Park and Recreation Committee
Regular MeetingWeston, WI · March 27, 2023
Minutes
Village of Weston, Wisconsin
MEETING MINUTES OF THE PARK & RECREATION COMMITTEE MEETING
Monday, March 27, 2023, 5:00 p.m.
AGENDA ITEMS
1. Meeting called to order by Chair Ermeling @ 5:00 P.M.
2. Roll Call by Recording Secretary: Jessica Falkowski
Member Present
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb (C) YES
Esker, Roger YES
Fiene, Nate (VC) YES
Village Staff in attendance: Falkowski (Clerk), Donner (Zoom), Osterbrink, and Wodalski.
3. Approval of minutes from previous meeting: November 28, 2022.
*M/S/P Fiene/Esker: to approve the November 28, 2022, minutes.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
4. Public Comments.
None
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
EDUCATIONAL PRESENTATIONS & REPORTS
5. Dan Higginbotham will be presenting information regarding a proposed trail on
Northwestern Ave.
Higginbotham presented information proposing a trail along and on Northwestern Avenue.
The proposed trail would connect and pass through parts of the City of Schofield, City of
Wausau, and Village of Weston. The City of Schofield sent out an RFP for a design on a
bridge. The bridge would cross the Eau Claire River to connect the existing path south of the
river to the proposed path on and along Northwestern. Marathon County Parks Foundation
has also been wanting to connect a trail from the Mountain-Bay to Camp Phillips path.
Higginbotham is asking the Village Parks and Recreation Committee for a notice of intent to
continue a trail from the existing paved trail from Camp Phillips Road through Yellowbanks
park to the Girl Scout property. Higginbotham is also asking the Village to add this proposed
trail to the Comprehensive Outdoor Recreation Plan. Once added to the Comprehensive
Plan the Village will be able to apply for grants.
Higginbotham states by adding this section of trail would allow an additional option for a
paddle/pedal area because Yellowbanks is also considered a canoe/kayak launch.
Wodalski commented that the Village received a grant from the DOT to repave Northwestern
this summer, 2023. The road will be made slightly wider and allow for a larger paved
shoulder for walking and biking. Wodalski has been in contact with Mark Thuot from City of
Schofield discussing a timeline and ideas of constructing a path through the neighborhoods
and on Northwestern Avenue.
POLICY ISSUES – DISCUSSIONS/RECOMMENDATIONS
6. Discussion and possible action Park Signage.
Osterbrink stated that the Committee decided in November 2022 to requote the project due to
receiving only one proposal. The Committee also decided to change the thickness of the sign
material from 1/4 inch to 1/8 inch and to have Village staff remove all the existing signs and
not the sign company from the original RFP.
Osterbrink received two proposals from companies by the February 22nd deadline.
Committee members questioned the large cost difference between the two companies.
Osterbrink responded that one company is large and does a lot of signage around the area
and the other company is two brothers that started a few years ago. The one brother used to
work for a signage company in Weston which the Village has worked with in the past. The
larger company is currently updating the primary, secondary, and tertiary signs for the Village.
The Village has a CIP budget of $25,000 for signage.
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
*M/S/P Fiene/Esker: motion to recommend awarding the Park Sign replacement
project to Sign Forge for $18,840.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
7. Discussion and possible action Proposal for Yellowbanks Disc Golf Course
Osterbrink mentioned members of WADGE and other groups came together making a
proposal to make Yellowbanks Disc Golf Course a playable course. This means making the
course more easily maintained and with more options of play. Currently, the course is mostly
maintained by dedicated volunteers from WADGE and other groups. The Village does
minimal maintenance, mowing and cutting down trees, due to limited staff. There is a
constant battle with thorny brush, down trees, restrictions with the pipeline easement, and
wetlands.
Osterbrink discussed the idea of having the wetlands delineated again so we know the areas
that can be worked on, material added or removed to help with maintenance. Also, the
discussion of maintaining the thorny brush, chemically wick or spray it besides mowing and
trimming.
Clark stated she has reached out to the group through Facebook asking what their vision for
this course is? An individual in the audience, a member of Team Hookup in Antigo
responded that their goal is to provide an 18-hole course in the Wausau area because there
is none. Currently, the closest courses are located at the Big Eau Pleine Park, Mosinee and
Standing Rocks in Stevens Point. Osterbrink mentioned that our course will not be able to
reach that level of play as those mentioned courses. Yellowbanks Disc Golf Course has
more limitations of what we can do to the site. The current plan is to provide 2 tee pads and 2
pins per hole.
Because of the new well house construction that includes the additions of a restroom facility
and shelter, the holes located out in the field will have to be removed and redesigned.
Prohaska Park is a possible additional Disc Golf Course location that has fewer site
limitations.
Corvino asked the audience members if they could see this site becoming a higher level of
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
play and drawing unto itself. Audience member responded that he could see it becoming a
higher level of play. A few positive changes could be to replace or add rubber tee pads or use
astroturf on a wooden deck for a tee pad, and have some of the baskets removed for
sandblasting and powder coating. Osterbrink stated that the wetlands are the biggest hurdle
to see where the improvements could be made.
Fiene would like to see the expanse of the wetlands by having the wetlands delineated to see
what the options are to make improvements to the course.
Wodalski stated that the wetlands delineations are only good for 5 years and areas 10,000
square feet or less only need a general permit.
Ermeling is concerned with maintenance once the improvements have been made.
Osterbrink stated that reconfiguring some of the holes and tee pads could help with
maintenance of the course and provide more options of play. Also providing a donation box
or collecting money at tournaments for maintenance of the course are possible options.
Clark provided the option of volunteering their time and equipment to help with mowing and
cutting down trees. Clark also provided suggestions of how to deal with the thorny brush.
Clark’s property is adjacent to the disc golf course, and they deal with some of the same
maintenance issues as the Village does with the course.
Osterbrink suggested planning the course layout and drafting a maintenance agreement
between the Village and volunteer groups in 2023 while the wellhouse and shelter are under
construction. Then reconstruct the course and have scheduled workdays with volunteers
starting in 2024.
