a court of competent jurisdiction.
6.1.1 Negotiation Following written notice of a Dispute, two (2) face-to-face meetings (or less if the Dispute is resolved)
shall be held.
JT ENGINEERING, INC -2-
6.1.2 Mediation If negotiation is unsuccessful, a mutually acceptable third party (Facilitator) having expertise in the
subject of the dispute shall be engaged to mediate the Dispute. Should the CITY and CONSULTANT be unable to
reach agreement on a Facilitator, either party may request a Circuit Judge Dane Co., WI to appoint said Facilitator.
The fee and expenses of the Facilitator shall be shared equally by the parties to the Dispute. The parties may present
evidence and arguments to the Facilitator. Unless the Facilitator and the parties agree otherwise, one (1) face-to-face
meeting shall be held within the sixty (60) day period beginning on the date of the Facilitator’s engagement.
Following the meeting, the Facilitator shall report to the parties whether he believes the Dispute is resolvable
through mediation. At that point the parties shall elect (a) to continue mediation, (b) replace the Facilitator and
continue mediation, or (c) end mediation. If the mediation is ended or otherwise unsuccessful in the resolution of
said Dispute, the Dispute shall be resolved by binding arbitration upon the request of either party or in the
alternative, by judicial adjudication.
6.1.3 Arbitration If the dispute is arbitrated, (a) the arbitration shall be decided in accordance with the current
construction Industry Arbitration Rules of the American Arbitration Association; (b) the demand for arbitration may
not be made more than one (1) year after the date on which the claim in dispute arose; and (c) the arbitration
proceeding may not include, by consolidation or otherwise, any third person. Any decision rendered by the
arbitrator(s) shall be final. Judgment may be entered upon the decision in any court having jurisdiction. The decision
shall not be subject to modification or appeal except to the extent permitted by Sections 10 and 11 of the Federal
Arbitration Act (9 U.S.C. 10, 11).
Section VII – SUSPENSION OF WORK
7.1 Convenience of the CITY
The CITY may order CONSULTANT to suspend, delay, or interrupt all or any part of the CONSULTANTS services for
such period of time as the CITY may determine to be appropriate for the convenience of the CITY.
7.2 Adjustment in Schedule
If the performance of all or any part of the CONSULTANTS services is, for an unreasonable period of time, suspended,
delayed, or interrupted by an act of the CITY, an appropriate extension of time shall be made for any such delay in the
performance of this Contract necessarily caused by such unreasonable suspension, delay, or interruption, and the Contract
modified in writing accordingly.
Section VIII – TERMINATION OF CONTRACT
8.1 Written Notice
It is expressly understood and agreed that the CITY may terminate this Contract at any time by giving the CONSULTANT
10 days written notice in writing either personally at one of the offices of the CONSULTANT or sent by registered mail,
return receipt requested, to the principal office of the CONSULTANT. The CONSULTANT may terminate this Contract
upon 30 days written notice in the event of nonpayment by the CITY of CONSULTANTS’ invoices rendered for a period of
60 days or in the event the CITY otherwise substantially fails to fulfill its obligations under this Contract.
8.2 Adjustment for Services Performed
In the event that this Contract is terminated by either the CITY or the CONSULTANT, the CONSULTANT shall be
compensated for all services performed to the date of termination including reimbursable expenses then due.
Section IX – INSURANCE
9.1 Coverage
Prior to commencing work, the CONSULTANT shall obtain and maintain in effect for the duration of this Contract at its own
expense the insurance with insurance companies licensed in the State where the project is located.
9.2 Minimum Coverage
The minimum required coverage is the following:
JT ENGINEERING, INC -3-
9.2.1 Worker’s Compensation and Employer’s Liability Worker’s Compensation and Employer’s Liability in
compliance with the statutory requirements of the State of Wisconsin.
9.2.2 General Liability Commercial general liability insurance covering operations, completed operations, contractual
agreements, and independent contractors, each with minimum limits of liability on an occurrence basis as set forth
below:
General Aggregate $2,000,000
Each Occurrence $1,000,000
Operations Aggregate $2,000,000
Personal Injury $1,000,000
9.2.3 Professional Liability Liability insurance in an amount of at least $1,000,000 total limit of liability per claim and
aggregate with a maximum deductible amount of $50,000.
Section X – GENERAL PROVISIONS
10.1 Independent
CONSULTANT represents that it is an independent contractor and is not an employee of the CITY.
10.2 Indemnification
CITY hereby agrees to indemnify, pay for defense, and hold CONSULTANT harmless from and against any and all losses,
damages, settlements, costs, charges, or other expenses or liabilities of every kind and character arising out of or relating to
any and all claims, liens, demands, obligations, actions, proceedings, or causes of action of every kind and character relating
to the negligent acts, errors, and/or omissions of the CITY, its employees, agents and third parties who perform any of the
services of CITY hereunder, and anyone else for whose acts the CITY is responsible under this contract.
CONSULTANT hereby agrees to indemnify, pay for defense, and hold the CITY harmless from and against any and all
losses, damages, settlements, costs, charges, or other expenses or liabilities of every kind and character arising out of or
relating to any and all claims, liens, demands, obligations, actions, proceedings, or causes of action of every kind and
character relating to the negligent acts, errors, and/or omissions of CONSULTANT, its employees, agents and third parties
who perform any of the services of CONSULTANT hereunder, and anyone else for whose acts CONSULTANT is
responsible under this contract.
10.3 Interpretation
Interpretation and enforcement of this Contract shall be in accordance with the laws of the State of Wisconsin.