*M/S/P Fiene/Corvino: motion to recommend staff to get a cost to complete a
wetland delineation for the Yellowbanks Disc Golf Course.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
8. Discussion and possible action Capital Improvement Projects
Osterbrink presented the current CIP list to the committee. Osterbrink explained that the
current list is just a plan and that projects may change due to priority. Updating the
Comprehensive Outdoor Recreation Plan (CORP) and conducting two Park Master Plans for
Kennedy and Prohaska Parks in 2023 are examples of possible changes to the CIP
depending on the outcomes of the plans.
Corvino has been conversing with Everest Youth Baseball and asked them their vision for
Kennedy Park. Osterbrink stated that Everest Baseball’s goal is to build the community and
have all age groups play at one location. Osterbrink added that talking with user groups is
part of establishing a master plan. A Master Plan is a plan that considers all user groups and
what would be best suited for that site.
Wodalski stated he is on the Board for Everest Youth Baseball and developing a Master Plan
for Kennedy will bring the Village and baseball groups together because there will be one
layout allowing for a shared vision. This will make it easier for each to work towards the end
goal.
Corvino commented that Kennedy Park will always be the home for baseball. He saw other
user groups such as soccer and rugby come and go from Kennedy Park. Corvino also stated
that Pickleball is a big group and are looking to expand and develop courts. Osterbrink added
the Wolf Pack, a Lacrosse group, is also looking for a site to become more visible and grow
their club.
Ermeling asked what projects have been completed in the 2022 CIP. Osterbrink responded
that the electrical connections and refurbishment of the water play structure were completed
at the Aquatic Center. The roof replacement at the Aquatic Center will be completed this
spring. The other 2022 projects were put on hold due to the pool leak. The approval of using
ARPA funds to pay for the leak was not officially approved until October 2022. Also, the
repairs are not completed yet.
Osterbrink stated that there are under-utilized areas in some of our parks. For example,
Kennedy, Kellyland, and Machmueller soccer fields are under-utilized due to the Soccer
Complex in Wausau and the multiple fields at the D.C. Everest Middle School. Those areas
could be a host site for a new user group(s). Master plans includes input from all user
groups, D.C. Everest School District, and surrounding facilities like Greenheck Turner of what
will complement these areas. Once these plans are completed, they will be added to the
CORP allowing the Village to apply for grants and other funds.
NO ACTION TAKEN
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
FUTURE ITEMS
9. Possible next meeting date: April 24, 2023 at 5:00 pm.
10. Topics for future meetings.
a. Comprehensive Outdoor Recreation Plan Update and Park Master Plans
11. Remarks from Staff
Osterbrink stated he will be contacting Committee members to meet with the consultant about
the master plans. Village staff has a project kickoff meeting with Rettler Wednesday, March
29th.
Osterbrink received 5 applications for summer help.
Aquatic Center roofing materials are due to arrive April 10th.
Camera update at the parks and pool – the company is wanting to start installation of the
systems in the first part of April, weather dependent.
There are two pre-season pool rentals scheduled, Horace Mann and John Muir.
Municipal Center open house is Saturday, May 13th from 10 a.m. - 2 p.m.
12. Remarks from Committee Members.
Fiene stated this was his last Park and Recreation Committee meeting. Fiene said thank you
to everyone and that it was an honor and privilege being on the committee.
Fiene asked for each president of organizations to be invited to give their input for the
development of the Master Plans for Kennedy and Prohaska parks.
13. Announcements.
None
14. Adjournment.
*M/S/P Fiene/Clark: motion to adjourn the meeting at 6:40p.m.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Zeyghami, Hooshang YES
Jessica Falkowski, Recording Secretary
Village of Weston Parks and Recreation Committee Meeting March 27, 2023
Agenda
OFFICIAL MEETING PACKET OF THE
PARKS AND RECREATION COMMITTEE
CHAIRPERSON/TRUSTEE BARBARA ERMELING PRESIDING
DIRECTOR OF PARKS AND RECREATION SHAWN OSTERBRINK; STAFF
ADVISOR
A meeting of the Parks and Recreation Committee, composed of five (5) appointed
members, will convene at Weston Municipal Center, which is located at 4747
Camp Phillips Road, Weston, on MONDAY, MARCH 27, 2023, at 5:00 p.m.
Village of Weston, Wisconsin
ATTENTION – NOTICE OF PUBLIC MEETING
Meeting: PARK AND RECREATION COMMITTEE
Members: Clark, Corvino, Ermeling (C), Esker, Fiene (VC)
Ex-Officio: Maloney
Staff: Osterbrink, Falkowski
Date/Time: Monday, March 27th, 2023, at 5:00 p.m.
Location: Weston Municipal Center, 4747 Camp Phillips Road, Weston, WI
54476
Agenda: The Agenda Packet will be sent out on Wednesday, March 22nd.
Attendance: Parks and Recreation Committee Members please indicate if you will
or will not be attending so we may determine in advance if there will
be a quorum.
Questions: Shawn Osterbrink Jessica Falkowski
sosterbrink@westonwi.gov jfalkowski@westonwi.gov
(715) 359-9988 (715) 359-9988
PLEASE NOTE THE FOLLOWING INFORMATION:
This notice was posted at the Municipal Center, and on the Village’s website at www.westonwi.gov, and was emailed
to local media outlets (Print, TV, and Radio) on 3/21/2023 @ 2:00 p.m. Any posted agenda is subject to change up until
24 hours prior to the date and time of the meeting.
A quorum of members from other Village governmental bodies (boards, commissions, and committees) may attend the
above-noticed meeting to gather information. Should a quorum be other government bodies are present, this would
constitute a meeting pursuant to State ex rel. Badke v. Greendale Village Bd., 173 Wis.2d 553,494 N.W.2d 408 (1993).
Wisconsin State Statutes require all agendas for Committee, Commission, or Board meetings be posted in final form,
24 hours prior to the meeting.
Any person who has a qualifying disability, as defined by the Americans with Disabilities Act, requiring that meeting or
material to be in an accessible location or format, must contact the Weston Municipal Center at 715-359-6114, so any
necessary arrangements can be made to accommodate each request.
VILLAGE OF WESTON, WISCONSIN
OFFICIAL MEETING AGENDA OF THE PARKS AND RECREATION COMMITTEE
`
TO THE HONORABLE TRUSTEE ERMELING AND FOUR (4) APPOINTED MEMBERS OF
THE COMMITTEE: The following items were listed on the agenda in the Village Clerk’s
Office, in accordance with Chapter 2 of the Village’s Municipal Code and will be ready for
your consideration at the regular meeting of the Parks and Recreation Committee on
Monday, March 27, 2023 @ 5:00 p.m., in the Village Board Room at the Weston Municipal
Center, 4747 Camp Phillips Road, Weston, WI. 54476.