10.4 Notices
Written notices may be delivered in person or by certified mail, or by facsimile, or by courier. All notices shall be effective
upon the date of receipt by the party. Notices shall be delivered or sent to the designated representative of the other party at
the address given on the last page of this Contract. An address may only be changed by written notice.
10.5 Applicable Law
If applicable to this Contract, CONSULTANT will comply with the requirements of:
10.5.1 The Equal Employment Opportunity clause in Section 202 of Executive Order 11246, as amended.
10.5.2 Utilization of Small and Disadvantaged Business Concerns (Public Law 95-507), and
10.5.3 All other federal, state and local laws and regulations or orders issued under such laws.
10.6 Entire Agreement
This Contract, including any schedules, attachments and referenced documents, is the entire agreement between the CITY
and the CONSULTANT. Any prior or contemporaneous agreements, promises, negotiations or representations not expressly
stated herein are of no force and effect. Any changes to this Contract shall be in writing and signed by the CITY and
CONSULTANT.
JT ENGINEERING, INC -4-
10.7 Execution Authority
This Contract is a valid and authorized undertaking of the CITY and CONSULTANT. The representatives of the CITY and
CONSULTANT who have signed below have been authorized to do so. IN WITNESS WHEREOF, the parties hereto have
made and executed this Contract as of the day and year shown on the cover page.
JT ENGINEERING, INC -5-
JT Engineering, Inc. City of Verona
281 W. Netherwood Road, Suite 1 111 Lincoln Street
Oregon, WI 53575 Verona, WI 53593
By: By:
Brian Chlopek, PE Luke Diaz, Mayor
Executive Vice President
Date: 9/15/25 Date
By: By:
Holly Licht, City Clerk
Date: Date
JT ENGINEERING, INC -6-
SCOPE OF SERVICES COMMENTARY
PROJECT: Dreger Development – Phase 2
CITY OF VERONA, DANE COUNTY
GENERAL – This is a utility expansion project that will include water main and sanitary sewer. There may
also be some minor roadway, sidewalk, and grading improvements at the limits of the project. The
expected scope of the construction work is assumed to generally follow the plans approved by the City
of Verona.
For the estimate of construction engineering costs, the scope is as follows:
A. Inspection
a. Construction oversight and inspection to verify that the construction complies with the
plans and specifications. Inspection staff will provide a daily report to the City
documenting details about the work that was completed. Inspector’s daily reports will be
filed on Microsoft Teams and shared with the City. Full-time inspection based on a 5-day
work week (Monday – Friday) is anticipated as attached in the Estimated Construction
Inspection Schedule.
B. Materials Verification – JT staff will facilitate coordination with Soils & Engineering Services, Inc.
(SES) for materials assurance provided by SES.
C. Survey – Verification survey for use in as-built drawings and for the City’s Geographic
Information System. No project staking by JT staff is included, as this is the responsibility of
others. JT will supply a dedicated GPS unit for data collection of underground utilities,
stormwater facilities, and as directed by the City.
D. Project Records – The following project records will be completed and submitted to the City of
Verona at the conclusion of the project:
1. As-built plan set depicting the actual construction of the project and any significant plan
changes
2. Assist the City in shop drawing and materials submittal reviews as directed by the City
3. Project diaries including project photos
City of Verona Estimated Construction Inspection Schedule
Dreger Development -
Phase 2
Project Project Engineer- Project
Classification Engineer Mid Project Manager Administrator Accountant
Hourly Wage $133.00 $149.00 $170.00 $210.00 $150.00
Hours Hours Hours Hours Hours
Week Begin Week End
Sunday Saturday
5-Oct-25 11-Oct-25 40 4 1 1
12-Oct-25 18-Oct-25 40 4
19-Oct-25 25-Oct-25 50 4
26-Oct-25 1-Nov-25 50 2 1 1
2-Nov-25 8-Nov-25 50 2
9-Nov-25 15-Nov-25 50 2
16-Nov-25 22-Nov-25 50 2
23-Nov-25 29-Nov-25 50 2 1 1
30-Nov-25 6-Dec-25 50 2
7-Dec-25 13-Dec-25 50 4
14-Dec-25 20-Dec-25 40 4
21-Dec-25 27-Dec-25 40 4 1 1
28-Dec-25 3-Jan-26
4-Jan-26 10-Jan-26
11-Jan-26 17-Jan-26
18-Jan-26 24-Jan-26
25-Jan-26 31-Jan-26
1-Feb-26 7-Feb-26
8-Feb-26 14-Feb-26
15-Feb-26 21-Feb-26
Totals 80 480 36 4 4
Cost $10,640.00 $71,520.00 $6,120.00 $840.00 $600.00
Total Estimated Contract Amount $89,720.00
Page 1/1
5400 King James Way, Suite 200
Madison, WI 53719-1703
608.663.1218
Toll Free: 800.810.4012
Fax: 608.663.1226
www.klengineering.com
September 15, 2025
Joe Jirsa
Construction Engineer – City of Verona
410 Investment Court
Verona, WI 53593
RE: KL Engineering Proposal for Construction Oversight Services
City of Verona Construction Inspection and Project Oversight
Avalon Ridge Development
Dear Joe,
KL Engineering, Inc. is pleased to provide you with this proposal for construction oversight services to
perform roadway and utility construction observation and project oversight associated with the Avalon
Ridge Development. The following attachments are included with this letter, and should be considered
part of our proposal for engineering services:
Attachment A – Project Understanding and Scope of Services
Attachment B – Schedule of Hours and Costs
Attachment C – Standard Billing Rate Schedule
Attachment D – General Terms and Conditions
The total cost for the services under this contract will be billed on an hourly basis utilizing the enclosed
standard billing rate schedule with a maximum cost of $113,337.60. The estimated hours and maximum
cost are based on the scope of services and schedule of hours and costs as detailed in Attachments A and
B, respectively.