A quorum of members from other Village governmental bodies (boards, commissions, and committees)
may/might attend the above-noticed meeting to gather information. Should a quorum of other government bodies
be present, this would constitute a meeting pursuant to State ex rel. Badke v. Greendale Village Bd., 173 Wis.2d
553,494 N.W.2d 408 (1993). No official actions other than those of the Parks and Recreation Committee shall take
place. Wisconsin State Statutes require all agendas for Committee, Commission, or Board meetings be posted in
final form, 24 hours prior to the meeting. Any posted agenda is subject to change up until 24 hours prior to the
date and time of the meeting. All items listed on this agenda may be acted upon by the Park Committee.
If not able to attend in person interested persons may also attend via the zoom link or
by phone.
Join Zoom Meeting by Computer:
https://zoom.us/j/5445915099
Join Zoom Meeting by Phone:
+1 312 626 6799 US (Chicago)
Meeting ID: 5445915099
AGENGA ITEMS.
1. Meeting called to order by Chair Ermeling.
2. Roll Call by Recording Secretary:
a. Clark
b. Corvino
c. Ermeling (C)
d. Esker
e. Fiene (VC)
3. Approval of minutes from previous meeting: November 28, 2022.
4. Public Comments.
Parks and Recreation Committee Meeting – Agenda 3/27/23
Prepared by: Shawn Osterbrink, Director of Parks, Recreation and Forestry
VILLAGE OF WESTON, WISCONSIN
OFFICIAL MEETING AGENDA OF THE PARKS AND RECREATION COMMITTEE
EDUCATIONAL PRESENTATIONS & REPORTS.
5. Dan Higginbotham will be presenting information regarding a proposed trail on
Northwestern Avenue.
POLICY ISSUES – DISCUSSIONS/RECOMMENDATONS.
6. Discussion and possible action Park Signage.
7. Discussion and possible action Proposal for Yellowbanks Disc Golf Course.
8. Discuss and possible action Capital Improvement Projects.
FUTURE ITEMS
9. Possible next meeting date: April 24, 2023.
10. Topics for future meetings:
a. Comprehensive Outdoor Recreation Plan Update and Park Master Plans.
11. Remarks from Staff.
12. Remarks from Committee Members.
13. Announcements.
14. Adjourn.
Parks and Recreation Committee Meeting – Agenda 3/27/23
Prepared by: Shawn Osterbrink, Director of Parks, Recreation & Forestry
Village of Weston, Wisconsin
MEETING MINUTES OF THE PARK & RECREATION COMMITTEE MEETING
Monday, November 28, 2022, 4:45 p.m.
AGENDA ITEMS
1. Meeting called to order by Chair Ermeling @ 4:45 P.M.
2. Roll Call by Recording Secretary: Jessica Falkowski
Member Present
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb (C) YES
Esker, Roger YES
Fiene, Nate (VC) YES
Village Staff in attendance: Falkowski (Clerk), and Osterbrink.
3. Approval of minutes from previous meeting: April 25, 2022.
*M/S/P Esker/Fiene: to approve the April 25, 2022, minutes.
Yes Vote: 4 No Vote: 0 Abstain: 0 Not Voting: 1 Result: PASS
Member Vote
Clark, Katrina -----
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
Committee member Clark arrived at the meeting at 4:49 p.m.
4. Public Comments.
None
EDUCATIONAL PRESENTATIONS & REPORTS
None
Village of Weston Parks and Recreation Committee Meeting November 28, 2022
POLICY ISSUES – DISCUSSIONS/RECOMMENDATIONS
5. Discussion and possible action Aquatic Center Leak Repairs
Osterbrink stated that we had multiple leaks at the pool that staff were able to isolate during
the season. This included the water line to the floor fountains and the underground lines that
provided water to parts of the play structure. In October Neuman Pools abandoned the line to
the floor fountains by plugging and capping those 4 fountains. Staff discussed this with the
administrator prior to completions. The idea was to save additional cost of them having to dig
up more of the pool surface to try and find the leak and make the repairs, just for 4 fountains.
The contractor did find two broken supply lines to parts of the play structure that were
repaired. The contractor then pressure checked their repairs and found they were still leaking
so they removed more of the pool surface and followed the lines to the pedestals of the play
structure. One pedestal was rusted through and the other was leaking around the mounting
bolts. These findings are additional leaks and costs from the original estimate. The remaining
pedestals were pressure checked and are fine.
Neuman also replaced all loose tile and all caulk inside the pool that was completed under
warranty.
The additional cost estimate is $37,200 to complete repairs next spring. Currently,
$39,815.96 has been spent on repairs. Village Board approved utilizing up to $40,000 in
ARPA funds to complete original cost estimate in September. The committee discussed
using ARPA funds for the additional cost of repairs to be completed in spring of 2023.
*M/S/P Fiene/Esker: motion to recommend to the Board of Trustees to use ARPA
funds to pay up to an additional $40,000 towards Aquatic Center leak repairs in
2023.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
6. Discussion and possible action Park Signage
Village of Weston Parks and Recreation Committee Meeting November 28, 2022
Osterbrink stated the Village recently replaced wayfinding signs and is currently installing new
entryway signs. This led to a discussion and decision at the August 2022 joint Public Works
and Park Committee meeting to update the park signs, so they are all uniform. Osterbrink
drafted and sent out a Request for Quotes (RFQ) in September to six companies and only
one company provided a quote by the November 2nd deadline. The RFQ provided the same
material specs as the wayfinding and entry signs, ¼ inch thick aluminum.
Osterbrink discussed available options of funding the cost of the signs through tourism dollars
or ARPA funds.
Osterbrink and Committee members discussed possible alternatives to lower the costs of the
signs. It was suggested to change the specs to either using 1/8- or 3/16-inch aluminum or
using di-bond material to make the signs instead of ¼ inch aluminum.
Corvino asked, if the Committee decides to requote the project will the work be able to be
done next spring? Osterbrink responded, he hoped so. Osterbrink mentioned he would also
contact the companies that were interested in the project but did not provide a quote if the
Committee decides to requote the project.
The current quote the Village received from Graphic House does not appear to have a
deadline.
*M/S/P Fiene/Clark: motion to recommend requoting the park signage project.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
7. Discussion and possible action Aquatic Center Roof Replacement.
Osterbrink drafted and sent a Request for Quotes (RFQ) to four contractors along with
posting the RFQ on the League of Municipalities website in October 2022 for Aquatic Center
roof replacement. The specs included three different options to quote: fiberglass-based
shingles, decra, and standing seam snap lock 24-gauge metal roofing.
Osterbrink received one quote by the November 23rd deadline. The quote came in less than
the budgeted $75,000 in the CIP.
Osterbrink recommends going with a standing seam snap lock metal roof because of the
durability and damaged panels can be replaced more easily than the decra shingles.
Village of Weston Parks and Recreation Committee Meeting November 28, 2022
Osterbrink stated that because of the roof pitch and constant replacement of current shingles
staff recommends not to consider the fiberglass-based shingle option.
Osterbrink discussed the option of going with a 26-gauge standing seam snap lock metal roof
(residential) versus a 24-gauge (commercial) for the Aquatic Center because of the high pitch
roof, the building’s age, and cost savings.
*M/S/P Esker/Fiene: motion to recommend to the Board of Trustees the quote for the
26-gauge standing seam snap lock metal shingles once received from contractor.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Fiene, Nate YES
8. Discussion and possible action Cameras Parks and various other locations.
Osterbrink stated Village staff have been working with two companies: New Era and Camera
Corner Connecting Point. New Era was contacted originally to provide an estimate of
providing and installing timed locks at park restrooms earlier this summer. Staff have not
received any information or quotes from New Era at this time.
Staff have worked with Camera Corner Connecting Point with the current system at the
Aquatic Center and the AV system at the new municipal center. The company also provides
Everest Metro with video and building security. Camera Corner Connecting Point has
provided the only proposal received and has worked with staff to answer their questions and
provided multiple solutions.
Committee members would like staff to continue to work on this project.
No action taken.
FUTURE ITEMS
9. Possible next meeting date: January 23, 2023.
Village of Weston Parks and Recreation Committee Meeting November 28, 2022
10. Topics for future meetings.
a. Proposed CIP Projects
11. Remarks from Staff
Osterbrink stated he submitted an insurance claim for the leak at the Aquatic Center. The
insurance company denied the claim due to pipes freezing and cracking and deterioration of
the piping because of the age of the pool. For the insurance to cover leaks in the pool, the
damage would need to be an act of God.
12. Remarks from Committee Members.
Ermeling stated she may not be present for the January meeting. Committee members
discussed changing the meeting time to 5 p.m.
13. Announcements.
Osterbrink announced that a post card will be sent to Village businesses and residents
stating the new municipal center will be open to the public December 12, 2022, and an open
house will be held sometime in spring.
14. Adjournment.
*M/S/P Fiene/Corvino: motion to adjourn the meeting at 6:01p.m.
Yes Vote: 5 No Vote: 0 Abstain: 0 Not Voting: 0 Result: PASS
Member Vote
Clark, Katrina YES
Corvino, Dino YES
Ermeling, Barb YES
Esker, Roger YES
Zeyghami, Hooshang YES
Jessica Falkowski, Recording Secretary
Village of Weston Parks and Recreation Committee Meeting November 28, 2022
REQUEST FOR CONSIDERATION
Public Mtg/Date: Park & Recreation Committee – 3/27/2023
Description: Proposed Path Northwestern Avenue
From: Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question: Informational Only.
Background
Dan Higginbotham will be presenting information regarding a proposed trail along
and on Northwestern Avenue. This proposed path will be partially on road and
partially off road and extends into the City of Wausau and goes towards the river
and into Schofield. Dan along with Bill Betram from the Wausau/Marathon County
Parks Foundation and others have been working on this over the past few months
and have already received letters of intent from at least three property owners
along the proposed route. The reason that the Village is involved in this proposed
trail is that some of it is located in Village right of way and they would also like to
have it enter Yellowbanks Park on the west side to get to the existing path on the
east side of the park. The trail through the park could be partially in the right of
way and partially in the park.
Attached Docs: Graphic of proposed route.
Letters of Intent.
______________________________________________________________________
Committee Action: No previous review.
Fiscal Impact: Not known at this time but they are trying to get it done
with grants and private funding.
Recommendation: None
Recommended Language for Official Action
______________________________________________________________________
Additional action:
REQUEST FOR CONSIDERATION
Notification of Intent
Trail Easement
The City of Wausau, City of Schofield and Village of Weston, located in
Marathon County, desire to continue their pedestrian and bike trail
construction with the addition of a new trail section to be located parallel
and along the north side of the Eau Claire River from the WI Central Limited
Railroad bridge on the west to County Road X on the east.
We recognize that this addition is conducive to the creation of a safe off-
street bike/pedestrian connection from the planned bike/pedestrian facilities
going north and south from the City of Schofield connecting to the City of
Wausau and the Village of Weston and further, linking other municipalities
within the region.
We also recognize that this trail is not only necessary for safety reasons but
will also create a complete bike/walkway thoroughfare from the Cedar
Creek Mall and Military Road in the Village of Rothschild to the City of
Wausau and also east to the Mountain Bay State trail that continues to the
City of Green Bay.
Therefore, consistent with this letter, Girl Scouts of the Northwestern
Great Lakes, Inc. is committed to working with the municipalities
listed in this letter to evaluate the granting of pertinent land rights at
Camp Del O’Claire, 3607 Northwestern Ave., Schofield Wisconsin to
allow for the construction, operation and maintenance of the
proposed project with the requested minimum 20-foot-wide
easement for the construction of a 10-foot-wide paved trail system
intended for pedestrians and bicycles (no motorized vehicles).
I, Patti Shafto-Carlson, as Chief Executive Officer of the Girl Scouts
of the Northwestern Great Lakes, Inc. execute this letter on behalf of
such corporation as of the date below. However, this letter is
executed with the understanding that no party will be bound by any
of the terms provided until a formal agreement is fully executed and
that the terms of this letter are not legally binding.