Conditions Assumed Under This Proposal
Josh Vollmer from KL Engineering will serve as the Lead Construction Inspector with assistance
from additional KL staff as necessary to match the contractor’s work operations.
All construction observation will be completed by June 1, 2026.
Basis of Payment and General Conditions
This work shall be completed in accordance with the attached General Terms and Conditions, which shall
be considered a part of this contract upon the written approval indicated below. KL Engineering will submit
monthly invoices for work completed under this proposal. City of Verona will reimburse KL Engineering
within 30 days of the date of the invoice.
Our professional services will be performed, our findings obtained, and our recommendations prepared in
accordance with generally accepted engineering principles and practices. No other warranty, either
expressed or implied is made.
We look forward to working with you on this project. Please let us know if you have any questions
regarding this proposal. You may indicate your approval for us to proceed by signing the appropriate
section of this proposal and returning it to us.
Sincerely, City of Verona
Approved by:_______________________
Title:______________________________
Christopher Ehlert P.E.
Director of Construction Services. Date:______________________________
Attachment A – Project Understanding and Scope of Services
KL Engineering Proposal for Construction Oversight Services
City of Verona Construction Inspection and Project Oversight
Avalon Ridge Development
September 11, 2025
Project Understanding
The purpose of this proposal is to provide the City of Verona roadway and utility construction
inspection and project oversight associated with the Avalon Ridge development, a
new residential development located in the SE quadrant of CTH PD and Main Street.
KL Engineering, Inc. shall serve as the lead inspector for the construction of Avalon Ridge
consist of but is not limited to:
• Mass Grading, Erosion Control, and Site Street Grading
• Sanitary, Storm, and Water Utility Construction
• Street Construction: Concrete Curb & Gutter, Asphalt, and Concrete
• Fine Grading and Final Restoration
Anticipated Scope of Services
The anticipated services to be provided by KL Engineering, Inc. include the following:
• Coordinate with the Municipality and the Construction Contractor(s).
• Review and have a thorough understanding of contract plans, specifications, and
contract special provisions.
• Attend all job-related meetings and provide construction updates.
• Conduct full‐time inspection of all phases of construction.
• Ensure all contractor work is in compliance to the project specifications and plans, City
specifications, applicable WisDOT specifications, and industry standards.
• Review materials for compliance to project specifications and plans and notify City’s
geotechnical consultant when testing services are needed. Shop drawings will be
reviewed by others.
• Receive certificates, computations and reference materials submitted by the Contractor,
and maintain files on the project site of all items submitted by the contractor.
• Review and submit to the City any suggestions or requests made by the contractor to
change or modify any requirements of the plans, specifications, or Contract Documents.
• Perform erosion control inspections; prepare and maintain reports weekly or after rain
events in accordance with the WisDOT/WisDNR agreement.
• Perform routine traffic control and detour inspections.
• Work in conjunction with the Contractor and City to resolve utility conflicts.
• Maintain a daily log of activities, labor, equipment, etc.
• Maintain a photo diary of all phases of construction.
• Generate substantial and final completion documents (punch list).
• Conduct final inspection and certify acceptance.
• Perform survey field verification of the contractor’s work for as‐built drawings.
• Generate as‐built drawings consisting of a pdf markup of the construction plans showing
any changes.
• Quantities for pay applications will be completed by contractor.
• Consultant will be responsible for measuring quantities only related to as‐built record
drawing requirements
Attachment B - Schedule of Hours and Costs
Avalon Ridge Construction
City of Verona
9/9/2025
Project Staff Expenses
Totals -- Labor +
Project Role Construction Lead Construction Engineer Construction Technician Project Administration 0 0 0 0 0 0 Labor Totals Miles Breakfast Lunch Dinner Lodging Permit Fee ($) Other ($) Expense Totals Expenses Subconsultant Totals
Staff Name Joshua Vollmer Aaron Passow Hope Archer Ellen Christians 0 0 0 0 0 0
Billing Rate Classification Senior Engineer II Engineer IV Technician I Senior Administration
Billing Rate $142.24 $131.06 $87.38 $111.76 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.70 $13.00 $15.00 $26.00 $150.00
Phase 1000 - Project Management / Administration
Task 01 - Project Management / Administration 10 10 20 $ - $ - $ - $ 2,540.00
Subtotal Hours/Units 10 10 20
Subtotal Costs $ 1,422.40 $ - $ - $ 1,117.60 $ - $ - $ - $ - $ - $ - $ 2,540.00 $ - $ - $ - $ - $ - $ - $ - $ - $ 2,540.00 $ -
Phase 2000 - Meetings
Task 01 - Meetings 10 10 $ - $ - $ - $ 1,422.40
Subtotal Hours/Units 10 10
Subtotal Costs $ 1,422.40 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,422.40 $ - $ - $ - $ - $ - $ - $ - $ - $ 1,422.40 $ -
Phase 8000 - Construction Oversight
Task 01 - Office Support / Submittal Review 20 20 $ - $ - $ - $ 2,844.80