Patti Shafto-Carlson, Chief Executive Officer
__ _______________________ 3-7-2023__
Signature Date
REQUEST FOR CONSIDERATION
Public Mtg/Date: Park & Recreation Committee – 3/27/2023
Description: Park Signage
From: Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question: Should the Park and Recreation Committee
recommend moving forward with the replacement of
Park Signage?
Background
Back in August at the joint Public Works and Park Committee meeting it was
discussed that the Village recently went through the process of replacing
wayfinding and entryway signs. It was decided that the Village should put out a
Request for Quotes to replace the park signs. The RFQ was drafted and sent out
in September to 6 sign companies to provide quotes. Unfortunately, the Village
received just one quote by the November 2nd deadline. We were quite surprised
that we didn’t get additional quotes. Out of the 5 other companies we heard from
2. One declined to submit a quote and the other stated they were going to look at
submitting one but they did not.
The one quote that we received was from Graphic House who is the contractor
that installed the new Village Entryway Signs.
Since receiving just one quote it the Committee decided we should requote the
project with a couple of changes. The Village will now be doing the removal of the
existing signs and we changed the sign material to 1/8 inch thick material instead
of 1/4 inch material. The project was re-quoted in January with a deadline of
February 22nd. This time we received two quotes. One from Graphic House and
one from Sign Forge. Unfortunately, due to the timing of when the quotes were to
be received and having to get the packet out the same day we were not able to
hold a February meeting so these proposals are now coming before the
Committee for their March meeting.
Proposals will be sent to Committee Members in a separate email.
Attached Docs: Request for Quotes
______________________________________________________________________
Committee Action: Sign proposal was previously reviewed at the 11/28/22
meeting prior to requoting with a couple of changes and
hoping to get additional proposals.
Fiscal Impact:
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Recommendation: None
Recommended Language for Official Action
I move to recommend awarding the Park Sign replacement project to Graphic
House,
Or
I move to recommend awarding the Park Sign replacement project to Sign Forge,
Or
I move to recommend not awarding the Park Sign replacement project,
Or
Something else.
______________________________________________________________________
Additional action:
REQUEST FOR CONSIDERATION
REQUEST FOR QUOTES
FOR
REMOVAL AND REPLACEMENT OF
VILLAGE PARK SIGNS
Village of Weston, Wisconsin
January 12, 2023
INTRODUCTION
The Village of Weston, Wisconsin is seeking quote from qualified contractors for the replacement of 9 Park Signs,
replacement of 1 playground sign, installation 4 wayfinding signs, and repainting of 4 decorative rock signs.
SCOPE OF WORK
In general, the contractor shall complete all the necessary work to replace the signs and any restoration work
required.
Village will complete removal and disposal of existing signs.
Costs for necessary permits will be covered by the Village.
The specific tasks for the project are listed below.
Wayfinding Signs
A. Construct new sign panels from router cut 1/8” aluminum sheet with smooth finished edges.
B. Custom color with ½” white border for wayfinding signs. Green to match the color of the primary tree in
the village logo. Tree graphic to be screen printed over primary panel color. Clearcoat UV anti-graffiti
coating applied. As shown on page 14.
C. Wayfinding signs shall be installed on metal signposts with stainless, galvanized or aluminum hardware.
D. Move placement of signs if necessary.
Park Signs
A. Park Signs and playground signs shall be designed like the tertiary sign on page 15.
B. Construct of 1/8” thick aluminum sign panel with custom screened graphic. Lettering in dark red.
Clearcoat UV anti-graffiti coating applied.
C. Posts shall all be 4” x 4” green treated and concreted in place.
D. Restoration with appropriate materials and seeding, if necessary, around posts.
E. Signs attached to posts with extra treated bracing if necessary and secured with stainless steel
hardware.
F. Move placement of signs if necessary.
Decorative Boulder Signs
A. Repaint lettering and pictures on 4 decorative rocks on the Eau Claire River Trail utilizing
exterior grade paint.
SCHEDULE FOR DELIVERABLES
Project completed by November 30, 2023.
PROJECT PROPOSAL
The quote must include the following minimum information:
1) Firm name, address, telephone number and contact person.
2) Any concerns your company would have with the proposed schedule for deliverables should also be
identified.
3) Project Cost Breakdown
a) Manufacture and installation of each sign.
b) Painting costs for each boulder.
QUOTE SUBMITTALS
1. Any restrictions on the use of data contained within a proposal must be clearly stated in the proposal
itself. Non-disclosure cannot be guaranteed after the selection stage of this procurement due to public
records law considerations.
2. Submit a copy of the quote to the individual specified in item 3 below, clearly marked Quote for the
replacement of Village of Weston Park Signs.
3. Quotes shall be received by 4:00 p.m. Wednesday, February 22, 2023, and sent via email or regular
mail to:
Shawn Osterbrink, sosterbrink@westonwi.gov
Director of Parks
Village of Weston
5500 Schofield Avenue
Weston, WI. 54476
Quotes received after the above stated day and time will NOT be accepted. Actual receipt by said time
is required.
Location 1, 3907 Northwestern
Sign and landscaping to be removed by Village. Sign will not be replaced.
Contractor to replace with new single sided 4’ x 4’ sign on 4” x 4” treated wood posts.
Signs removed by Village. Two camping prohibited signs at Yellowbanks. Not replaced.
Location 2, 3512 Camp Phillips
Contractor to install a new single sided 4’ x 4’ sign angled to the southeast on treated wood 4” x 4”
posts.
7200 Quentin
Not proposing any changes to this sign.
Location 3, 5500 Von Kanel
Contractor to replace with new single sided 4’ x 4’ sign on 4” x 4” treated wood posts.
Location 4, 5, 6, 6100 Rogan
Contractor to replace with new single sided 4’ x 4’ sign on 4” x 4” treated wood posts.
Replace 2 existing wayfinding signs at entrance to Kellyland Park/Dog Park. Signs to be sized
appropriately for the necessary wording and look like and use colors as shown on the second sign
below (Fieldhouse, skate park one). One with a right arrow and one with a straight arrow.
Location 7, 6002 Alderson
Contractor to replace two existing Kennedy Park signs with two new single sided 4’ x 4’ signs on 4” x
4” treated wood posts.
Location 8, 6412 Teagan
Contractor to replace Will’s playground sign and replace with appropriately sized sign with same
design as park sign at Robinwood Park.
.
Contractor to replace with new single sided 4’ x 4’ sign on 4” x 4” treated wood posts.
Location 9, 2500 Parkway
Contractor to replace with new single sided 4’ x 4’ sign on 4” x 4” treated wood posts.
Location 10, Directly east of 8605 Progress Way
Contractor to replace existing Dale E. Smith Waterfowl Refuge sign the one by the observation tower
with a new single sided 4’ x 4’ sign on 4” x 4” treated wood posts.
Location 11, 5600 Ryan
Not proposing to replace these signs but all boulder signs on the trail need the lettering and pictures
to be repainted. There are four total.
5700 Babl
No changes proposed for this sign.
Location 12, 7403 Ryan Street
Install new 4’ x 4’ sign on 4” x 4” treated wood posts on the southwest corner of property and have it
say “Prohaska Family Memorial Park”.
Recommended Replacement
Panel Dimensions 42” 42” 42” Wayfinding Signs
70”
54” Sign Panel to be constructed from router cut 1/4”
aluminum sheet with smooth finished edges. Custom
paint color with 1/2” white border. (Green to match
the color of the primary tree in the village logo.) Tree
graphic to be screen-printed over primary panel color.
30” Clearcoat UV anti-graffiti layer shall be applied to
painted surfaces.
All type to be cut in engineer grade white reflective
vinyl. Font is ClearviewHWY 1-W. Minimum letter
height based upon 5” capitals. Do not adjust kerning
or tracking. (Appropriate line spacing for various
0” configurations will be supplied upon selection of a
preferred design.)
Posts to be 4” diameter galvanized brushed-finish
tubing, thickness TBD by fabricator. Suitable
galvanized rain cap to be installed on top of posts.
Drawings are design-intent only. Final design and shop
drawings to be supplied by the fabricator. Where applicable,
a professional engineer shall be required to approve and
stamp shop drawings prior to fabrication and installation.
Fabricator to design and engineer all footings and mountings
in accordance with applicable regulations and best industry
Appropriate panel size is determined by the amount of content on the sign. practices. Breakaway base required for all roadway signage.
Community Entryway
and Wayfinding Plan
RECOMMENDED: August 13, 2019 7
q Custom sign cabinet, welded aluminum framing and facing,
thickness as required, facing panels painted white.
Recommended
Welded aluminum framing and facing, thickness as
w Brushed aluminum edge molding and perimeter facing. Replacement Entryway
required, mounted to cabinet, recessed from front face. e
Router or water-jet cut, 1/4” aluminum, r
Signs, Overview
1” offset, pin-mounted to cabinet. Dimensional lettering. See descriptions to the right.
Router or water-jet cut, 1/4” aluminum, metallic green t
horizontal panel, curved, mounted in front of sign cabinet.
Cinderblock base, with stone cladding. Stone work to match y
Municipal Center monument sign. Concrete footer as per
fabricator. Level concrete pad, to anchor the base, flush to grade.
The redesigned primary entryway signs may be
constructed as internally or externally illuminated
units. Village preference is internal illumination.
Internally Lit: 2” thick clear acrylic push through
lettering with dark red semi-opaque facing. Internal
LED lighting within cabinet. Lighting and lettering
accessible from maintenance panel on back of
Primary: External or Internal Lighting (Internal Preferred) cabinet.
Externally Lit: 2” thick dark red dimensional lettering,
Custom panel, 1/4” aluminum, white, with brush metallic perimeter molding. u flush mounted to exterior of custom sign cabinet.
1” thick dimensional lettering flush mounted to panel. i Internal access to sign cabinet is not required.
Custom cut, 1/4” painted aluminum, flush mounted behind main panel. o 1/4” thick aluminum sign panel with
custom screened graphic. Letttering
Custom cut, 1/4” painted aluminum, 1/2” offset mount, in front of main panel. a
in dark red, reflective,engineers grade
Custom cut, 1/4” painted aluminum, 1” offset, s vinyl. Clearcoat UV anti-graffiti coating.
pin-mounted to main panel. applied to surface.
4” diameter galvanized brushed-finish tubing, thickness TBD by d
fabricator. Suitable galvanized rain cap to be installed on top of posts.
Drawings are design-intent only. Final design and shop
drawings to be supplied by the fabricator. Where applicable,
a professional engineer shall be required to approve and
stamp shop drawings prior to fabrication and installation.
Fabricator to design and engineer all footings and mountings
in accordance with applicable regulations and best industry
practices. Breakaway base required for all roadway signage.
Secondary Tertiary
Community Entryway
and Wayfinding Plan
RECOMMENDED: August 13, 2019 5
1 Village of Weston
Marathon County, WI
2
µ
Map Date: 9/26/2022
Adoption Date (Village): N/A
Map by the Village of Weston Public Works, Utilities,
& Technology Services Department
0 0.275 0.55 1.1 Miles
Park Sign
5&6 Replacement Map
Legend
3 4 11
1 - Yellow Banks Park
7 2 - Yellow Banks Disc Golf Course
3 - Williams Park
4 - Weston Dog Park
8 5 - Kellyland Park
6 - Kellyland Park
7 - Kennedy Park
12 10 8 - Robinwood Park
9 - Sandhill Meadows Park
10 - Dale E. Smith Waterfowl Refuge
11 - Eau Claire River Trail
9 12 - Prohaska Family Memorial Park
REQUEST FOR CONSIDERATION
Public Mtg/Date: Park & Recreation Committee – 3/27/2023
Description: Proposal for Yellowbanks Disc Golf Course from the
Wausau Area Disc Golf Enthusiasts (WADGE)
From: Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question: Should the Park and Recreation Committee
recommend partnering with WADGE on improvements
and a long-term plan for maintenance of this facility?
Background
Members of WADGE have observed the commitment the Village is making to this
facility with the addition of a shelter and restroom areas and would like to make
their own commitment along with help from the Village to make this course into a
legitimate disc golf venue. This property was purchased by the Village for future
well sites, which are currently being built. Knowing that there was a large portion
of property that would not be used for the wells it was determined that after
shutting down the course at Machmueller that this might be a viable option to
build a new course. From the beginning we knew this property would pose
challenges to building and maintaining a proper course. Between the multiple
types of thorny brush, pipeline easement (limits access), elevation change from
the upper to lower portion, soil conditions, wetlands and the inability to make
areas that can be mowed, which makes them easier to maintain it has definitely
been a struggle.