Task 02 - Field Support 600 20 120 740 1700 80 $ - $ - $ 2,390.00 $ 100,840.80
Task 03 - As-Built Drawings 10 10 $ - $ - $ - $ 1,422.40
Task 04 - Change Orders $ - $ - $ - $ -
Task 05 - Stormwater Inspection / Certification 30 30 $ - $ - $ - $ 4,267.20
Subtotal Hours/Units 660 20 120 800 1700 80
Subtotal Costs $ 93,878.40 $ 2,621.20 $ 10,485.60 $ - $ - $ - $ - $ - $ - $ - $ 106,985.20 $ 1,190.00 $ - $ 1,200.00 $ - $ - $ - $ - $ 2,390.00 $ 109,375.20 $ -
Total Hours/Units 680 20 120 10 830 1700 80
Total Costs $ 96,723.20 $ 2,621.20 $ 10,485.60 $ 1,117.60 $ - $ - $ - $ - $ - $ - $ 110,947.60 $ 1,190.00 $ - $ 1,200.00 $ - $ - $ - $ - $ 2,390.00 $ 113,337.60 $ -
Project Total Cost $113,337.60
KL Project Total Cost (Rounded) $113,337.60
Subconsultant Total -
Total Contract $113,337.60
STANDARD BILLING RATE SCHEDULE
EFFECTIVE NOVEMBER 1, 2024
Limited Term Employee $77.00
Administration $90.00
Senior Administration $110.00
Technician I $85.00
Technician II $90.00
Technician III $95.00
Technician IV $105.00
Technician V $110.00
Senior Technician I $120.00
Senior Technician II $130.00
Senior Technician III $140.00
Senior Technician IV $150.00
Senior Technician V $160.00
Surveyor I $90.00
Surveyor II $95.00
Surveyor III $100.00
Surveyor IV $110.00
Surveyor V $115.00
Senior Surveyor I $120.00
Senior Surveyor II $125.00
Senior Surveyor III $135.00
Senior Surveyor IV $140.00
Senior Surveyor V $145.00
Engineer I $113.00
Engineer II $117.00
Engineer III $124.00
Engineer IV $129.00
Engineer V $132.00
Senior Engineer I $135.00
Senior Engineer II $140.00
Senior Engineer III $150.00
Senior Engineer IV $160.00
Senior Engineer V $165.00
Senior Specialist I $125.00
Senior Specialist II $135.00
Senior Specialist III $145.00
Senior Specialist IV $155.00
Senior Specialist V $180.00
Technical Leader I $165.00
Technical Leader II $170.00
Technical Leader III $180.00
Project Leader I $165.00
Project Leader II $170.00
Project Leader III $180.00
Senior Technical Leader $185.00
Senior Project Leader $185.00
Discipline Leader $190.00
Director $205.00
Executive $220.00
Expenses
Out-of-pocket direct job expenses (reproductions, sub-consultants, equipment rental, etc.) at cost
Travel Expenses
Company or Personal Car Mileage IRS rate
Lodging and Subsistence at cost
Billing and Payment
Travel time is charged for work required to be performed out-of-office.
Invoicing is on a monthly basis for work performed. Payment for services is due within 30 days from the date of the invoice.
An interest charge of 1.5% per month is made on the unpaid balance starting 30 days after the date of the invoice.
This schedule of billing rates is effective November 1, 2024 and will remain in effect until October 31, 2025 unless
unforeseen increases in operational costs are encountered. We reserve the right to change rates to reflect such increases.
I:\Accounting\_Acct\HR\Billing Rates\BILLRATE2025.docx Rev. 10/29/24
Attachment D
KL ENGINEERING, INC.
General Terms and Conditions of the Engineering Services
1. KL Engineering, Inc. will begin engineering services upon written 8. Termination of this agreement by the Owner or KL Engineering, Inc.,
authorization to proceed. Receipt of a signed contract will be shall be effective upon seven (7) days’ written notice to the other party.
considered written authorization. For projects requiring phased The written notice shall include the reasons and details for termination.
services a written authorization of approval of the prior phase and KL Engineering, Inc., will prepare a final invoice showing all charges
notice to proceed on the subsequent phase must be received prior to incurred through the date of termination; payment is due as stated in
commencement of services. Phases, when applicable, shall be paragraph 2. If the Owner violates the agreements entered into
divided into study and report phase, preliminary design phase, final between KL Engineering, Inc., and the Owner or if the Owner fails to
design phase and construction phase. carry out any of the duties contained in these terms and conditions,
KL Engineering, Inc., may upon seven (7) days’ written notice,
2. KL Engineering, Inc. will bill the Owner monthly with net payment due suspend services without further obligation or liability to the Owner
in thirty (30) days. Past due balances shall be subject to an interest unless, within such seven (7) day period, the Owner remedies such
charge at a rate of 1½% per month. In addition, KL Engineering, Inc., violation to the reasonable satisfaction of KL Engineering, Inc.
may after, giving seven (7) days’ written notice, suspend service under
any agreement until the Owner has paid in full all amounts due for 9. Reuse of any documents and/or engineering services pertaining to
services rendered and expenses incurred, including the interest this project by the Owner or extensions of this project or on any other
charge on past due invoices. project shall be at the Owner’s sole risk. The Owner agrees to defend,
indemnity, and hold harmless KL Engineering, Inc., from all claims,
3. The quoted fees and scope of engineering services constitute the damages, and expenses including attorneys’ fees and costs arising
estimate of the fees and tasks required to perform the services as out of such reuse of the documents and/or engineering services by the
defined. This agreement, upon execution by both parties hereto, can Owner or by others acting through the Owner.