Earlier this year I met with Pete Hoover the original designer of the course who
had previously met with members of their club to develop this proposal. Through
our discussion and review of their proposal it became evident that some of the
items within the proposal may not be possible. Mostly due to the wetlands on this
site. Unfortunately, was not as productive as we hoped, but we did come out with
a request. WADGE is requesting that we have the wetlands delineated at this site
so we can determine what areas can be worked on without disturbing the
wetlands, therefore determining what and where improvements can be made.
Attached Docs: Proposal from WADGE.
______________________________________________________________________
Committee Action: No previous review.
Fiscal Impact: Not known at this time but there are some rough numbers
put in the proposal from WADGE.
Recommendation: None
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Recommended Language for Official Action
I move to recommend working with WADGE on improvements and course
maintenance,
Or
I move to recommend staff get a cost to complete wetland delineation,
Or
I move to recommend not moving forward at this time,
Or
Something else.
______________________________________________________________________
Additional action:
REQUEST FOR CONSIDERATION
Yellow Banks DGC Upgrade Proposal Jan. 2023
Appreciation. Gratitude. Motivation to help and offer expertise. All things our area disc
golf player base deeply feels now that Weston has gone all-in on making Yellow Banks
a legitimate disc golf venue. Dedicating an entire property and building a park shelter
for we “discers” has not gone unnoticed. That’s why we feel an obligation to offer
planning, financing and support to make it the best it can be.
When the course was built 12 years ago, both the local DG scene and our club,
Wausau Disc Golf Enthusiasts (WADGE), were both in their infancy. That is no longer
the case. The game has grown exponentially, now featuring a national tour series, a
doubling of registered PDGA members and a steady expansion of area leagues,
tournaments and even other area clubs. WADGE is leading the effort to coordinate
projects on the courses we’ve helped build and maintain while cooperating with other
organized player groups. We are undergoing a club restructuring/reorganization to
make that happen with the belief that we’re better together than randomly divided into
ununified club factions.
First, though, a bit of history: At Shawn Osterbrink’s request, Yellow Banks DGC was
initially designed by licensed designer Pete Hoover as an 18-hole layout. Although not
an ideal property, both Hoover and area players were grateful to have another place to
play disc golf after his designed course at Macmueller Park was removed. The new
Yellow Banks course was to be completed in phases, with the current 11 holes as the
start. Several Eagle Scout projects helped get it going, especially with stairway
accesses built to make climbing hillsides and accessing the back 9 possible. Many
volunteer work days were organized and sponsored by WADGE, with volunteers from
Wausau, Stevens Point, Marshfield, Mosinee and even the UP coming to help with
clearing and brushing. Over a hundred man-hours were put in, yet for a number of
reasons, the village did not support the course’s completion.
Without Weston’s commitment to the project, players’ interest at YB waned, WADGE
gradually stopped doing formal work days and the only course work done for many
years was billed as “resurrecting YB” from the encroaching weeds and rough. The club
still volunteered help by loaning equipment to willing volunteers, replacing/repairing tee
pads, installing treated wood stairtreads to improve safety and beating back the weeds,
but those sporadic efforts alone were not sustainable. The course was (and still is)
virtually unplayable during the peak summer months when thorny ash, berry brambles
and other prickers make retrieving errant throws an invitation to injury. We had
renewed hope several years ago when a Weston resident and active player, Tom R,
agreed to help redesign the course with Hoover’s help, but Tom’s life circumstances
changed and his commitment along with them.
The rebuild stalled and we were back to resurrection efforts. The most recent effort was
quite successful. This past fall a player group contacted Mr. Osterbrink for permission
to run a work day at Yellow Banks and got approval. The problem was that he was
under the impression that it was being done under the guises of WADGE, the group
which has improved/maintained the course over the past 11+ years. It was not. This
was likely a misunderstanding, as many players who volunteered are actively involved
in many WADGE activities and a part of several clubs. In the future, WADGE
respectfully requests that its long-time stakeholders be consulted before any volunteer
groups propose doing course maintenance/improvement activities at YB. Failure to do
so will only guarantee wasted resources and untrained individuals making unintended
structural changes to the course.
Regardless of which group does the work, the question is how can we avoid the two-to-
three seasonally required “resurrection” efforts just to make Yellow Banks safely
playable? The key seems to be making 3-4 of the most commonly overgrown fairways
actually accessible for and maintained by mowing. That, in turn, makes brushing back
uncontrolled rough actually feasible rather than weed-whipping entire fairways. And
given the limited resources available to Weston Parks, WADGE feels obligated to help
with financing, course maintenance expertise and volunteer resources to make that
happen. The only thing we ask in return is Weston’s help in making the course safer
and more playable.
Improvement Plan
Full implementation of any plan can’t happen until the park shelter and well construction
get finished, but here is an overview of what we’d hope to see done and the respective
roles/duties Weston and WADGE and would assume. Please advise if anything is
missing, unclear or not permissible by village ordinance, WI law or federal law.
Task 1 Service routes created to allow access to holes 1, 2, 3 and 4 with grading
equipment/SkidSteer. Deeper shallows filled with wood chips/earth
(where allowed*) so that trip hazards are fewer and smooth enough to
mow. Seeding likely unneeded. Accesses will also make cutting/removal
of deadfall/debris much easier after storms.
Weston Fill material provided/staged at select dump spots for easy access. Once
grass establishes, estimated to require 45 minutes of added mowing every
two weeks from June-Sept.
WADGE Club would rent/operate SkidSteer with permission and guidance from
Weston Parks. Fill areas marked, work plan and hold harmless
agreement formally signed.
Task 2 Re-designing several holes to accommodate the structural additions of a
shelter and well houses. Tee pads (and 2 baskets?) moved as needed
and novice tee pads added to encourage more youth/beginner play. With
use of Weston’s 7 surplus baskets (already purchased/designated for the
original 18-hole layout), permanent secondary pin placements would be
added on seven of the eleven holes. This is a common upgrade on quality
courses to provide varied challenges for players. The older baskets are
getting worn and need re-coating, so the new ones could serve as a single
alternative while that is being done. New coating color of orange.
Weston Cost share with WADGE on the basket sandblasting and re-coating.
Approximately $1200 total ($125/basket). Use of the 7 surplus baskets
Weston already owns.
WADGE Cost share ½ with Weston on the basket re-coating. Club would assist
Shawn O in the placement/installation of the new baskets, which require
unique anchoring measures due to wetland designation*.
Task 3 Refurbish/re-level tee pads with crushed limestone underlayer. The
current crushed granite is functional, but is prone to uneven compaction.
Weston Provide/stage material for club to spread and tamp. Club’s 7 surplus pads
used to replace worn ones. Old ones used for smaller novice/beginner
pads.
WADGE Spread and tamp underlayer. Club’s 7 surplus pads used to replace worn
ones. Old ones used for novice/beginner pads. Possible future plan for
concrete pads on holes not in wetland areas.
Task 4 Tee sign replacement and addition of a master layout sign once
construction is done and revised layout approved. Signs done by Tim Z,
an area player and professional graphic designer. His resume includes
disc golf signs at Standing Rocks, Yulga and Wisconsin Lions Camp
DGC’s and even custom disc stamps for specific events/fundraisers. 5-
year $100 renewable hole sponsorships sold to offset costs. Sponsor tags
separate from actual tee signs to save costs in case of theft, vandalism or
future sponsor changes.
Weston Provide treated lumber and mounting hardware for signs. Consult club on
installation location (critically important for player safety and proper
visibility)
WADGE Solicit hole sponsors with focus on area businesses, local volunteers and
area players. Fully fund sign design/manufacturing and plan with Weston
Parks for installation.
Task 5 Provide a revenue stream for Weston Parks and a player course guide by
installing a donation tube and a master layout sign near the new shelter.
Course scorecards offered under master sign or kiosk. Rebuild the kiosk
so that its sliding windows are more secure and locking mechanism is
sturdier. Deter theft/vandalism with trail cams trained on shelter/tube
area.
Weston Fund/install the donation tube (voluntary $2 - $3/day), trail cams and
master sign. Heavy-gauge steel and a heavy-duty anchor required to foil
theft. Consult WADGE on design, location and installation of tube and
sign.
WADGE Consult as outlined above. Fund/provide scorecards.
Hopefully this plan makes sense to improve YB at minimal expense to Weston. It also
can help re-establish a cooperative working relationship between Weston/WADGE and
between WADGE/other motivated clubs. Local players have the energy, motivation and
resources to see YB become a destination course. Let’s meet to talk about getting this
done.
WADGE Board of Directors
REQUEST FOR CONSIDERATION
Public Mtg/Date: Park & Recreation Committee – 3/27/2023
Description: Capital Improvement Projects (CIP)
From: Shawn Osterbrink, Director of Parks, Recreation &
Forestry
Question: Should the Park and Recreation Committee
recommend additional projects for the CIP?
Background
Staff has begun working on reviewing the current CIP list of projects. We would
like to start discussing this with the committee to get their thoughts on the items
currently in the plan and get thoughts from the committee on future projects. Staff
will also begin to add equipment and facility needs. Review of this document may
also include changing years on projects depending on priorities, etc. This is just a
plan so projects can change on a regular basis. With the Village just starting to
work on the update to the Comprehensive Outdoor Recreation Plan and two Park
Master Plans we expect that this document will change based on what comes out
of this process. We also expect to see some additional requests from Everest
Youth Baseball as we complete the Kennedy Park Master Plan.
The CIP is relatively complete through 2023 but additional equipment and projects
need to be included for years 2024, 2025 and 2026. Once projects are identified for
the Village, budget estimates can be completed and the amount of funding that
may be available per year can be determined. The amount of funds available is
determined by how much the Village can afford based on debt service and what
the Village Board approves.
You will also notice that 2022 projects are still on this list. Some of these items
were not completed.
Attached Docs: Current CIP
______________________________________________________________________
Committee Action: No previous review.
Fiscal Impact: N/A
Recommendation: None
Recommended Language for Official Action
I move to recommend including _______________ projects in the CIP,
REQUEST FOR CONSIDERATION
REQUEST FOR CONSIDERATION
Or
Something else.
______________________________________________________________________
Additional action:
REQUEST FOR CONSIDERATION
2022
Proj. ID Project Name General Grants/Other Rev Total
AQ10 Slide and Activity Pump Upgrades - Aquatic Center $ 35,000 $ 35,000
AQ11 Shower Upgrades - Aquatic Center $ 19,000 $ 19,000
AQ13 Insulate and heat furnace room - Aquatic Center $ 25,000 $ 25,000
AQ14 Roof Replacement - Aquatic Center $ 75,000 $ 75,000
AQ16 Electrical Connection Upgrades - Aquatic Center $ 10,000 $ 10,000
AQ15 Refurbish Water Play Structure - Aquatic Center $ 99,350 $ 99,350
Slide Repairs and Cleaning - Aquatic Center $ 25,000 $ 25,000
P6 Kennedy Park Play Structure Upgrades $ 40,000 $ 40,000
P9 Sandhill Park Play Structure $ 80,000 $ 80,000
P10 Yellowbanks Shelter Roof $ 8,000 $ 8,000
2023
Aquatic Center - Replace Wood Posts around Pool & Safety Netting $ 25,000 $ -
Regenerative Filter Media Conversion at Aquatic Center $ 275,000 $ 275,000
P7 Kennedy Restroom Replacement $ 80,000 $ 80,000
Play Structure Upgrades - Kellyland $ 80,000 $ 80,000
Replace Main Park Signs (6 total) $ 25,000 $ 25,000
Finishing Mower Attachment for Trackless Machine $ 30,000 $ 30,000
Replacement Mower/Snowblower #115 $ 80,000 $ 80,000
2024
P1 Prohaska Park Development $ 500,000 $ 500,000
Aquatic Center Play Equipment/Structures $ 50,000 $ 50,000
Play Structure Upgrades - Robinwood $ 80,000 $ 80,000
Replacement Hockey Boards $ 75,000 $ 75,000
2025
Play Structure Upgrades - Yellowbanks $ 30,000 $ 50,000 $ 80,000
2026
Play Structure Upgrades - Williams $ 30,000 $ 50,000 $ 80,000
END OF
PACKET