be amended only by written instrument signed by both parties. For
those projects involving conceptual or process development service, 10. KL Engineering, Inc., will provide engineering services in accordance
activities often cannot be fully defined during initial planning. As the with generally accepted professional practices. KL Engineering, Inc.,
project progresses, facts uncovered may reveal a change in direction does not make any warranty or guarantee, expressed or implied, nor
which may alter the scope. KL Engineering, Inc., will promptly inform have any agreement or contract for services subject to the provisions
the Owner in writing of such situations so that changes in this of any uniform commercial code. Similarly, KL Engineering, Inc., will
agreement can be made as required. not accept those terms and conditions offered by the Owner in its
purchase order, requisition, or notice of authorization to proceed,
4. Costs and schedule commitments shall be subject to change for except as set forth herein or expressly agreed to in writing. Written
delays caused by the Owner’s failure to provide specified facilities or acknowledgement of receipt, or the actual performance of services
information or for delays caused by unpredictable occurrences subsequent to receipt of such purchase order, requisition, or notice of
including, without limitation, fires, floods, riots, strikes, unavailability of authorization to proceed is specifically deemed not to constitute
labor or materials, delays or defaults by suppliers of materials or acceptance of any terms or conditions contrary to those set forth
services, process shutdowns, acts of God or the public enemy, or acts herein.
or regulations of any governmental agency. Temporary delays of
services caused by any of the above which result in additional costs 11. KL Engineering, Inc., intends to serve as the Owner’s professional
beyond those outlined may require renegotiation of this agreement. representative for those services as defined in this agreement, and to
provide advice and consultation to the Owner as a professional. Any
5. KL Engineering, Inc., will maintain insurance coverage for: Worker’s opinions of probable project costs, reviews and observations, and
Compensation, General Liability, Auto Liability, and Professional other decisions made by KL Engineering, Inc., for the Owner are
Liability. KL Engineering, Inc., will provide information as to specific rendered on the basis of experience and qualifications and represents
limits upon written request. If the Owner requires coverages or limits the professional judgment of KL Engineering, Inc. However, KL
in addition to those in effect as of the date of the agreement, premiums Engineering, Inc., cannot and does not guarantee that proposals, bids
for additional insurance shall be paid by the Owner. The liability of KL or actual project or construction costs will not vary from the opinion of
Engineering, Inc., to the Owner for any indemnity commitments, or for probable cost prepared by it. Owner agrees to hold KL Engineering,
any damages arising in any way out of performance of this contract is Inc., harmless for any claim arising out of or related in anyway to
limited to such insurance coverages and amounts which KL project or construction costs.
Engineering, Inc., has in effect.
12. This agreement shall not be construed as giving KL Engineering, Inc.,
6. Owner shall indemnify and hold harmless KL Engineering, Inc. from the responsibility or authority to direct or supervise construction
and against all judgments, losses, damages, and expenses (including means, methods, techniques, sequence, or procedures of
attorney fees and defense costs) to the extent such judgments, losses, construction selected by the contractors or subcontractors or the
damages, or expenses are caused by any negligent act, error, or safety precautions and programs incident to the work of the
omission of Owner or any person or organization for which Owner is contractors or subcontractors.
legally liable. Upon completion of all Services, obligations, and duties
provided for in this Agreement, or in the event of termination of this 13. This agreement shall be construed and interpreted in accordance with
Agreement for any reason, the terms and conditions of this Article shall the laws of the State of Wisconsin.
survive.
14. This agreement cannot be changed or terminated orally. No waiver of
7. In the event of a dispute between KL Engineering, Inc. and Owner compliance with any provision or condition hereof should be effective
arising out of or related to this Agreement, the aggrieved party shall unless agreed in writing duly executed by the parties hereto.
notify the other party of the dispute within a reasonable time after such
dispute arises. If the parties cannot thereafter resolve the dispute, 15. This agreement contains the entire understanding between the parties
each party shall nominate a senior officer of its management to meet on the subject matter hereof and no representations, inducements,
to resolve the dispute by direct negotiation or mediation. Should such promises or agreements not embodied herein (unless agreed in
negotiation fail to resolve the dispute, KL Engineering, Inc. and Owner writing duly executed) shall be of any force or effect, and this
agree that all disputes between them arising out of or relating to this agreement supersedes any other prior understanding entered into
Agreement shall be submitted to non-binding mediation unless the between the parties on the subject matter hereof.
parties mutually agree otherwise. During the pendency of any dispute,
the parties shall continue diligently to fulfill their respective obligations
hereunder.
K:\Forms\GeneralTermsConditions.docx
AECOM Project Name: US 18/151 Design, City of Verona
AECOM Project No.: 60718474
Change Order No.: 1
Client’s Name: City of Verona
Date: 9/17/2025
CHANGE ORDER
This Change Order No.1 with an effective date of September 17, 2025 is issued under the Consulting Services
Agreement (“Agreement”) dated October 9, 2023 by and between City of Verona, a Wisconsin Municipality
(“Client”) and AECOM Technical Services, Inc., a California Corporation (“AECOM”); each also referred to
individually as a “Party” and collectively as “Parties”. This Change Order modifies the Agreement as follows:
1. Changes to the Services:
None
2. Change to Deliverables:
None
3. Change in Project Schedule (attach schedule if appropriate):
Extend end contract date to June 1, 2026.
4. Change in AECOM’s Compensation:
The Services set forth in this Change Order will be compensated on the following basis:
[X ] Time and Materials with a Not- to-Exceed amount of ($ 850,000.00) (to reducing).
Therefore, the total authorized Compensation, inclusive of this Change Order is $ 2,070,000.00.
5. Project Impact:
None
6. Other Changes (including terms and conditions):
None
U.S. Consulting Services Agreement – Change Order (March 19, 2018)
Page 1 of 2
AECOM Project Name: US 18/151 Design, City of Verona
AECOM Project No.: 60718474
Change Order No.: 1
Client’s Name: City of Verona
Date: 9/17/2025
7. All other terms and conditions of the Agreement remain unchanged.
8. Each Party represents that the person executing this Change Order has the necessary legal authority to
do so on behalf of the respective Party.
AECOM Technical Services, Inc. CLIENT: City of Verona
Signature Signature
Jess Billmeyer
Printed Name Printed Name
Vice President
Printed Title Printed Title
9/17/2025
Date Date
Address 1350 Deming Way, Suite 100 Address
Middleton, WI 53562 111 Lincoln Street
Verona, WI 53593
[End of the Change Order]
U.S. Consulting Services Agreement – Change Order (March 19, 2018)
Page 2 of 2
AECOM Project Name: West Road Design, City of Verona
AECOM Project No.: 60731271
Change Order No.: 1
Client’s Name: City of Verona
Date: 9/17/2025
CHANGE ORDER
This Change Order No.1 with an effective date of September 17, 2025 is issued under the Consulting Services
Agreement (“Agreement”) dated April 22, 2024 by and between City of Verona, a Wisconsin Municipality
(“Client”) and AECOM Technical Services, Inc., a California Corporation (“AECOM”); each also referred to
individually as a “Party” and collectively as “Parties”. This Change Order modifies the Agreement as follows:
1. Changes to the Services:
None
2. Change to Deliverables:
None
3. Change in Project Schedule (attach schedule if appropriate):
None
4. Change in AECOM’s Compensation:
The Services set forth in this Change Order will be compensated on the following basis:
[X ] Time and Materials with a Not- to-Exceed amount of $ 850,000.00 (to adding).
Therefore, the total authorized Compensation, inclusive of this Change Order is $ 3,730,100.00.
5. Project Impact:
None
6. Other Changes (including terms and conditions):
None
U.S. Consulting Services Agreement – Change Order (March 19, 2018)
Page 1 of 2
AECOM Project Name: West Road Design, City of Verona
AECOM Project No.: 60731271
Change Order No.: 1
Client’s Name: City of Verona
Date: 9/17/2025
7. All other terms and conditions of the Agreement remain unchanged.
8. Each Party represents that the person executing this Change Order has the necessary legal authority to
do so on behalf of the respective Party.
AECOM Technical Services, Inc. CLIENT: City of Verona
Signature Signature
Jess Billmeyer
Printed Name Printed Name
Vice President
Printed Title Printed Title
9/17/2025
Date Date
Address 1350 Deming Way, Suite 100 Address
Middleton, WI 53562 111 Lincoln Street
Verona, WI 53593
[End of the Change Order]
U.S. Consulting Services Agreement – Change Order (March 19, 2018)
Page 2 of 2
Proposal Proposal#: 20683 W5745 Woodchuck Lane
AECOM Date: 18-Jul-25 P.O. Box 409
Plymouth, WI 53073-0409
Attn: Zach Topel Department Totals
Phone: (920) 893-5905
7049 Cross Country Rd. Pipe Fitting $844.00 Fax: (920) 893-5908
Verona, WI 53593
We hereby propose to furnish all material and labor necessary to complete work as described below, in a good and
workmanlike manner, for the sum of: $844
Eight Hundred Forty-Four Dollars
Description
See attached CO scope of work and breakdown from Pieper Power for wiring of the exhaust fan and louver.
According to plans and specifications as drawn by: AECOM
Project #: 24-025 Project: North Booster Station
Location of Work: Verona, WI Owner: City of Verona
Terms: Net 30 Days. Finance charge of 1-1/2% per month (Annual Percentage rate of 18%) added after 30 days after first billing date.
Respectfully Submitted,
Accepted By: Date: Brian Marquardt
Per: Brian Marquardt
Title:
ROHDE BROTHERS, INC.
This proposal when signed by you and returned to us shall constitute a valid and binding contract, which shall be governed and construed according to the laws
of the State of Wisconsin. This proposal is subject to 30 days acceptance from the date of this proposal and may be changed without notice before actual receipt
of acceptance. This proposal is based on a form of contract using the latest editions of AIA Document A201. “General Conditions of the Contract for
Construction” in conjunction with either AIA Document A101, “Standard Form of Agreement Between Owner and Contractor” of AIA Document A401,
“SUBCONTRACT Standard Form of Agreement Between Contractor and Subcontractor”, or on a time and material form of contract using the latest edition of
Rohde Brothers, Inc. “Standard Form of Construction Contract Proposal For Cost Of Work Plus A Fee”. Rohde Brothers shall also be reimbursed for all
expenses it incurs while protecting its rights in the performance of this work. This shall include any appropriate legal or administrative action that Rohde
Brothers must take to protect its interests, such as, but not limited to, attorney and accounting fees, court reporter fees, filing fees, the actual cost of effecting
service of papers or providing witnesses, and expenses incurred by Rohde Brothers itself.
CONFIDENTIAL CUSTOMER COPY
City of Verona
Breakdown of Rohde Proposal #20683
Proposal Name: North Booster Station
Subcontract Total
Pieper Power $ 804.00
Total Before Adjustment $ 804.00
Allowable Adjustment 5.0%
Total Subcontract Cost $ 844.20
Material Total: $ 0
Total Labor $ 0
Total Subcontractor $ 844
Total Change Order $ 844
Page: 1 of 1 Printed: 7/18/2025 6:07:19 AM by: marquardtb
CHANGE ORDER SUMMARY
JOB NAME: Verona NBPS
Rohde Brothers, INC. CHANGE ORDER NUMBER: PCO#2
W5745 Woodchuck Ln REVISION NUMER: N/A
P.O. Box 409 DATE: 7/17/2025
Plymouth, WI 53073 JOB NO: IN00006435
ATTENTION : Brian Marquardt CONTRACT NO: SC-2915
AMOUNT OF C/O: $804
REGARDING YOUR REQUEST FOR QUOTATION:
Additional wire and terminations to tie in (1) Exhaust fan louver.
SUMMARY: A. LABOR $643
B. MATERIALS $37
C. DJE $19
SBO: YES
SUBTOTAL $699
OVERHEAD & PROFIT 15.00% $105
D. SUBCONTRACTS $0
OVERHEAD & PROFIT 0.00% $0
SUBTOTAL $804
BOND $0
INSURANCE $0
GRAND TOTAL $804
ADDITIONAL CALENDAR DAYS EXTENDED TO CONTRACT COMPLETION DATE: 0
THIS AMOUNT ONLY COVERS THE DIRECT COSTS IN LABOR, MATERIALS, SUBCONTRACTS AND EQUIPMENT NECESSARY TO EXECUTE THE
CHANGED WORK DESCRIBED IN THE PROPOSAL. AT THE PRESENT TIME, WE CANNOT ASSESS OR EVALUATE THE OVERALL IMPACT OF THE
CHANGED WORK ON OUR ORIGINAL CONTRACT SCOPE OF WORK. WE THEREBY RESERVE OUR RIGHTS TO CLAIM FOR ANY INDIRECT COSTS
WHICH MAY ARISE IN THE FUTURE AS A RESULT OF DELAYS TO THE WORK, OUT OF SEQUENCE WORK, INEFFICIENCIES, EXTENDED CONTRACT
COMPLETION, LABOR AND MATERIAL ESCALATION AND/OR ACCELERATION AND EXTENDED WARRANTIES.
OPS-14, 15, 16 This price is valid for 14 days. This form was approved:
JOB NUMBER C.O. NO. DATE REVISION
Verona NBPS IN00006435 PCO#2 17-Jul-25 N/A
A. LABOR
*SUPER INTENDENT 0 HRS @ $146.32 TOTAL $0.00
** SUPERVISOR 0 HRS @ $117.50 TOTAL $0.00
*** SAFETY 0 HRS @ $79.29 TOTAL $0.00
ELECTRICIAN 5 HRS @ $128.59 TOTAL $642.95
ESTIMATOR 0 HRS @ $85.00 TOTAL $0.00
ENGINEER 0 HRS @ $50.00 TOTAL $0.00
@ TOTAL $0.00
@ TOTAL $0.00
@ TOTAL $0.00
TRAVEL @ TOTAL $0.00
SUBSISTENCE @ TOTAL $0.00
PREMIUM COSTS TOTAL $0.00
LABOR TOTAL $642.95
B. MATERIALS
MATERIAL PER "TAKE-OFF" TOTAL $37
MISCELLANEOUS MATERIAL & WASTE 0.00% TOTAL $0
SUBTOTAL $37
FREIGHT AND HANDLING TOTAL $0
SPECIAL EXPEDITING TOTAL $0
SALES TAX 0.0% TOTAL $0
MATERIAL TOTAL $37
*SUPER INTENDENT - 6% OF TOTAL MAN HOURS
** SUPERVISOR - 12 % OF TOTAL MAN HOURS
*** SAFETY - 3 % OF TOTAL MAN HOURS
TS11A
JOB NUMBER C.O. NO. DATE REVISION
Verona NBPS IN00006435 PCO#2 17-Jul-25 N/A
C. DJE QUANTITY UNIT PRICE AMOUNT
Field Office $0.00
Telephone $0.00
Field Office Supplies $0.00
Field Office Equipment $0.00
Blueprinting $0.00
$0.00
$0.00
First Aid and Safety Supplies $0.00
$0.00
Warehousing $0.00
Storage Charges $0.00
Freight Charges $0.00
$0.00
Special Insurance $0.00
$0.00
Permit and Inspection Fees $0.00
$0.00
$0.00
Equipment and Tools 3.00% of Labor 1 $19.29 $19.29
Truck - Jobsite Van $7.50 $0.00
Truck - Pick-Up $0.00
Truck - Stake $0.00
Truck - Line $0.00
Fuel - (On Jobsite) $0.00
$0.00
Travel and Trips Expenses $0.00
Lodging Expenses $0.00
Living Allowance $0.00
Entertainment $0.00
Double Union Benefits $0.00
$0.00
Job Clean-Up $0.00
$0.00
Temp Power Consumption Charges $0.00
Utility Comp Charges - Temp Service $0.00
Utility Comp Charges - Perm Service $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
TOTAL: $19
ESTIMATING FORM
PROJECT CODE # PAGE OF
Verona NBPS
LOCATION ARCH. OR ENG. ESTIMATE NO.
Notes: SPECIFICATION NO. SCALE DRAWING NO.
ESTIMATED BY PRICED BY REVIEWED T.S. REVIEWED DATE
7/17/2025
Labor
Description Quan. Material Unit Material Extension Labor Unit Notes
Extension
Type THWN-THHN, copper, stranded, #12 100 $0.29 $28.50 0.00866 0.866
Terminations 1 $7.60 $7.60 1 1
Testing and commissioning 1 1 1
Mobilization/Demobilization 2 0.75 1.5
Total this page - $37 - 5 -
TS 24 Total all pages - $37 - 5 -
Owner: City of Verona, Wisconsin
Project: North Pump Station and Electrical System Updates
Project No.: 2022-109.1 Contract: 2022-109.1
Contractor: Rohde Brothers, Inc.
W5745 Woodchuck Ln
Plymouth, WI 53073
Estimate Prepared By: Brian Marquardt
Name
Project Manager
Title
9/11/2025
Date
SUMMARY
ORIGINAL CONTRACT AMOUNT 581,100.00
APPROVED CONTRACT REVISION AS OF 10,761.00
ADJUSTED CONTRACT AMOUNT 591,861.00
REQUEST THIS ESTIMATE
TOTAL COMPLETED TO DATE 591,861.00
PREVIOUS REQUESTS FOR PAYMENT 572,401.92
TOTAL EARNED THIS REQUEST 19,459.08
RETAINAGE 0% 0.00
CURRENT PAYMENT DUE 19,459.08
AECOM
Name
September 17th, 2025
Date
City of Verona
Name
Date
Owner's approval
Date
W5745 Woodchuck Lane
P.O. Box 409
Plymouth, WI 53073 REQUEST FOR PAYMENT
Phone: (920) 893-5905 REQUEST #: 12
Email: ar@rohdebros.com
PERIOD: 9/1/2025 - 9/30/2025
INVOICE #: 57601
TO: Town of Verona DATE: 9/11/2025
111 Lincoln St
Verona, WI 53593 TERMS: Net 30
PROJECT #: 24025 / 2022-109.1
PROJECT: Verona North Pump Station CONTRACT FOR:
7049 Cross Country Rd
Verona, WI 53593
ORIGINAL CONTRACT AMOUNT $581,100.00
APPROVED CONTRACT REVISION(S) AS OF 9/11/2025 $10,761.00
ADJUSTED CONTRACT AMOUNT $591,861.00
TOTAL COMPLETED & STORED TO DATE $591,861.00
RETAINAGE (5% until 50% Completion, then 0%) $0.00
TOTAL EARNED LESS RETAINAGE $591,861.00
LESS PREVIOUS REQUESTS FOR PAYMENT $572,401.92
CURRENT PAYMENT DUE $19,459.08
BALANCE TO FINISH, INCLUDING RETAINAGE $0.00
TOTAL EARNED THIS REQUEST $19,459.08
LESS RETAINAGE $0.00
SUBTOTAL $19,459.08
SALES TAX $0.00
PAYMENT DUE THIS REQUEST $19,459.08
PROJECT: Verona North Pump Station
APPLICATION NUMBER: 12
APPLICATION DATE: 9/11/2025
PERIOD TO: 9/30/2025
PROJECT NOs: 24025 / 2022-109.1 /
CONTINUATION SHEET
ITEM DESCRIPTION OF WORK SCHEDULED WORK COMPLETED MATERIAL TOTAL COMPLETED & RETAINAGE BALANCE TO
NO. VALUE PREVIOUS THIS STORED STORED TO DATE 5% FINISH
APPLICATION APPLICATION This Request % Up to 50%
(A) (B) (C) (D) (E) (F) (G) (H) (I) (J)
01 Job Supervision $20,000.00 $18,000.00 $2,000.00 $20,000.00 100%
02 Submittals $10,000.00 $10,000.00 $10,000.00 100%
03 O&M's $5,000.00 $4,000.00 $1,000.00 $5,000.00 100%
04 Project Closeouts $5,000.00 $4,000.00 $1,000.00 $5,000.00 100%
05 Permits & Bonds $5,200.00 $5,200.00 $5,200.00 100%
06 Mobilization $1,000.00 $1,000.00 $1,000.00 100%
07 Demobilization $1,000.00 $1,000.00 $1,000.00 100%
08 Procurement
09 Process Pipe, Fittings, & Valves $67,000.00 $67,000.00 $67,000.00 100%
10 Hangers $5,000.00 $5,000.00 $5,000.00 100%
11 LW Allen/Altronex
12 43 21 00 Large Booster Pumps $75,000.00 $75,000.00 $75,000.00 100%
13 43 21 00 Small Jokcey Pump $25,000.00 $25,000.00 $25,000.00 100%
14 40 61 14 Instrumentation & Controls $9,766.00 $9,766.00 $9,766.00 100%
15 40 71 13 Inline Magnetic Flow Meter $10,000.00 $10,000.00 $10,000.00 100%
16 Motor Control Center $147,595.00 $147,595.00 $147,595.00 100%
17 North Booster Station Well-4 RTU Modifications $44,719.00 $44,719.00 $44,719.00 100%
18 Labor Installation
19 Measure & Planning $15,000.00 $15,000.00 $15,000.00 100%
20 Deliveries $3,000.00 $3,000.00 $3,000.00 100%
21 Piping Labor $15,000.00 $15,000.00 $15,000.00 100%
22 Equipment Setting $15,000.00 $15,000.00 $15,000.00 100%
23 Demolition $5,000.00 $5,000.00 $5,000.00 100%
24 Startup/Commissioning $3,000.00 $3,000.00 $3,000.00 100%
25 Subcontractors
26 Controls/Power Wiring (Pieper Electric) $68,283.00 $68,283.00 $68,283.00 100%
27 Painting (Omni Glass & Paint) $25,537.00 $25,537.00 $25,537.00 100%
28 Change Orders
CO1 CO 1 - Moving piping $3,503.00 $3,503.00 $3,503.00 100%
CO2 CO 2 - Air Compressor Panel Relocation $6,414.00 $6,414.00 $6,414.00 100%
CO3 CO 3 - Wiring Exhaust Fan $844.00 $844.00 $844.00 100%
Totals $591,861.00 $587,017.00 $4,844.00 $591,861.00 100%